GLD-SSA-GL-201 MOM KXN Weekly Meeting (On 16 April 2020)
GLD-SSA-GL-201 MOM KXN Weekly Meeting (On 16 April 2020)
Zoom conference
Location and time : Recorded by : SSSA
(14:30 PM – 16:00 PM)
Item Discussion and Conclusion in the meeting Due Date Status Action By
SSSA requested GLD to support information of CT & PT wiring for EDMI March 2020 Closed GLD
SSSA requested GLD to support drawing of utility system to confirm that underground April 2020 Open GLD
Acknowledged by
Document no : GLD-SSA-GL-201 1
Item Discussion and Conclusion in the meeting Due Date Status Action By
Single line diagram comment issue by SSSA April 2020 Open GLD
SSSA team will support technical onsite on 30 Mar 2020 30 Mar 2020 Closed SSSA
5. - SSSA cannot go to site because of COVID-19 but GLD asked SSSA for
SSSA requested GLD to support standard code for calculation and MV cable area March 2020 Closed GLD/SSSA
6. selection
GLD requested SSSA to support information for fork lift 2 tons or 4 tons selection - Closed SSSA
7.
- SSSA informed GLD to select 4 tons
GLD requested SSSA to support monitoring system information whether it can control March 2020 Closed GLD/SSSA
- SSSA have to discuss with supplier of monitoring and will feed back
8.
information later
- GLD confirmed to not use at this moment but requested SSSA to prepare
9. GLD requested procedure for unloading and check sheet from SSSA March 2020 Open GLD/SSSA
SSSA Ask detail drawing of 22kV electrical pole. April 2020 Open GLD
11.
- GLD updated detail drawing of 22kV
12. SSSA Confirm the inverter size in your drawing correct. Information. - GLD/SSSA
SSSA informed that underground works and drainage system should be finished before Information -
13.
the rainy season.
14. SSSA asked for the position of storage area. April 2020
SSSA requested GLD to add information of equipment volume and work percent in April 2020 Closed GLD
15.
master schedule project.
SSSA asked for pond and pump station position. Because the Plant layout general April 2020 Closed GLD
- GLD confirmed that this project doesn’t have pond and pump station.
17. SSSA asked for shipping date of equipment to KXN project. April 2020 Open GLD
Acknowledged by
Document no : GLD-SSA-GL-201 2
Item Discussion and Conclusion in the meeting Due Date Status Action By
SSSA requested gutter detail and layout and 100 years of rainfall information for April 2020 - GLD/SSSA
SSSA requested GLD separate the manhole of MV cable with LV cable. April 2020 - GLD/SSSA
19. - GLD asked SSSA support standard information for separate the manhole and
distant.
20.
21.
22.
23.
24.
Acknowledged by
Document no : GLD-SSA-GL-201 3