MINUTES OF MEETING on 25 Sep 2019

Project Name : Solar Rooftop Project for Big C

Subject : Big C Weekly meeting

Meeting With : ISL,SSSA Document no. : BIGC-SSA-GL-230

ISL office & Line conference


Location and time : Recorded by : ISL
(10:00 PM – 12:30 PM)

Participant Company Participant Company

ISL
Kullamas Udomkijja Via Line Call

Theerarat Suwansichon ISL

Kanhapong Sangsithianukaul SSSA

Siwarut Suwanlapaporn SSSA

Aniwat Choosong SSSA

Jathurong Phansombun SSSA

Acknowledged by

_________________________ _________________________ _________________________


ISL SSSA

Document no : BIGC-SSA-GL-
230 1
Item

Discussion and Conclusion in the meeting

Due Date

Status

Action By

Acknowledged by

_________________________ _________________________ _________________________


ISL SSSA

Document no : BIGC-SSA-GL-
230 2
1.

LD phase of phase 1.2

- Sharp will submit the waived date and evident to ISL.  within 5 Mar’19

- SSSA would like to propose the condition for LD counting

- SSSA will send draft letter to ISL K.Kullamas & P’Songsak

- To be hold and to be discussed later

- SSSA will upload BNYN handover package soft-file within 5 Apr

- ISL will submit BYST with comment back to SSSA within 2 Apr and SSSA will submit BYST back (only soft-file

without sign) within 5 Apr

- SSSA will submit BPHR hard copy (without sign) within 3 Apr

- Without BAYY, ISL will conclude the VO and send to SSSA

- SSSA will correct data for relief LD of phase1.2 within 15th July 2019

- SSSA will correct data for relief LD of phase1.2 within 17th July 2019

- SSSA will send LD letter Phase 1.2 to ISL by Yoshimi San within 17th July 2019

- ISL will confirm meeting time & schedule to clarify the email

- LD clarification meeting is required, SSSA proposed tentative on 21th Aug between ISL and SSSA. ISL request

for support document for clarification first

- SSSA submitted letter no. SSSA-ISL-LTR-19-003 on 4th September (1 from 3). SSSA will submit other 2 letters

later and ISL will check and reply back.

- SSSA submitted to ISL on 11 Sep 19, waiting leader of ISL confirm

Note : ISL recommend SSSA follow SPI purchase status

1-Mar-19

20 Mar’19

17 Jul’19

21 Jul’ 19

23 Aug’ 19

11 Sep’ 19

19 Sep’ 19

Hold until #1.2 completed

Yoswaris/

Kanhapong/

Yoshimi San

2.

INSURANCE :

Acknowledged by

_________________________ _________________________ _________________________


ISL SSSA

Document no : BIGC-SSA-GL-
230 3
BWNY: Sharp is requested to provide the additional documents for ISL’s insurance claim;

- Claim letter stating quantity and price of damaged items

- Supporting documents to confirm the claim price i.e. quotations, invoices

- Copy of the overall contract work showing summary of project value.

- Copy of the contract work including BOQ showing the price of damage item.

- Project schedule for the contract work.

- Drawing diagram or other document showing the size and length of the damage cable and also highlight the location

damage cable.

K. Salang will provide document to claim.

SSSA will send draft letter for ISL to submit insurance

- SSSA already submitted on 26 Mar, waiting for ISL conclude with insurance and will inform SSSA later

- ISL requests SSSA to clarify and breakdown the cost from last letter (BWNY-SSA-GL-404 Rev.A BOQ). SSSA will bring

the clarification and information, then will discuss in the meeting on 3 May 2019

- Recovery Work schedule, Delivery & working plan schedule and submit to ISL

***Check contract about Force Majeure > ISL request SSSA to minimize the schedule and discuss again on 3 May 2019

- ISL requested Time line of this incident and actions / responses from SSSA

- Add commissioning work into schedule plan.

- Add Warranty condition to be same as original in the letter.

- ISL requested SSSA to consider and confirm about payment term (how many % advance payment, and the left ISL will

pay SSSA after received money from their Insurance)

- SSSA will insert the payment term on the quotation and submit to ISL for confirmation.

- ISL requested to revise Quotation breakdown Item#1, exclude SPD VO work, and attach all Specification in original

documents submission. And resubmit with new transmittal sheet.

- SSSA will update number in excel file and S-curve compare between plan and actual. And revise and create new report

of all Monthly reports (1 to 4 Months) for Insurance purpose only.  tentative 26 Jun’19

- ITE will negotiate Asefa to reduce the price and will prepare original quotation from Asefa. And the meeting with

insurance will be setup.

- Additional VO of SPD of BWNY will be submitted to ISL within 19 Jun’19.

- Revise MC plan at 97.5% on xxx (due to demobilization 2.5% // OM training 1% on xxx)

Plan curve follow original project schedule, 100% on xxx.

Remove out the recovery plan.

- Revised quotation by breakdown the detail for insurance submission. And also revise the notice letter by remove the

date and VO letter as well. >>> SSSA already revised on 20 th June 2019.

- Revise term of payment to be 10% down payment & 20% once Relay, PQM & Also panel arrived at site. And 70% after

work completion within 30 days. >>> SSSA already revised on date 20 th June 2019

- SSSA submitted all in transmittal no BWNY-SSA-GT-022

Acknowledged by

_________________________ _________________________ _________________________


ISL SSSA

Document no : BIGC-SSA-GL-
230 4
- SSSA will add schedule for both BWNY and BHD1

- 30th Aug will update progress

- (K.Salang Incharge)

- SSSA will inform schedule plan about BWNY on 9 th Aug 2019

- SSSA will update number in excel file and S-curve compare between plan and actual work.

Also revise and create new report of all Monthly reports (1 to 5 Months) for Insurance

 SSSA submitted on 20th Aug

- Re-issue BOQ (in contract) and resubmit to ISL

- Revise wording in quotation and resubmit to ISL

- Submit communication diagram and cloud claiming items with explanation

- ISL requested to send S-curve and detail in timeline + lead time process

- Issue with transmittal document no.

