Professional Documents
Culture Documents
May 2017
Queen Elizabeth Olympic Park, Stratford City and Adjacent Areas Community Energy Network Concession
Information for Developers of Commercial-only Developments (May 2017)
CONTENTS
1 Introduction ...................................................................................................................................... 4
1.1 Background ................................................................................................................................ 4
1.2 Community Energy Network Overview...................................................................................... 4
1.3 Elements of the Community Energy Network ........................................................................... 5
1.4 Summary of Connection and Supply Arrangements .................................................................. 6
1.5 Principles of the Concession ...................................................................................................... 7
2 Town Planning and Strategic Objectives ........................................................................................... 8
2.1 Planning Objectives .................................................................................................................... 8
2.2 The Development Corporation’s Environmental Sustainability Policy ...................................... 8
2.3 Legacy Communities Scheme ..................................................................................................... 8
3 Process for Developing Secondary Networks and Acceptance for Maintenance ........................... 10
3.1 Connection Agreement ............................................................................................................ 10
3.2 Heat Supply Agreements.......................................................................................................... 10
4 How to Arrange a Connection ......................................................................................................... 11
5 Key Technical Requirements ........................................................................................................... 13
5.1 Achieving Correct Flow and Return Temperatures .................................................................. 13
5.2 Minimising Heat Losses from the Secondary Network ............................................................ 13
5.3 Water Quality ........................................................................................................................... 13
6 Spatial Consideration for Site Layout and Masterplanning ............................................................ 14
6.1 Wayleaves ................................................................................................................................ 14
6.2 Heating Substations ................................................................................................................. 14
6.3 Space for Temporary Heating Plant ......................................................................................... 14
6.4 Access to Metering................................................................................................................... 15
7 Key technical information ............................................................................................................... 16
7.1 Carbon Emission Performance ................................................................................................. 16
7.2 Environmental assessments ..................................................................................................... 17
Appendix A Commercial Only Developments Connection and Consumption Charges ..................... 19
Appendix B Projection of long term heat network operation for calculating Carbon Emission
Factors for use in preparing Energy Statements for planning applications........................................... 21
Appendix C 12-month projection of heat network operation for calculating Carbon Emission
Factors and primary energy use for Part L compliance purposes ......................................................... 29
Appendix D Olympic Park Long Term Cooling Network Carbon Emission Factors and Data Inputs for
use in preparing Energy Statements for Reserved Matters Planning Applications ............................... 35
Appendix E Olympic Park Cooling Network Carbon Emission Factors and Heat Sources for use in
Part L Compliance Calculations .............................................................................................................. 41
Appendix F Agreement Flow Chart .................................................................................................... 45
Appendix G Information for BREEAM assessments ........................................................................... 46
2
Queen Elizabeth Olympic Park, Stratford City and Adjacent Areas Community Energy Network Concession
Information for Developers of Commercial-only Developments (May 2017)
Guidance
Section Summary of changes Version
Appendix B and (Heating network data for use in energy modelling calculations for energy February 2017
Appendix C statements and for Part L respectively) updated to reflect changes to the
heat generation plant mix and plant efficiencies.
Appendix D and (Cooling network data for use in energy modelling calculations for energy February 2017
Appendix E statements and for Part L respectively) updated to reflect changes to the
cooling generation plant mix and plant efficiencies
Section 7.2 and Added to provide information on the NOx emission credits and Leak February 2017
Appendix G Detection credits that can be obtained in building assessment
methodologies. These new additions have been provided in response to
requests from design teams for this information.
General Change record added. Minor additions and cosmetic changes to the February 2017
document format.
Appendix A Updated to reflect updated connection charges and annual service and May 2017
energy charges for the period 1st April 2017 to 31st March 2018.
Section 6.2 Additional guidance added determining appropriate numbers of May 2017
sub-stations
3
Queen Elizabeth Olympic Park, Stratford City and Adjacent Areas Community Energy Network Concession
Information for Developers of Commercial-only Developments (May 2017)
1 Introduction
1.1 Background
The construction of the Queen Elizabeth Olympic Park (Olympic Park) for the London 2012 Olympic
and Paralympic Games included a commitment to provide a combined cooling, heat and power
(CCHP) generation facility and heating and cooling distribution networks on the site. This was part of
the Sustainable Development Strategy for the London 2012 Games and in particular was designed to
deliver substantial carbon savings in line with the London Plan and progressively tighter government
legislation. The network was designed to serve the London 2012 Games and the Legacy
development of the Olympic Park. It also serves Stratford City.
The Community Energy Network was realised by means of a 40-year Concession Agreement with the
combined aims of achieving competitive energy prices for consumers while making it easier and
more cost effective for development to meet carbon reduction targets. The Concession was
procured by the Olympic Delivery Authority (ODA) by means of an OJEU procedure. When it became
operational in 2010 it was the largest single investment in a district energy scheme to have been
made to date in the UK.
4
Queen Elizabeth Olympic Park, Stratford City and Adjacent Areas Community Energy Network Concession
Information for Developers of Commercial-only Developments (May 2017)
The Concession Employer is the London Legacy Development Corporation (LLDC) jointly with
Stratford City Developments Limited (SCDL). ODA was initially joint employer with SCDL but its role
transferred to LLDC after the Games.
Part of the function of the Concession is to provide a quasi-regulatory framework, as there is no
independent regulation of district heating in the UK. The Concession envisages and enshrines a spirit
of mutual understanding and co-operation between the parties.
The Concession Agreement establishes key performance criteria and minimum service level
provisions that ENGIE must meet. It also establishes key requirements for the joint employers,
including defining the process for the timely procurement of a successor energy company to operate
and upgrade the Energy Network after the current initial 40 year concession expires. This is to
ensure the continued provision of heating and cooling services beyond the initial concession period.
