MINUTES OF MEETING on 16 Apr 2020

Project Name : Solar Farm Project for KXN

Subject : Weekly meeting

Meeting With : GLD,KXN,SSSA Document no. : GLD-SSA-GL-201

Zoom conference
Location and time : Recorded by : SSSA
(14:30 PM – 16:00 PM)

Participant Company Participant Company

Mr. Johnny GLD

Mr. Viboon GLD

Mr. Souk GLD

Ms. Laksamee SSSA

Mr. Kanhapong SSSA

Mr. Nantawat SSSA

Mr. Siwarut SSSA

Mr. Natheethon SSSA

Item Discussion and Conclusion in the meeting Due Date Status Action By

GLD onsite progress updating Information - GLD/SSSA

1. - Currently, concrete pile pouring and installation

- Electrical equipment storage area is under process

SSSA requested GLD to support information of CT & PT wiring for EDMI March 2020 Closed GLD

2. - GLD waiting information from Schneider

- GLD sent wiring diagram of main switchgear to SSSA

SSSA requested GLD to support drawing of utility system to confirm that underground April 2020 Open GLD

route line will not effect to civil work.


3.
- Waiting for GDL to submit

- GLD updated utility systems drawing

Acknowledged by

_________________________ _________________________ _________________________


GLD SSSA

Document no : GLD-SSA-GL-201 1
Item Discussion and Conclusion in the meeting Due Date Status Action By

Single line diagram comment issue by SSSA April 2020 Open GLD

4. - GLD will check comment first and then feedback to SSSA

- GLD will revise the single line diagram

SSSA team will support technical onsite on 30 Mar 2020 30 Mar 2020 Closed SSSA

5. - SSSA cannot go to site because of COVID-19 but GLD asked SSSA for

online support meeting via ZOOM

SSSA requested GLD to support standard code for calculation and MV cable area March 2020 Closed GLD/SSSA

6. selection

- GLD sent standard code for calculation

GLD requested SSSA to support information for fork lift 2 tons or 4 tons selection - Closed SSSA
7.
- SSSA informed GLD to select 4 tons

GLD requested SSSA to support monitoring system information whether it can control March 2020 Closed GLD/SSSA

or manage the Power output (P , Q, S) and power factor of system or not ?

- SSSA have to discuss with supplier of monitoring and will feed back
8.
information later

- GLD confirmed to not use at this moment but requested SSSA to prepare

solution for future

9. GLD requested procedure for unloading and check sheet from SSSA March 2020 Open GLD/SSSA

10. Next meeting on 26 Mar 2020 Information - GLD/SSSA

SSSA Ask detail drawing of 22kV electrical pole. April 2020 Open GLD
11.
- GLD updated detail drawing of 22kV

12. SSSA Confirm the inverter size in your drawing correct. Information. - GLD/SSSA

SSSA informed that underground works and drainage system should be finished before Information -
13.
the rainy season.

14. SSSA asked for the position of storage area. April 2020

SSSA requested GLD to add information of equipment volume and work percent in April 2020 Closed GLD
15.
master schedule project.

SSSA asked for pond and pump station position. Because the Plant layout general April 2020 Closed GLD

16. arrangement doesn’t show position.

- GLD confirmed that this project doesn’t have pond and pump station.

17. SSSA asked for shipping date of equipment to KXN project. April 2020 Open GLD

Acknowledged by

_________________________ _________________________ _________________________


GLD SSSA

Document no : GLD-SSA-GL-201 2
Item Discussion and Conclusion in the meeting Due Date Status Action By

SSSA requested gutter detail and layout and 100 years of rainfall information for April 2020 - GLD/SSSA

18. checking the suitability of the gutter’s size.

SSSA requested GLD separate the manhole of MV cable with LV cable. April 2020 - GLD/SSSA

19. - GLD asked SSSA support standard information for separate the manhole and

distant.

20.

21.

22.

23.

24.

Acknowledged by

_________________________ _________________________ _________________________


GLD SSSA

Document no : GLD-SSA-GL-201 3

You might also like