- SSSA confirm sent document on 16 Sep 19

- SSSA waiting ISL reply back on 20 Sep 19

- ISL send detail to insurance, waiting insurance team review. <Closed>

BWCR : Heavy storm incident <- issue closed

- SSSA will update number in excel file and S-curve compare between plan and actual. And revise and create new report

of all Monthly reports (1 to 4 Months) for Insurance purpose only.  tentative 19 Jun’19

- Revise MC plan at 97.5% on 7 Jul’18 (due to demobilization 2.5% // OM training 1% on 5 Jul’18)

Plan curve follow original project schedule, 100% on 26 Jul’18.

Remove out the recovery plan.

- SSSA submitted all in transmittal no BWCR-SSA-GT-036

9 Mar’19

22 Mar 19 26 Mar’19

30 Apr 19

3 May’ 19

13 May’19

24 May’19

28 May’19

26 June’19

Open

Acknowledged by

_________________________ _________________________ _________________________


ISL SSSA

Document no : BIGC-SSA-GL-
230 5
Yoswaris / K.Monthicha / K.Kanhapong

- Insurance requested more detail in timeline + layout plan with replacement PV module

- Schedule relief also need to revise date to match with the realistic

- SSSA confirm sent document on 16 Sep 19.

- SSSA revised time line for attach COD date, layout replacement PV module and revised schedule within 20 Sep 19

- SSSA will revised as K.Songsak comment and sent back to ISL on 25 Sep 19

4.

BHD1 : Heavy storm incident

 SSSA will update number in excel file and S-curve compare between plan and actual. And revise and create new

report of all Monthly reports (1 to 4 Months) for Insurance purpose only.  tentative 3 Jul’19

 Insurance request to take photos all 34 damaged(37-3=34 ) PV panels,

 Revise incident report and recheck actual amount of damage within 18 Jun’19.

 ISL requested SSSA design team to re-arrange the marked PV type B to reinstallation in the same string.

 Klip lock for new roof to be confirmed by SSSA whether no any issue.

 ISL requested SSSA to issue VO (insurance scope) to ISL for approval (since insurance claim process quite take

time)

 Revise MC plan at 97.5% on xxx (due to demobilization 2.5% // OM training 1% on xxx)

Plan curve follow original project schedule, 100% on xxx.

Remove out the recovery plan.

 ISL confirmed that BHD1 shall be same type ND_AF320 only.

If no more 320W type, then ISL agreed to relocate ND-AF320 PV panels from BBPI and to be used for BHD1.

SSSA will submit proposal with Engineering documents to ISL.

***But anyway within 45+7 days from 18 Jun’19 BHD1 shall be completed.

 ISL requested if SSSA want to relocate PV 320W from BBPI, SSSA need to relocate

Total 1 inverter, not only 2 strings <<< SSSA will discuss internally and will submit

“Letter of Clarification” on the next meeting

 SSSA will add schedule for BWNY , BHD1 and BBRR

- (K.Aekapol Incharge)

 SSSA will update number in excel file and S-curve compare between plan and actual work.

Also revise and create new report of all Monthly reports (1 to 5 Months) for Insurance

Acknowledged by

_________________________ _________________________ _________________________


ISL SSSA

Document no : BIGC-SSA-GL-
230 6
 tentative 31 August’19

 SSSA will rearrange PV string to collect all PV(with problem including footprint) to connect together

 SSSA will recheck all PV which affected by heavy storm and will submit report to ISL for power output

confirmation, SSSA confirm by current & voltage than other than failure 34 modules operating normally

 ISL requested SSSA to submit letter clarification of PV module model changing (320 -> 330). SSSA will submit

letter within 30th Aug 2019 and will submit revised quotation of 330W model to ISL,

 Letter no. SSSA-LTR-BIGC-034 Clarification letter for changing PV model was submitted on 19 Sep 19

 SSSA will submit technical clarification letter of changing from 320W -> to 330W total 36 modules. ISL will claim to

insurance total 36 modules.

 Revised drawing can use only cloud concept to show and add note to explain difference of 320 , 330 installation,

SSSA will submitted within 27 Sep 19

 SSSA will inform timeline + schedule of lead time and installation of changing to 330W

 Request letter to clarify technical using 36 PV modules.

 SSSA submit letter for confirmation quotation to ISL with timeline process procurement & installation on 20 Sep

19

 SSSA inform to ISL that location of new PV module 330W has to install on existing roof because distance of “u”

follow manual can’t install on new SCG roof. Result is SSSA will change location PV module 330W to existing roof

and submit layout PV module to ISL on 27 Sep 19

BBRR : (K.Patiwat Incharge)

 SSSA will update number in excel file and S-curve compare between plan and actual work.

Also revise and create new report of all Monthly reports (1 to 5 Months) for Insurance

 tentative 7 September’19

 PEA still confirmed on 7th Aug that BBRR will finish grid connection for BBRR within August

 Schedule relief letter for BBRR should revise to write down only starting date

 ISL inform concept first synchronization before relocation equipment.

10 July’19

12 July’19

Acknowledged by

_________________________ _________________________ _________________________


ISL SSSA

Document no : BIGC-SSA-GL-
230 7
24 Jul 19

29 Aug 19

Open

Kanhapong/

Laksamee

3.

Project Document submission schedule;

Acknowledged by

_________________________ _________________________ _________________________


ISL SSSA

Document no : BIGC-SSA-GL-
230 8
Project NTP 1st MC to Permanent Handover Package
Phase KWP NTP MC
Name to MC Synch 1st sync Sync. (Add responsibility)