Pricing of connections and the heating and cooling energy supplies to commercial and residential
developers are established by means of a price control formula (PCF), which is subject to
procedurally defined reviews. The PCF embodies a requirement for the Concession’s cost of energy
to be less than or equal to the “avoided cost” of widely available comparable alternatives.
Key requirements for developers and consumers include:
Entering into a Connection Agreement with ENGIE for the provision of heating or cooling
services. This among other things defines the maximum heating (and in some cases cooling)
demand required and associated charges for making a connection;
Entering into Supply Agreements with ENGIE. These establish ENGIE’s service obligations in
providing heat (and in some cases cooling) to consumers and the charges that consumers will
pay in return for those services.
Designing and constructing secondary distribution networks and heating and cooling supply
systems within the developers’ buildings or plot in accordance with a Technical Specification
provided by ENGIE.
The Technical Specification aims to ensure that secondary network systems are designed to enable
efficient operation of the network as a whole, for example by enabling appropriate flow and return
temperatures and by avoiding unnecessary wastage of heat.
5
Queen Elizabeth Olympic Park, Stratford City and Adjacent Areas Community Energy Network Concession
Information for Developers of Commercial-only Developments (May 2017)
responsibility for maintenance operation or billing in relation to the secondary network. ENGIE can
provide secondary metering and billing services beyond the bulk meter as part of the Connection
Agreement, subject to request from, and agreement with, the developer.
For Residential and Mixed Residential/Commercial Developments ENGIE will provide a full heat
metering and billing service to the end consumer, avoiding the need for developers to make their
own long term arrangements. This information note covers Commercial Only connections, however,
a separate note is available providing a summary of arrangements for Residential and Mixed
Residential/Commercial Developments.
A summary of the process for taking forward connection agreements is described in section 4.
7
Queen Elizabeth Olympic Park, Stratford City and Adjacent Areas Community Energy Network Concession
Information for Developers of Commercial-only Developments (May 2017)
2
Your Sustainable Guide the Queen Elizabeth Olympic Park 2013.
http://queenelizabetholympicpark.co.uk/~/media/QEOP/Files/Public/Misc%20documents/LLDC_Your_sustainability_guide
_to_the_Queen_Elizabeth_Olympic_Park2030.pdf
3
Carbon Offset – Local Plan Supplementary Planning Document. LLDC. August 2016
8
Queen Elizabeth Olympic Park, Stratford City and Adjacent Areas Community Energy Network Concession
Information for Developers of Commercial-only Developments (May 2017)
Reserved matters planning applications must be accompanied by an Energy Statement that sets out
how these standards have been addressed. If for any reason the required carbon reduction
standards cannot be met on site, the LCS requirement is that any shortfall in the targets would need
to be met by payments into the LLDC Offset Fund at £46 per residual annual tonne of CO2 emissions
for 30 years. Since LCS Planning Permission was granted LLDC has adopted a carbon offset policy
with a potential carbon price of £60 per annual tonne of CO2, for 30 years. Note that this is a
maximum capped figure, with the amount payable based on scheme viability.
The heat network and CCHP engines and biomass boilers that serve it have been designed to make a
substantial contribution to delivering the targets.
9
Queen Elizabeth Olympic Park, Stratford City and Adjacent Areas Community Energy Network Concession
Information for Developers of Commercial-only Developments (May 2017)
The template documents that form part of the Connection Agreement include a Technical
Specification for both commercial and residential mixed use developments.
Developers should make early contact with ENGIE to develop all technical aspects of the primary
connection and secondary network in consultation with them, to gain the benefit of ENGIE’s
experience, and to minimise the risk of disagreements and disputes. The Development Corporation
will aim to participate actively in the process to ensure consistency of approach across all
developments in the Olympic Park.
The key contractual stages in getting connected to the network are summarised below:
4
The Connection Agreement includes a Technical Specification for the Secondary Network.
10
Queen Elizabeth Olympic Park, Stratford City and Adjacent Areas Community Energy Network Concession
Information for Developers of Commercial-only Developments (May 2017)
The developer and design teams are encouraged to engage with ENGIE as early as possible to
ensure that essential connection arrangements can be made on time and to the technical
standards required.
ENGIE’s key point of contact for network connections is Peter Hamnett. Developers should first
make contact with Peter to set up an initial meeting with ENGIE, the developer’s M&E consultant
and a representative from LLDC, at which the process can be explained and the developer’s
requirements can be discussed.
Peter’s contact details are as follows:
Peter Hamnett
ENGIE
King’s Yard
1 Waterden Road
Queen Elizabeth Olympic Park
London
E15 2GP
Mobile: 07870 251863
peter.hamnett@engie.com
Following the initial meeting ENGIE will issue a Request for Information Form. This will require the
following information to be provided by the developer:
Details of the development including floor areas by development type, and numbers and
types of residential units;
Peak demand and annual heat demand estimates for the development; and
Development timescales including anticipated start on site, building completion dates and
phasing arrangements, and estimated “heat on” dates.
Following receipt of a completed Connection Request Form, ENGIE under the terms of the
Concession Agreement is obliged to prepare a Connection Offer setting out the proposed costs of
connection, in accordance with the regulated charges. This will need to be reviewed and agreed by
the developer before reaching a signed Connection Agreement.
Following the signed Connection Agreement, a process of design reviews and inspections is followed
for the secondary network design and the secondary network construction. Assuming the design and
installation has been carried out in accordance with the Connection Agreement and associated
Technical Specification, formal acceptance of the secondary network will be achieved and a
connection established.
