You are on page 1of 25

U

'F
iI
mmiurl 01 4
- PS-
Airports
24.9. I Aerodrome (airfield or airport) 24/23 24.9. I3 Runway effective slope 24/23
24.9.2 Aerodrome beacon 24/23 24.9.14 Shoulder 24/23
24.9.3 Aerodrome elevation 24/23 24.9.15 Stopway 24/23
24.9.4 Aerodrome reference point 24/23 24.9.16 Strip 24/24
24.9.5 Aerodrome reference field length 24/23 24.9.17 Taxiway 24/24
24.9.6 Apron 24/23 24.9.18 Threshold 24/24
24.9.7 Barette 24/23
24.9.8 Clearway 24/23 References 24/24
24.9.9 Crosswind component 24/23
24.9.10 Instrument approach runway 24/23 Bibliography 24/24
24.9.11 Non-instrument runway 24/23
24.9. I2 Obstacle 24/23
Airport location 2413

24.1 Introduction (4) Financial appraisal.


(5) Airspace.
The planning and design of an airport is complex and involves (6) Topography.
specialists in airport planning, traffic forecasting, aeronautical (7) Obstructions to aircraft operations.
ground lighting, telecommunications and navigational aids, air (8) Meteorology.
traffic control, baggage handling, and many other activities. The (9) Construction problems.
development of an airport will involve architects, structural, (10) Utility services.
electrical, mechanical and telecommunications engineers, plan-
ners, economists, interior designers, quantity surveyors and There is no particular order in which these should always be
other specialists, as well as civil engineers. considered, and there are few fundamental criteria to provide a
Traditionally, civil engineers have played a major role in the clear basis for rejection of a site from further consideration,
development of airports and the co-ordination and management other than perhaps the intrusion of unacceptable obstructions
of all the disciplines involved. This is, perhaps, because so many into the approach surfaces. There are clearly wide variations
aspects of civil engineering have always been involved, such as between what might be an acceptable site high in the Andes, in
the design of loadbearing pavements, access roads and car the desert of Jordan, on the southern tip of Shetland, QI on the
parks, surface water drainage, water supply, fire-fighting mains, shores of Loch Neagh. An initial selection of sites for subse-
foul drainage (including sewage treatment), as well as major quent comparative analysis has to be made in the knowledge of
building structures. these factors, but the final selection is made from an objective
Airports have been required to cope with the increase in comparison of each.
passenger traffic, the number of aircraft movements, and the size
and weight of aircraft. The character of the airport has also
changed, with greater emphasis on security, safety, comfort and 24.2.2.1 Passenger catchment area
convenience of passengers, efficiency and economical operation, Where regional airports are concerned, a journey time of about
and with the need for the involvement of more specialists in 45min from a centre of population is normally considered
their planning and design. acceptable. In developed countries it will be necessary to assess
In order to consider the civil engineering aspects of an airport the effect on journey time of any planned improvement or new
in perspective, reference is made in this chapter to the location, highways. In less developed countries, it may be necessary to
standards and general concepts of airports, as well as to the consider the effect the airport may have on the existing highway
other facilities which together make an airport. Only those system.
aspects of civil engineering which are particular to airports are A major international airport will attract passengers from a
dealt with in detail. much wider catchment area. including those using feeder air
routes from regional airports, and the proximity to a centre of
population may be less critical.
24.2 Airport location

24.2.1 Basic considerations 24.2.2.2 Environment


The site selected for a new airport development must be capable An airport affects the environment in three major ways,
of providing the longest possible useful life in order to secure the through: (1) land use; (2) noise and (3) ecology.
maximum return on the large investments which are required In the UK most existing airports have been developed from
for its development. Many factors require examination in order wartime airfields. Where new sites have been sought, as for the
to determine the most suitable site, but before consideration is third London Airport, there have been objections and lengthy
given to the criteria involved, it is necessary to define the inquiries, essentially on these environmental issues. In develop-
purpose for which the airport is required, and the size of the ing countries the emphasis is likely to be different.
facilities to suit this requirement. The area required by an airport is large. A modest regional
The need for an airport might be because: ( I ) none exists and airport may occupy 450 ha; a major international airport might
it is believed air services will meet a specific physical or require SO00 ha. Unfortunately, one of the requirements for an
economic demand; (2) an existing airport cannot be expanded to airport site, namely relatively flat and well-drained land, is often
meet growing traffic; or (3) an existing site has become environ- also the best agricultural land in an area, or alternatively is an
mentally unacceptable. area suitably distant from a population centre to be designated
The facilities to be accommodated and considered will include for industrial use.
the length and direction of the runway, the number of runways, To avoid these conflicts, areas unsuitable for other use need to
the terminal building and apron, and ancillary requirements be looked at. Such sites may involve major earthwork problems
such as cargo handling, airport maintenance, catering and car as, for example, the site being considered for the new Bangkok
parking. The scale of these facilities and, hence, the overall area Airport, which is largely waterlogged, or incur the possibility of
of land needed for the airport site, will be assessed in relation to disturbing the natuhl ecological balance, as was a major
national or regional planning of airspace use (if such exists), objection to proposals for the proposed development of the
traffic forecasts, and an assessment of aircraft types appropriate third London Airport at Maplin.
to predicted use. Noise became a major environmental issue in the 1960s and
1970s and is an important aspect of airport planning. Certifica-
24.2.2 Criteria for comparative analysis of sites tion procedures introduced by the International Civil Aviation
Organization (ICAO) in 1972 have resulted in a new generation
The essential factors to be considered in selection of an airport of quieter aircraft, such as the Boeing 757, introduced into
site include: service by British Airways on domestic routes in the UK early in
1983. It is no longer permissible for earlier and noisier aircraft,
( I ) Passenger catchment area. such as the Trident and the BA 1-1 I, to be used in the UK. Such
(2) Environment. improvements and restrictions are unlikely to apply to develop
(3) Economic appraisal. ing countries for many years.
2414 Airports
24.2.2.3 Economic appraisal may be critical if there is the possibility of aircraft operations
An economic appraisal compares the total cost of each site to conflicting with operations from an adjacent airport, particu-
the whole community.The comparison will take into account: larly if this is sited across a national border in another country.
( I ) the capital cost of site acquisition and construction; (2) Otherwise, air traffic control services, and particularly landing
access to the airport by airport employees; (3) access for and take-off procedures, can usually be adapted to meet the
passengers and cargo; (4) noise and other environmental fac- particular site requirements.
tors; and ( 5 ) operation of the airport. These costs will be offset
by the revenue earned directly by the airport operator, the 24.2.2.6 Topography
airlines, and airport-associated and airport-attached businesses.
Many of these will be the same regardless of the site, but others For the purpose of comparison of several sites it is not neces-
may be affected considerably. sary, initially, to quantify the amount of work required to
construct the airport on that site. It is necessary to compare the
advantages and disadvantages and to identify any difficulties.
24.2.2.4 Financial appraisal Ideally, an airport should be located on relatively flat ground,
A financial appraisal compares alternative sites on the basis of having effective natural drainage. The site should not be
the capital costs of development only, although it can be hemmed-in by hills, rivers, roads or development which may
considered as including direct costs and revenues related to hinder future expansion, or form potential obstructions to
operating the airport, loan receipts, repayments and interest aircraft approaching or departing.
charges. The assessment can be made largely from examination of
existing maps and aerial photographs, but an inspection of the
site should be considered essential.
24.2.2.5 Airspace
All countries who are members of ICAO, have a government
authority responsible for Air Traffic Control. In the UK, 24.2.2.7 Obstructions to aircraft operations ,
National Air Traffic Services (NATS) is responsible and pro- Objects which project above the imaginary obstruction surfaces
vides a combined service to both the Civil Aviation Authority (Figure 24.1') are classified as obstructions and will need to be
(CAA) and the Ministry of Defence. The siting of an airport removed if possible, or marked, if a particular site is chosen and

Outer limits of conical surface


are such that the height of the
surface here is b above the
inner horizontal surface
Figure 24.1 Plan view of obstruction surface (second and
horizontal sections of approach surface for non-precision and
precision approach are not shown for clarity)
Standards 2415
Table 24.1 Aerodrome reference codes

Code Element I Code Element 2

Code Aeroplane reference field length Code Wing span Outer main gear. wheel span
number letter

1 2 3 4 5
1 Less than 800 m A Up to but not including I5 m Up to but not including 4.5 m
2 800 m up to but not including B I5 m up to but not including 24 m 4.5 m up to but not including 6 m
1200 m
3 1200 m up to but not including C 24 m up to but not including 36 m 6 m up to but not including 9 m
1800 m
4 1800 m and over D 36 m up to but not including 52 m 9 m up to but not including 14 m
E 52 m up to but not including 60 m 9 m up to but not including 14 m
*Distana bctwan the outside alga of the main gear whals

developed. At .a. stage of initial site appraisal, possibly before 24.3.1 Airport reference codes
even the alignment of a runway has been determined, it is the
potential of objects becoming obstructions which needs to be From 24 November 1983, ICAO Annex 14' was subject to
assessed, together with the degree of problems they could create amendment. Two-element reference codes, incorporating
in terms of removal or by inhibiting the location or alignment of numbers 1 to 4 together with letters A to E are now assigned to
a runway. airports depending on the main runway length, aircraft wing
span and outer main gear wheel span in accordance with Table
24.1.
24.2.2.8 Meteorology
For any site to be appraised properly, meteorological records of 24.3.2 Runway length
wind direction, strength and frequency, together with visibility
range and cloudbase height are necessary. This information The actual runway length should be adequate to meet the
provides the data for determining the runway alignment, and operations requirements of the aeroplanes for which the runway
the need for and type of approach aids needed to provide the is intended and should not be less than the longest length
required level of usability. determined by applying the corrections for local conditions to
There is usually sufficient data available in the general vicinity the operations and performance characteristics of the relevant
of an airport site in the UK for a valid interpolation to be made. aeroplanes.
This is frequently not the case in developing countries. It may be noted that the actual runway length can be reduced
within certain limits if a stopway or clearway is provided.
Further comment on the design of runway length is made in
24.2.2.9 Construction problems sections 24.4.3 and 24.4.4.
Any particularly difficult construction can usually be recognized
in the initial stages of appraising a site. Such a problem in the 24.3.3 Runway width
UK is usually limited to the particular site characteristics, which
may be poor soil conditions or bad drainage. In other countries The width of a runway should not be less than the appropriate
these difficulties may extend to difficulties of access and lack of dimensions in Table 24.2.
suitable materials for construction.

