You are on page 1of 19

Compendium of selected research in ground

engineering
Prepared for Quality Services, Highways Agency

J D Lewis

TRL Report 517


First Published 2001
ISSN 0968-4107
Copyright TRL Limited 2001.

This report has been produced by TRL Limited, undedas part


of a Contract placed by the Highways Agency. Any views
expressed are not necessarily those of the Agency.

TRL is committed to optimising energy efficiency, reducing


waste and promoting recycling and re-use. In support of these
environmental goals, this report has been printed on recycled
paper, comprising 100% post-consumer waste, manufactured
using a TCF (totally chlorine free) process.
CONTENTS
Page

Executive Summary 1

1 Introduction 3

2 Research themes and list of report summaries 3

3 Report summaries 5

Abstract 17

Related publications 17

...
111
Executive Summary

This document has been prepared as a compendium of


selected research undertaken by TRL Limited (the
Transport Research Laboratory) between 1993 and 1998.
The research is represented by summaries drawn from a
selection of benchmark reports on specific areas of ground
engineering commissioned by the Highways Agency as
part of a broad-based research programme.
The compendium has been produced to indicate some of
the key subject areas, or themes, covered by the
geotechnical research undertaken by TRL for the
Highways Agency over recent years.
The summaries of twenty three key research reports are
presented in this document, grouped under seven linked
themes. The summarised reports focus on engineering
within appropriate environmental frameworks, aspects of
recycling and reuse of materials, specialised laboratory
testing, in situ trials and testing, and the performance
monitoring of materials and processes. They also detail
innovative construction and maintenance issues associated
within sustainable highway engineering practice. The
specific themes selected are as follows:
0 Recycling and reuse of materials in highway
construction.
0 Specialised testing and the performance of construction
materials.
0 Compaction practice and equipment performance.

0 Lime stabilisation.

Earthworks construction, performance, maintenance and


repair.
Reinforced earthworks.
Stabilisation of slopes by bio-engineering techniques.
The summaries have been compiled as a compendium
for the purpose of highlighting some of the principal areas
of applied research undertaken by TFU within the ground
engineering discipline in recent years. A number of the
reports summarised in this document have contributed to
the development of internationally recognised standards in
highway engineering. The document introduces the reader
to some of the areas of geotechnical research
commissioned by the Highways Agency in subjects of
interest to a broad range of practitioners, but they are also
of direct relevance to specialists within the fields of civil
and geotechnical engineering.

1
1 Introduction 2 Research themes and list of report
summaries
As part of an Implementation Support project commissioned
by the Highways Agency, the following report has been The following is a list of the report summaries presented in
prepared in the form of a compendium of summaries drawn Section 3 of this report.
from a series of selected benchmark reports on specific areas The list also presents the linked themes within which the
of ground engineering research. The reports for which summaries have been grouped for the purpose of
summaries are presented were commissioned by the readership interest and ease of presentation, and it also
Highways Agency as part of a broad-based programme of includes a brief introduction to the subjects covered by the
research undertaken by TRL Limited (the Transport reports listed within each theme.
Research Laboratory) between 1993 and 1998.
This compendium has been produced to indicate some Theme 1
of the key subject areas, or themes, covered by the
geotechnical research undertaken by TRL for the Recycling and reuse of materials in high way construction
Highways Agency over recent years. However, the work The summaries presented under this theme are as follows:
covers only a small part of the breadth of geotechnical 1.1 The use of recycled bituminous materials for capping
engineering research undertaken by TRL for the Highways layers
Agency, and its predecessors, in recent decades.
Authors: A F Toombs, R A Snowdon and D P Steele
The subject areas addressed within the reports
summarised in this document are considered to be of 1.2 The use of recycled bituminous planings for capping
particular interest to a range of potential users, including on the A74
those involved in designing and implementing highway Authors: D P Steele and R A Snowdon
infrastructure development and improvement schemes.
The seven linked themes covered by the report The reports represented by these first two summaries
summaries presented in this document are as follows: address specific technical aspects of sustainable highway
construction, principally the use of recycled pavement
0 Recycling and reuse of materials in highway
materials as capping to avoid disposal of otherwise waste
construction.
planings. The reports focus on presenting the results of a
0 Specialised testing and the performance of construction comprehensive laboratory test programme undertaken by
materials. TRL and an associated range of field trials carried out by
0 Compaction practice and equipment performance. TRL and collaborating local authorities. These studies
0 Lime stabilisation. investigated the compliance of asphalt planings with the
existing specification requirements and also addressed the
Earthworks construction, performance, maintenance and
development of new specifications where required.
repair.
Reported field trials on the A74 involved extensive in situ
0 Reinforced earthworks.
monitoring to quantify the performance and suitability of
0 Stabilisation of slopes by bio-engineering techniques. these materials under live traffic loads.
For information purposes, each report summary includes
a heading identifying the author(s) of the report from Theme 2
which it is extracted, the TRL Project Report number and Specialised testing and the performance of construction
the date when the report was produced. These details will materials
be of use should further information be required regarding
The summaries presented under this theme are as follows:
the subjects covered.
It is considered that specialists and other interested 2.1 Acceptability testing of fills with oversize particles
parties will benefit from an awareness of the subject matter Author: M G Winter
covered by these selected summaries and their associated 2.2 Rounded granular capping materials
reports. When reading the summaries presented, interested
parties may wish to find out more about the themes Authors: D J MacNeil and R A Snowdon
covered and the innovative approaches adopted by TRL in 2.3 Moisture content measurement of recycled
delivering the Highways Agency’s technical requirements. bituminous planings using the nuclear density gauge
Further information regarding TRL’s research Author: F A Yuille
programmes or any of the summaries presented in this
document and their associated unpublished reports, can be 2.4 Embankment on soft ground: review of the results of
obtained by contacting TRL Limited on 01344 773 131 centrifuge tests
(email: enquiries@trl.co.uk). Author: J P Love
The reports represented by these four summaries focus on
matters associated with specialised testing of natural and
recycled materials, relating this to their performance in
highway construction. Issues associated with the effects of