Agreed connection charges are paid in stages according to the following schedule:
11
Queen Elizabeth Olympic Park, Stratford City and Adjacent Areas Community Energy Network Concession
Information for Developers of Commercial-only Developments (May 2017)
a) 40% of the Connection Charge will be paid by the developer ten business days after the
effective date of the Connection Agreement;
b) 20% of the Connection Charge will be paid by the developer six months after the effective
date of the Connection Agreement;
c) 20% of the Connection Charge will be paid by the developer twelve months after the
effective date of the Connection Agreement; and
d) the final 20% of the Connection Charge will be paid by the developer when the Connection is
established and available for commencement of the supply of heat.
Note that any risk related to development timing sits with the developer and not with ENGIE, and
connection charges become due strictly in accordance with the agreed schedule.
The process for establishing Supply Agreements will be set out by ENGIE as part of developing the
Connection Agreement.
12
Queen Elizabeth Olympic Park, Stratford City and Adjacent Areas Community Energy Network Concession
Information for Developers of Commercial-only Developments (May 2017)
5
CP1 2015, Heat Networks: Code of Practice for the UK, CIBSE / ADE, 2015
13
Queen Elizabeth Olympic Park, Stratford City and Adjacent Areas Community Energy Network Concession
Information for Developers of Commercial-only Developments (May 2017)
6.1 Wayleaves
Where the primary heating or cooling network crosses or enters a development plot, a wayleave
needs to be provided. The required wayleave is 1.5m from the outside edge of the outer pipe on one
side and 5m from the outside edge of the outer pipe on the other side. The wider 5m wayleave on
one side is to allow for vehicles to drive along and be parked should maintenance or pipe
replacement be required. The 1.5m is the required excavation zone. Developers should ask ENGIE to
provide an up to date network arrangement drawing showing the installed locations of the primary
network, prior to developing plot layouts and zonal masterplans. A primary network easement
drawing can be provided by ENGIE on request.
shutdowns for maintenance or to make new connections to the primary network. In the rare event
that a shutdown is required, the temporary plant will ensure an uninterrupted supply of heat while
any necessary works are carried out.
The temporary plant will include containerised boiler plant, an electrical generator, and fuel tanks
for the boiler and ancillaries. The spaces must be within 20m of a connection point to the primary
network. They could be located in car parks, in lay-bys, in wider pieces of road, on otherwise grassed
areas that may need to be strengthened, etc. The spaces will be used very rarely, but if needed they
must be capable of being occupied by temporary plant within a matter of hours. Developers should
liaise with ENGIE to ensure that design proposals have adequately addressed this requirement.
15
Queen Elizabeth Olympic Park, Stratford City and Adjacent Areas Community Energy Network Concession
Information for Developers of Commercial-only Developments (May 2017)
16
Queen Elizabeth Olympic Park, Stratford City and Adjacent Areas Community Energy Network Concession
Information for Developers of Commercial-only Developments (May 2017)
energy use of homes and buildings connected to the heat network, as required by Part L of Building
Regulations.
When considering emissions for biomass this guidance note and the illustrative CO2 emission factors
included in Appendix B and Appendix C use primary energy and carbon dioxide emission factors for
‘Solid fuel: wood chips’ taken directly from SAP Table 12. These are assumed for both domestic and
non-residential buildings, as the biomass boilers serving the network burn wood chip. For non-
domestic buildings, in the context of the Olympic Park community energy network it is considered
incorrect to apply the ‘biomass’ figure quoted in the National Calculation Method (NCM) Modelling
Guide Table 26 to a building served (in part) by a standalone woodchip boiler. The figure in Table 26
corresponds to the entry for ‘Community heating schemes: heat from boilers – biomass’ in SAP
Table 12, which is for the national average mix of heating fuels (note ‘o’). It is considered less robust
to take a national average figure for biomass when the fuel type and source can clearly be identified
as wood chip. Applying the SAP Table 12 factors results in higher primary energy use but
significantly lower carbon dioxide emissions than using the ‘biomass’ figure in the NCM Modelling
Guide Table 26.
17
Queen Elizabeth Olympic Park, Stratford City and Adjacent Areas Community Energy Network Concession
Information for Developers of Commercial-only Developments (May 2017)
criteria. Please contact 'peter.hamnett@engie.com' for the appropriate documentation that can be
submitted as part of a BREEAM assessment.
18
Queen Elizabeth Olympic Park, Stratford City and Adjacent Areas Community Energy Network Concession
Information for Developers of Commercial-only Developments (May 2017)
A.1 Introduction
This note is intended to provide developers with an early understanding of the likely charges for
making a connection to the Olympic Park heat and cooling networks for commercial developments
and the likely cost of the heat or cooling supplied. The primary cooling network does not serve all
planning delivery zones and cooling will only be available in those zones where the primary network
has been installed to facilitate this.
Under the terms of a commercial connection, ENGIE is responsible for:
Providing one or more heat (and/or cooling) connection with the developer’s secondary
network(s).
Responsible for metering the bulk heat (and/or cooling) supplied from the primary network
to the substation(s) that provide the interface with the secondary network.
The developer will be responsible for all metering and billing services for individual customers
connected to their secondary network.
19
Queen Elizabeth Olympic Park, Stratford City and Adjacent Areas Community Energy Network Concession
Information for Developers of Commercial-only Developments (May 2017)
If a Connection Variation is required for a Connection, any increased Connection Charge will be
based on a unit cost as per the table above. A Connection Variation might occur where the heat
loads were underestimated at the time of the original connection.
20
Queen Elizabeth Olympic Park, Stratford City and Adjacent Areas Community Energy Network Concession
Information for Developers of Commercial-only Developments (May 2017)
?