BOYI 992.25
31-Jul-17 15-Dec-17 89 31-Jul-18 228 22-Aug-18 Completed, M7 25 Jun’19
BSSW 992.25
31-Jul-17 15-Dec-17 129 24-Jan-19 405 12-Feb-19 Completed
BIGC
1.1 BLKB 992.25
31-Jul-17 22-Dec-17 98 26-Sep-18 278 26-Sep-18 COC done // wait M7
Completed, M7 25 Jun’19 roof
BPTN 996.48
11-Sep-17 09-Feb-18 109 20-Jul-18 161 11-Aug-18 leakage, PR report pending
Ig fault, PR report pending ,
BAYY 996.48
16-Oct-17 15-Feb-18 116 12-Dec-18 300 12-Dec-18 M6 & M7 still pending
BYST 996.48
16-Oct-17 15-Mar-18 148 09-Jan-19 300 23-Jan-19 Completed, M7 25 Jun’19
7 Jun’19 SSSA received back
BIGC on 10 July 2019 , will re
BPHR 789.12
1.2 301 submit on 12th July 2019
31-Oct-17 15-Feb-18 102 13-Dec-18 13-Dec-18
BNYN 432
09-Dec-17 16-Mar-18 97 08-Jan-19 298 22-Jan-19 Completed
BTTK 587.52
13-Dec-17 09-Mar-18 85 19-Dec-18 285 19-Dec-18 Completed
14 Jun’19
23-Apr-19 305 02-May-19 5 Jul’19
BKR2 875.52 Will submit on 2 Aug’ 19
SSSA submitted on 2 Sep 19
26-Feb-18 22-Jun-18 108 20 Sep re-submit
5 Jul’19
29-Apr-19 297 23-May-19 19 Jul’ 19
BSWP 576 26-Feb-18 06-Jul-18 116 Will submit on 16 Aug’ 19 30
Aug’ 19 20th September 2019
28 Jun’19
10-Apr-19 287 02-May-19 5 Jul’19
Will submit on 7 Aug’ 19
14 Aug’ 19
SSSA submitted on 26 Aug’
BDKT 564.48 26-Feb-18 27-Jun-18 79
19 and ISL will comment and
BIGC
send back on 6 Sep’19/ SSSA
1.3
confirm resubmit on 11 Sep’19
20 Sep re-submit
Will resubmit to ISL
on 12th July 2019
SSSA resubmitted to ISL on
26-Feb-19 253 13-Mar-19 24th July
BRCR
996.48 SSSA will submit CD on 5 Sep
26-Feb-18 18-Jun-18 103 -Remaining warranty letter
Submitted 21 Jun’19,
21-Mar-19 254 01-Apr-19 Reviewing by ISL SSSA
received back on 9 July
SSSA and ISL agreed to
BSKT 996.48
clarify back on 21th Aug
SSSA will submit CD on 6 Sep
ISL request report on 6 Sep
26-Feb-18 10-Jul-18 131 (Arrestor spark)
25-Jul-19
BLLK 996.48 5-July-19 277 SSSA will submit on 4 Oct
20-Jul-18 01-Oct-18 59 (remaining PR test activity)

BCYP 996.48 17-Jun-19 255 26-Jun-19 SSSA will submit on 4 Oct


BIGC 20-Jun-18 05-Oct-18 96
1.4
BBRR 766.08
20-Jul-18 02-Oct-18 62

BWNY 593.28
20-Jul-18 04-Oct-18 66
BSPY 996.48
20-Jul-18 19-Oct-18 75

Acknowledged by

_________________________ _________________________ _________________________


ISL SSSA

Document no : BIGC-SSA-GL-
230 9
21 Jun’19
test 28
on Jun’ 19 19
Relay 7th Aug
BTYR 915.84 meeting comment with ISL
SSSA rd will submit on th 27 Sep
on 3 July 2019
Zero,9 Thermo)
August
25-Jun-18 17-Oct-18 110 30-Aug-19 (without PR,
14-Mar-19 245 02-Apr-19 2019 28th Aug (tentative clarify
BLPN 846.72
BNKT 996.48 30th Aug). SSSA on will11
submit
25-Jun-18 22-Oct-18 116 20-Aug-19 302 SSSA will submit Oct 27
02-Apr-18 12-Jul-18 101 Sep
BIGC BHD1 996.48 30-Jul-19 (but Revised comments,
2.2 1-Aug-18 19-Nov-18 110 18-Jul-19 241 off 2 inverters) 21 Jun’19,
SSSA will resubmit
will submit on 25 Oct
07-Feb-19 209 13-Mar-19 3rd July 2019 15th August 2019
BLPG 996.48
SSSA will clarify thon 21th Aug
BKTK 478.08 Relay test on 29 Aug 19 Aug
BIGC 2019 tentative clarify 23rd
2.1 Project 14-Jun-18
02-Apr-18 18-Oct-18
13-Jul-18 93 to
NTP
102 9-Sep-19
1st MC to 1st Permanent SSSA
Handoverwill submit
Submitted CD on on
Package 19 11SepOct
Phase KWP NTP MC
Name MC Synch sync Sync. (Add responsibility)
BPKN 512.64 Relay test on 28th Aug 19
BNWK 996.48 14-Jun-18 19-Oct-18 98 10-May-19
9-Sep-19 295 24-May-19 15 Jul’19
SSSA willon 20th September
submit on 25 Oct
02-Apr-18 19-Jul-18 104 2019
BBDG 633.6
27-Aug-18 05-Dec-18 94 10-Sep-19 SSSA will submit
28 Jun’19, on 18 Oct
will submit
BHD2 593.28 22-Mar-19 254 03-Apr-19 SSSA
BPBR 887.04 3rd Julywill
2019submit
19th on 252019
Aug Sep 18
27-Aug-18
02-Apr-18 10-Dec-18
11-Jul-18 100
100 6-Sep-19 18
20thOct
Sep
BIGC
2.3 28 Jun’19
Relay test 22
nd
on 27August
th 2019
Aug 19
BCB2 806.4
27-Aug-18 10-Dec-18 103 01-Apr-19
17-Sep-19 244 18-Apr-19 SSSA will
SSSA submitted
submit 2on Sep
nd
16 Oct
BWCR 552.96
-SSSA will submit CD &
BRET 702.72 02-Apr-18 31-Jul-18 117 handover final 30 Sep
27-Aug-18 02-Dec-18 97 SSSA will submit on 31 Oct
Bad weather calculates 15
BBPI 581.79
05 Apr’19 9-Aug-19 83 days.

BCTR 997.92 75 Bad weather calculates 21


05 Apr’19 30-Jul-19 days.
BIGC
3 BPCB 997.92 76 Bad weather calculates 3 days.
05 Apr’19 1-Aug-19

BKBI 997.92 77 Bad weather calculates 9 days


05 Apr’19 31-Jul-19

4.

Zero export test of Huawei inverter;

Currently ALSO is not able to control the response time of Huawei inverter (more than 13sec response time)

-SSSA will send the letter about this problem to follow this Zero export issue, and continue advance testing with

existing condition in order to complete the handover project document submission first -> SSSA will submit letter

within 5 Apr.