Table 24.2 Runway widths (m)


24.3 Standards
Code letter
Details of international requirements for the layout of airfields
are covered in the ICAO Standards and recommended practices Code
for aerodromes,' Annex 14, and this publication is revised number A E C D E
periodically. Any aerodrome (airfield or airport) requires a
licence to accept a commercial service. The technical and other 1 18 18 23 - -
requirements for the licensing of a site on an aerodrome in the 2 23 23 30 - -
UK are incorporated in Civil Aviation Publication CAP 168, 3 30 30 30 45 -
Licensing of aerodromes, published by the CAA.' In general, this 4 - - 45 45 45
conforms with and amplifies the information given in ICAO
Annex 14, except for certain modifications which have been Nore: The width of precision approach runway code number I or 2 should bc not
found appropriate to aerodromes in the UK. less than 30 m.
The detailed standards and recommendations regarding air-
port layout, including recommendations for length, clearance
and for the vertical alignment of runways and taxiways are
given in Annex 14 with respect to the various airport reference 24.3.4 Runway vertical alignment
codes. The following excerpts from Annex 14 are given for
guidance only and reference should be made to Annex 14' or Recommendations in relation to the various components of
CAP 1682 for full details. vertical alignment are given in Table 24.3.
2416 Airports
Table 24.3 Runway vertical alignment Table 24.5 Taxiway widths

Code letter Taxiway


width ( m ) Code letter
4 3 2 1
23 E or D and the taxiway is intended to be used
Maximum effective slope I% I% 2% 2% by aeroplanes with an outer main gear wheel
Maximum slope 1.25% 1.5% 2% 2% span equal to of greater than 9 m.
Maximum change between 18 D and the taxiway is intended to be used by
consecutive slopes 1.5% 1.5% 2% 2% aeroplanes with an outer main gear wheel span
Maximum rate of change of of less than 9 m; C and-the taxiway is intended
slope per 30m d.l‘/, 0.2% 0.4% 0.4% to be used by aeroplanes with a wheel base
Minimum radius of curvature equal to or greater than 18 m.
( 4 30000 15000 7500 7500 15 C and the taxiway is intended to be used by
Minimum distance between aeroplanes with a wheel base less than 18 m.
successive points of 10.5 B
intersection of vertical 7.5 A
curves is the sum of the
absolute numerical values of Note: The second subdivision of the 18 and the IS m widths are defined by the
the corresponding slope wheel base. not the wheel span.
changes multiplied by the
factor given in metres 30000 15000 SO00 5000 24.3.7 Taxiway vertical alignment
Notes: ( I ) The maximum slope for a runway code number 4 should not u d Recommendations in relation to the various components are
0.8% for the first and last quarters. given in Table 24.6.
(2) The maximum slope for a runway code number 3 precision approach
category II or 111 should not exceed 0.8% for the first and last quarters.
Table 24.8 Taxiway vertical alignment

24.3.5 Runway transverse slopes Code letter


Recommendations for the transverse slopes are given in Table E D C B A
24.4.
Table 24.4 Runway transverse slopes Maximum slope 1.5% 1.5% 1.5% 3% 3%
Maximum change of slope
Code letter per 30m 1% I% I% - -
Minimum radius of
E D C B A curvature (m) 3000 3000 3000 - -
Minimum change of slope
1.5% 1.5% I .5% 2% 2% per 25m _ _ - 1% 1%
Minimum radius of
Note: The transverse slopes should not exceed 1.5 or 2% as applicable nor be less curvature (m) - - - 2500 2500
than I % except at runway or taxiway intemctions where flatter slops may be Maximum transverse slope 1.5% 1.5% 1.5% 2% 2%
necessary.

24.3.6 Taxiway widths 24.3.8 Taxiway minimum separation distances


The width of a straight portion of a taxiway should be not less Recommendations for taxiway minimum separation distances
than that given in Table 24.5. are given in Table 24.7.
Table 24.7 Taxiway minimum separation distances
~

Distance between taxiway centreline and runway centreline Taxiway Taxiway & Aircraft
centreline to apron stand
taxiway taxiway taxilane
centreline centreline to centreline to
Instrument runways* Other runwa.vs* object object

Code I 2 3 4 I 2 3 4
number
Code
letter
~

A 82.5 82.5 - - 37.5 47.5 - - 21 13.5 12


B 87 87 - - 42 52 - - 31.5 19.5 16.5
C - - 168 - - - 93 - 46.5 28.5 24.5
D - - 176 176 - - 101 101 68.5 42.5 36
E - - - 180 - - - 105 76.5 46.5 40
*The separation distances shown represent ordinary combinations of runways and taxiways. The basis for development of these distances is given in the ‘Aerodrome Design
Manual, Part 2’.
Standards 24/7
24.3.9 Aprons - clearance distances airport and beyond its limits are defined. It is necessary to
An aircraft stand should provide the clearances between an restrict the creation of new objects and to remove or mark
aircraft using the stand and any adjacent building, aircraft on existing objects (whether man-made or naturally occurring)
another stand and other objects as shown in Table 24.8. which project above these imaginary surfaces. A plan view of
them is shown in Figure 24. I and dimensions are given in Tables
24.9 and 24.10. The main components are:
Table 24.8 Apron clearance distances
(I) An inner horizontal surface located 45 m above the airport
Code letter Clearance ( m ) elevation extending to a horizontal distance a measured
from the aerodrome reference point.
A 3 (2) A conical surface with a slope of 5% above the horizontal, a
B 3 lower edge coincident with the periphery of the inner
C 4.5 horizontal surface and an upper edge located at a height b
D 7.5 above the inner horizontal surface.
E 7.5 (3) Transitional surfaces along the side of the strip and part of
Nore: Thnc clcarmm can be reduced in special circumstanax where the code the side of the approach surface q that slopes upwards and
letter is D or E - for details rcferena should be made to ICAO Annex 14. outwards at c% to the inner horizontal surface.
Consideration must also be given to the provision of service roads and to (4) Take-off surfaces established for each runway direction. The
manoeuvring and storage area for ground equipment. limits of the take-off surfaces are determined by an inner
edge, two sides of which initially are diverging and then
24.3.10 Aprons - slopes parallel and an outer edge, the inner and outer edges being
perpendicular to the flight path.-The inner edge has a length
Slopes on an apron including those on an apron taxilane should I and is at the end of the clearway if provided (and if it
be sufficient to prevent accumulation of water on the surface of exceeds the specified distance) or at a distance m from the
the apron but should be kept as level as drainage requirements end of the runway. Each side diverges at a rate of n%
permit. On an aircraft stand the maximum slope should not relative to the extended centreline of the runway until a
exceed 1%. specified maximum width p is reached, continuing thereafter
at that width to the outer edge. The distance between the
24.3.11 Obstruction surfaces inner and outer edges, or length of take-off surface, is 9 and
the surface slopes up at r% to the horizontal.
Imaginary surfaces which extend over the area occupied by the ( 5 ) Approach surfaces established for each runway direction

Table 24.9 Approach runways: dimensions for obstacle limitation surfaces

Runway classification Non-instrument code number Non-precision approach Precision approach


code number
Category I code Category II or
number I l l code number
Surface and dimensions 4 3 2 1 4 3 2, 1 4, 3 2, 1 4, 3

Inner horizontal
Height 45 45 45 45 45 45 45 45 45 45
Radius a 4OOO 4001) 2500 2000 4OOO 4OOO 3500 4OOO 3500 4000

Conical
Slope 5% 5% 5% 5% 5% 5% 5% 5% 5% 5%
Height b 100 75 55 35 100 75 60 100 60 100

Transitional
Slope C 14.3'/0 14.3% 20% 20% 14.3% 14.3% 20% 14.3% 14.3% 14.3%

Approach.
Length of inner edge d 150 150 80 60 300 300 150 300 I50 300
Distance from
threshold e 6 0 6 0 6 0 3 0 6 0 60 6 0 6 0 60 60
Divergence (each side) f 10% 10% 10% 10% 15% 15% 15% 15% 15% 15%
First section
Length g 3000 3000 2500 1600 3000 3000 2500 3000 3000 3000
Slope h 2.5% 3.33% 4% 5% 2% 2% 3.33% 2% 2.5% 2 Yo
Second section
Length I 3 m t 3 m t 3 m t 12000t 3000t
Slope i 2.5%. 2.5% 2.5% 3% 2.5%
Horizontal section
Length ,84007 mt 8400t 8400t
Total length 15000 15000 2500 I5000 15000 15000
'All dimensions arc measured horiwntally.
tVariabk hgth. Under anain circwnslanas the length of the second EeEtion may bc inncavd but the length of the horizontal section will be d u d by the same amount.
2418 Airports
Table 24.10 Take-off runway: dimensions for obstacle limitation surfaces

Runway classifcation Non-instrument code number Non-precision approach Precision approach


code number
Category I code Category I1 or
number III code number
Surface and dimensions 4 3 2 1 4 3 2, I 4, 3 2, I 4, 3

Take-off climb
Length of inner edge I 180 180 80 60 180 180 60 180 80160 180
Distance from runway
end’ m 60 60 60 30 60 60 60130 80 60130 60
Divergence (each side) n 12.5% 12.5% 10% 10% 12.5% 12.5% 10% 12.5% 10% 12.5%
Final width P 1200 1200 580 380 1200 I200 5801380 1200 5801380 1200
1800t 18007 18007 I8007 18007 1800t
Length 9 I5000 15000 2500 1600 15000 I5000 2500 15000 2500 15000
I600 I600

Slope (Yo) r 2 2 4 5 2 2 415 2 415 25


*The take-offclimb surfaa starts at the end of the clearway if thc clearway length eacads the specified distana
tl8OOm when thc intcndcd track includes changes of heading greater than IS% for opcrntions conducted in IMC. VMC by nlght

used for the landing of aeroplanes. The limits of the


approach surfaces are determined by an inner edge, two
diverging sides (when viewed from the runway end) and an
outer edge, the inner and outer edges being perpendicular to
the flight path. The inner edge of length d is located at a
distance e from the runway threshold. Each side diverges at
a rateJ% from the extended centreline of the runway to the
outer edge and the length to the outer edge is g. The slope of I I I
thc surface above the horizontal is h%. Non-precision
approach and precision approach runways have an ap- I I I I
proach surface in which the outer section length .j is at a- p n ------I
e1 L-,---
Zone 2 J
flatter slope k% and with a horizontal section beyond.