Previous page
is blank
clast (stone) and matrix dominance of local and regional interpretation of MCV results for moisture content control,
soil types on their relative performance under laboratory to enable the acceptability assessment of cohesive soils
conditions are addressed, along with their relative stabilised with either quicklime or flaked lime. This
acceptability for use as general and construction fills or as technique reduces long term risk and helps to avoid the
granular capping materials. Supporting field assessments potential for heave in these soils, the performance of which
were carried out on the stability of selected materials differs marginally with the type of lime used.
during full-scale trafficking trials, and a field assessment
of the suitability of the nuclear density gauge for moisture Theme 5
content assessment of bituminous planings is reported. The
Earthworks construction, performance, maintenance and
techniques and benefits of centrifuge modelling to
repair
determine design and performance criteria associated with
reinforced earthworks are also discussed in detail, with The summaries presented under this theme are as follows:
particular consideration given to the effects of underlying 5.1 An investigation of the mechanism of shallow failure
clay foundation materials. of Gault Clay embankment slopes
Authors: G I Crabb and D M Hiller
Theme 3 5.2 Monitoring of the Gault Clay embankment slope at
Compaction practice and equipment performance Dunton Green
The summaries presented under this theme are as follows: Author: G I Crabb
3.1 The performance of machine-mounted compactors 5.3 The repair of a highway embankment by grout
Authors: A F Toombs and D P Steele injection
3.2 Chalk classification and compaction trials on the Authors: D G Boden, K C Brady and D J Ayres
A289 Wainscott Northern bypass 5.4 Performance of slope maintenance and repair
Authors: A F Toombs and R A Snowdon techniques on the Cambridge Northern bypass
Author: D G Boden
The reports represented by these summaries describe
research undertaken on current and recent compaction 5.5 Performance of the polystyrene fill embankment on
practice in highway engineering. Consideration is given to the A1 20 Dovercourt bypass
operating procedures and an evaluation is undertaken of Authors: K Raby and R A Snowdon
the types of plant used, including their appropriate use in
confined spaces, for example, for trench reinstatement. The majority of the reports represented by these
Specifications for material classification, acceptability and summaries focus on the assessment of the performance of
compaction are presented, and the performance of plant earthworks in Gault Clay, the material with one of the
and materials where chalk is the formation material is also highest percentage failure for both embankments and
discussed. cuttings on the highway network in England and Wales.
The long term performance of an embankment constructed
on very soft alluvial deposits using ultra-lightweight
Theme 4 polystyrene fill is also presented. The case histories
Lime stabilisation investigate failure mechanisms, detail procedures and
The summaries presented under this theme are as follows: techniques adopted for slope monitoring, quantify the
effect of drainage on pore water pressure development,
4.1 The effect of lime stabilisation on the MCV of two
describe the long term performance of structures, and
cohesive soils
assess the relative effectiveness of a range of repair and
Authors: D P Steele and D J MacNeil strengthening techniques used in particular cases. The
4.2 Lime stabilisation of two cohesive soils using SG60 latter include grout injection, lime stabilisation, granular
and flaked lime replacement, use of gabion and anchored type walls,
geosynthetic containment and the use of rock ribs, and lead
Authors: D J MacNeil and D P Steele
the reader in to aspects associated with reinforced
4.3 A laboratory investigation of a lime stabilised earthworks addressed within Theme 6.
capping layer failure
Authors: R A Snowdon, D J MacNeil and D P Steele Theme 6
The reports represented by these summaries describe the Reinforced earthworks
effectiveness of lime stabilisation techniques and practice The summaries presented under this theme are as follows:
both in the laboratory and on site, the latter relating to 6.1 Reinforced slopes and embankments
construction of the M40. The reports confirm that the
Authors: K C Brady, W McMahon and D G Boden
Moisture Condition Value (MCV) is the best method for
assessing and controlling compaction effectiveness and for 6.2 A review of the adequacy of HA68 for designing
quantifying the anticipated performance of stabilised soils. steepened slopes
The reports discuss the importance of the correct Author: D G Boden

4
6.3 Aspects of the design and construction of two 3 Report summaries
reinforced embankments on the A414
Authors: K C Brady, W McMahon and D G Boden Theme 1
The reports represented by the summaries within this theme Recycling and reuse of materials in highway construction
describe techniques for design, construction and 1.1 The use of recycled bituminous materials for
instrumentation of steepened highway cuttings and capping layers
embankments with reinforced side slopes and bases. The
performance of the latter on weak compressible ground is Authors: A F Toombs, R A Snowdon and D P Steele
detailed. The reports also focus on the specification of the Project Report No: PRJCE/25/94
mechanical properties of geosynthetic reinforcements as Date: I994
well as their ability to withstand site compaction operations.
An investigation of the adequacy of HA68 for the design of The use of recycled pavement materials, such as asphalt
reinforced earthworks is described. The latter focuses on planings, in highway reconstruction or widening schemes
design procedures associated with pull out resistance for a has environmental benefits in that provision is not required
range of potential failure mechanisms, the adoption of for the supply of natural and perhaps scarce material nor
appropriate design factors, and the identification of for the disposal of the otherwise waste planings. In
mechanisms to improve the mobilisation of pull out addition, the recycling and use of material obtained on site
resistance, including lengthening basal reinforcement layers. reduces and confines the haulage plant required for their
transportation to the immediate site, thus reducing
congestion on local roads due to construction traffic. Their
Theme 7 use also saves energy and reduces the problem associated
Stabilisation of slopes by bio-engineering techniques with handling and disposal of these classified waste
The summaries presented under this theme are as follows: materials. Schemes may also be completed in a shorter
time resulting in lower costs for the client and considerable
7.1 Review of plant species for the improvement of slope
benefits to the road user.
stability
This report presents the results of a study at TRL into the
Author: C A Mamott use of asphalt planings for capping layers. The work was
7.2 Vegetated reinforced steep slopes aimed at investigating the compliance of asphalt planings
with the existing requirements and developing new
Author: R A Snowdon
specifications for these materials should they be considered
7.3 Vegetation for slope stability: construction of a trial necessary. The test programme comprised standard
embankment classification, laboratory compaction and strength tests, and
Authors: R A Snowdon, D J MacNeil and A H Brookes also included investigations into the effect of temperature on
these properties. Consideration was given to variations in
7.4 Live willow poles for slope stabilisation on the A249 the standard test procedures in order to apply them to these
at Iwade non-standard materials. Results were also obtained from
Author: D H Barker field trials camed out by local authorities on certain road
The reports represented by the final four summaries focus reconstruction or widening schemes where recycled
on important research undertaken in recent years on the planings were to be used as capping.
use, performance and effectiveness of selected vegetation The results show that, although the nature and behaviour
to stabilise highway earthworks. This is with particular of these materials are different from soils, gravels or other
reference to slopes steepened as part of the motorway unbound aggregates, there is no reason why asphalt
planings should not be used for capping provided they
widening programme of recent years and the associated
potential for increased risk of shallow and deep seated comply with certain requirements. The report includes a
failures within earthworks. The reports consider the suggested classification for recycled bituminous materials
and associated modifications to Clauses in the
reduced risk of shallow failure by the provision of slope
Specification for Highway Works (MCHW 1 ) and HA 44
stabilisation through plant root systems effecting a
(DMRB 4.1.1).
networked reduction in moisture content and porewater
pressure. The performance and relative effectiveness of a
range of species planted on steepened and reinforced 1.2 The use of recycled bituminous planings for
slopes is discussed; 500 live willow poles planted as a capping on the A74
form of vegetated soil nailing in a cutting on the A249 is Authors: D P Steele and R A Snowdon
reported as a case example. The interim findings are also
Project Report No: PR/CE/93/95
reported of an extensive study of the handling, planting
and long term maintenance and performance monitoring of Date: 1995
selected trees, shrubs and perennial species planted on a A full-scale trial has been carried out on the A74 to
trial embankment of over-consolidated cohesive fill at investigate the performance of recycled bituminous
TRL’s Crowthorne site. Elements of these reports are planings as a capping layer. The performance of the
summarised in TRL Reports 506,508 and 5 15. planings was monitored to provide data on their suitability