-final zero export report to be submitted later

- BSKT , BLPG , BHD2 , BWCR zero export test will continue even Alsoenergy cannot finish after 3 Apr.

SSSA will issue letter about this delaying to ISL > 26 April 2019

25 April 2019 - BDKT BKR2

26 April 2109 - BLPG BWCR

30 April 2019 - BSKT BSWP

BHD2 waiting for changing PQ

- Follow up Report from BLPN and BRCR (within 29 April 2019)

- Waiting SSSA update.

-ISL requested to specific the minimum response time of PEA setting, less than 30sec and worst case 13 second of

first 4 sites. SSSA will revise the letter and official submit to ISL.--> changed to notice by email.

- BSWP waiting Alsoenergy to confirm testing date of Zero export test.

- ISL prefer to confirm system communication whether affect to zero export function or not in ph#3.  Sunglow

informed that it should no issue for 3 circuits, INV 3 ports // Relay, PQM & EDMI in 1 port // Also (weather

station)

- ***Urgent! ISL requested official document to clearly explain that Sungrow INV able to perform Zero

export function (before relay operating)

Acknowledged by

_________________________ _________________________ _________________________


ISL SSSA

Document no : BIGC-SSA-GL-
230 10
- SSSA plan to do zero export trial testing around middle of August (after installation completion)

Zero export test & report table status: <<< SSSA will submit on 17th July 2019

and will continuous update

- SSSA will attach as separate file to minutes of meeting

- Pending schedule test and report on 13 Sep

- SSSA submit to ISL some site but ISL comment back to SSSA, remaining SSSA revise document. SSSA will

create tracking document for track progress work submit to ISL on 30 Sep

22 Mar’19

19 Apr’ 19

30 Apr’ 19

13 May’19

24 May’19

28 May’19

6 June’19

26 June’19

Middle of Aug’ 19

17 July’19

7 Aug’19

23 Aug’ 19

13 Sep’19

Open

K.Laksamee

5.

PQM setting :

- OM team will submit PQM setting for Phase# 1.1, 1.2, 2.1 within 30 Jun’19

- SSSA OM team will start at the same time with SPD installation work, after ISL confirm VO. OM team will

estimate time after one phase done for more precise schedule plan.

- Week#21will start from Phase#1.1

- To be performed same period of additional SPD installation, now is waiting SPD delivery around end of July’19

- SSSA will submit setting of phase 1.1 to ISL first

- SSSA will attach download record data from PQM start from handover package ph#1.2

- SSSA (PM Team) will download record data from PQM and start from

Acknowledged by

_________________________ _________________________ _________________________


ISL SSSA

Document no : BIGC-SSA-GL-
230 11
handover package phase # 1.2, 1.3, 1.4, 2.1, 2.2, 2.3

- SSSA will submit in excel file (not hard-copy)

28 Jun’19

#1.1 submit in 19 Jul’ 19

2 Aug’ 19

21 Oct 19

Open

Yoswaris/ K.Salang/

K.Kanhapong

6.

BKR2: Low PR

-SSSA will continue PR test record and analysis the root cause in parallel.

-Temp sensor not proper fixing to backside PV panel.

- SSSA will resend PR testing report and remark about root cause & attach the corrective photo after re-installation.

- SSSA already checked the installation of PV temperature sensor and found it properly installed.

- SSSA will plan schedule to recheck 4 inverters which cause low power output compared to other inverters  after

checked they are normal.

- Recheck and reinstall Temp sensor, then calculation 3 days PR

- SSSA inform that now checking and solution then will inform to ISL on 17th July 2019

- SSSA confirming and will send to ISL on 24th July 2019 on 30th Aug 19

- SSSA will submit new report to ISL

- SSSA has to confirm PR test date (why change data from previous submission). SSSA has to submit PDF (previous

data)

- SSSA re-submit original data in PDF file.

17 May’’19

24 May’19

31 May’19

14 Jun’19

21 Jun’19

28 Jun’ 19

10 July’ 19

17 July’ 19

24 July 19

Acknowledged by

_________________________ _________________________ _________________________


ISL SSSA

Document no : BIGC-SSA-GL-
230 12
30 Aug 19

11 Sep 19

Open

Closed

Yoshimi San

7.

BHD2: PQM & Dropout Fuse

-SSSA will send incident report and urgently replace dropout fuse to be 200A on Phase A&C (PEA replaced by using

50A as temporary)

- PQM rectification and recovery works under insurance claim process.

Wait ISL confirm the quotation to SSSA

- Revise quotation of Dropout Fuse replacement resend to ISL.

- Insurance requested for damaged fuse picture but because SSSA doesn’t have so insurance requested for

replacement picture instead.

- SSSA will submit failure report of dropout fuse

- To be updated next meeting

- ISL inform to SSSA that this case does not waiting ISL’s insurance confirmation ,

And ISL would like SSSA to submit “VO letter and Quotation” then ISL will sign it later.

-SSSA Submitted in transmittal no (BIGC-SSA-GT-080) on 4th July 2019

-ISL inform SSSA that ISL is waiting Insurance approval also

- SSSA will submit burnt picture for insurance -> SSSA already sent on 25th July 2019.

Now ISL pending from insurance (insurance already approved but waiting for money transferring only) within 13 Sep

19

- SSSA will share data download PQM to ISL on 23 Sep 19 >> Combine table PQM download data

10 May’’19

24 May’19

29 May’19

14 Jun’19

21 Jun’19

5 Jul’ 19

10 Jul’ 19

11 Sep 19

Open

Closed

ISL

Acknowledged by

_________________________ _________________________ _________________________


ISL SSSA

Document no : BIGC-SSA-GL-
230 13
8.

BPHR: PQM & ARK damaged due to 22kV line fault from the Tree

-PQM already replaced

-Remain damage of communication port of ARK, to be replaced, waiting new spare for replacement.

-Within 21 Jun’19 the quotation will be obtained and will claim to insurance and execute the work

-ISL requested to recheck and confirm the material defect lot from also,

If it come from material defect.

-SSSA will confirm ARK status back within 28th Jun’ 19 (will summarize all record and send to ISL)

- SSSA inform to ISL that waiting quotation PQM (Janitza) from ITE and will submit on the

Next meeting and ISL would like SSSA to submit “VO letter and Quotation”

then ISL will sign it later.