24.4 Airport concept and layout


24.4.1 General
Growth of aviation over recent years has been accompanied by
a continuous process of change, and airport planners have
increasingly become aware of the need to provide flexibility for
future extensions and modifications of the facilities. bearing in of layout allows considerable scope for future extension of the
mind that 10 to I5 years may elapse between master planning airport facilities.
and commissioning of a major airport. An airport is designed to meet many needs but compromise is
Conceptual planning has been influenced by the trend to- inevitable since some of the most important requirements
wards larger aircraft for handling the increasing numbers of present varying degrees of incompatibility. The main factors
passengers. The number of air passengers carried throughout are:
the world on scheduled services by airlines of ICAO member
states has risen from I I I million in 1961 to 639 million in 1981. ( I ) Rapid and efficient handling of passengers.
The size of aircraft has increased greatly; the Boeing 747, for (2) Minimum walking distances.
example, is 70.5111 long and has a wingspan of 59.7111 and a (3) Simple directional guidance for passengers.
maximum height of 19.4 m, whereas the earlier Boeing 707 had (4) Maximum runway movement rates.
corresponding dimensions of 44.2, 39.8 and 12.7 m. ( 5 ) Minimum taxiing times.
The ability of modern aircraft to land in crosswinds has (6) Rapid aircraft turnround on the apron.
resulted in a much reduced need for subsidiary runways in
different directions. Also, the potential capacity of two indepen- Whilst layouts of the airside facilities of runways, taxiways and
dent runways means that few airports now need to be planned aprons are governed by international standards described pre-
with more than two runways which can be parallel. Thus, a viously, no such standards exist for the design of passenger
simple pattern of widely separated parallel runways has terminal buildings and other ground facilities. It is therefore in
emerged which assists the planner to achieve a rational layout this part of the airport plan that the designer can exercise his
with the ground handling facilities located between the runways individual skill,
and served by a common access ‘spine’ as illustrated in Figure No two terminal buildings are the same but modern airports
24.2. for large- and medium-sized aircraft generally follow the pattern
Examples of such layouts can be seen at Amman, Changi of parallel runways with the terminal facilities based on one of
(Singapore), Munich and Athens. It will be noted that this type two principles, either: ( I ) centralized handling; o r (2) decentral-
Airport concept and layout 24/9

ized handling. In the former, all the facilities such as check-in, and enable runway length to be computed for given sets of
baggage-handling, customs and immigration, restaurants, bars, conditions.
concessions, banks, etc. are concentrated in one location, with At a specific airport runway take-off length will be determined
associated car and aircraft parking facilities. There is, however, by range considerations. Landing length is controlled by the
limited airside and landside frontage. Aircraft sometimes have maximum landing weight of an aircraft with allowance being
to be parked away from the building with access by piers or made for the condition of the runway pavement in terms of
apron buses and landside car parks tend to involve long walking braking ability.
distances. It should be noted that runway lengths quoted in documents
Decentralization involves the distribution of these facilities such as the ‘UK Air Pilot’ do not necessarily equate to actual
over several centres in the terminal complex. The concept physical lengths of pavement as account may be taken of the
includes the range of variations from independent, or unit, existence of a stopway, a clearway or a displaced threshold.
terminals, each with the full complement of facilities, to the
provision of facilities at the aircraft whereby passengers
undergo a complete check-in (the gate check-in concept).
24.4.4 Temperature and elevation effect on runway
The small airport for light aircraft will almost certainly have length
centralized handling facilities and it may well require one or The average daily temperature (over 24 h) for the hottest month
more cross-runways owing to inability of light aircraft to of the year is of interest to the designer and it will be necessary to
operate in strong crosswinds. increase the length of the runways where high temperatures are
Various aspects of planning the airport layout follow in recorded (see ICAO Annex l4).’ The elevation of the airport has
greater detail. a like effect, and the basic length of a runway should be
increased as also described in Annex 14.
24.4.2 Runways
The number of runways at any airport, other than one for light 24.4.5 Wind effect on alignment
aircraft, will be determined from the number of aircraft The use of an airfield is controlled to a certain extent by the
expected in a given period, usually,an hour, but it is difficult to wind. Crosswind components may prevent safe usage of the
give general guidance since the capacity of any runway or .runway and the direction of the runway should be aligned to
runway system depends on a variety of factors such as: keep instances of unacceptably high crosswinds to a minimum.
To do this, a full summary of wind duration, speed and
(I) Aircraft types. direction is required, taken over a period of years. From this a
(2) Landing aids. convenient graphical method of determining runway orien-
(3) Air traffic control techniques. tation as devised by Marwick is as follows.
(4) Ground movement capability (e.g. taxiway and apron facili- The recorded hours (as percentage total) for each range of
ties). velocities are plotted in the sectors intercepted between concen-
tric circles representing these velocities (Figure 24.3). The run-
There will be significant differences between the capacities under way is then drawn in a trial direction through the centre of the
instrument flight rules (IFR) and visual flight rules (VFR) and circles and two parallel lines representing 13 knots (or any
the IFR capacities will be lower. The major airports handling permissible crosswind component) to the same scale as the
high rates of commercial air transport movements operate circles.
under IFR even in good weather conditions. All winds falling outside these lines are in excess of the critical
As an indication, the capacity of a single runway handling a for that particular runway direction. Further trial and error
mixture of air transport and general aviation aircraft will be in establishes the desired pattern.
the order of 37 movements per hour, assuming roughly equal Alternatively, a computer may be employed to follow a
numbers of landings and take-offs. The maximum figure may similar process in order to establish the percentage usability of
rise to about 50 movements per hour under VFR but, of course, an airfield having one or several runways in various orien-
VFR operations are entirely dependent on favourable weather tations.
conditions. In a multi-runway layout, the main runway may be set in the
For parallel runways, maximum capacity is achieved when direction of the prevailing winds and the subsidiary runways are
separation is sufficient to enable each runway to be operated laid in the direction which yields the minimum crosswind
independently with mixed landings and take-offs. The total component effect and the maximum percentage usability for the
capacity will then be in the order of 74 movements per hour. A whole system. The present tendency is to aim for a single
minimum runway centreline spacing of 1800 m is required for runway system with high permissible crosswind components.
this mode of operation. The prevalence and nature of gusts and air turbulence in the
The staggering of the parallel runways depicted in Figure 24.2 area must be considered separately.
reduces taxiing distance at the expense of increased total land
requirements.
24.4.6 Taxiways
At busy airports there will certainly have to be a parallel taxiway
24.4.3 Runway length for the full length of the runway and, at some of the more
Runway length is dependent on the following main variables: sophisticated airports, there may be double or even treble
parallel taxiways. Exit taxiways linking the runway and parallel
(1) Aircraft performance. taxiway must be conveniently located so that landing aircraft
(2) Aircraft take-off or landing weight. can vacate the runway as soon as possible. The exit taxiways
(3) Aircraft reference temperature. may either be perpendicular to the runway and parallel taxiway
(4) Airport elevation. or, where particularly rapid turn-off from the runway is desir-
(5) Runway gradient. able, they may be angled up to 45’ to the runway centreline for
small aircraft although, for the larger aircraft, the maximum
Performance curves are published by aircraft manufacturers angle should be about 30’ which will permit runway exit speeds
24110 Airports

Figure 24.3 Graphical method to determine runway usability

up to 60 m.p.h. (96 km/h). At the other end of the scale, an 24.4.8 Centralized concepts
airport with only low movement rates may not require a parallel
The centralized concept may be considered to include the
taxiway, and back-tracking on the runway would be acceptable.
following variations: (I) simple terminals; (2) linear terminals;
Taxiways should lead directly on to the end of the runway to
(3) finger terminals; (4) satellite terminals; and ( 5 ) mobile lounge
enable aircraft to move rapidly into the take-off alignment with terminals, although, depending on the extent of facilities pro-
maximum occupancy of the runway, although again, at airports
vided in the satellite and mobile lounge terminals, these latter
with low movement rates, taxiing along the runway may be
variations may tend towards the decentralized concept.
acceptable to achieve economy in taxiway construction costs.
The simple terminal consists of a common area for all
passenger handling facilities with several exits on to a small
aircraft parking apron. It is only suitable for airports with low
24.4.7 Terminal area passenger and aircraft movements or is adaptable to general
The temiinal area has three main constituents: the aircraft aviation operations whether located as a separate complex in a
apron, the terminal building and car parking with the associated large airport or as an airport used exclusively by small general
road system. Their relation to each other will be determined in aviation aircraft.
principle by whether the centralized or decentralized concept is The linear terminal concept is merely an extension of the
adopted and, at major airports, by the method of internal simple terminal concept in which the latter is repeated to
surface transport. There are other factors which influence the provide additional apron frontage and increased space for
relationship such as the pattern Bf airline operations, the ratio of passenger processing which may feature a two-level arrange-
domestic to international passengers, number of transfer pas- ment for separating arriving and departing passengers. Pas-
sengers, etc. senger walking distance from set-down kerb to aircraft is
The various centralized and decentralized concepts are illus- relatively short. Linear terminals can easily be extended
trated in Figure 24.4. although this may destroy the advantage of short walking
Airport concept and layout 24/11