5
and on material acceptability requirement for the then these tests are commonly used to determine soil
proposed introduction of Specification for Highway Works acceptability for earthworking and the removal of such
(SHW) Class 6F3 capping. large particles, often referred to as scalping, can have a
Comparison of the in situ compaction data and the profound effect on measured properties.
laboratory results shows that the relatively poor state of It is not known what proportion of UK earthworks might
compaction achieved on site, i.e. high air voids, could have comprise materials with large proportions of particles
been improved significantly if a lower limit for moisture larger then 20mm but it is likely to be significant given the
content of OMC-2% had been applied to the planings. This extent of glacially deposited soils. Consequently, it is not
is now a requirement for material acceptability in the SHW in the public interest to base the properties of embankment
Class 6F3. This would have probably reduced some of the construction materials on the limitations of laboratory
settlement measured during the trafficking trial and scale tests and risk the exclusion of readily available
improved the in situ CBR values as indicated by the materials with satisfactory engineering properties.
dynamic cone penetrometer results. If the proportion of stones is small, then they act as
The performance of planings as capping layers was only ‘plums’ within the matrix which will determine the bulk soil
marginally lower than that of an SHW Type 1 granular behaviour. Tests on the matrix may thus be used in place of
sub-base material and was well within the trafficking tests on the bulk material. If, on the other hand, the stone
requirements for sub-base materials. Extrapolated in situ content of a given soil is sufficiently high that the stones
and laboratory results indicate that the SHW Method 6 come into contact and thus determine the bulk soil
compaction requirements applied to unbound recycled behaviour, then tests on the matrix material passing a 20mm
bituminous materials should produce a satisfactory state of sieve may not be used in place of tests on the bulk soil.
compaction within the capping layer. An extensive laboratory test programme has been
conducted to determine the proportion of particles larger
Theme 2 than 20mm at which the transition from matrix to stone
Specialised testing and the performance of construction determined behaviour occurs. The resultant data have been
materials supplemented by some 48 data sets taken and reanalysed
from the available literature.
2.1 Acceptability testing of fill with oversize particles In general it was found that for stone contents up to 45%
Author: M G Winter to 50% the matrix controls the compaction behaviour.
Project Report No: PR/CE/208/96 Tests on the matrix can thus be used to determine
acceptability. For stone contents greater than 45% to 50%
Date: 1996
the stones determine compaction behaviour. For these
Problems have been identified and reported by engineers and cases alternative approaches to acceptability determination
contractors regarding the use of BS1377 soil tests required for are required, and recommendations for additions to HA 44
determining materials acceptability requirements within the in the Design Manual for Roads and Bridges are given to
Specification for Highway Works. In particular, the allow material acceptability testing within the requirements
laboratory compaction tests to determine optimum moisture for the Specification for Highway Works.
content and maximum dry density values, and the Moisture
Condition Value (MCV) test, require the tests to be canied
2.2 Rounded granular capping materials
out on materials specimens with a maximum particle size.
Classes of materials in the S H W for general fills and Authors: D J MacNeil and R A Snowdon
structural fills can often contain high percentages of particles Project Report No: PR/CE/69/96
larger than allowed in the BS1377 test. This can lead to
Date: 1996
suitable materials being rejected solely on the basis that the
material cannot be tested to BS1377. Problems have been identified and reported by some HA
This particular project was established to provide advice regional geotechnical engineers with local gravels when being
on the effect of large particles on the BS1377 test method used as SHW Class 6F1 and 6F2 materials for capping layers.
used for material acceptability testing within the Series 600 In particular, their poor traffickability performance during
Earthworks of the SHW, with a view to raising the BSI377 construction of the pavement sub-base layer has been
limiting values for the percentage of large particles highlighted. Whilst these materials perform satisfactorily in
permitted whilst retaining the validity of the tests in the long term as a subgrade improvement layer there is a need
relation to the control of earthwork compaction. to address the traffickabilityproblem. It is recognised that this
Soils can contain a broad spectrum of particle sizes, is primarily a ‘local’ problem and that any suggested
often ranging from clay to large boulders. In contrast, amendment to the SHW material acceptability criteria should
laboratory test procedures for determining the acceptability not result in a restriction in the use of other suitable materials.
of fills for earthworking require the removal of particles This part of the research project was established to
larger than a predetermined maximum size. For example, investigate a possible test method for reliably identifying
the removal prior to test of the particles retained on a such rounded materials, and to provide engineering advice
20mm test sieve is an integral part of the MCV test while on their method of working if found to be applicable.
the three main British Standard compaction tests limit the Due to problems reported during highway construction
proportion of particles larger than 20mm to 30%. All of with unstable rounded gravels that comply with the

6
acceptability requirements for this class of material, an materials, to be used in earthworks construction.
examination of methods that may enable the rejection of such Specifications for materials classification, acceptability
materials has been undertaken and is presented in the report. and compaction are given to ensure these materials are
The assessment of stability problems with rounded selected and placed to provide satisfactory long term
capping materials suggested a number of different factors performance. There is a need to investigate any individual
could be responsible. Rounded capping materials could be problems in material acceptability testing and to consider
compacted to meet the requirements of the Specification their possible implication for the MCHW 1. Specific
for Highway Works but subsequent trafficking with material studies have been carried out and include the
narrow tyred lorries, used to deliver sub-base materials, provision of advice on the specification and use of
resulted in unacceptable rutting of the capping layer. recycled and waste materials as earthworks fills.
For the test program undertaken, three test methods were Nuclear density gauges (NDG) are permitted within
considered to have sufficient potential to be indicative of Clause 612 of the Specification for Highway Works
stability whilst not compromising the present acceptability (MCHW 1) to measure the moisture content of fill material
requirements specified for capping materials. The methods in connection with end-product compaction requirements,
evaluated were: mean angularity of constituent particles; or if required, field tests with method compaction.
degree of interlocking of capping materials as measured in Research has been camed out into the use of recycled
300mm shear box tests; and resistance to penetration as bituminous planings as SHW Class 6F3 capping material and
measured with the Dynamic Cone Penetrometer (DCP). Class 6N selected granular fill for structures (MCHW 1). If
For the different types of tests examined, their
bituminous materials are found to be suitable as Class 6N
effectiveness in discriminating between stable and unstable
materials, it will be necessary as a part of the end product
capping materials was judged, where possible, against the
requirement to determine the dry density and moisture
degree of stability of the tested capping materials indicated
content of the compacted material, possibly using a nuclear
by full scale trafficking trial data.
density gauge. Therefore, a study has been carried out to
The conclusions drawn from this study are as follows:
investigate the suitability of the NDG for moisture
Angularity testing may be used to rank materials in term readings on recycled bituminous planings.
of degree of interlocking. However, it is not considered For the samples of material tested, the bituminous
feasible to define stability in terms of an angularity cut- content of the planings produced significantly higher
off value. moisture content readings on the NDG compared to oven
A basic interpretation of shear box data permits an drying. Therefore, it is essential that a calibration is
evaluation of the ranking stability of unbound capping obtained if the NDG is used for moisture content control
materials. A more advanced analysis, in terms of - with these materials, within the Table 6/1 SHW end-
qcri) which is indicative of the energy required to product compaction requirements.
overcome interlocking, is unable to discern stability, Whilst it is strongly recommended that a calibration is
probably due to the effects of soundness of test particles. always obtained, an approximation of the actual moisture
The DCP testing reflects the degree of stability of a content could be made by subtracting the percentage
capping material, however, it can only be used to give bitumen content from the indicated NDG reading.
an indicative ranking of stability.
The implications of these conclusions are considered in 2.4 Embankment on soft ground: review of the results
terms of possible modifications to the SHW and/or the of centrifuge tests
relevant Advice Note. It is suggested that, on balance, Author: J P Love
stability problems with rounded capping materials can be
best dealt with by: Project Report No: PR/CE/115/96
0 Highlighting possible problem materials and restricting
Date: 1996
their use locally. One of the longer term research programmes undertaken at
Proposing a trafficking trial as the most appropriate test TRI.. has concerned the design and construction of
method to indicate stability. embankments over weak compressible ground. This work
Modifying the use of a capping layer constructed with has been prompted by the requirements of land
such materials so that the sole function of the capping conservation and environmental concerns which have
layer is as a subgrade improvement layer. increasingly meant that new sections of highway are
restricted to corridors of land deemed unsuitable for
housing, industry or agriculture. A number of reports were
2.3 Moisture content measurement of recycled produced by TRL on the subject in the 1970s, including
bituminous planings using the nuclear density gauge appraisals of the methods of analysis and of the options
Author: F A Yuille available for construction.
Project Report No: PWCE/l03/96 More recently, geosynthetics have been used as basal
reinforcements to embankments, and although a number of
Date: 1996
methods have been proposed for analysing the performance
The MCHW 1 Series 600 Earthworks allows the majority of such structures, their usefulness for routine design is
of naturally occurring materials, and many wastes largely untested. To assess the validity and economy of the