-ISL informed to SSSA that will check status this situation still can claim insurance or not?

ISL inform to SSSA that actually this case is too late for claim ISL insurance

But ISL said let SSSA try to submit VO letter and Quotation to ISL within 23 rd July 2019

-ISL informed to SSSA about accident that should be inform accident within 30 days

- SSSA will revise quotation that breakdown unit rate of ARK & Janitza -> 23rd Aug 2019 SSSA will submit ISL on 18

Sep 19

- ISL requested to submit revised claiming report followed BHD2 pattern so ISL will submit to insurance (use previous

PFR-19001 to modify)

- SSSA discussion and submit data on 23 Sep 19

28 Jun’ 19

10 Jul’ 19

23 July 19

13 Aug 19

23 Aug 19

11 Sep 19

18 Sep 19

Open

Closed

K.Aekkapol / K.Kanhapong

9.

Huawei spare part

1) Star wrench

2) USB flash drive (Bluetooth)

Acknowledged by

_________________________ _________________________ _________________________


ISL SSSA

Document no : BIGC-SSA-GL-
230 14
-SSSA will order and inform delivery time line to ISL on 3 rd July 2019

- SSSA will check quantity of each item then will inform to SSSA on 24 th July 2019

- SSSA will check quantity of each item then will inform to SSSA on 14 th Aug 2019

- SSSA will check quantity of each item then will inform to SSSA on 30 th Aug 2019

- SSSA will submit spare part big C phase 1.3 (Without BSWP) & 2.1 (BLPG, BPLN) , submitted on 11 Sep 19

- SSSA submitted spare part Big C phase 2.1 (BWCR) on 16 Sep 2019

- Big C phase 2.1 remaining BNWK, BHD2 within October 19

* Note : For the item spare part has no item, SSSA will show VO deduct item or purchase new spare part for submit ISL. >>

SSSA will draft VO deduct product other item not in contract to ISL for review on 2 Oct 19

10 Jul’ 19

17 Jul’ 19

24 July 19

14 Aug 19

30 Aug 19

11 Sep 19

16 Sep 19

October 19

Open

K.Kanhapong

10.

JAS

-SSSA inform ISL that will submit Handover package of JAS on 24th July 2019

- PR test , SSSA did but not yet send to ISL

- SSSA will submit other package except civil calculation and PR first

- SSSA shall submit pending document breakdown progress to ISL every week

- SSSA will recheck PR test report

- Update status pending document to ISL on Friday 23th Aug, SSSA submit hand over package not all item remaining

below;

1. PR test not submit, will be submit on 23 – 27 Sep 19 >> Submitted on 25 Sep 19

2. Calculation ( submitted 3 document)

24 July’19,

13 Aug 19

20 Sep

Acknowledged by

_________________________ _________________________ _________________________


ISL SSSA

Document no : BIGC-SSA-GL-
230 15
(JAS)

Open

K.Laksamee,

K.Kanhapong,

Yoswaris

11.

BNKT

-ISL inform SSSA that PEA will takeoff Relay for test and PEA will be test finish

On 10th July 2019. If PEA available on the next week ,

ISL will appointment PEA to do first sync later. Then ISL request SSSA to do trip test also.

-ISL required soft file from SSSA , will submit next meeting

-ISL informed 1st sync schedule 20th Aug 2019

-SSSA will prepare spare Bluetooth USB and prepare application in phone for PEA checking

-PEA already witnessed 1st synchronization on 20th Aug but failed.

-SSSA will fix grounding following PEA comment

-ISL requested for weekly report to update progress

- SSSA will submit clarify document protection angle to ISL on 6 Sep

-SSSA request fix grounding follow PEA comment on 7 Sep 2019, remaining M7 (BNKT) reply back to SSSA.

- PEA comment receptacle in PQM meter has to install for PQM test, combine ground HV and equipment, clamp

steel wire not match 2 material.

- SSSA revised ground system on 8 Sep 19 and will submit report on 17 Sep 19

- SSSA will submit drawing and photo directly to PEA Kor.3 on 20 Sep 19 23 Sep 19 but PEA has comment on

drawing that re-submitted on 27 Sep 19

17 Jul’19,

24 July 19

20 Aug 19

7 Sep 19

17 Sep 19

20 Sep 19

27 Sep 19

Open

K.Laksamee,

K.Kanhapong,

Yoswaris

12.

Acknowledged by

_________________________ _________________________ _________________________


ISL SSSA

Document no : BIGC-SSA-GL-
230 16
-ISL request will test Relay Modbus Communication (Change parameter of trip status)

At BTYR first. SSSA will inform to ISL later

-SSSA inform to ISL that will change testing to supplier area office and will inform date to ISL later. And also can

comply to all relay model all site or not? (Question from ISL)

- SSSA will confirm relay testing at ASEFA factory whether on 2nd Aug back to ISL

-> SSSA will submit modbus address to ISL for Alsoenergy to confirm only for BTYR

-SSSA will submit relay testing+setting back to ISL for reconfirmation with Alsoenergy

-SSSA will submit testing function 81 after

-SSSA will update next week

- SSSA request closely due date of test relay. >> Target testing date at BSPY site

17 Jul’19,

24 July 19,

2 Aug 19

7 Aug 19

21 Aug 19

11 Sep 19

Open

K.Laksamee,

K.Kanhapong,

Yoswaris

13.

ISL requested to install 2 TVs in ISL office

- ISL required VO reduction TV all project and VO addition TV for Office also, SSSA will clarify within 18 Sep 19

- SSSA submitted TVx2 set installation check sheet on 16 Sep 19

- SSSA clarify ISL will purchase new TV all site to ISL. ISL request unit price and delivery date from SSSA on 20 Sep

19

- SSSA confirm delivery TV 2 Pcs to Big C on 4 Oct 19. For the other remaining TV, ISL requests SSSA confirm

delivery date.

25 July’19

23 Aug’ 19

6 Sep’ 19

16 Sep 19

20 Sep 19

4 Oct 19

Acknowledged by

_________________________ _________________________ _________________________


ISL SSSA

Document no : BIGC-SSA-GL-
230 17
Open

Closed

Open

K.Aekkapol/

K.Kanhapong,

14.