21
Queen Elizabeth Olympic Park, Stratford City and Adjacent Areas Community Energy Network Concession
Information for Developers of Commercial-only Developments (May 2017)
Table 1: Summary of long term data provided by ENGIE to assist with SAP 2012 and SBEM
calculations to support planning stage Energy Statements
B.2 Background
B.2.1 Policy S.2 Energy in new development (LLDC Local Plan 2015-31)
The LLDC Local Plan was adopted on 21 July 2015 and expects carbon reductions from new
developments to be in line with London plan policy 5.2, for which GLA provides guidance.
6
https://www.london.gov.uk/priorities/planning/strategic-planning-applications/preplanning-application-meeting-
service/energy-planning-gla-guidance-on-preparing-energy-assessments
7
While the modelling for Energy Statements to support Reserved Matters applications uses ‘Part L software’, and may be
referred to as ‘Part L modelling’, the approach and some inputs used when modelling for Energy Statements are different
from those that must be used when modelling with the same software to demonstrate compliance with Building
Regulations later in the development process.
22
Queen Elizabeth Olympic Park, Stratford City and Adjacent Areas Community Energy Network Concession
Information for Developers of Commercial-only Developments (May 2017)
GLA’s March 2016 guidance confirms that a target of zero regulated CO2 emissions will apply to
homes in major developments from 1 October 2016, with “at least a 35 per cent reduction in
regulated carbon dioxide emissions (beyond Part L 2013) on-site”. From the 1st October 2016 non-
domestic development must achieve a 35% reduction in regulated emissions on site. Zero carbon is
expected to apply for non-domestic buildings from 2019 but no guidance is provided on the
definition for zero carbon for non-domestic buildings.
Condition LCSO.124 of the Legacy Communities Scheme planning application established a
requirement for a site wide 20% reduction in regulated CO2 emissions from on site renewable
generation sources. This target was established based on contemporary GLA guidance for calculating
the renewable percentage. At that time the CO2 reduction achieved from renewables was expressed
as a percentage of the remaining emissions after savings from efficiency and CHP/district heating
had been deducted. In April 2015, GLA updated their guidance on the preparation of energy
statements and the percentage is now calculated by dividing the CO2 reduction achieved from
renewables by the Part L regulated emissions baseline without first deducting the savings from
efficiency and CHP. For the same CO2 saving from renewables the stated percentage reduction will
now be lower under the new calculation methodology than it was previously. While Energy
Statements should follow the latest GLA guidance in presenting the savings achieved, for reserved
matters applications needing to demonstrate that Condition LCSO.124 has been met, developers
should include an additional section setting out the percentage savings that would have been
achieved by the calculation methodology in place at the time condition LCSO.124 was set and which
was used in the Energy Statement that accompanied the Legacy Communities Scheme outline
application8.
8
Legacy Communities Scheme Regulation 22 and additional information submission. Revised Energy Statement. AECOM.
February 2012 Ref: LCS-GLB-ACC-ENST-002
23
Queen Elizabeth Olympic Park, Stratford City and Adjacent Areas Community Energy Network Concession
Information for Developers of Commercial-only Developments (May 2017)
9 th
Talal Khan of ENGIE Email to AECOM 19 December 2014.
24
Queen Elizabeth Olympic Park, Stratford City and Adjacent Areas Community Energy Network Concession
Information for Developers of Commercial-only Developments (May 2017)
10
The Government’s Standard Assessment Procedure for Energy Rating of Dwellings version 9.92 October 2013.
11 th
Email from Talal Khan ENGIE to AECOM 19 December 2014
25
Queen Elizabeth Olympic Park, Stratford City and Adjacent Areas Community Energy Network Concession
Information for Developers of Commercial-only Developments (May 2017)
In Table 4 the total heat loss from generator to consumer is derived from the following formula,
where heat losses are expressed as a decimal fraction between 0 and 1:
Total heat loss = 1 - ((1 - % Primary Network Loss) x (1 - % Secondary Network Loss))
In addition to heat losses, the SAP 2012 calculation assumes a default Parasitic Electricity Factor of
1% of the heat load to take account of the CO2 emissions for the electricity used to pump the heat
supplied. This also needs to be included when developing a carbon factor for non-residential
buildings.
26
Queen Elizabeth Olympic Park, Stratford City and Adjacent Areas Community Energy Network Concession
Information for Developers of Commercial-only Developments (May 2017)
27
Queen Elizabeth Olympic Park, Stratford City and Adjacent Areas Community Energy Network Concession
Information for Developers of Commercial-only Developments (May 2017)
Olympic Park
(ODA Site) Stratford City
Olympic Park No Secondary No Secondary
(ODA Site) Network Stratford City Network
Heat split
Proportion of heat from biomass 20.5% 20.5% 4.9% 4.9%
Proportion of heat from gas boilers 10.8% 10.8% 22.0% 22.0%
Proportion of heat from CHP 68.7% 68.7% 73.1% 73.1%
Delivered heat
Delivered heat from biomass boilers 0.205 0.205 0.049 0.049 kWh
Delivered heat from gas boilers 0.108 0.108 0.220 0.220 kWh
Delivered heat from CHP 0.687 0.687 0.731 0.731 kWh
Total heat delivered 1.000 1.000 1.000 1.000 kWh
Heat losses (% of heat generated)
Primary Heat losses % of heat generated 6.5% 6.5% 5.5% 5.5%
Secondary Heat losses % of heat supplied to
15.0% 0.0% 15.0% 0.0%
secondary network
Total Heat losses % of heat generated 20.5% 6.5% 19.6% 5.5%
Distribution loss factor 1.258 1.069 1.245 1.058
Heat generated
Heat generated by biomass boilers 0.258 0.219 0.061 0.052 kWh
Heat generated by gas boilers 0.135 0.115 0.274 0.233 kWh
Heat generated by CHP 0.865 0.735 0.910 0.773 kWh
Total heat generated 1.258 1.069 1.245 1.058 kWh
Generator and network efficiencies
Energy Centre Biomass Boiler Efficiency 79.88% 79.88% 79.88% 79.88%
Energy Centre Gas Boiler Efficiency 82.33% 82.33% 84.80% 84.80%
Energy Centre CHP Thermal Efficiency 36.89% 36.89% 37.20% 37.20%
Energy Centre CHP Electrical Efficiency 39.40% 39.40% 38.38% 38.38%
Parasitic' electricity factor 1.00% 1.00% 1.00% 1.00%
Delivered fuel
Biomass fuel delivered 0.323 0.274 0.076 0.065 kWh
Gas delivered to gas boilers 0.164 0.140 0.323 0.274 kWh
Gas delivered to CHP engines 2.344 1.992 2.446 2.079 kWh
Electricity generated from CHP 0.923 0.785 0.939 0.798 kWh
Electrical energy for heat distribution 0.013 0.011 0.012 0.011 kWh
Carbon emission factors
Biomass 0.016 0.016 0.016 0.016 kgCO /kWh
Mains Gas 0.216 0.216 0.216 0.216 kgCO /kWh
?