I 000 000000
Linear terminals

~ Simple terminals

0
0
0
U
Finger terminals Satellite terminals

r---
I
O O O b O l
0 1 I I
oopoo;
yJ r - -J

Mobile lounge terminals Unit terminals


Figure 24.4 Terminal area concepts

distance if directional signing is inadequate, and passengers Primary


cannot leave their cars opposite the appropriate aircraft depar- reception
ture gate with its adjacent passenger processing facilities. building
The finger or pier terminal has evolved from the early
provision of a covered walkway between the simple terminal
and the aircraft such that later arrangements now incorporate
holding lounges at the gate and vertical separation of departing
and arriving passengers. A disadvantage of the concept is the
long walking distance involved from the central processing
facilities to the aircraft gate. There are many examples of this
arrangement, that for Belfast Airport being illustrated in Figure Term ina I
buildizLufl
24.5. The necessity for provision of adequate space between
fingers for manoeuvring aircraft is to be noted.
The features of the satellite concept are similar to those of the East
finger concept except that aircraft gates are located at the end of pier
a long concourse rather than being spaced at intervals along it.
Walking distances are relatively long and later developments
have incorporated a people-mover system between the central
terminal and satellites, as at London Gatwick. An advantage is
that satellite gates can be served from a common holding
lounge. The aircraft parking arrangement more readily allows
the introduction of self-manoeuvring stands although the Figure 24.6 Belfast airport
24112 Airports

wedge-shaped stands tend to impair the operation of aircraft passengers. The terminal is served by twenty wide-bodied air-
servicing equipment. Expansion is difficult with the satellite craft stands of which sixteen are linked to the building by a pier.
concept other than by introduction of additional satellites. The The planning of the building is based on the principle of
ultimate satellite arrangement is depicted at Paris Roissy (see centralized processing which is provided in three levels.
Figure 24.6) where the main building containing the common
facilities is completely surrounded by satellites containing wait- Upper level: Departing passengers are processed on
ing-lounges, access between terminal and satellite being by this level where after check-in, immigra-
tunnel. tion and security passengers enter a com-
The mobile lounge or passenger transporter concept has been mon departures lounge which in effect is a
used at Dulles International Airport, Washington, D.C. The pier 25 m wide and some 640 m long with
mobile lounges transport passengers between the common pro- satellite areas at each end.
cessing facilities in the central terminal and the aircraft parking Mezzanine level: Immigration and health control are
apron,or aprons, where they can be used as holding lounges. located on this level where arriving pas-
This arrangement reduces walking distances and allows con- sengers are processed and then proceed to
siderable operational flexibility for aircraft parking-apron ar- baggage reclaim at the lower level.
rangements with excellent opportunities for future expansion. Ground level: The baggage hall, customs and arrivals
The cost of providing and operating independent service build- concourse are located on this level
ings and mobile lounges together with time involved in moving together with associated public facilities
passengers by the mobile lounges will, however, often prove a and access to road transport.
disadvantage.
The major function criteria adopted in the design include:

( I ) Centralized passenger processing.


(2) Complete segregation of arriving and departing passengers
for security reasons.
(3) Maximum unassisted walking distance from the check-in to
aircraft gate is 200 m.
(4) 75% of aircraft stands are served via loading bridges.
(5) Complete vertical separation of arriving and departing
passenger flows.
(6) Maximization of non-aeronautical revenues.

24.4.9 Decentralized concept


In this concept, independent unit terminals, each incorporating
the complete passenger processing and aircraft parking facilities
are built around a system of interconnecting access and service
roads. The separate terminals may take the form of any of the
centralized concepts previously described and be built to the
requirements of specific airlines or groups of airlines (as at
Kennedy, New York) or may be split for operation by route
type (as at Heathrow, London) into arrival and departure;
alternatively, they may be split into domestic and international
functions.
Figure 24.8 Roissy, Paris. Note 'drive-through' parking (A) car This concept is usually justifiable at high-volume airports
park where walking distances become excessive with finger terminals.
It can, however, cause problems for transfer passengers unless a
high level of inter-terminal connecting services is provided, as at
Dallas, Forth Worth, US, illustrated in Figure 24.7. Future
extension of the decentralized concept can be difficult because of
24.4.8.1 Heathrow Terminal Four the land requirements for each terminal. Development costs are
One of the largest terminal building projects in the world came high because similar facilities must be provided at each unit
into operation in 1986 at Heathrow Airport and is a good terminal.
example of centralized passenger processing. The need for a Sophisticated developments of the centralized satellite ter-
fourth passenger terminal was recognized back in 1975 when minal can result in this concept merging towards a decentralized
passenger forecasts suggested that the three terminals in the system if each satellite contains complete passenger processing
central area would reach saturation capacity by the early 1980s. facilities. Complete decentralization is not achieved, however, if
As there is not sufficient space within the central areas to a central terminal is retained with common car-parking pro-
provide for the extra capacity it was decided that the only site vision.
that could be made available for development to meet demand
on time was to' the south of the airport.
The Terminal Four complex occupies some 40 ha of land and 24.4.10 Apron layout
has direct access to London's orbital motorway (M25) and, the The overall size and layout of the aircraft apron will depend on
A30. It is also linked directly to the underground system as well the number and type of aircraft likely to be parked at any one
as to the other three terminals by a frequent bus service through time. The number of stands is derived from the aircraft standard
the cargo tunnel. busy rate (SBR, see section 24.5 for general definition) and is a
The designed annual throughput of Terminal Four is 8 complicated process often necessitating computer simulation
million international passengers with one-way flow of 2000 studies. Small airports are treated empirically and a rough rule
Airport concept and layout 24113

Ii

Figure 24.7 Dallas, Forth Worth (A) car park

is to increase the SBR by 10% and round up to the next whole Table 24.11 Aircraft stand areas
number. ~~ ___ ___ ___

Minimum wing-tip clearances between adjacent aircraft and Nose-in parking Self-manoeuvring
from aircraft to buildings must be maintained according to the (m) (m dia.)
standards previously referred to. The area of the stand will also
be governed by the mode of parking. Nose-in parking, in which Airbus 85 x 85 100
the aircraft must be mechanically pushed backwards on leaving Long haul 65 x 65 90
the stand, requires special vehicles for this purpose but is more Medium haul 50 x 50 60
economical in overall area requirements than stands where the Short haul 40 x 40 50
aircraft is self-manoeuvring. Most large and busy airports tend General aviation - 30
'to adopt nose-in parking. Typical stand areas for various groups
of aircraft are given in Table 24. I I .
Access of aircraft to and from the parking stand is obtained Each stand position must be of sufficient area to accommo-
by defined taxilanes on the apron surface. The width and other date the wide variety of mobile ground service equipment which
design parameters required for these taxilanes should be similar is required for the modern aircraft. Generally, a minimum 3 m
to those for independent taxiways as previously described such should be added to the apron depth to permit service access and
that the necessary wing-tip and obstacle clearance are main- IOm additional depth may be required. for operation of the
tained. push-out vehicle used in the case of nose-in parking.
24114 Airports

. A service road, typically 7 to 10 m wide, should be provided and 24.13. Perrettbgives the following approximate guide for the
adjacent to the terminal building. Vertical clearance of 5 m total capacity of the terminal:
should be available over the road.
A graphical design method for determining the separation of (1) 1500 passengers per hour in each direction for every
aircraft parking stands has been devised by the ICAO in the IS 000 m2 of area available to the public.
Aerodrome design manual,’ Part 2 and, in Airport aprons.’ the (2) I500 passengers per hour each way for every 25 OOO m2 of
FAA has published graphs and equations for the determination total terminal (excluding office accommodation).
of clearances for aircraft turning and taxiing out of a parking
position. -The Apron and terminal building planning report,5 Reductions of 30 to 40% could be made in the areas for
prepared for the FAA, provides scaled outlines for six groups of terminals handling predominantly domestic traffic. Conversely,
aircraft and gives general guidance for planning airport apron- the space could be increased drastically if, for example, there
terminal complexes. were a high proportion of visitors.
Perrett gives additional useful data on terminal building
design and the Airport terminals reference manual’ (IATA) is
24.4.11 Terminal building layout also helpful.
The functions, flow pattern, accommodation, configuration and
size of the terminal building or buildings need individual
assessment for the factors of influence are many and differ in Table 24.13 International Air Transport Association standards
each case. Simulation and computer models have been de-
veloped to aid design of this most complex of buildings and are Passenger requirements in any specific Space ,required per
likely to be used for the larger terminals. area peak hour passenger
The usual approach to determining the required floor area is (m2)
to estimate the requirement for each facility derived from the
peak hour or SBR passenger demand (see section‘24.5). After Standing passengers I .o
categorizing the peak hour passengers into international and Seated passengers 1.5
domestic types and also into terminal and transit passengers, it Plus 10% additional circulation and
is possible to estimate the number olpassengers to be processed airline requirements space at lounges
in each facility, such as check-in desks, lounges, customs and
immigration, etc. and, hence, to determine the space require-
ment for each facility to ensure reasonable provision. Various
guides are obtainable for estimating the space requirements of 24.4.12 Car parking layout
the different facilities. The Federal Aviation Administration and The problems arising out of making provision for car parking
IATA have published the guidelines summarized in Tables 24. I2 are among the most difficult facing the airport designer. In
general, the majority of passengers travel to and from airports
by car. Visitors and airport workers must also be catered for.
Table 24.12 Federal Aviation Administration standards There are five main categories of car parking:
Domestic terminal space facility Space required per (1) Kerbside - for setting down and picking up.
peak hour passenger (2) Short term - say up to 15 h.
(m’) (3) Long term.
(4) Staff - both airport and airline.
Ticket lobby I .o (5) Visitors - accompanying departing passengers, meeting
Airline operational 4.8 arriving passengers and casual spectators.
Baggage claim I .o
Waiting rooms 1.8 The parking areas required to accommodate these various
Restaurants 1.6 demands can be considerable and air travellers may comprise a
Kitchen and storage I .6 small proportion of the total car users. No standard guidelines
Other concessions 0.5 are available for determining the various parking requirements
Toilets 0.3 which are likely to differ from airport to airport. Estimates of
Circulation, mechanical and traffic flow must be made by conventional methods such as
maintenance, walls 11.6
- census sampling. A decision must be made on the comparative
Total: 24.2 proportion of short-term and long-term parking if, indeed, the
alternatives are considered desirable. It is normal to price these
facilities differentially to encourage rapid turnover in the short-
term car park, which is usually located closest to the terminal
International terminal space facility Space required per building. On large airports, long-term parking may be extensive
(additional to domestic requirements) peak hour passenger and the distance from the terminal building may necessitate a
(m’) shuttle bus service.
~ ~