7
proposed methods, a series of centrifuge models was The performance of machine-mounted vibratory
commissioned from the University of Cambridge, and data compactors differs considerably from that of conventional
have been collected from two instrumented reinforced vibratory compaction plant, due primarily to the damping
embankments on the A414; thus both ultimate and effect of a relatively high static downforce on the dynamic
serviceability limit states have been investigated. forces. Although they are capable of achieving a satisfactory
A series of centrifuge tests was undertaken by state of compaction in cohesive and granular soils at the low
Cambridge University on 6 metre high (prototype) moisture contents associated with method compaction
embankments built over soft clay. In most cases a layer of specifications,they generally require more passes or thinner
geosynthetic reinforcement was installed at the base of the layers to be used than for conventional machines. Machine-
models, but no reinforcement was used in two of them. mounted compactors therefore require separate categories in
The tests were undertaken to provide data for failure or any type of method compaction specification.
near-failure conditions against which predictions derived The report suggests a method compaction specification
from various design approaches could be compared to for these compactors to be included in the SHW and in the
assess their reliability and economy. Highways Authority and Utilities Committee (HAUC)
There are a number of factors that influence the Specification for trench reinstatement. Recommendations
performance of reinforced earthworks, some of which are are also made for the particular operating procedures that
difficult to quantify accurately. This, coupled with the are required for these types of plant.
inter-dependence of some of the factors precludes a
definitive back analysis of the Performance, whether full 3.2 Chalk classification and compaction trials on the
scale structures or models. Nevertheless, the exercise A289 Wainscott Northern bypass
identified those factors that have a substantial effect on the
results obtained from the various methods of analysis. Authors: A F Toombs and R A Snowdon
The performance of the centrifuge models was shown to Project Report No: PR/CE/161/97
be highly dependent upon the strength of the underlying Date: 1997
clay foundation. The dependence was such that even a
small change in assumed strength (of say &2kN/mz) The MCHW 1 Series 600 Earthworks allows the majority
swamps any difference introduced by the method of of naturally occurring materials, and many waste materials,
analysis; furthermore it had a dramatic effect on the to be used in earthworks construction. Specifications for
strength of the reinforcement required to maintain stability. material Classification, acceptability and compaction are
It is therefore important, for economic and safety given to ensure these materials are selected and placed to
reasons, that the strength of the foundation soils is provide satisfactory long term performance. However, a
determined accurately at the site investigation stage. few problems have occurred with certain materials in
Recommendations on how this can be achieved should be differing geographical locations. There is a need to
provided in an Advice Note that covers the design and investigate these individual problems and their possible
construction of embankments on soft clay. It should be implications to the MCHW 1.
appreciated that the strength profile at many sites will be This particular project was established to provide advice
much more complex than that manufactured for the on the classification and compaction of chalk.
centrifuge models, and will be much more difficult Following a review by Greenwood (1 992) comparing
therefore to determine accurately. Far less emphasis should the French and UK methods of classifying, specifying and
be placed on the method of analysis as it is unlikely that compacting chalk, trials were required to validate the
the use of sophisticated methods of analysis, such as finite suggested modification to the MCHW and Advice Note
elements, could be justified for most highway works. HA 44 presented in the review. A suitable site containing a
Class 3 chalk, which met both sets of classification
requirements, was located on the A289 Wainscott
Theme 3
Northern bypass. Data on the states of compaction were
Compaction practice and equipment performance collected and analysed enabling a direct comparison of
3.1 The performance of machine-mounted compactors compaction methods.
The conclusions drawn from this study are as follows:
Authors: A F Toombs and D P Steele
Chalk can be classified using intact lump dry density
Project Report No: PR/GE/22/93 and natural moisture content as the classification
Date: 1993 criteria. The use of Chalk Crushing Value (CCV) should
be discontinued.
Research has been carried out to evaluate the application
and performance of machine-mounted compactors in the Construction control of chalk for general earthworks is
compaction of fill in confined spaces. These attachments recommended to be by moisture content alone provided
fall into two basic types, (i) vibrating wheels normally the material classification and engineering
fitted to the front forks of a wheeled excavatorAoader and characteristics have been determined at the ground
primarily intended for compacting backfill in narrow investigation stage. Intact lump dry density may be
trenches down to lOOmm in width and (ii) vibrating plates, introduced for specific control where chalk is required
which when fitted to the end of an articulated excavator or for selected fill.
backhoe arm of a loader, are capable of reaching and The new descriptive scheme for chalk proposed by
compacting in confined or restricted areas. Greenwood (1 992) should be adopted.

8
Recommendations are presented in the report for To investigate whether the flaked lime would be an
consideration as amendments to the clauses of the MCHW acceptable alternative to the SG60 lime, a laboratory trial
and Advice Note HA 44 current at the time to implement was carried out on two cohesive soils. Using the
the findings from the trials. procedures specified in the relevant British Standards,
soaked CBRs, dry densities, particle densities and moisture
Reference contents were measured and heave due to soaking was
observed for a 28 day period.
Greenwood J R (1992). Classification and specification
The reported results are divided into three stages,
of chalk for earthworks. Unpublished report by Travers namely stabilisation, compaction and CBR testing. Within
Morgan Consulting Group.
the range of Moisture Condition Values suggested for
acceptability in the Specification for Highway Works
Theme 4 (MCHW 1) and HA 44 (DRMB 4.1. I), the stabilisation
Lime stabilisation results for both soils are consistent. The compaction
results, as measured via dry densities and air voids, were
4.1 The effect of lime stabilisation on the MCV of two broadly similar when comparing SG60 and flaked lime
cohesive soils mixes and the CBR values were also consistent. The only
Authors: D P Steele and D J MacNeil obvious difference between the performance of the two
Project Report No: PR/GE/26/93 lime types is shown in their respective heave performance.
The flaked lime specimens heaved by up to 4.3mm more
Date: 1993
than the comparable SG60 specimens and took, with only
An investigation was carried out to assess the effect of one exception, between 2 and 14 days longer to reach a
lime stabilisation on the MCV of two cohesive soils. stable state.
Results of MCV calibrations against moisture content were In conclusion, the report indicates that stabilisation with
obtained for each material before and after stabilisation flaked lime results in a soil with similar handling
with standard SG60 Quicklime and are discussed. characteristics to a soil stabilised with SG60 lime; that the
The results of the investigation indicate that lime relative performance of comparable mixes were closely
stabilisation has a significant effect on the MCV moisture matched; that, even though the flaked lime mixes showed a
content calibration which reflects the change in the plastic tendency to heave more than comparable SG60 mixes, the
properties of the soils studied. The investigation has also magnitudes of the differences were relatively small, and
highlighted that it is possible to obtain an MCV, within the that the flaked lime will perform to a similar standard as
typical working range of MCV 8 to MCV 12, which lies the SG60 lime.
on the ‘dry leg’, as opposed to the normal ‘wet leg’, of the The report recommends that further research, possibly to
MCV calibration curve. As other research has shown that include other types of cohesive materials suitable for lime
material drier than MCV 12 on the wet leg is liable to stabilisation, should be undertaken to verify the
significant heave, the correct interpretation of an MCV preliminary results obtained during this study.
result is vital if unsuitable materials are not to be
mistakenly classed as acceptable for use in highway 4.3 A laboratory investigation of a lime stabilised
construction. capping layer failure
The report recommends that further research, to include
lime stabilisation of other suitable cohesive materials, is Authors: R A Snowdon, D J MacNeil and D P Steele
required to provide advice on the use of the MCV test for Project Report No: PR/CE/74/94
determining the acceptability of cohesive materials Date: 1994
stabilised with lime.
During the summer of 1989, lime stabilisation was used to
construct the capping layer on the M40 Banbury IV
4.2 Lime stabilisation of two cohesive soils using SG60
Contract. By the end of the following winter localised
quicklime and flaked quicklime
areas of the completed pavement were showing heaves up
Authors: D J MacNeil and D P Steele to 150mm.
Project Report No: PR/GE/27/93 Following the failure, an investigation was carried out
by the University of Birmingham with a brief to review the
Date: 1993
ground investigation report, site testing and construction
Most lime stabilisation projects use quicklime in the records and consider possible causes of the heave. Within
standard SG60 form, which is a fine ground, powdered the report conclusions, the primary cause of the heave was
lime. On larger projects, the design of the spreaders limits the formation of ettringite and thaumasite crystals due to
dust clouds during mixing. However, on smaller projects, increased sulphate levels, combined with a seepage of
for example slope stabilisation, access may be limited, water into the lime stabilised layer. The report also stated
resulting in the lime being spread directly from bags, that ‘the site monitoring records indicated that a
increasing the risk that lime dust can be blown onto considerable portion of the materials was compacted at the
construction staff and the surrounding area. In an attempt dry end of the specified range’: poor compaction would
to overcome this problem, Buxton Lime Industries have produce a material with high air voids, thus allowing
now produced a flaked version of the lime. ingress of water.