BRCR & BSKT :

- ITE will submit Calculation & Drawing , Technical Clarification letter ,

Extend Warranty more 1 year (Only Cable tray) to ISL

- Draft letter for BSKT, BRCR sizing should be submitted within Friday 23th Aug (warranty should cover all

cable+tray in inverter house)

- SSSA submitted warranty letter to ISL on 11 Sep and ISL reject the letter.

- SSSA will resubmit new warranty (DC cable) letter to ISL on 19 Sep 19 20 Sep 19 2 Oct 19

7 Aug’19

13 Aug’ 19

23 Aug’ 19

11 Sep’ 19

19 Sep’ 19

20 Sep 19

2 Oct 19

Open

K.Laksamee,

K.Kanhapong/

ITE

15.

ISL required SSSA to confirm site for Comparison Foundation Calculation at

BigC Phase # 1,2,3 (Which project have casting concrete slab that double floor slab

for inverter house)

- SSSA will update project list and send email

- ISL requested SSSA to confirm including adding foundation on existing concrete slab (not only in second floor)

-- Please see on page No.16

- Clarify result of calculation should be pass all site within 20 Sep 19 30 Sep 19

Acknowledged by

_________________________ _________________________ _________________________


ISL SSSA

Document no : BIGC-SSA-GL-
230 18
7 Aug’19

13 Aug’ 19

28 Aug’ 19

4 Sep’ 19

20 Sep 19

30 Sep 19

Open

K.Laksamee,

K.Kanhapong

16.

DM ph#3 VO deduct because using ISL meter within 17 Sep 19 27 Sep 19

11 Sep 19

17 Sep 19

27 Sep 19

Open

Kanhapong

17.

BigC#1,2,3 :

Ground rod at 22kV pole will be separated between lightning and equipment

- ISL request plan re-work, SSSA will submit later

- SSSA will send table list on 17 Sep 19 and clarify data on 19 Sep 19

OHGW cable

- ISL requested SSSA to check all sites and move OHGW cable to top of equipment

- ISL request addition check sheet for recheck grounding and overhead ground wire

17 Sep 19

Open

Siwarut / Laksamee / Kanhapong

18.

BSPY :

- Relay testing on end of August or early of September

- ISL will submit letter to claim ARK from ITE and SSSA will forward to ITE

- ITE installed ARK to BSPY on 31 Aug 19

- ISL submitted to SSSA on 22 Aug 19

- ISL request modify source of shunt trip at ACC that has to use source from UPS follow PEA recommend

- Remaining revised internal wiring ACC for submit ISL&PEA, SSSA will submit to ISL on 16 Sep 19 -> SSSA

Acknowledged by

_________________________ _________________________ _________________________


ISL SSSA

Document no : BIGC-SSA-GL-
230 19
already submitted but now pending for PEA approval

- SSSA will confirm UPS connection on site within 4th October 25 Sep 19

- ISL request to recheck PQM setting and preparing power quality meter to recheck normal PF

16 Sep 19

4 Oct 19

Open

Laksamee / Kanhapong

19.

BTYR :

- SSSA will clear tree on CTPT on electrical pole by contacting PEA (subcontractor) for removing work.

- SSSA will confirm back the tree removing schedule to ISL

- OM training Big C on 5 Sep 19

- SSSA will reply plan to shut down date for remove tree and revise PQM (tentative 30 Sep 19)

- PQM parameter , relay parameter >> report will submit 27 Sep 19

- Grounding + OHGW checking in same time

- Inverter room has water on floor <- need to

23 Aug’ 19

30 Sep 19

Open

Kanhapong / Laksamee

20.

BCB2

- Testing relay tentative in 27 August 2019

- Add comment from Line massage BCB2 as P’Songsak comment

- Relay tested on 27 Aug 19 with PEA

- First synchronization with PEA on 17 Sep 19

- Big C already changes CAP. BANK and SSSA has to change re-setting inverter to normal state after PQM

removed.

- Re-setting over voltage of relay

- SSSA will re-issue parameter for discussion with ISL before re-setting on 30 Sep 19

27 Aug’ 19

17 Sep 19

30 Sep 19

Open

Kanhapong / Laksamee

21.

Acknowledged by

_________________________ _________________________ _________________________


ISL SSSA

Document no : BIGC-SSA-GL-
230 20
KSSP

- SSSA can submit KSSP red mark first (which already revised comment)

- SSSA shall submit pending document breakdown progress to ISL every week

- Update status pending document to ISL on Friday 23rd Aug 2019

Input target

Open

Kanhapong / Laksamee

22.

Overall weekly report 1 page

- All sites should submit until handover date (site by site that not get letter COC yet)

information

Kanhapong

23.

Organization chart

- ISL requested to submit update organization chart within this week

- SSSA submitted representative letter on SSA-LTR-BIGC-030

- SSSA submit organization chart and representative letter on 4 Sep 19 and ISL reject document

- SSSA will revised representative letter (add document number) and organization chart phase 1 & 2 on 23 Sep

19

- ISL request resume of K.Kannapong (Project Manager) on 23 Sep 19

6 Sep’ 19

19 Sep 19

Open

k.Kanhapong / k.Aniwat

24.

Performance testing report

- Recheck BAYY PR test final report and submit within this Friday

- Recheck BPTN PR test final report and submit within next week

- SSSA will send soft file of BAYY and BPTN to ISL on 16 Sep 19 with signature confirm cover page.

6 Sep’ 19

16 Sep 19

Open

k.Kanhapong / k.Aniwat

Acknowledged by

_________________________ _________________________ _________________________


ISL SSSA

Document no : BIGC-SSA-GL-
230 21
25.

- Timeline inspection activity between MC – Test relay – first sync.

11 Sep’ 19

Open

k.Kanhapong / k.Aniwat

26.

Status CD, Spare part and Hard copy hand over project summary

- SSSA will issue table list of summary status and key

- SSSA submitted on 19 Sep

16 Sep’ 19,

Open

K.Kanhapong

K.Laksamee

27.

BRET

- Relay test with PEA on 16 Oct 19

- First synch. on 17 Oct 19 (Tentative)

16 Sep’ 19,

16 Oct 19

Open

K.Kanhapong

K.Laksamee

28.