Grid Supplied Electricity 0.519 0.519 0.519 0.519 kgCO /kWh
?
Grid Displaced Electricity 0.519 0.519 0.519 0.519 kgCO /kWh
?
Carbon emissions ?
Biomass carbon emissions 0.005 0.004 0.001 0.001 kgCO /kWh
Gas boiler carbon emissions 0.036 0.030 0.070 0.059 kgCO /kWh
?
Gas CHP carbon emissions 0.506 0.430 0.528 0.449 kgCO /kWh
?
Emissions for heat distribution 0.007 0.006 0.006 0.005 kgCO /kWh
?
Gas CHP electricity credit emissions -0.479 -0.407 -0.487 -0.414 kgCO /kWh
?
Total emissions factor (kgCO /kWh) 0.074 0.063 0.119 0.101 kgCO? /kWh
?
?
Table 6 Derivation of Carbon Factors for Use in Preparing Energy Statements
28
Queen Elizabeth Olympic Park, Stratford City and Adjacent Areas Community Energy Network Concession
Information for Developers of Commercial-only Developments (May 2017)
C.1 Summary
This note provides information that developers and their design teams may need when carrying out
calculations to demonstrate compliance with criterion 1 of Building Regulations Approved
Documents L1A and L2A 2013.
For Part L 2013 SAP modelling for dwellings, information is required on the proportion of heat
delivered from each generator, the generator efficiencies, and the heat losses in the network up to
the point of connection with the dwelling. For Part L 2013 modelling for non-domestic buildings, only
a carbon factor for the district heating supply is entered into the calculation software. This is
determined from the same information required for SAP calculations. The heat losses assumed in
the calculation need to take account of losses in both the ENGIE East London Energy (ENGIE) primary
network up to the heat substation as well as losses in any secondary network connecting from the
heat substation to the consumer. Figures are provided in Table 7 for two examples, one where no
secondary network is present, for example where there is a direct connection to a commercial
building, and one assuming secondary network losses of 15%. Where a secondary network is present
developers and their design team should make their own assessment of losses and amend the
secondary heat loss factor and hence the total carbon emission factor in Table 7 accordingly.
Versions of this guidance published up to April 2015 contained separate information for calculating
Part L emission factors for the Olympic Park12 and Stratford City developments respectively. As of
this version (October 2016) a single network figure has been published for Part L reflecting the fact
that the two interlinked networks are increasingly being operated as a single network.
The performance of the network will change over time as additional loads are connected. This note
is based on data provided by ENGIE for the period January 2016 to December 2016 inclusive taking
into account the heat loads that are expected to have been connected over that period.
12
The Olympic Park boundary is referred to in the Concession Agreement as the ‘ODA Site’.
29
Queen Elizabeth Olympic Park, Stratford City and Adjacent Areas Community Energy Network Concession
Information for Developers of Commercial-only Developments (May 2017)
OLYMPIC PARK HN
Secondary No secondary
network with network
15% losses
Heat Splits
Proportion of heat from gas boilers 25.0% 25.0%
Proportion of heat from CHP 47.0% 47.0%
Proportion of heat from biomass 28.0% 28.0%
Heat losses % of heat generated
Primary Heat losses % of heat generated 10.6% 10.6%
Secondary Heat losses % of heat supplied to 15.0% 0.0%
secondary network
Total Heat losses % of heat generated 24.0% 10.6%
Generator and Network Efficiencies
30
Queen Elizabeth Olympic Park, Stratford City and Adjacent Areas Community Energy Network Concession
Information for Developers of Commercial-only Developments (May 2017)
13 nd
Email from Paul Woods ENGIE to AECOM 22 June 2016.
14
Email from Paul Woods ENGIE to AECOM 28th June 2016
15
The Government’s Standard Assessment Procedure for Energy Rating of Dwellings version 9.92 October 2013.
16 th
Email from Paul Woods ENGIE to AECOM 28 June 2016
31
Queen Elizabeth Olympic Park, Stratford City and Adjacent Areas Community Energy Network Concession
Information for Developers of Commercial-only Developments (May 2017)
Where a secondary network is provided, for example to serve each home in a residential
development, design teams will need to take account of the additional heat losses for the secondary
network. Supply agreements for the CEN assume that ENGIE will cover the cost of the heat losses in
the secondary network up to a level of 15% of the heat consumed by the development. The costs of
any losses above 15% are shared equally between consumers and will appear on their bill. Design
teams should make their own assessment of heat losses and ensure these are less than 10% to
account for potential performance gaps and avoid these charges. ENGIE can provide advice on how
to design to achieve low heat losses.