9
This report presents the results of a series of laboratory report. Porewater pressures were measured several times
studies focusing on the importance of site compaction per day by an array of automatically recording hydraulic
control and the effect of time on the properties of lime piezometers at depths from 0.5m to foundation level over
stabilised materials. Results from the TRL laboratory trials the full cross section of the slope. Rainfall was also
have demonstrated the importance of compacting lime measured by automatic rain gauges. Movement was
stabilised materials to an air void content of 5% or less. At measured on two sites by monthly inclinometer
this level of compaction, the probability of long term measurements. Also, automatic stereoscopic cameras were
heave will be reduced significantly for cohesive materials positioned to photograph the slopes daily to provide a
with a total sulphate level approaching the maximum record of any large scale movement. Long term records of
suggested in Advice Notes on the design and construction porewater pressure, rainfall and movement are presented
of lime stabilised capping. Also, the control of moisture for each site.
content using the Moisture Condition Value is the It has been found that porewater pressures in the upper
preferred method as the MCV is not affected by the 1.5m depth of soil vary in an annual cycle due to seasonal
changes in plasticity of the material that occur during the wetting and drying. Below this is a region of more stable,
stabilisation process. lower porewater pressure. In the two steeper slopes there is
a region of sub-atmospheric porewater pressure which
Theme 5 probably extends under the carriageway and tapers off
towards the toe of the slope. Except for two piezometers at
Earthworksperformance, maintenance and repair
2m depth at the Cambridge site there is very little evidence
5.1 An investigation of the mechanism of shallow that there is any long-term increase in porewater pressure
failure of Gault Clay embankment slopes at any depth within the slopes. This suggests that the
Authors: G I Crabb and D M Hiller pressure in all slopes is approximately in equilibrium with
the groundwater and infiltration. Therefore, the likelihood
Project Report No: PRJGEI30l93
of deeper seated future failures is low unless a path is
Date: 1993 created for deeper water ingress. Steps should therefore be
Shallow failures on the slopes of highway embankments taken to minimise water entry into a slope, such as care in
I. the design and installation of Carriageway drainage to
and cuttings, typically in the over-consolidated plastic
clays of southern England, are a common feature of trunk avoid run-off on to the crest of high slopes, and leakage
roads and motorways. To determine the extent of this within the slope. The presence of vegetation cover is an
problem and the factors contributing to failure, a survey of important part of the equilibrium of extraction of water
570km of motorway was carried out between 1980 and from the slope and infiltration.
1988 (Perry, 1989). The survey covered the principal Soil tests to determine both the peak and critical state, or
geologies encountered on the motorway system in England fully-softened, strength parameters have been carried out
1: at City University on soil samples recovered from each
and Wales and included about 21% of its total length. The
length of failed slopes found amounted to over 17km of site. Stability analyses using the observed geometries and
embankment and over 5.5km of cutting. porewater pressure show clearly that the appropriate
A typical shallow failure was found to be a slab slide strength parameters required to result in the limiting factor
extending from the crest to the toe of the slope. The depth of safety of 1.Oare at least as low as those for the critical
to the failure surface rarely exceeded 1Sm. The material state (or the fully softened) strength determined for the
with the highest percentage of failure, in both Gault Clay (qcrit = 23"). The factors of safety using peak
embankments and cuttings, was the Gault Clay. Nearly strength parameters are much too high to indicate that peak
half of the Gault Clay embankment slopes between 5.0m strength was achieved at failure. In the case of the slope at
and 7.5m high and with a slope angle of 1 in 2.5 had Dunton Green, which has not failed, the porewater
failed. Based on a maximum of one per cent failure, the pressures would need to rise significantly higher than
steepest slope recommended in Perry (1 989) for Gault measured to date to precipitate a failure. The assumption in
Clay embankments greater than 5m high is 1 in 5. design of any greater cp' or c' parameters derived from tests
The work described in the report was designed to give a on over-consolidated materials will inevitably yield
clearer understanding of the failure mechanism by the long erroneously high factors of safety.
term study of selected sites. The three sites chosen were Slopes in over-consolidated clay should be designed
Gault Clay embankment slopes over 6.5m high at slopes of therefore using the fully softened or critical state strength.
1 in 2, 1 in 3 and 1 in 4. The steeper slopes were adjacent This can be obtained from standard laboratory tests on
to existing failures and were judged therefore to be at risk fully reconstituted, normally consolidated materials, or
of failure in the near future. The flatter slope was chosen to alternatively from in situ material tested at much higher
compare its porewater pressure regime with those of the confining stresses than those normally used so that it
steeper slopes and assess its stability using equivalent behaves as a normally consolidated material.
strength parameters. It is clear that these are long term, drained failures. The
One steeper slope was monitored from 1984 until 1988 mechanism is a combination of two effects. The first is the
and the other from 1985 until 1989, during which times swelling and softening of the near surface material, which
failures occurred at both sites. The remaining unfailed under the influence of shear strains in the slope, reduces its
slope was monitored from 1985 to the production of this strength towards the critical state. The most highly stressed