BLPN

- Using new inverter setting of overvoltage and attach in hand over document

- ISL request submit in transmittal

- SSSA submitted new inverter setting in transmittal no BPLN-SSA-025 on 19 Sep 19

28 Aug’ 19

Open

Closed

K.Kanhapong

Acknowledged by

_________________________ _________________________ _________________________


ISL SSSA

Document no : BIGC-SSA-GL-
230 22
K.Laksamee

29.

Milestone payment

- SSSA has to submit planning release payment before 5 of month for next month (for this month has to submit

before 20 Sep 19

28 Aug’ 19

Open

K.Kanhapong

K.Laksamee

30.

OM training date

- BPBR on 26 Sep 19 : 10.00 AM

- BLLK on 25 Sep 19 : 14.00 PM

- BCB2 tentative on 30 Sep 19

Information

Open

K.Kanhapong

K.Laksamee

31.

Transmittal receive document from ISL

- ISL request SSSA to issue transmittal for sign receive document when SSSA receiver document from ISL

Information

SSSA/ISL

32.

Re-setting power factor

- BKTK >> re-setting power factor and update internal wiring drawing at ACC

- BPKN >> re-setting power factor and update internal wiring drawing at ACC

- BBDG >> re-setting power factor and update internal wiring drawing at PQB

Open

SSSA/ISL

Acknowledged by

_________________________ _________________________ _________________________


ISL SSSA

Document no : BIGC-SSA-GL-
230 23
33.

Inverter operation power output

- SMA normal

- Huawei & Sungrow, power output abnormal as compare with specification of power DC input

Open

SSSA/ISL

34.

BAYY

- Ig fault report should be submit to ISL

Open

SSSA/ISL

35.

BKR2, BDKT

- Warning sign for sky light should be discuss with ISL that from JCM comment. (ISL inform this issue not VO

price)

Open

SSSA/ISL

36.

- Next meeting

2 Oct’ 19, 13:00pm

K.Kanhapong

K.Laksamee

Acknowledged by

_________________________ _________________________ _________________________


ISL SSSA

Document no : BIGC-SSA-GL-
230 24
VO work VO work VO work Download
VO work
Install Antenna Install SPD Install SPD record data PM Report
SPD in
Phase Project Name KWP Project In PQM Panel In PQM Panel from PQM
Monitoring
Manager For Monitoring For Relay
Panel
Name (PM)

992.25 Finish Finish Finish Plan Finish

Jittipat(James 29-May-19 29-May-19 4-June-19 23-Oct-19 19-Sep-19

BOYI

BIGC

1.1

BSSW 992.25 Finish Finish Finish Plan Finish

Somporn(Tum 5-June-19 5-June-19 5-June-19 24-Oct-19 19-Sep-19

BLKB 992.25 Finish Finish Finish Plan Finish

Aniwat(Grand) 31-May-19 31-May-19 31-May-19 25-Oct-19 20-Sep-19

BPTN 996.48 Jathurong Finish Finish Finish Plan Finish

(Champ) 7-June-19 7-June-19 7-June-19 26-Oct-19 19-Sep-19

996.48 Finish Finish Finish Plan Finish Change Janitza

Somporn(Tum 5-June-19 6-June-19 10-July-19 6-Oct-19 19-Aug-19 already on 12th

) July 2019

BIGC
BAYY
1.2

Acknowledged by

_________________________ _________________________ _________________________


ISL SSSA

Document no : BIGC-SSA-GL-
230 25
996.48 Finish Finish Finish Plan Finish
BYST
Patiwat(Best) 19-June-19 19-June-19 15-July-19 1-Oct-19 1-Sep-19

Finish Finish Finish Plan Finish


BPHR 789.12
Aekkapol(Ake) 14-June-19 14-June-19 18-July-19 19-Oct-19 22-Aug-19

Plan
Finish Finish
BNYN 432 Jathurong Finish 2-Oct-19 Finish
20-June-19 16-July-19
(Champ) 20-June-19 1-Sep-19

Finish Finish Finish Plan Finish


BTTK 587.52
Jittipat(James) 10-June-19 10-June-19 10-June-19 21-Oct-19 23-Aug-19

ISL request write


BIGC Finish Finish Finish
BKR2 875.52 Jittipat(James) Plan Finish in CD hand over
1.3 17-June-19 17-June-19 12-July-19
4-Oct-19 25-Aug-19 document

Finish Finish Finish Plan Finish


BSWP 576
Patiwat(Best) 19-June-19 19-June-19 15-July-19 30-Sep-19 31-Aug-19

ISL request write


Finish Finish Finish
BDKT 564.48 Jittipat(James) Plan Finish in CD hand over
18-June-19 18-June-19 13-July-19
7-Oct-19 25-Aug-19 document

Finish
BRCR Jathurong Finish Finish Plan Finish
996.48 3-August-19
(Champ) 1-July-19 1-July-19 6-Nov-19 17-Sep-19

ISL request write


Finish Finish Finish
BSKT 996.48 Somporn(Tum) Plan Finish in CD hand over
12-June-19 12-June-19 17-July-19
20-Oct-19 21-Aug-19 document

Plan Change Janitza


BIGC Finish Finish Finish
BLLK 996.48 Jittipat(James) 28-Oct-19 Finish already on 12th
1.4 10-July-19 10-July-19 10-July-19
14-Sep-19 July 2019

Finish Finish Finish Plan Finish


BCYP 996.48
Jittipat(James) 16-June-19 16-June-19 14-July-19 9-Oct-19 24-Aug-19

Finish Finish Finish Plan Waiting PEA


BBRR 766.08
Patiwat(Best) 25-Aug-19 25-Aug-19 25-Aug-19 3-Oct-19 1st Sync

Finish Finish Finish Plan Finish


BWNY 593.28 Lightning strike
Salang 11-Sep-19 11-Sep-19 11-Sep-19 7-Nov-19 12-Sep-19

Finish Finish Finish Plan Finish


BSPY 996.48
Witsawa(Bird) 13-Sep-19 13-Sep-19 9-Aug-19 29-Oct-19 13-Sep-19

BIGC BLPN 846.72 Finish Finish Finish Plan Finish

Acknowledged by

_________________________ _________________________ _________________________


ISL SSSA

Document no : BIGC-SSA-GL-
230 26
2.1 Aekkapol(Ake) 15-June-19 15-June-19 20-July-19 17-Oct-19 22-Aug-19