Public health 1.s 24.4.13 Airport access


Immigration I .o
Customs 3.3 In addition to the terminal building, apron and car parking
Agriculture 0.2 arrangement, the airport planner must consider and make
Visitors’ waiting rooms I .s provision for the alternative modes of surface access by which
Circulation, baggage assembly, utilities, air passengers, airport workers and visitors may move to and
walls, partitions -7.5 from the airport.
Total: 15.0 Although road access for cars must invariably provided,
consideration must also be given to provision for taxis and
Traffic forecasts 2411 5

public buses. Other modes of access such as railways may also approach areas, together with runway centreline and edge
be favoured -London Gatwick and Heathrow have surface and lighting. Taxiway lighting usually consists of green centreline
underground railway links respectively from the city centre lights supplemented with blue-edged lights at junctions and
which carry in excess of 42% of all persons passing through the around the apron area.
airports. For visual guidance in the angle of descent, visual approach
The design of access road systems and other modes of airport slope indicators (VASls), or precision approach path indicators
access are outside the scope of this chapter. (PAPls) are provided.

24.4.14 Ancillary buildings 24.4.22 Telecommunications


It has been customary to collect the remaining airport buildings Telecommunications is a general term covering radio naviga-
under this heading but some, such as large hangars, cargo tional aids and radar in addition to data and voice communi-
terminals, etc. may be major projects in their own right. cations.
All modem airports require telecommunication services to
some degree and in the case of a larger international airport
24.4.15 Control tower those can be quite extensive. These services will consist of some
This should give controllers a view of all the runways and is or all of the following:
designed round the equipment required for air traffic control.
Large areas of false floor to accommodate cabling may be ( I ) Air-ground radio communication.
needed. The tower is generally a separate building and not a part (2) Land mobile radio.
of the terminal building. (3) Navigational aids.
(4) Final approach and landing aids.
( 5 ) Radar.
24.4.16 Apron control (6) Direct speech communication.
Some airports include an apron control cabin located so that an (7) Direct data communication.
apron controller can direct aircraft to the apron stands from the (8) Public communication services.
taxiways.
Recommendations and requirements concerning telecommuni-
cation requirements are given in the ICAO Annex 108.’
24.4.17 Aircraft catering building The positioning of the various telecommunication facilities is
This should preferably be located close to the terminal area and extremely important and must conform to the accepted ICAO
is a specialist catering building run by the airlines. recommendations in respect of siting and the grading of sur-
rounding areas.
The following electronic services, not covered by the term
24.4.18 Cargo terminal building ‘telecommunications’, are also required in most cases:
This facility may be a simple framed building or a sophisticated ( I ) Meteorological systems.
terminal such as that of British Airways at Heathrow Airport (2) Flight information display systems.
which comprises transit sheds housing computer-controlled (3) Public address systems.
mechanical handling equipment, office blocks, vehicle parking, (4) Security systems.
loading bays and circulation. There are no particular civil
engineering requirements.
24.4.23 Airport security
24.4.19 Maintenance hangars Attacks on civil aircraft for the furtherance of extreme political
aims, both on the ground and in the air, have become a major
These may range from a simple framed building to a major feature of air travel since around 1970. Security on the ground
structure suchas the British Airways hangar for the Boeing 747 at airports has therefore had to be developed to counter this
at Heathrow Airport, London. The structure basically is a trend.
cladding for the maintenance requirements but consideration of New technology is playing a significant role in upgrading the
large clear spans and door openings will determine the struc- standard of security at airports but there are some basic
tural forms. problems that remain unsolved. Airport security has made
major advances since the early 1970s but it is only new terminals
24.4.20 Buildings for electrical and electronic or airports that incorporate security as part of initial planning.
equipment In most cases, the attempt was to make secure an existing
building, which in most cases proved very expensive and not
These, generally, are simple buildings designed to house particu- 100% successful.
lar items of equipment, some of which may require a controlled Computers play a prominent role in sophisticated security
environment. The manufacturers advise on this point. The systems together with more advanced X-ray and electronic
buildings for certain navigational aids cannot have ferrous ‘sniffer’ equipment but the process is in a continuous state of
metal above a specified level and the manufacturer’s advice evolution in order to cope with new types of explosives and
should be sought. Others may require special shielding. Gener- plastic guns that are not easily detected on X-ray machines.
ally speaking, there are no particular construction problems. Apart from the severe high cost of security, the human factor
is always at the centre of most security systems used at airports
24.4.21 Airfield lighting for screening passengers and their baggage.
The extent of the approach and runway lighting provided not
only depends on the airport classification but should be compat- 24.5 Traffic forecasts
ible with the radio and radar landing aids provided. It generally
consists of high-intensity centreline and crossbar lighting for the The capacity of the apron, terminal building and car parks is
24/16 Airports

determined from the traffic forecasts. Such forecasts are nor- (2) Adequate strength to resist the effects of repetitive loading.
mally made on an annual basis and are split into scheduled and (3) Absence of loose particles which could be sucked into
charter flights for both domestic and international services. aircraft engines.
These annual forecasts are determined by one of two main (4) Imperviousness to water - resistance to jet blast.
methods: firstly, extrapolation of historical data and, secondly, ( 5 ) Resistance to fuel spillage (particularly on aprons and
by analysis of such factors as future income levels, regional and maintenance areas).
national development plans, future population forecasts, tourist (6) Good surface drainage.
potential, etc. This analysis is usually carried out on a computer. (7) Ability to accept temperature movements.
The annual figures are then converted to hourly flows, each (8) Good skid resistance.
called standard busy rate (SBR). (9) Good riding surface for comfort in the aircraft.
The SBR is defined as that rate which is exceeded 29 times in (10) Economy in construction and maintenance.
the year, and has been found to give a reasonable basis for
design.
It is essential to obtain an estimate of the short-period flow 24.6.3 General requirements of an aircra€t pavement
rates for passengers and aircraft. This can be done by an From an operational point of view it is difficult at busy airports
analysis of monthly, weekly, daily and hourly aircraft move- to close down a runway, taxiway or apron for the purposes of
ment patterns but, unless the relevant data is available, an pavement maintenance or strengthening; indeed, routine main-
assessment using ratios of standard busy hour passenger rates to tenance may have to be carried out at night. Pavements designed
annual movements is more likely to be the only suitable method. to fulfil the needs of only the immediate future may prove to be
In general the ratios decrease with increasing annual movements expensive in the long term. A runway may be required to have a
and they tend to be higher at airports with high proportions of life of 20 years or more and the designer must anticipate
international leisure traffic. They also tend to be high where one requirements as far into the future as possible.
route dominates the schedules, as occurs at many small airports,
and therefore such airports need to be independently con-
sidered. Special consideration should clearly also be given at 24.6.4 Construction
airports such as Aberdeen and Sumburgh where there is a high The three types of pavement construction may be grouped as
proportion of helicopter operations. Table 24.14 gives an indi- follows: ( I ) rigid; (2) composite; and (3) flexible.
cation of the ranges of ratios. An example ofeach of the three types is shown in Figure 24.8.
The passenger SBR is then used to determine the SBR of the In the UK it is usual practice to provide for all pavement
aircraft movements estimating the likely mix of aircraft, capa- types a 100 mm thick layer of dry lean concrete directly on the
city and load factors, taking future trends into account. compacted subgrade. This gives immediate weather protection
and acts as a working platform for placing subsequent layers. It
is interesting to compare this with American practice where,
Table 24.14 Standard busy rate (SBR) values under certain conditions, full-depth asphalt flexible pavements
may be laid directly on the subgrade.
Annual passenger movements SBRlannual
movement ratio
24.6.5 Choice of construction
100 OOO 0.002-0.003 The choice of type of construction and of materials depends on
250 000 0.001-0.002 the location and function of the pavement, or overlay, the
500 000 0.0007-0.0012 ground conditions or existing pavement and, very importantly,
I million 0.0006-0.0010 the cost. It is normal to carry out several designs, using all
2-5 million 0.00040.0009 possible materials combinations, and to cost each design for
comparison. A compromise between technical excellence and
economy is often necessary.