10
regions will reach failure first and progressively shed load, with rainfall in the first 10 months some 29.4% above
as the strength reduces, to other lower stressed regions. average. Taking the worst credible porewater pressures
This mechanism of progressive failure may play a part in based on the measured data, the potential failure surface
shallow slope failures and should be the subject of future considered in PWGE/30/93, and using the same method
work. The second is the equilibrium of infiltration of of stability analysis, resulted in a factor of safety of 1.06.
rainwater from the slope surface with flow through the This is lower than that reported previously and indicated
slope and evapo-transpiration at the surface. that the slope had only a small margin of safety under
The depth of the failure surface is controlled by the conditions of high rainfall.
resulting distribution of porewater pressure. Deeper failure
surfaces are unlikely to develop because the porewater 5.3 The repair of a highway embankment by grout
pressure reduces with depth and showed little change injection
during the monitoring period.
The sites studied provide some evidence that the porewater Authors: D G Boden, K C Brady and D J Ayres
pressure in the near surface zone may be slightly higher in Project Report No: PWGE/8/93
slopes that are less steep, but that this effect is balanced by the Date: 1993
increase in stability resulting from geometry.
Shallow slip failures are a common feature on the trunk
road and motorway network in the UK; a survey of the LJK
Reference motorway network by Perry (1 989), showed that a further
Perry J (1989). A survey of slope condition on motorway 65km of slopes were likely to fail. The cost of their repair
earthworks in England and Wales. Research Report RR199. represents a substantial expenditure to the Highways
Crowthome: TRL Limited. Agency. This report briefly describes the use of grout
injection techniques to repair earthworks, followed by a
5.2 Monitoring of a Gault Clay embankment slope at description of the A45 site and details of the repair work.
Dunton Green Although grout injection has been widely used to repair
slope failures on railway earthworks, the technique does not
Author: G I Crabb appear to have been used to repair highway earthworks. The
Project Report No: PWCE/81/94 grout injection technique was used to repair a section of
Date: 1994 failed embankment on the A45 north of Cambridge, in order
to assess the effectiveness and economy of the technique.
This report is a supplement to the unpublished TRL Project The slope was 45 metres long and up to seven metres high,
Report PWGE/30/93 (see previous summary 5.1) which with side slopes of 1:2, and was formed from over-
described a project, begun in December 1983, to investigate consolidated Gault Clay. The slip surface was about 1.5
the shallow failure of highway earthwork slopes. The report metres deep. The main purpose of the works was to regrade
described a long term study of selected sites and gave a and stabilise the shallow slope failure, but a secondary
clearer understanding of the failure mechanisms involved. interest was the use of deep grout injection to prevent deep
The three sites chosen were Gault Clay embankment slopes seated failure of highway earthworks.
over 6.5m high at slope angles of 1 in 2, 1 in 3 and 1 in 4. The grout injection technique involves the injection of
The two steeper slopes, at Cambridge on the A45 and aerated cementitious grout under pressure, through hollow
Nepicar on the M26, were adjacent to existing failures and steel tubes, into the regraded slope. The steel tubes are
were therefore judged to be at risk of failure in the near driven vertically in a pattern across the slope and holes are
future. The failure of these slopes is described in the earlier not grouted until the grout injected into adjacent holes has
report. The Cambridge slope was monitored from 1984 until gained sufficient strength to maintain slope stability. In total
1988 and that at Nepicar from 1985 until 1989. 912 batches of grout, each of 0.1lm3,were injected at 21 1
The third and flattest slope at Dunton Green on the M26 points on the slope over 22 working days. In all, 23 tonnes
was chosen to compare its porewater pressure regime with of ordinary portland cement, 69 tonnes of sand and 300
those of the steeper slopes and assess its stability using litres of foaminglstabilising agent were used. No problems
equivalent strength parameters. Porewater pressures were were caused by grout migration during the works.
measured several times per day from 1985 to 1994 by an The grout was successfully injected into the region of the
array of automatically recording hydraulic piezometers at slip planes, at about 1.5 metres depth. However, the high
depths from 0.5m to foundation level over the full cross strength of the intact clay prevented effective penetration of
section of the slope. Movement was measured by sets of grout at points deeper then about 3.5 metres. The programme
monthly inclinometer measurements. Automatic daily of deep injection was abandoned midway through the works,
photography of the slope has provided a record of any and so the use of the technique to prevent deeper seated
large scale movement. Updated long term records of failures of highway embankments seems limited. No uplift of
porewater pressure, rainfall and movement are presented the road pavement was noted during the site works and no
for the whole of the measurement history. movement of the face of the slope or the pavement was
The data suggest that there were changes in the slope recorded in the 18 months or so following the end of the
between 1992 and the production of this report in 1994. grouting operations. The injection of grout initially stabilised
This is as a result of a progression from several years the shallow translational slide, but partial failure occurred
with rainfall as much as 39% below average to 1994, after four years (see following summary 5.4).

11
The cost of the site work was about €870 per metre run The embankment on the Cambridge Northern Bypass
of embankment. The cost of the grout injection, net of provided a useful test of six reinstatement and two
ancillary works, was about E450 per metre run; this was 50 preventative techniques. Two sections have failed,
per cent higher than the cost of reinstating failed slopes movements are continuing in another, and other sections
using geotextile reinforcement. The cost of grout injection have given rise to maintenance problems. The geo-mesh
may reduce as experience is gained through usage and, plus anchors section showed signs of distress at an early
unlike other methods of reinstating highway earthworks, stage but it was some 10 years before it failed completely.
the technique can be used without excavating an unstable As the adjacent control section failed after five years, it
slope. In addition, the technique can be used on sites with can be concluded that the geo-mesh plus anchors slowed
limited access and limited stockpile area, since the slope down failure but was unable to prevent it. Part of the grout
repair can be carried out from the slope. Thus grout injection section failed within four years of construction.
injection techniques may find some application in the The granular replacement, lime stabilisation, gabion wall,
repair of highway earthworks. The main restriction on the anchored tyre wall and geosynthetic containment
technique is that the soil comprising the failed slope must
reinstatement techniques have provided stable repairs. The
be dry enough to be dragged back to profile before
use of rock ribs has prevented further failures along a
grouting commences. Care must be taken in controlling
section of the embankment and this section was not unduly
grout migration; provision must be made in protecting road
affected by the failure of an adjacent section. The three
drainage gulleys and other underground services.
The use of grout injection for the prevention of deep most cost effective techniques are, in order of increasing
seated slips requires hrther study and more powerful plant cost, rock ribs, geosynthetic containment and lime
would have to be used. However, the frequency of deep stabilisation. Further research into the use of rock ribs
seated long term slips on highway earthworks is low. seems warranted, as this may provide further savings in
maintenance costs.
Reference
5.5 Performance of the polystyrene fill embankment on
Perry J (1989). A survey of slope condition on motorway
the A120 Dovercourt bypass
earthworks in England and Wales. Research Report
RR199. Crowthorne: TRL Limited. Authors: K Raby and R A Snowdon
Project Report No: PIWE194197
5.4 Performance of slope maintenance and repair Date: 1997
techniques on the Cambridge Northern bypass
Earthworks on highway schemes are constructed to the
Author: D G Boden Specification for Highway Works. In order to meet the
Project Report No: PRJCE/52/95 demands for new construction techniques, and a wider use
Date: 1995 of fill materials, research is required to enable their
performance and acceptability requirements to be
Shallow slip failures on the slopes of cuttings and
established. The project spans a range of individual studies
embankments are a common feature of the trunk road
network in the UK, and the cost of their reinstatement covering the use of lime stabilisation of cohesive materials,
represents a substantial expenditure for the Highways the use of recycled and waste materials for capping layers,
Agency. Failures can undermine the road structure damage the use of polystyrene ultra-lightweight fill on poor
drainage, cabling and safety fences, and occasionally ground, vegetation for the prevention of shallow slope
obstruct the hard shoulder of the carriageway. failure, and the general requirements for compaction
Following its construction in the late 1970s, numerous specifications and material acceptability limits. All of these
failures have occurred along the slopes of the embankments will lead to greater economic efficiency in highway
supporting the Cambridge Northern Bypass A14 (formerly construction when implemented through the SHW and
the A45). The embankments, which are up to 8 metres high, departmental Advice Notes.
were Constructed from the locally available over- As part of the study into the use of polystyrene fill for
consolidated Gault Clay. Typically the failures have been embankments on poor load bearing ground, an opportunity
shallow translational slides. During the winter of 1983/84, arose to continue monitoring the post construction
TRL in conjunction with the then Eastern Regional Oflice performance of such an embankment on the A120
of the DOT and Cambridgeshire County Council, used five Dovercourt bypass. The report describes the long term
repair and two strengthening techniques along a length of performance of the embankment.
embankment on the bypass near Cambridge. A section was Extensive foundation treatments were required before
left untreated to act as a control, but this section failed construction of two approach embankments, on very soft
subsequently and was repaired in 1991 using grout injection alluvial deposits, to a bridge crossing an existing railway line.
(see previous summary 5.3). Whilst one of the embankments could be constructed using a
TRL has undertaken site surveys from time to time to conventional granular fill, it was necessary to construct the
monitor the performance of the embankment. This report other using an ultra-lightweight polystyrene fill in order to
gives a brief description of the site, details of the repair minimise differential settlements occumng at the bridge
and strengthening techniques used, and a summary of their abutments. In order to control placement of the fill during
performance up to November 1994. construction,instrumentationwas installed to monitor pore