Finish Finish Finish Plan Finish


BLPG 996.48
Aekkapol(Ake) 19-July-19 19-July-19 19-July-19 18-Oct-19 22-Aug-19

Finish Finish Finish Plan Finish


BNWK 996.48
Somporn(Tum) 9-July-19 9-July-19 9-July-19 30-Oct-19 16-Sep-19

Finish Finish Finish Plan Finish


BHD2 593.28
Aekkapol(Ake) 15-June-19 15-June-19 20-July-19 16-Oct-19 22-Aug-19

Change Janitza
Finish Finish Finish
BWCR 552.96 Somporn(Tum) Plan Finish already on 11th
11-June-19 11-June-19 11-July-19
8-Oct-19 24-Aug-19 July 2019

BIGC Finish Finish Finish Plan Plan


BTYR 915.84
2.2 Somporn(Tum) 2-July-19 2-July-19 16-Sep-19 5-Oct-19 5-Oct-19 PQ Damage

Finish Finish Finish Plan Finish


BNKT 996.48
Krasaesin(Tube) 1-July-19 17-Sep-19 17-Sep-19 1-Nov-19 17-Sep-19

Finish Finish Finish Plan Finish


BHD1 996.48
Aekkapol(Ake) 22-Aug-19 22-Aug-19 22-Aug-19 15-Oct-19 22-Aug-19

Finish Finish Finish Plan Finish


BKTK 478.08
Patiwat(Best) 30-Aug-19 30-Aug-19 30-Aug-19 11-Oct-19 24-Sep-19

Finish Finish Finish Plan Finish


BPKN 512.64
Patiwat(Best) 27-Aug-19 27-Aug-19 27-Aug-19 10-Oct-19 28-Aug-19

BIGC Finish Finish Finish Plan Finish


BBDG 633.6
2.3 Patiwat(Best) 19-Aug-19 19-Aug-19 19-Aug-19 12-Oct-19 9-Sep-19

Finish Finish Finish Plan Finish


BPBR 887.04
Krasaesin(Tube) 18-Sep-19 18-Sep-19 18-Sep-19 2-Nov-19 18-Sep-19

Finish Finish Finish Plan Finish


BCB2 806.4
Somporn(Tum) 14-Sep-19 14-Sep-19 9-Aug-19 31-Oct-19 14-Sep-19

Finish Finish Finish Plan


BRET 702.72
Patiwat(Best) 31-Aug-19 31-Aug-19 31-Aug-19 8-Nov-19

BIGC Have in Also Finish Finish Finish


BBPI 581.79
3 Patiwat(Best) Panel 24-July-19 24-July-19 24-July-19

Have in Also Finish Finish Finish


BCTR 997.92
Krasaesin(Tube) Panel 29-July-19 29-July-19 29-July-19

Have in Also Finish Finish Finish


BPCB 997.92
Chanwit(Arm) Panel 26-July-19 26-July-19 26-July-19

BKBI 997.92 Have in Also Finish Finish Finish

Acknowledged by

_________________________ _________________________ _________________________


ISL SSSA

Document no : BIGC-SSA-GL-
230 27
Aniwat(Grand) Panel 28-July-19 28-July-19 28-July-19

Variation Install SPD in Monitoring , Antenna and SPD in PQM submission schedule (Update on 30 th September 2019)

Check Foundation Inverter Room


Remark
No. Phase Project Adding concrete slab on existing concrete slab
Update on : 9 Sep 2019
1 BigC 1.1 BOYI There is no adding concrete slab -
2 BigC 1.1 BSSW There is no adding concrete slab -
3 BigC 1.1 BLKB There is no adding concrete slab -
4 BigC 1.1 BPTN There is no adding concrete slab -
5 BigC 1.2 BAAY There is no adding concrete slab -
6 BigC 1.2 BYST There is no adding concrete slab -
7 BigC 1.2 BPHR There is no adding concrete slab -
8 BigC 1.2 BNYN There is no adding concrete slab -
9 BigC 1.2 BTTK There is no adding concrete slab -
10 BigC 1.3 BRCR There is no adding concrete slab -
11 BigC 1.3 BKR2 There is no adding concrete slab -
12 BigC 1.3 BSKT There is no adding concrete slab -
13 BigC 1.3 BDKT There is no adding concrete slab -
14 BigC 1.3 BSWP There is no adding concrete slab -
15 BigC 1.4 BSPY There is no adding concrete slab -
16 BigC 1.4 BBRR There is no adding concrete slab -
17 BigC 1.4 BLLK There is no adding concrete slab -
18 BigC 1.4 BCYP There is no adding concrete slab -
19 BigC 1.4 BWNY There is no adding concrete slab -
20 BigC 2.1 BHD2 There is no adding concrete slab -
21 BigC 2.1 BLPN There is adding concrete slab Result of calculation : Pass
22 BigC 2.1 BLPG There is adding concrete slab Result of calculation : Pass
23 BigC 2.1 BWCR There is no adding concrete slab -
24 BigC 2.1 BNWK There is no adding concrete slab -
25 BigC 2.2 BPKN There is no adding concrete slab -
26 BigC 2.2 BKTK There is no adding concrete slab -
Strength enough for
27 BigC 2.2 BTYR There is no adding concrete slab concrete 5 cm.

Acknowledged by

_________________________ _________________________ _________________________


ISL SSSA

Document no : BIGC-SSA-GL-
230 28
28 BigC 2.2 BNKT There is no adding concrete slab -
29 BigC 2.2 BHD1 There is no adding concrete slab -
30 BigC 2.3 BBDG There is adding concrete slab Result of calculation : Pass
31 BigC 2.3 BPBR There is adding concrete slab Result of calculation : Pass
32 BigC 2.3 BRET There is adding concrete slab Result of calculation : Pass
33 BigC 2.3 BCB2 There is adding concrete slab Result of calculation : Pass
34 BigC 3 BBPI There is no adding concrete slab -
35 BigC 3 BCTR There is adding concrete slab Result of calculation : Pass
36 BigC 3 BKBI There is adding concrete slab Result of calculation : Pass
37 BigC 3 BPCB There is adding concrete slab Result of calculation : Pass

Acknowledged by

_________________________ _________________________ _________________________


ISL SSSA

Document no : BIGC-SSA-GL-
230 29