24.6 Aircraft pavements 24.6.6 Rigid pavements


Concrete surfacing is resistant to fuel spillage and to engine
exhaust blast, has good friction characteristics and good resis-
24.6.1 General tance to scuffing. It is thus often preferred for aircraft parking
Pavements suitable for the aircraft that will use them are and fuelling areas and for turning areas at runway ends.
required for runways, taxiways, aprons, maintenance areas, etc. However, because of the need for construction in bays, with
The determination of pavement type and thickness is complex joints at regular intervals, it is often considered less suitable for
with many interacting variables involved which are often diffi- runways and taxiways, where the uniform surface afforded by
cult to quantify. The first mathematical approach to airfield bituminous surfacing is of advantage.
pavement design was introduced in 1945. Since then, there has A concrete pavement is usually considered as being rigid
been progressive refinement of the approach to suit increasing because the load is spread over a wide area of subgrade by virtue
loads and complex landing gear configurations. of its inherent flexural strength. The concrete can be reinforced
This section is intended to provide guidance to the principal or unreinforced and is divided into rectangular bays to restrict
considerations and methods used in aircraft pavement design. the tensile stresses which are induced by a combination of three
factors:
h.6.2 Function of aircraft pavements ( I ) Contraction of the slab due to falling temperature and
The general functions of aircraft pavements are as follows: concrete shrinkage. This movement is restricted by the
friction between the slab and the subgrade and as a result
( I ) Adequate strength for all aircraft types likely to use the tensile stresses are induced in the slab.
airport. (2) Warping of the slab due to a temperature gradient through
Aircraft pavements 24117

Original

Surface dressing or 'friction cou


Wearing course of rolled asphalt

Cement, bitumen or
tar bound base

(Natural foundation

Level at which
Kvalue is determined
for all pavement types

Figure 24.8 Alternative recommended types of aircraft pavements

the thickness of the slab. High surface temperatures cause Slot Crack forms
the slab to dome until it is supported mainly at the edges, \ during curing
whilst low surface temperatures cause the corners to curl
upwards.
(3) Loading. Slabs are usually most susceptible to loading near
their corners which may cause cracks to form across the
corner. Acute angles in slabs should therefore be avoided.
Alternative shape Preformed crackinducer.
Wood or concrete
The bays are separated by contraction joints and the bay size
depends on the slab thickness. The maximum bay sizes should Figure 24.9 Contraction joint
be as indicated in Table 24.15.
Expansion joints may be provided in thin slabs but may be
Table 24.15 Maximum bay sizes of concrete runways entirely omitted in slabs more than 250 mm in thickness.
Single butt construction joints as shown in Figure 24.10 are
Slab thickness Bay size recommended since those incorporating a joggle are susceptible
(mm) (m) to cracking. Dowels may be omitted for slabs 275 mm thick and
over.
150 or less 3 The pavement quality concrete (PQC) used in rigid pave-
151-224 3.75 ments should be designed on the basis of its flexural strength
225-274 5.25 measured by loading 152 x 152 mm test beams, rather than on
275 and over 6 cube strength. It is the strength of the concrete when it is first
loaded which is of importance so that age factors may be taken
into account. The aggregate/cement ratio should not exceed
The contraction joints may be formed by using crack inducers 6.3: 1 and the water/cement ratio should be less than 0.50.
as shown in Figure 24.9. Load is usually transferred between
adjacent slabs by aggregate interlock in which case no dowel Slot (in fresh concrete)
bars are needed. If the aggregate particles in the concrete are not
too hard, however, a more satisfactory solution is achieved by
continuous casting of the slab, perhaps employing slipforming
techniques, followed by sawing the joints after the concrete has
set. Slots in the surface of concrete pavements, whether pre-
formed or sawn, should be as narrow as possible; they should be Hardene; Doiel Fresh'
filled with a semi-compressible material such as hardboard or concrete concrete
fibreboard, depending upon the subgrade, and need not be
sealed. Figure 24.10 Construction joint
24118 Airports

The PQC. slabs should be placed over a layer of dry lean Table 24.18 Steel reinforcement in rigid pavements
concrete having an aggregate/cement ratio of 15: 1 and a
minimum cube strength of 5.2 MN/mz. Schedule of reinforcement
In order to improve the skid resistance of the concrete
surface, the concrete may be wire combed or small transverse Slab Main steel Transverse steel
grooves may be cast into the wet concrete surface. It is essential thickness
that experiments are carried out to ensure that such treatment is (mm) Minimum Spacing Minimum Spacing
applied at the correct time. Alternatively, the hardened concrete area limiis area limits
may be scored with diamond cutting drums. (mmz/m (mm) (mm*/m (mm)
Well-constructed concrete pavements show little cracking and width) width)
are resistant to both jet blast and fuel spillage. They are ideal at
runway ends, taxiway junctions, aprons and on maintenance 100 425 295 125-175
areas where aircraft stand or are slow-moving.
Joints can be largely eliminated if prestressed concrete con- 125
struction is adopted but this form of construction is unlikely to 150 530
be economic under most conditions. I75

200
24.6.7 Composite pavements 225 635 125-175
Composite construction can often provide an economical solu-
tion, with the advantages of a bituminous surfacing without the 250 740 170 150-225
disadvantages of a concrete pavement.
In a continuous reinforced concrete pavement, cracking 275
(accentuated by exposure to heavy traffic) is likely to develop 300
whatever quantity of reinforcement is incorporated. However, if 325 825
the continuous reinforced concrete pavement is overlaid by 350
bituminous surfacing, the cracking is reduced since the variation
in the temperature in the concrete is lowered and those cracks Source; Manin. F.R. and Macrae. A. R. (1971) ‘Current British pavement design‘.
Paper 6. Proceedings. Conference on AirfieW Pavement Design. Institution of Civil
which do form in the concrete are not subject to wear and are Engineers.
unlikely to be severe. While there is some tendency for cracks to
form in the bituminous surfacing above those in the concrete
they are usually minor and can be resealed easily. based surface sealant. Dense tar surfacing (DTS) by the Mar-
The flexural strength of the concrete slab gives this form of shall method, where tar replaces bitumen as the binder, has also
construction good load-spreading properties, and a good riding been successfully used in areas subject to fuel spillage.
quality surface can be obtained. It is not as resistant to jet blast, A flexible pavement is one which depends on its thickness and
heat and fuel spillage compared with the rigid pavement so it is elasticity to disperse the load to such an extent that the subgrade
often used on runways and taxiways where aircraft are likely to is not overstressed. It is made up of a number of layers of
be moving fairly rapidly. granular materials increasing in rigidity and decreasing in
Pavement-quality concrete should be used for the reinforced flexibility towards the surface. The lower materials may be
slab overlying 100mm of dry lean concrete. The minimum unbound, or bound with bitumen or cement. The middle layers
cross-sectional areas specified for reinforcement for the appro- should be asphalt, bitumen o r tarmacadam. The surface layers
priate concrete slab thickness, as recommended by Martin and should be impervious and Marshall asphalt or dense-tar surfac-
Macrae? are given in Table 24.16. ing specifications are usual. The following factors have to be
The surfacing, normally l00mm in thickness, should be considered in relation to the design:
rolled Marshall asphalt or dense tar surfacing laid in two
courses. This two-course work reduces the tendency to sym- ( I ) The overall depth of pavement must be such that the
pathetic cracking in the wearing course over cracks in the strength of the subgrade is not exceeded.
underlying slab. (2) The strength of each individual layer of the pavement must
be such as to resist the pressure at that level.
(3) The shearing strength of the surfacing and layers beneath
24.6.8 Flexible pavements must exceed the shear stresses produced by the tyre load.
The top structural layers of flexible aircraft pavements are
usually of a hot rolled asphalt, with the mix designed and For very light-duty pavements several layers may be omitted.
controlled by the Marshall method (bituminous concrete in When dry lean concrete is used on the subgrade to provide a
American terminology). This achieves high density and stability good working surface it must be weak, otherwise cracks which
and affords an excellent riding surface which has good friction form in this layer are likely to spread upwards towards the
characteristics in dry conditions. In wet weather, however, flat surface. An aggregate/cement ratio of 18: 1 for gravel or 22: 1
gradients and surface tension lead to retention of surface water. for crushed rock is usually suitable.
It is common to provide an open-textured, non-structural, Well-designed flexible pavements have good riding qualities
friction course on top of bituminous surfacings to prevent the but some surfaces are susceptible to jet heat and fuel spillage
build up of surface water where aquaplaning could otherwise may cause softening of the surface.
occur. Relatively high landing and take-off speeds of modern air-
Water drains through the interstices of the friction course and craft, combined with the flat transverse slopes on runways, have
passes to the runway edge along the impervious top structural led to the problem of aquaplaning.
layer of the pavement. Bituminous surfacing is not resistant to
aviation fuel and proprietary materials are available as surface
treatments to provide fuel resistance where required. Examples 24.6.9 Overlays of existing pavements
are ‘Salviacim’, an epoxy-based surfacing, and ‘Jetseal’, a tar- It is often necessary to overlay existing pavements to provide
Aircraft pavements 24/19