12
water pressures and ground movement. Following produced by TRL on the subject over the last few decades,
construction some of the instrumentationwas used to measure including appraisals of the methods of analysis and of the
the longer term performance of the embankments. options available for construction and repair.
Apart from difficulty in handling the polyester Since the mid 1980s or so there has been a rapid growth
membrane which was used for protection against in continental Europe of the use of reinforced soil
hydrocarbon spillage, no significant problems occurred techniques to steepen earthwork slopes, but the take up of
during construction. The polystyrene embankment was the technique in the UK seemed to be restricted by the
monitored for approximately five years after construction. paucity of information on the design of these types of
Although settlement continued for a longer period than structure. To remove this restraint, the Department of
expected, settlement values recorded show that the Transport issued Advice Note HA68 (DMRB 4.1.4) in
embankment performed within the predicted range of 1994. In early 1995 a designer in Scotland expressed
values. As the rate of settlement has virtually reached zero concern that the design procedures outlined in HA68 may
no further significant settlement is anticipated. not provide sufficient pull out resistance for all potential
Using polystyrene fill allowed the embankment to be failure mechanisms. TRL was thus commissioned to
constructed to its full height without any intermediate investigate their concerns.
consolidation stages, as would have been required with HA68 describes the use of a two part wedge mechanism
conventional granular fill materials. Only minimal to determine the disturbing forces in a steepened slope. The
maintenance of the camageway has been required on both mechanism providing the maximum disturbing force (T-)
embankments at the bridge abutments. determines the amount of reinforcement needed to resist
rupture, and the mechanism requiring no restoring force
Theme 6 (Tab) determines the extent of the reinforced zone. The
designer’s enquiry related to the possibility of mechanisms
Steepened slope design and performance occumng which have a lower factor of safety against pull
6.1 Reinforced slopes and embankments out failure than that provided by the ‘extreme’ mechanisms
(T- and To,,). In support of their submission, the designer
Authors: K C Brady, W McMahon and D G Boden
provided details of analysis camed out during the appraisal
Project Report No: PR/CE/5 1/97 of the soil nail trials undertaken at Tinney Bank.
Date: 1997 The two part wedge mechanisms presented by the
designer were shown to have adequate pull out resistance,
The use of geosynthetics as reinforcement to soils has
but other mechanisms were found for both horizontal and
increased dramatically over the past decade and the use
inclined reinforcement which have an out of balance force
of reinforced soils is now perceived as the standard
exceeding the available pull out resistance provided by the
method for repairing failed slopes. Increased use has
reinforcement. The problem only seems to arise for
demanded the continued development and revision of
mechanisms lying close to the To, mechanism and the
Design Standards, Advice Notes, approval certificates
difference between the out of balance force and the
and specifications governing usage. This project was set
available pull out resistance was always small. From the
up to provide advice and input to the generation of such
limited design examples considered as part of this reported
documents and also to provide advice on problems that
project, it would appear that soil nails are more likely to be
may arise on highway projects.
sensitive to the problem of inadequate pull out resistance
Design methods for the reinforcement of highway slopes
by reinforced soil and soil nailing techniques (HA 68/94) than are horizontal geosynthetic reinforcements. Appendix
and other Design Standards and specifications covering the
G of HA68 advises checking for the existence of
use of geosynthetic reinforcements are now in place. The mechanisms likely to have an out of balance force
project focused on specification of the mechanical exceeding the available pull out resistance, but gives little
guidance on how this can be done. Such mechanisms can
properties of geosynthetics, in particular their ability to
withstand compaction operations. European standards be found using spot checks or an automatic grid search,
covering testing, design and installation procedures have but these checks may take some considerable time. Checks
been studied. can be carried out by hand but they are demanding of the
designer and a spreadsheet or computer program is
essential for such work.
6.2 A review of the adequacy of HA68 for designing In most of the cases where mechanisms having
steepened slopes insufficient pull out resistance were found, a satisfactory
Author: D G Boden solution would have been reached if one or more of the
Project Report No: PR/CE/107/96 following measures had been applicable:
0 The pull out resistance of the basal layer had been
Date: 1996
mobilised (i.e. if a structural facing or wrap around was
One of the longer term research programmes undertaken at used).
TRL has concerned the design, construction and repair of 0 The basal layers of reinforcement were lengthened.
highway slopes. This work has been prompted by the need
for economic road construction and more recently A lower value of the direct shear factor had been
motorway widening. A number of reports have been adopted.

13
To ensure that design carried out to the rules given in The construction of embankments on weak
HA68 provide adequate pull out resistance, consideration compressible ground presented problems of both stability
should be given to the following: and serviceability and therefore a number of construction
0 Expanding the guidance given in Appendix G of HA68. expedients were employed. These included: the installation
This could include advice on how to complete spot checks of vertical drains to accelerate the rate of dissipation of
and grid searches, and could be done in conjunction with a excess pore water pressures; the installation of instruments
worked example included in Appendix J. to monitor the pore water pressures and deformations
0 Changing the semi-empirical rules governing the extent
within the subsoils; the incorporation of a layer of
of the reinforced zone. reinforcement at the base of the embankments to increase
stability during construction; and the placement of a
0 Giving prominence to the advice for checking pull out
surcharge layer of soil to accelerate primary consolidation
resistance.
and also to reduce in-service creep movements.
An additional outcome of this report is that The experience of the construction of the embankments
consideration should be given to the release of an updated on the A414 bears testimony to the economy of the
version of HA68 to enhance its utility by improving its techniques used. In both cases, the total cost of the
readability and to provide a better balance between the construction expedients was far outweighed by the savings
advice given in the main text and in its appendices. accruing from their application. The successful application
of these techniques on this section of highway should
6.3 Aspects of the design and construction of two promote their use on future works and thereby provide
reinforced embankments on the A414 substantial savings in construction costs.
Authors: K C Brady, W McMahon and D G Boden
Project Report No: PR/CE/64/96 Theme 7
Date: 1996 Stabilisation of slopes by bio-engineering techniques
Another of the longer term research programmes 7.1 Review of plant species for the improvement of
undertaken at TRL has concerned the design and slope stability
construction of embankments over weak compressible Author: C A Mamott
ground. This work has been prompted by the requirements
of land conservation and environmental concerns which Project Report No: PR/CE/97/96
have increasingly meant that new sections of highway are Date: 1996
restricted to corridors of land deemed unsuitable for Shallow slip failures on embankments and cutting are more
housing, industry or agriculture. A number of Laboratory likely to occur in certain materials as identified during the
Reports were produced on the subject in the 1970s, survey of slope condition on motorway earthworks, reported
including appraisals of the methods of analysis and of the in Research Report RR199. The reinstatement of these
options available for construction.
shallow failures can be costly and the potential for slip may
More recently, geosynthetics have been used as basal
be reduced by the use of vegetation planted to provide
reinforcements to embankments, and although a number of
reinforcement,through the plant root system, and a reduction
methods have been proposed for analysing the performance
in moisture content and pore water pressure. However, there
of such structures, their usefulness for routine design is
is a potential conflict between the engineering requirements
largely untested. To assess the validity and economy of the
of cut as well as fill materials to maintain stability and the
proposed methods, a series of centrifuge models was
conditions required to promote plant growth.
commissioned from the University of Cambridge (see
The use of vegetation will increase environmental
previous summary 2.4), and data have been collected from
mitigation and reduce the need for costly maintenance of
two instrumented reinforced embankments on the A4 14;
thus both ultimate and serviceability limits states have been shallow slip failures on highways embankments and
investigated. The report describes aspects of the design and cuttings. More appropriate planting regimes will reduce
construction of the two instrumented reinforced the requirement for replacement planting.
embankments on the A414. This report presents the results of a literature review
The A414 is a primary east-west route linking a number undertaken as the first phase of a project designed to:
of towns around the north of London and crossing arterial 0 Identify potential species which can be used to stabilise

roads radiating from the capital. The development of these cohesive clay soils which show high percentage of slip
towns and the consequential growth in road traffic failures and were identified in Research Report RR199.
demanded the upgrading of this highway, but environmental Provide information on their handling, planting and long
considerations meant that new sections of road had to be term maintenance.
constructed over poor ground. The search for cost effective
Provide advice on the associated economics.
solutions led Hertfordshire County Council (HCC) to
commission the construction of reinforced embankments for The principal aim of this review was to identify a
the Stanstead Abbotts bypass and for the Stanstead Abbotts selection of plant species to be use in controlled environment
to Harlow section of the A414. trials to determine their growth in over-consolidatedclay