Table 10 summarises the percentage heat losses for the primary network only and for illustrative
purposes the total that would result assuming secondary network losses of 15%. It also shows the
equivalent Distribution Loss Factor that would be entered into SAP.
Overall network
Heat Losses: 15%* No Secondary
Secondary Network
Network
losses
ENGIE Primary Network Loss (% of heat generated) 10.6% 10.6%
Assumed Secondary Network loss (% of heat supplied 15.0% 0.0%
to the secondary network that is lost before reaching
the consumer)
Total Heat Loss (% of heat lost from the generator to 24.0% 10.6%
the consumer)
SAP Distribution Loss Factor 1.316 1.119
*This is an illustrative figure only design teams must calculate their own secondary
losses and use these in calculations
Table 10 Illustrative Heat Loss Inputs
In Table 10 the total heat loss from generator to consumer is derived from the following formula,
where heat losses are expressed as a decimal fraction between 0 and 1:
Total heat losses = 1 - ((1 - % Primary Network Loss) x (1 - Secondary % Network Loss))
In addition to heat losses the SAP 2012 calculation assumes a default Parasitic Electricity Factor of
1% of the heat load to take account of the CO2 emissions for the electricity used to pump the heat
supplied. This also needs to be included when developing a carbon factor for non-residential
buildings.
32
Queen Elizabeth Olympic Park, Stratford City and Adjacent Areas Community Energy Network Concession
Information for Developers of Commercial-only Developments (May 2017)
33
Queen Elizabeth Olympic Park, Stratford City and Adjacent Areas Community Energy Network Concession
Information for Developers of Commercial-only Developments (May 2017)
Overall network
Secondary Heat Network Losses: 15% None
Total Heat losses % of heat generated 24.0% 10.6%
Distribution loss factor 1.316 1.119
Heat generated [kWh]
Heat generated by biomass boilers 0.368 0.313
Heat generated by gas boilers 0.329 0.280
Heat generated by CHP 0.619 0.526
Total heat generated 1.316 1.119
Energy Gas Boiler Efficiency 84.00% 84.00%
Energy Centre CHP Thermal Efficiency 38.00% 38.00%
Energy Centre CHP Electrical Efficiency 39.00% 39.00%
Energy Centre Biomass Boiler Efficiency 84.00% 84.00%
Parasitic' electricity factor 0.010 0.010
Delivered fuel [kWh]
Gas delivered to gas boilers 0.392 0.333
Gas delivered to CHP engines 1.628 1.383
Electricity generated from CHP 0.635 0.540
Electrical energy for heat distribution 0.013 0.011
Biomass fuel delivered 0.439 0.373
Mains Gas 0.216 0.216
Grid Supplied Electricity 0.519 0.519
Grid Displaced Electricity 0.519 0.519
Biomass 0.016 0.016
Carbon emissions [kgCO₂/kWh]
Gas boiler carbon emissions 0.085 0.072
Gas CHP carbon emissions 0.352 0.299
Emissions for heat distribution 0.007 0.006
Gas CHP electricity credit emissions -0.329 -0.280
Biomass carbon emissions 0.007 0.006
Total emissions 0.121 0.102
34
Queen Elizabeth Olympic Park, Stratford City and Adjacent Areas Community Energy Network Concession
Information for Developers of Commercial-only Developments (May 2017)
D.1 Summary
This note provides information that developer’s and their design teams may require when preparing
Energy Statements to support reserved matters planning applications and for demonstrating that
planning energy and CO2 targets have been met where buildings are connected to the Community
Energy Network.
Energy Statements prepared for planning applications in London are typically based on the CO2
emissions expected for normal operation at the full build out of the plant and equipment. Different
inputs based on performance to date will be required for approved Part L software when preparing
Building Regulations applications and these are covered by a separate note (See Appendix E).
The current and future cooling network is not expected to supply cooling to residential buildings.
This note only considers information required for non-residential buildings. If developers are
considering connecting residential buildings to the cooling network they will need to seek further
information from ENGIE.
For non-residential buildings information is required on the proportion of cooling delivered from
each source, the efficiency of the plant used to generate cooling and the losses in the network up to
the point of connection with the building. This information is used to calculate the carbon emission
factor for the district cooling supply. The emission factor is used to determine the equivalent
Seasonal Energy Efficiency Rating (SEER) required for SBEM or equivalent modelling software.
The carbon factor needs to take account of losses in ENGIE’s primary network up to their cooling
substation. ENGIE have confirmed that these losses should be set to 2%. Figures are provided in
Table 13 for the two designated site areas of the Olympic Park and Stratford City.
Olympic Park Stratford City
(ODA Site)
Heat losses: Assuming no secondary network
Cooling split
Proportion of cooling from vapour compression chillers 32.1% 67.3%
Proportion of cooling from absorption chillers 67.9% 32.7%
Cooling losses (% of cooling generated)
Total cooling losses % of cooling generated 2.0% 2.0%
Generator and network efficiencies
Energy centre absorption chiller efficiency 123% 123%
Energy centre vapour compression chiller efficiency 450% 450%
Energy centre CHP thermal efficiency 37.0% 37.0%
Energy centre CHP electrical efficiency 39.0% 39.0%
Total emission factor per unit of cooling (kgCO 2/kWh) 0.058 0.089
Total SEERequivalent 8.88 5.82
Table 13: Summary of long term data provided by ENGIE to assist with SBEM calculations to support
planning stage Energy Statements
35
Queen Elizabeth Olympic Park, Stratford City and Adjacent Areas Community Energy Network Concession
Information for Developers of Commercial-only Developments (May 2017)
D.2 Background
17
https://www.london.gov.uk/what-we-do/planning/planning-applications-and-decisions/pre-planning-application-
meeting-service-0
18
While the modelling for Energy Statements to support Reserved Matters applications uses ‘Part L software’, and may be
referred to as ‘Part L modelling’, the approach and some inputs used when modelling for Energy Statements are different
from those that must be used when modelling with the same software to demonstrate compliance with Building
Regulations later in the development process.
