Professional Documents
Culture Documents
COMMISSIONING PROCEDURE
For
0 2016.4.29
Construction Xiong Pei Zeng Bin Pu Xiaoqin Guo Baodong
OWNER
VIETNAM ELECTRICITY
THERMAL POWER PROJECT MANAGEMENT BOARD 3
CONSULTANT
POWER ENGINEERING CONSULTING JOINT STOCK COMPANY 3
CONTRACTOR
THE CONSORTIUM OF CHENGDA-DEC-SWEPDI-ZEPC
SUBCONTRACTOR
THE COMMISSIONING & TEST INSTITUTE OF SICHUAN ELECTRIC
SECTI POWER INDUSTRY
CONTRACT No.
PROJECT DUYEN HAI 3 THERMAL POWER PROJECT
DH3-05082011
Commissioning Procedure of coal pulverizing system
FILE NAME
Contents
1. Objective of Commissioning ..................................................................................................... 3
2. Content of Commissioning ........................................................................................................ 3
3. Compilation Basis ..................................................................................................................... 3
4. Tools and Instruments................................................................................................................ 4
5. Conditions to be met prior to commissioning ........................................................................... 4
6. Commissioning Procedure......................................................................................................... 4
7. Safety measures ......................................................................................................................... 9
CHENGDA-DEC-SWEPDI-ZEPC
1. Objective of Commissioning
2. Content of Commissioning
3. Compilation Basis
5.1 The installation work is over and the commissioning team agreed to accept the system to
start commissioning.
5.2 A punch list covers all defects or unfinished works is confirmed by the construction sub-
contractor and commissioning team that the defects or unfinished works do not affects
commissioning and system normal running.
5.3 Work permit system is in working.
5.4 Safety isolation measures are implemented.
5.5 Loop check and DCS interface verification have been executed.
5.6 The sundries inside coal mill system have been cleared away.
5.7 The individual commissioning of coal mills completed.
5.8 The individual commissioning of coal feeders completed.
5.9 The individual cold adjustment of burners is completed;
5.10 The individual commissioning for the oil station is completed, the favorable operation
condition, normal parameters and the correct display of DCS state are correct.
5.11 The individual commissioning of the valve is completed, the on/off actions are normal and
the display of the DCS state are correct.
5.12 Motors have passed through electric test successfully, and are in good condition and rotate
in correct direction in two running hours without load.
6. Commissioning Procedure
(2) Check and ensure restore of the coupling of motor and coal mill reducer are over. and
operate it by hand, to be normal;
(3) Clearance between roller and bowl shall be adjusted larger temporarily. Clearance shall
be adjusted to meet security requirement adequately.
(4) Result of lubrication oil system test of coal mill is passed;
(5) Start coal mill and shut down it after 5 seconds. Check:
1) Starting current;
(4) When coal mill starts or stops, steam temperature, steam pressure and water level will
fluctuate violently. Adjust feed water and desuperheating water in time. Contact steam
turbine to increase or decrease load in good time.
(5) After mill is put into operation, analyze fineness of pulverized coal in time and maintain
it to the design size. Regulate burning and improve air distribution to ensure good
combustion.
(6) Keep watch on running parameters which shall be within normal range during mill
operation.
(7) Inform coal handling system to remove foreign matters in raw coal as much as possible
in trial run to prevent foreign matters from entering mill to cause vibration.
(8) After the flame is stable, and load of boiler is stable the flame detector should be
adjusted, in two steps:1-to the mills, one by one, 2-second time, when the fire is done
only by coal mills, the flame detectors should be checked and re-adjusted if it is
necessary.
6.5.3 Dynamic monitor and maintenance of system
When pulverizing system is put into operation, intensify inspection and monitor for
rotating equipments; enhance supervision of running parameters. If any deviation is
found, regulate it in time to ensure that system is in optimum running condition.
(1) Supervision and maintenance of temperature at mill outlet;
(2) Supervision and maintenance of air flow at mill inlet;
(3) Current change of coal mill and feeder; maintenance of coal feed rate;
(4) Change of lubrication oil temperature of coal mill; adjust cooling water rate if necessary;
(5) Supervision of temperature of rolls and motor winding of coal mill;
(6) Current change of primary air fans on both sides; deviation and adjustment of primary
air pressure on both sides;
(7) Supervision of bearing temperature of primary air fan; supervision of temperature of
motor winding of primary air fan;
(8) Supervision of seal air pressure and current of coal mill;
(9) Observation, supervision and adjustment of combustion in furnace;
(10)Supervision and regulation of steam temperature, steam pressure, water level and flue-
gas temperatures of boiler;
(11)Check pebble coal contained in raw coal every two hours in the initial period of mill
running. Eliminate pebble coal in time to calculate its content in raw coal. If pebble coal
content exceeds normal limit, find out the cause and remedy it.
6.5.4 Normal shutdown of pulverizing system
(1) The corresponding oil layer shall be capable of being put quickly into service before
each pulverizing system stops.