14
soils. The review addresses the problem of slope failures on any major problems. Other systems, which rely on the
clay embankments and discusses the characteristicsthat are vegetation to assume the role of providing long term face
required in vegetation to stabilise slopes, particularly in reinforcement, to prevent erosion when the support
relation to the role of roots in soil reinforcement and reduction provided by the biodegradable facing fails, may require
in moisture content. It also takes into account specific changes in construction methods for new work.
requirements of vegetation growing alongside highways, such Also, long term maintenance requirements need to be
as salt tolerance and resistance to pollution from exhaust considered during the design stage and repair techniques
fiunes. This information is used to identify several species of will need to be developed for use on existing walls.
potential value in improving slope stability of over- Whilst each highway widening scheme will be site
consolidated clay embankments and cuttings, from which specific in terms of its location, slope geometry and aspect,
twenty five species have been selected for the growth trials in there are general points that should be considered during
fill materials consisting of Gault Clay and cohesive units of the design stage when reinforced vegetated slopes are to be
the Reading Beds (Lambeth Group). used. As yet, some of these points have to be addressed
and will only be solved in the longer term as this use of
7.2 Vegetated reinforced steep slopes vegetation expands.

Author: R A Snowdon 7.3 Vegetation for slope stability: Construction of a


Project Report No: PR/CE/177/97 trial embankment
Customer: Highways Agency Authors: R A Snowdon, D J MacNeil and A H Brookes
Date: 1997 Project Report No: PR/CE/3/98
As a result of the motorway widening programme there is Date: 1998
an increase in the use of steep reinforced slopes which
include vegetation to prevent erosion at the face, in addition The construction by TRL of a trial embankment has
provided a typical highway earthworks slope which will
to providing a completed structure that is environmentally
acceptable. An evaluation of the methods used to establish enable a long term study on the growth of vegetation and
its effects on the stabilisation of shallow slips, on an over-
vegetation, and the problems encountered, on these steep
consolidated cohesive fill.
reinforced slopes was required.
Based on results from ongoing vegetation trials, selected
Over recent years, the requirement for motorway
species of trees, shrubs and perennial plants have been
widening has led to an application of reinforced steepened
planted in individual panels on the north and south facing
slopes. This has allowed the steepening of existing
1 :2 side slopes of an embankment constructed from
earthworks slopes, up to 70°, to accommodate extra
Reading Beds (Lambeth Group) cohesive fill.
carriageway lanes within the existing motorway land
Instrumentation has been installed to monitor any changes
comdors. Whilst the use of these types of construction is
in pore water pressure resulting from vegetation effects.
significantly cheaper than hard structures, e.g. concrete,
Initial results in 1997 showed that the trees and shrubs
evidence of their early life performance shows a wide range
generally survived their first season, but suffered from the
of success and failure in the establishment of vegetation.
exceptionally hot dry spring. The lower growing
Vegetation can play an important role in preventing
perennials also succumbed to competition with the grasses.
shallow slip failures in earthworks slopes by the removal
Apart from a trend in increased suction below 0.75m depth
of excess moisture from the embankment, or cutting, and
during the summer months, and marginally higher suctions
by providing tensile reinforcement through the roots.
on the north facing slope, no defined patterns appeared
However, when applied to steep reinforced slopes, the lack
from the pore water pressure measurements to enable any
of available moisture becomes the primary problem in
specific effects of the trees, shrubs or perennial plants on
establishing and successfully maintaining the required
the moisture rkgime to be identified.
level of vegetation for reinforcement when biodegradable
The long term monitoring phase of the trial was completed
facing material has ceased to function.
in November 2000, with any significant data obtained during
A survey of vegetated reinforced slopes, and subsequent the trial of the effects of vegetation on the stability of side
follow-up discussions with consultants, contractors and slopes fed into the findings from other ongoing research
manufacturers, illustrated highly variable success rates in projects relating to the use of vegetation on highway slopes
establishing these vegetated slopes. Lack of sufficient for implementation through relevant Advice Notes.
moisture, coupled with a southerly orientation of the face
were the primary causes for failure of the vegetation. A
combination of the lack of available water due to rainfall 7.4 Live willow poles for slope stabilisation on the A249
run-off and desiccation within the top soil can create a at Iwade
hostile micro-climate. Author: D H Barker
Systems which use a reinforcing geotextile for soil Project Report No: PR/CE/133/97
retention may only require vegetation to provide an
aesthetic facing and a long term barrier to ultra-violet Date: 1997
degradation. It is envisaged that planting in both new and This project involved the incorporation of some 500 live
existing slopes at the layer interfaces should not present willow poles in a new cutting slope on the A249 Iwade

15
improvement scheme to enhance the existing level of
stability in the cut slope. The poles were installed to
augment the buttressing action of a series of counterfort
drains along an 80m length of south-east facing slope.
Other drainage measures were incorporated at the crest of
the slope to intercept surface water flow from a nearby
farm. The 1 in 3 slope was cut in the Lambeth Group
(Woolwich Beds Clay overlying Woolwich Beds Sands)
containing discontinuous sub-horizontal shear surfaces.
Some occasional seepage had been recorded during a site
investigation in 1987.
Following the installation of the poles during the late
spring of 1996, two visits were made to the site to carry
out monitoring of pole condition and root growth in spring
1997. Whilst the percentage of live poles is somewhat
lower than could be expected, the low survival rate can be
attributed to a number of factors specific to this site. These
relate to significant changes in the slope’s moisture rkgime
combined with some problems encountered with the pole
installation methods and handling of the live poles.
However, valuable information has been gained during the
early life of this trial which will be applicable to future
schemes using live willow poles for the enhancement of
slope stability.
In addition to the points relating to the A249 Iwade trial,
there is a more general need for specific trials to study the
mechanism of root development of live willow poles under
a range of differing soil types and moisture regimes. This
would then allow uprooted samples to be tested at various
stages of root development, both in the short and long
term. Such information would not only enhance
knowledge of the effects of vegetation, but would also be
useful if live poles were to be considered as a form of
vegetated soil nailing in the prevention of shallow slips on
highway embankment and cutting slopes.
This trial is scheme specific and will continue to be
monitored, including both the performance of the willow
poles and the geotechnical instrumentation installed in the
slope. Whilst the information in the report can be applied
to any future scheme using this technique, insufficient data
exists from this reported study for implementation through
Highways Agency Advice Notes.

16
summarised in this

so oftdirect relevance to spqcialists

le, W Mc,Mi$on and D R Carde;.

TU508 M FIille$anj D J MacNeil.


(I I

ood and J R Crabtree (Macaulay

nd Walesby J Perry.

344 770783 or 770784,

,x ab i

17

You might also like