36
Queen Elizabeth Olympic Park, Stratford City and Adjacent Areas Community Energy Network Concession
Information for Developers of Commercial-only Developments (May 2017)
renewables was expressed as a percentage of the remaining emissions after savings from efficiency
and CHP/district heating had been deducted. In April 2015, GLA updated their guidance on the
preparation of energy statements and the percentage is now calculated by dividing the CO2
reduction achieved from renewables by the Part L regulated emissions baseline without first
deducting the savings from efficiency and CHP. For the same CO2 saving from renewables the stated
percentage reduction will now be lower under the new calculation methodology than it was
previously. While Energy Statements should follow the latest GLA guidance in presenting the savings
achieved, for reserved matters applications needing to demonstrate that Condition LCSO.124 has
been met, developers should include an additional section setting out the percentage savings that
would have been achieved by the calculation methodology in place at the time condition LCSO.124
was set and which was used in the Energy Statement that accompanied the Legacy Communities
Scheme application19.
37
Queen Elizabeth Olympic Park, Stratford City and Adjacent Areas Community Energy Network Concession
Information for Developers of Commercial-only Developments (May 2017)
network operators. The figures presented in this note have been based on ENGIE’s prediction of how
the network will be operating by 2033.
20 th
Talal Kahn of ENGIE Email to AECOM 19 December 2014.
38
Queen Elizabeth Olympic Park, Stratford City and Adjacent Areas Community Energy Network Concession
Information for Developers of Commercial-only Developments (May 2017)
D.4.1 CO2 Calculation for Building Part L Energy and Carbon Modelling
For SBEM or equivalent approved calculations for non-residential buildings it is not possible to adjust
the cooling fuel or carbon factor of the fuel. It is assumed that local electric chillers are used and the
option to select district or communal cooling is not available. To correctly calculate the cooling
carbon emissions it is necessary to adopt an SEER which is equivalent to the ratio of the ENGIE
network carbon factor to grid electricity (SAP 2012 Table 12).
The carbon factor used to determine the SEER is calculated from the cooling split, generator
efficiencies, cooling losses, parasitic electricity use, CHP electricity generated, and the respective
emission factors for the fuels used and displaced. The network carbon factor is used to calculate the
SEER as demonstrated below:
SEERequivalent = grid electricity carbon factor / cooling network carbon factor
Table 17 provides the derivation of the emission factors for the two sites.
Olympic Park (ODA
Site) Stratford City Units
Heat losses: Assuming No Secondary Network
Cooling split
Proportion of cooling from VC chillers 32.1% 67.3%
Proportion of cooling from absorption chillers 67.9% 32.7%
Delivered heat (for cooling)
Delivered cooling from VC chillers 0.321 0.673 kWh
Delivered cooling from absorption chillers 0.679 0.327 kWh
39
Queen Elizabeth Olympic Park, Stratford City and Adjacent Areas Community Energy Network Concession
Information for Developers of Commercial-only Developments (May 2017)
40
Queen Elizabeth Olympic Park, Stratford City and Adjacent Areas Community Energy Network Concession
Information for Developers of Commercial-only Developments (May 2017)
E.1 Summary
This note provides information that developer’s and their design teams may require when carrying
out calculations to demonstrate compliance with criterion 1 of Building Regulations Approved
Document L2A 2013 when connecting to the Community Energy Network. Separate figures are
provided for the Olympic Park and Stratford City developments respectively.
The current and future cooling network is not expected to supply cooling to residential buildings.
This note only considers information required for non-residential buildings. If a developer is
considering connecting residential buildings to the cooling network they will need to seek further
information from ENGIE East London Energy (ENGIE).
For non-residential buildings information is required on the proportion of cooling delivered from
each source, the efficiency of the plant used to generate cooling and the losses in the network up to
the point of connection with the building. This information is used to calculate the carbon emission
factor for the district cooling supply. The emission factor is used to determine the equivalent
Seasonal Energy Efficiency Rating (SEER) required for SBEM or equivalent modelling software for
Part L2A 2013.
The carbon factor calculation needs to take account of losses in ENGIE’s primary network up to their
cooling substation. ENGIE have confirmed that the primary losses are negligible and should be set to
2%. Figures are provided in Table 18 for the two designated sites: Olympic Park and Stratford City.
The performance of the network will change over time as additional loads are connected. This note
is based on data provided by ENGIE for the period April 2017 to March 2018.
Olympic Park Stratford City
(ODA Site)
Heat losses: Assuming no secondary network
Cooling split
Proportion of cooling from vapour compression chillers 60.0% 84.0%
Proportion of cooling from absorption chillers 40.0% 16.0%
Cooling losses (% of cooling generated)
Total cooling losses % of cooling generated 2.0% 2.0%
Generator and network efficiencies
Energy centre absorption chiller efficiency 123% 123%
Energy centre vapour compression chiller efficiency 450% 450%
Energy centre CHP thermal efficiency 37.00% 37.00%
Energy centre CHP electrical efficiency 39.00% 39.00%
Total emission factor per unit of cooling (kgCO 2/kWh) 0.083 0.104
Total SEERequivalent 6.27 5.00
Table 18 Summary of data provided by ENGIE to assist with Part L2A 2013 compliance calculations
41
Queen Elizabeth Olympic Park, Stratford City and Adjacent Areas Community Energy Network Concession
Information for Developers of Commercial-only Developments (May 2017)
21
Email from Paul Woods ENGIE to AECOM. 16 January 2017
42
Queen Elizabeth Olympic Park, Stratford City and Adjacent Areas Community Energy Network Concession
Information for Developers of Commercial-only Developments (May 2017)
E.3.1 CO2 Calculation for Part L2A Energy and Carbon Modelling
For SBEM or equivalent approved calculations for non-residential buildings it is not possible to adjust
the cooling fuel or carbon factor of the fuel. It is assumed that local electric chillers are used and the
option to select district or communal cooling is not available. To correctly calculate the cooling
carbon emissions it is necessary to adopt an SEER which is equivalent to the ratio of the ENGIE
network carbon factor to grid electricity (SAP 2012 Table 12).