greater strength or to repair a damaged surface, to improve ride 100 mm subbase of rolled dry lean concrete. As the system was
or friction characteristics, or to provide resistance to fuel designed.around the parameters of rigid pavements, the inclu-
spillage. Overlays are usually of bituminous materials, for ease sion of flexible pavements into a common reporting system
of construction and potential for minimizing disruption of could only be accomplished by inserting in the group scale
existing operations. However, some work has been carried out flexible pavement thicknesses derived empirically and from
using concrete overlays bonded to original concrete slabs. experience.
Economic and prac!ical considerations would generally mitigate
against such treatment, except in cases where concrete surfacing
24.6.10.4 The LCG method for rigid pavements
might be considered essential.
The LCG method requires the following data: (1) aircraft LCG;
(2) subgrade modulus; and (3) concrete flexural strength.
24.6.10 Pavement design, UK method The highest LCG corresponding to the aircraft expected to
use the airport, excepting the occasional visitor, is selected for
the design. The soil subgrade is classified by its subgrade
24.6.10.1 Development modulus or k value. The minimum flexural strength of the
The construction of aircraft pavements did not commence until concrete is estimated for the time the pavement is to be loaded;
shortly before the outbreak of war in 1939 and design principles this may be 6 months after construction. If no information
at this time were based on experience of highway construction. is available it is reasonable to use the common value of
The use by heavy bomber aircraft rapidly overstressed some 3.5 MN/mz.
of these early pavements, and led to investigations into the The design chart is entered at the upper value of the LCG
behaviour of paved surfaces and subgrades and the develop- band and the pavement quality concrete thickness is then read
ment of pavement design methods. off the corresponding band of the 'Rigid' column. An example is
The first mathematical approach to airfield pavement design given on the published chart.
was made in 1945 when a design manual for concrete pavements Some points should be noted:
was issued by the Air Ministry which contained design charts
for single-wheel loads based on Westergaard's equations. ( I ) The LCG grouping for the aircraft or the LCN value must
Investigations into the behaviour of pavements under increas- be taken from the corresponding column as the LCN values
ing loads continued as heavier jet-powered military aircraft with differ from that calculated by the original LCN method or
larger and more complex landing gears came into service. which are given in the ICAO Aerodrome design manual,"
Part 3.
( 2 ) The LCG system and design method is basically related to
24.6.10.2 The load classifcation number (LCN) system UK practice and to the soils commonly found in the UK.
The principle of relating aircraft loads and pavement strength Not only are these often clay soils with low strength but with
by means of a numerical scale, the load classification number all-the-year-round rainfall it is normally advantageous to
(LCN), first established in 1945, remained the UK design and prepare a working surface on which to lay the pavement-
evaluation system until 1971. quality concrete. For these reasons the LCG method always
The LCN was recognized by ICAO and incorporated into its incorporates a 100 mm layer of dry lean concrete. This could
'Aerodrome Manual, Part 2' as a recommended method of be omitted with certain suitable soils.
aircraft and pavement classification in 1956. (3) The LCG system recognizes that over 95% of aircraft
In the late 1960s the LCN system.was becoming increasingly operate on the central 30 m of runway and almost all taxi
difficult to apply to the heavy gear loads and a reappraisal of along the centreline of taxiways. Thus, the central strips of
pavement design methods was undertaken utilizing both the runways and taxiways, to which must be added all the
latest analytical methods available at that time and the ex- aprons or holding areas, can be considered as channelized
perience gained with the many heavy aircraft pavements con- areas. For 'non-channelized areas' one group lower can be
structed between 1950 and 1965. A revised system which intro- selected to reduce the required design thickness.
duced the concept of load classification groups (LCGs) for
pavement evaluation replaced the LCN system in 1971 and is
currently in use in the UK. This is set out in Design and
24.6.10.5 The LCG method for composite pavements
evaluation of aircraft pavements'O published in 1971 by the
Department of the Environment, London. The LCG method is also appropriate to design a pavement
which is a composite of a reinforced concrete slab to spread the
aircraft load with a bituminous surface. The design process is
24.6.10.3 The load classification group (LCG) system exactly similar to that of unreinforced rigid pavements except
The load classification group (LCG) system was published in that the composite column of the chart is used.
1971, and was recognized as a rigid pavement system by ICAO
in 1974.
24.6.10.6 The LCG method forjexible pavements
A coarse scale of seven groups was superimposed upon the
old LCN scale, reflecting broadly the seven ICAO aircraft The simplest way of designing a flexible pavement is to use a
classification groups, as can be seen on the design and evalu- similar process as for unreinforced rigid pavements except that
ation chart in Figure 24.1 1. the flexible column of the chart is used.
The seven groups are referenced by roman .numerals in A flexible pavement constructed to such a design would be
descending order as gear loads and pavement strengths increase, satisfactory, for the whole construction is in bound material.
thus group VI1 is the group of lowest strength and group I is the There is only one system of construction accepted which com-
highest. prises a 100 mm layer of bitumen bound surfacing, a thick layer
Since it is UK practice to construct rigid pavements without of cement, bitumen or tar-bound base material on the standard
load transfer devices at joints, provision is made at the design 100 mm of dry lean concrete.
stage for the increased stresses due to edge and corner load cases Some confusion has existed between the LCN values and the
by increasing the theoretical slab thickness and by providing a LCG system since both use the common.term LCN. The actual
24/20 Airports
Surface water drainage design 24/21

LCN values derived under the two systems are, however, 24.6.1 I .3 Rigid pavement thickness design
different and unrelated and must not be confused or inter- The FAA advisory circular Airport pavement design and evalu-
changed. ation‘*gives design charts for groups and individual aircraft and
use of the charts requires the following:

24.6.10.7 Evaluation of existing pavements ( I ) Concrete flexural strength.


The majority of aircraft pavement works have consisted of (2) Subgrade modulus.
strengthening and extending existing pavements. The evaluation (3) Gross weight.
of these pavements is rarely an easy matter as there is no (4) Number of the equivalent annual departures of the design
mathematical basis on which a calculated evaluation can be aircraft.
made.
Pavement evaluations are normally made either by assess- The charts give the total concrete slab thickness for critical
ment or by physical testing. Assessments are made either by a areas, which can then be reduced by the appropriate factors for
‘reverse design’ procedure or by the professional judgement of non-critical areas.
an experienced pavement engineer. Where a reasonably accur-
ate assessment cannot be made, physical testing by means of 24.6.11.4 Flexible pavement thickness design
plate bearing rigs or, more recently, by means of deflection
measurements made with a heavy falling weight deflectometer, The FAA advisory circular ‘Airport Pavement and Design’ also
can be carried out. gives flexible pavement design charts for the same aircraft
groups and aircraft as for the rigid pavements. Use of the figures
requires the following:
24.6.10.8 The pavement classification number (PCN).and
design system ( I ) The CBR value of the subgrade.
(2) The gross weight.
The ICAO now requires airports to classify airfield pavements (3) The annual departures of the design aircraft.
by means of the pavement classification number (PCN) and
publishes in Design manual, Part 3 , aircraft classification The figures give the total pavement thickness of a three-layer
numbers (ACN) relating to types and thicknesses of pavement. construction and the thickness for the critical and non-critical
The relationship between the ACN and PCN measures the areas of the bituminous surface or wearing course, the thickness
ability of the aircraft to use the relevant pavement. It is a of the granular base course and, by deduction, the thickness of
classification system but it is not a pavement design system. the granular subbase.
The Airfield Pavements Branch of the Property Services In addition to the design charts, the FAA present a further
Agency (PSA) has recently been developing a new design system chart which shows the minimum base course thickness, and this
for use in the UK and to be published in late 1987. It is expected has to be calculated as a check against the thickness determined
to provide the design relationship to pavement classification from the main charts.
numbers which is currently absent from the ACN/PCN system.
24.6.11.5 Pavement evaluation
The advisory circular contains separate charts for evaluating the
24.6.11 Pavement design - FAA method strength of an existing pavement.

24.6.11.1 General 24.7 Surface water drainage design


The FAA design method is based on the gross weight of the
critical aircraft operating at the maximum take-off weight. The 24.7.1 General
areas of traffic concentration are considered as ‘critical areas’, As for all traffic-bearing pavements, a carefully designed water
which comprise the central portion of the runway, aprons, drainage system is a necessary requirement of an airport.
taxiways and runway ends, where departing traffic will load the Inadequate drainage may reduce the loadbearing capacity of the
pavement. .The design charts produce a pavement thickness subgrade, decrease skid resistance on the surface and cause
which is appropriate to critical areas; non-critical areas can have breakdown of surface vegetation.
a reduced thickness. In general, the same basic design methods for calculating
runoff are used for airports as for highways or urban areas. On
the ‘landside’ of an airport, the metho‘ds,of dealing with the
24.6.11.2 Equivalent design aircraft departure collection and disposal of surface water b y way of gullies and
The design method requires the following initial steps: piped systems are conventional. On the ‘airside’ there are
problems which are particular to airports, largely related to the
(1) An estimate of the annual departures (half the total move- areas involved and the relatively flat grades, which are dealt with
ments) of all aircraft forecast to use the pavement. in this section.
(2) Determination of the design aircraft.
(3) Calculation of the equivalent number of departures of the 24.7.2 Drainage for runways
design aircraft.
A runway has longitudinal gradients limited to being not steeper
It should be noted that arrivals are neglkted since the landing than 1.25% on major runways and not steeper than 2% on
weight of an aircraft is less than the take-off weight. The design minor runways. It is wide (up to 45 m), with transverse slopes,
method provides a pavement life of 20 years with the forecast limited to between I and 1.5% on major, and between 1 and 2%
annual departures. on minor, runways. Gullies and gratings are not acceptable on
the runway itself, nor are open ditches within the strip.
24f 22 Airports
It is normal to have a shoulder about 3 m wide adjacent to the 24.8.1 Aircraft sanitation
runway edge, sloping at 5% away from the runway, often with a
subsoil drain under. Ideally. the strip will then slope away from The aircraft toilets are emptied into vehicles and the contents
the runway at a slope of about 1.5% to carry surface water are disposed of at airport sanitation buildings. These house
runoff either to a storm drain system with grated inlets and macerators or comminutors which discharge into the foul
manholes or, if the ground slopes away from the runway to the drainage system. The buildings require an electrical power
edge of the strip, to an open channel. Where the strip slopes supply.
towards the runway, as is permitted within the design standards,
then a piped system with grated inlets has to be provided, 24.8.2 Fuel installation
preferably at the edge of the shoulder. The supply of fuel to aircraft is normally carried out by the fuel
Because of the flat gradients and the potential for a film of
companies who contract for a specified period. There are two
water developing, friction courses have been used on many
means of distributing fuel to the aircraft aprons: ( I ) by aircraft
runways in the UK. These are a thin open texture of bituminous
refuellers; and (2) by a hydrant system.
overlay, whereby the water flows through the interstices on the
Aircraft refuellers are usually employed and they range from
impervious surface of the runway, to the edge, where the
2250 to 82 000 I. The larger is an articulated vehicle with an
collection and disposal is normal.
overall length of 21.5 m, a height of 3.65 m (including radio
aerial), a width of 3.2m, a turning circle of 21.4111 absolute
24.7.3 Taxiways minimum and a laden weight of 91 t.
Hydrant systems consisting essentially of a distribution
Permitted gradients on taxiways are such that these, also, have network terminating in pits in the apron which contain hose
flat longitudinal and transverse gradients. They are dealt with in couplings, have been installed at some airports but have, up to
a similar way to runways.
now, not been very popular for two main reasons. The first is the
inherent inflexibility.The mixes of aircraft at any airport change
24.7.4 Aprons rapidly and the parking stands on aprons have rarely remained
constant for more than 2 or 3 years with the result that the
The maximum recommended gradient on an apron is I%, hydrant point has frequently been in the wrong position almost
sloping away from any buildings to minimize any risk arising as soon as it has been installed. The second is that the fuel
from fuel spillage. Drainage is usually by continuous grated slot companies’ tenure is normally shorter than the hydrant system
drains dividing the apron into drained areas such that drainage life and individual companies have not been prepared to finance
paths are not excessively long. It is undesirable to have frequent the high capital cost. However, with the advent of very large
changes of gradient on an apron. aircraft of enormous fuel consumption, even larger fuel dis-
pensers become less attractive and the hydrant system is likely to
24.7.5 Subsoil drainage become of increasing interest in the future. Nose-in aircraft
parking is becoming the standard with jet aircraft; this is tending
Subsoil drainage may be necessary to drain low-lying water- to prolong the life of fixed apron stand positions and is a factor
logged areas, or to keep a fluctuating water table well below
encouraging the greater use of hydrants.
subgrade level. Open-jointed porous pipes laid in a ‘herring- Both the aircraft refuellers and hydrant systems incorporate
bone’, ‘parallel’ or ‘gridiron’ system should be used. Depths safety features which prevent the pumping of fuel if the hosepipe
should be as generous as possible, and should not be less than should become disconnected.
0.6 m or greater than 1.2 m below the surface.
24.8.4 Ground movement signs
24.7.6 Stilling ponds These are placed adjacent to taxiways and aprons to direct the
pilots. Details are given in ICAO Annex 14 and CAP 168. In
Airports are most frequently sited on low-lying relatively flat addition, aircraft stand number signs are provided either free-
land, and therefore it is common for problems to arise in the standing or fixed to the terminal buildings or pier.
discharge of surface water from the airport into the natural All these signs will require an electrical power supply.
main drainage system, particularly when the flow is high in the
latter. The use of stilling ponds is common. These provide
storage until the level in the main drainage system has fallen, or 24.8.5 Crash and rescue services
relieve the peak flow in the main channel. Fire engines and crash tenders are housed in buildings with
quick and easy access to the aprons, taxiways and runway. The
24.7.7 Main drainage channels scale of provision for the UK is given in CAP 168 and the
requirements are related to the heaviest aircraft in regular
Another feature of airport sites is that there is often a natural operation at the airport.
major watercourse flowing across them. Where possible this At some airports where a crash in water is possible, rescue
should be diverted, but if this is not possible and a culvert has to boats should be provided.
be constructed, this should be sized generously, designed for
aircraft loading, and be of sufficient length to pass under
runway and strip. 24.8.6 Boundary and security fences, including crash
access
Airports should be fenced properly and the choice of fence
depends on availability and cost. Whilst a 1.2m fence is
adequate over most of the perimeter, security and customs may
24.8 Ancillary services require a higher fence topped with barbed wire strands in the
terminal area separating the landside from the airside. The
There are several ancillary services associated with the airport airside/landside fence will require manned gates at all accesses,
and the main ones are described in the following sections. which should be kept to a minimum.
References 24/23