(2) Switch control of coal feeder from auto mode to manual mode. Decrease feeder speed
gradually to minimum coal feed rate and decrease air flow to 70% rated air flow of mill.
Strictly control normal temperature at mill outlet during the above-mentioned procedure.
(3) After load of coal mill is reduced to the minimum, close correspondingly hot air damper
of mill and open correspondingly cold air damper. Switch control of air flow and
temperature to manual mode.
(4) Shut down coal feeder and close the baffles at inlet and outlet of coal feeder when
temperature at mill outlet drops to about 50℃. Keep coal mill running for another 5-10
min at least to eliminate coal deposit in bowl.
(5) Shut down coal mill after coal deposit in mill is eliminated. Close the baffles at inlet and
outlet of mill.
(6) Maintain seal air pressure for 5-10 minutes after mill stops. Stop seal air.
(7) Shut down lubrication oil station 15 min. after mill stops.
(8) Shut down primary air fan and close damper at outlet of primary air fan after all mills
stop.
(9) Shut down seal air fan.
6.5.5 Hot regulation of pulverizing system
When pulverizing system is putting into operation, intensify supervision of equipments
in system. If any deviation is found, regulate it in time to ensure that the system is in
optimum running condition and combustion is stable in boiler.
(1) Regulation of fineness and uniformity of pulverized coal
(2) After pulverizing system is put into operation normally, measure the fineness and
uniformity of pulverized coal in primary air. Regulate air flow and opening of deflector
baffle in pulverizing system.
(3) Regulation of air-coal ratio of pulverizing system
Control temperature at mill outlet within normal range. Regulate opening of cold/ hot air
dampers at mill inlet to change air flow of mill and to guarantee optimum air-coal ratio
of pulverizing system under certain load.
(4) Optimization of pulverizing system
Regulate combustion mode and distribute combustion load reasonably according to
boiler load requirement, steam temperature change of main heater and reheater to
guarantee boiler parameters and economical efficiency in operation.
6.5.6 Running in trial start-up of entire system
(1) The entire system shall be subject to no-load running, on-load running, full-load running,
30-day reliability-demonstrating test to test reliability of system.
(2) Dynamic regulation of system: During the system is putting into operation, especially in
the regulation of fineness of pulverized coal and air flow, intensify the supervision of
equipments to guarantee that the system is in optimum running condition.
6.5.7 Complete trial operation record: Refer to ITP for main parameters in trial.
7. Safety measures
(1) All operating personnel participating commissioning shall strictly follow safety
regulations at site, thus to ensure safe and reliable commissioning.
(2) In case that equipment damage, personnel injury, etc. during commissioning are possible
or have occurred, stop commissioning immediately and analyze the cause;
commissioning shall not be continued untill solution is provided.
(3) “Heating up” of mill is carried out at shutdown conditions. “Heating up” of mill is
normally started when hot air temperature at the outlet of preheater reaches to 180°C
and boiler operation reaches about 25% rated load.
(4) The temperature rise rate at the outlet of mill shall be controlled within 5°C/min in order
to guarantee that no excessive temperature difference thermal stress will occur with the
components of mill and at the pulverized coal pipe bends.
(5) The mill must be subject to comprehensive check after it starts operation. For example
the operating conditions of oil station of the mill, if the pipe and sealing points are tight
without leak and if the temperature of shaft bush and the sound of operation of mill are
normal, etc.
(6) The air/pulverized coal ratio must be guaranteed within proper range to avoid excessive
variation of air/pulverized coal ratio affecting combustion effect or even leading to
flame out.
(7) Due to the resistance influence inside the mill proper and the primary air pipe, the
air/pulverized coal flow speed will be excessively low. This will not only make the
operating conditions of mill unstable, but also lead to over-firing of burner. In order that
the ignition is stable, the mill shall be operated at >50% rated output condition.
(8) Starting two mills simultaneously to supply pulverized coal to boiler is strictly not
allowed to prevent excessive pulverized coal from entering the hearth to cause excessive
positive pressure or explosion of incomplete combustion.
(9) Current, pressure difference, outlet temperature, coal feeding capacity, primary air
volume of mill must be monitored during operation. Decisive and correct handling must
be made in case abnormality is observed.
(10) The oil station of mill proper must be frequently checked so that any abnormality if
observed can be solved timely.
(11) In case the mill still cannot restore operation after 1 hour of emergency shutdown, the
mill must be operated with no load to continue running to discharge empty the mass
accumulated coal in the abrasive wheel.
(12) In the shutdown period, pay special attention to the temperature of the shell of the
grinding system so as to find out any abnormal phenomenon or ignition hazard.
7.2 HAZID/HAZOP
Potential
Num Activity Potential Hazard Factor Prevention Measure
Hazard Result
Wear proper work clothes and keep the safe distance
High temperature object with high temperature object. If need to contact with
1 Site work Personnel scald
surface high temperature object, wear heat insulated gloves or
protective equipment.
involved
properly.
6 Site work Mal-operation damaged and operation approval system and never carry out work