The carbon factor used to determine the SEER is calculated from the cooling split, generator
efficiencies, cooling losses, parasitic electricity use, CHP electricity generated, and the respective
emission factors for the fuels used and displaced. The network carbon factor is used to calculate the
SEER as demonstrated below:
SEERequivalent = grid electricity carbon factor / cooling network carbon factor
43
Queen Elizabeth Olympic Park, Stratford City and Adjacent Areas Community Energy Network Concession
Information for Developers of Commercial-only Developments (May 2017)
Table 22 provides the derivation of the emission factors for the two sites.
Olympic Park (ODA
Site) Stratford City Units
Heat losses: Assuming No Secondary Network
Cooling split
Proportion of cooling from VC chillers 60.0% 84.0%
Proportion of cooling from absorption chillers 40.0% 16.0%
Delivered heat (for cooling)
Delivered cooling from VC chillers 0.600 0.840 kWh
Delivered cooling from absorption chillers 0.400 0.160 kWh
Total cooling delivered 1.000 1.000 kWh
Cooling losses
Heat gain % of cooling generated 2.0% 2.0%
Secondary heat gain % of cooling supplied to secondary
0.0% 0.0%
network
Total cooling losses % of cooling generated 2.0% 2.0%
Distribution loss factor 1.020 1.020
Cooling generated at Energy Centres
Cooling generated by VC chillers 0.612 0.857 kWh
Cooling generated by absorption chillers 0.408 0.163 kWh
Total cooling generated 1.020 1.020 kWh
Generator and network efficiencies
Energy centre absorption Chiller COSP 123.0% 123.0%
Energy centre VC Chiller COSP 450.0% 450.0%
Energy centre CHP Thermal Efficiency 37.00% 37.00%
Energy centre CHP Electrical Efficiency 39.00% 39.00%
'Parasitic' electricity factor (% of cooling) 0.00% 0.00%
Heat generated (for absorption chiller)
Heat generated by CHP (for absorption) 0.332 0.133 kWh
Delivered fuel
Electricity delivered for VC chillers 0.136 0.190 kWh
Gas delivered to CHP engines 0.897 0.359 kWh
Electricity generated from CHP 0.350 0.140 kWh
Electrical energy for cooling distribution 0.000 0.000 kWh
Carbon emission factors
Mains gas 0.216 0.216 kgCO₂/kWh
Grid electricity 0.519 0.519 kgCO₂/kWh
Grid displaced electricity 0.519 0.519 kgCO₂/kWh
Carbon emissions
Electric chiller carbon emissions 0.071 0.099 kgCO₂/kWh
Gas CHP carbon emissions 0.194 0.077 kgCO₂/kWh
Emissions for cooling distribution 0.000 0.000 kgCO₂/kWh
Gas CHP electricity credit emissions -0.182 -0.073 kgCO₂/kWh
Total emissions 0.083 0.104 kgCO₂/kWh
Total SEERequivalent 6.27 5.00 kW/kW
Table 22 Derivation of Carbon Factors for Use in Part L compliance calculations
44
Queen Elizabeth Olympic Park, Stratford City and Adjacent Areas Community Energy Network Concession
Information for Developers of Commercial-only Developments (May 2017)
45
Queen Elizabeth Olympic Park, Stratford City and Adjacent Areas Community Energy Network Concession
Information for Developers of Commercial-only Developments (May 2017)
Outcomes for the Olympic Park community energy network are as follows:
BREEAM 2014: No credits will be achieved as the calculated NOx emissions are found to be
over 200mg/kWh
22
Or a scheme consisting of multiple buildings.
46
Queen Elizabeth Olympic Park, Stratford City and Adjacent Areas Community Energy Network Concession
Information for Developers of Commercial-only Developments (May 2017)
The cooling provided by the network is generated by multiple Vapour Compression chillers
and an Absorption Chiller.
The refrigerants used are ammonia and a water/lithium bromide mixture.
The resultant Direct Effect Life Cycle CO2 equivalent emissions (DELC CO2e) is found to be less
than 100 kgCO2e/kW which achieves 2 credits under ‘Pol 01’ for lifecycle impact of
refrigerants.
For the purpose of BREEAM, water/lithium bromide mixture is classed as natural and
environmentally benign refrigerants by the BRE and does not require leak detection.
Leak detection is required for the ammonia based chillers, and this has been provided.
Therefore the leak detection credit will be achieved for the cooling network.
All 3 of the maximum 3 ‘Pol 01’ credits can be achieved.
As part of a formal BREEAM assessment, evidence is required to demonstrate compliance with the
criteria. Please contact 'peter.hamnett@engie.com' for the appropriate documentation that can be
submitted as part of a BREEAM assessment.
47
Queen Elizabeth Olympic Park, Stratford City and Adjacent Areas Community Energy Network Concession
Information for Developers of Commercial-only Developments (May 2017)
48