The perimeter fence should be provided’ with a number of 24.9.10 Instrument approach runway
frangible gates so that crash and rescue services can get quickly
to the scene of any crashes which may occur outside the A runway intended for the operation of aircraft using non-
boundary. visual aids providing at least directional guidance in azimuth
adequate for a straight-in approach. Those runways served by
instrument landing systems (ILS) are designated precision ap-
24.9 Definitions proach runways and are further identified as either category I, I1
or III dependent on the sophistication of the ILS system and the
The following definitions are taken from these ICAO ‘Standard ability to permit operations in various levels of reduced horizon-
and Recommended Practices for Aerodromes’, Annex 14 and tal and vertical visibility.
CAP 168, ‘Licensing of Aerodromes’.

24.9.11 Non-instrument runway


24.9.1 Aerodrome (airfield or airport)
A runway intended for the operation of aircraft using visual
Any area of land or water designed, equipped, set apart or approach procedures.
commonly used for affording facilities for the landing and
departure of aircraft and including any area or space, whether
on the ground, on the roof of a building or elsewhere, which is 24.9.12 Obstacle
designed, equipped or set apart for affording facilities for the All fixed (whether temporary or permanent) and mobile objects,
landing and departure of aircraft capable of descending or or parts thereof, that are located on an area intended for the
climbing vertically, but shall not include any area the use of surface movement of aircraft or that extend above a defined
which for affording facilities for the landing and departure of surface intended to protect aircraft in flight.
aircraft has been abandoned and has not been resumed.

24.9.2 Aerodrome beacon 24.9.13 Runway effective slope


The slope computed by dividing the difference between the
Aeronautical beacon used to indicate the location of an aero-
maximum and minimum elevations along the runway centreline
drome.
by the runway length.

24.9.3 Aerodrome elevation 24.9.14 Shoulder


The elevation of the highest point of the landing area.
An area adjacent to the edge of a paved surface so prepared as
to provide a transition between the pavement and the adjacent
24.9.4 Aerodrome reference point surface for aircraft running off the pavement.
The designated geographical location of an aerodrome.
24.9.15 Stopway
A defined rectangular area at the end of the take-off run
24.9.5 Aerodrome reference field length available, prepared and designated as a suitable area in which an
The minimum length required for take-off at maximum certifi- aircraft can be stopped in the case of an abandoned take-off.
cated take-off weight, sea-level, standard atmospheric condi-
tions, still air and zero runway slope as described by the 24.9.16 Strip
certificating authority or equivalent data from the aeroplane An area of specified dimensions enclosing a runway to provide
manufacturer. for the safety of aircraft operations.

24.9.6 Apron 24.9.17- Taxiway


A defined area on a land aerodrome, intended to accommodate A defined path, on a land aerodrome, selected or prepared for
aircraft for the purpose of loading or unloading of passengers or use of taxiing aircraft.
cargo, refuelling, parking or maintenance.
-
24.9.18 Threshold
24.9.7 Barette
The beginning of that portion of the runway usable for landing.
Three or more aeronautical ground lights closely spaced in a
transverse line so that from a distance they appear as a short bar
of light.
References
24.9.8 Clearway I International Civil Aviation Organisation (1983) International
stand0rd.s and recommended practicesjor aerodromes, Annex 14
A rectangular area at the end of the take-off run available and (8th edn). ICAO.
under the control of the aerodrome licensee, selected or pre- 2 Civil Aviation Authority (1984) Licensing ojaerodromes. CAP
pared as a suitable area over which an aircraft may take a 168. CAA.
portion of its initial climb to a specified height. 3 International Civil Aviation Organization (1977) Aerodrome design
manual: taxiways, aprons and holding bays. (1 st edn, Part 2)
ICAO, Document 9157-AN/901. Montreal.
24.9.9 Crosswind component 4 Federal Aviation Administration (1965) Airport aprons, Advisory
Circular AC 1S0/5355-2. FAA.
The velocity component of the wind measured at or corrected to 5 Ralph M. Parsons Co. (1975) The apron and terminal building
a height of IOm above ground-level at right angles to the planning report. Report FAA-RD-75-191, FAA. (Rev. March
direction of take-off or landing. 1976) .
24/24 Airports

6 Perret, J. D. (1971) ‘The capacity of airports - planning (d) ‘Airport services manual’ (1st edn) Part I : ‘Rescue & fire fighting’,
considerations’, Proc. lmtn Civ. Engrs. paper no. 7372, 50. Document 9137.
435-450. (e) ‘Airport services manual’ (1st edn) Part 2: ‘Pavement surface
7 International Air Transport Association (1976) Airport Terminals conditions’, Document 9137.
Reference Monual(6th edn), IATA. (f) ‘Manual on air traffic forecasting’ (1st edn) Document 8991.
8 International Civil Aviation Organization (1972) International (9) ‘Heliport manual’ (1st edn) Document 9261.
standnrds and recommended practices: oeronoutical (h) ‘Stolport manual’ (1st edn) Document 9150.
telecommunicatiom, Annex 108, Vols I & II (3rd edn). ICAO.
9 Martin, F. R. and Macrae. A. R. (1971) ‘Current British pavement
design’, paper 6, Proceedings. Conference on Aircraft Pavement US Federal Aviation Administration advisory circulars
Design, Institution Civil Engineers. (a) I50/5300-6A ‘Airport design standards, general aviation airports,
10 Department of the Environment (1971) Design ond evaluotion of basic & general transport’ (2.24.81).
aircraft pavements, DOE. (b) 150/5200-8 ’Planning and design criteria for metropolitan STOL
I1 International Civil Aviation Organization (1977) Aerodrome design ports’ (I 1.5.70).
manual(Ist edn) Part 4: Document 9157-AN/901, ICAO. (c) 150/5325-2c ’Airport design standards - airport served by air
12 Federal Aviation Administration (1978) Airport pavement design carriers -surface gradient and line of sight (2.6.75).
p d evaluation, FAA advisory circular AC I50/5320-6C. (d) 150/5325-4 ‘Runway length requirements for airport design’
(4.5.65).
(e) I5015325-5B ‘Aircraft data’ (7.30.75).
Bibliography (I) 150/5335-1A ‘Airport design standards - airports served by air
carriers - taxiways (5.1 5.70).
International Civil Aviation Organization ( I C A O ) (g) 150/5335-4 ‘Airport design Standards - airports served by air
carriers - runway geometrics (7.21.75).
publications
(h) 150/5340-4C ‘Installation details for runway centreline &
(a) ‘International standards and recommended practices - touchdown zone lighting systems (5.6.75).
environmental protection’, Annex 16 (1st edn) Vol 1. 6) 150/5340-19 ‘Taxiway centreline lighting system’ ( I I.4.68).
(b) ‘Aerodrome design manual’ (1st edn) Part 4 ‘Visual aids’, (k) l50/5340-24 ‘Runway & taxiway edge lighting system’ (9.3.75).
Document 9157. (I) 150/5370-10 ‘Standards for specifying construction of airports
.(c) ‘Airport planning manual’ (1st edn) Part I: ‘Master planning’, (10.24.74).
Document 9134. (m) I50/53W-l B ‘Heliport design guide’.

You might also like