Structural Steel

Description Days Start Finish Remarks

Level 4
Insert Plate Fixing 10 09-05-2023 19-05-2023 Completed
Marking & Cutting MS Plate 10 08-05-2023 18-05-2023 Completed
Shifting MS Plate 8 13-05-2023 21-05-2023 Completed
Fabrication
Tacking 20 22-05-2023 11-06-2023 Completed
Welding (Fabrication Yard ) 20 12-06-2023 02-07-2023
Shifting to Location 7 03-07-2023 10-07-2023
Erection of Material (Preparation of
12 05-07-2023 17-07-2023
Derek / Scaffolding)
Position Welding 20 05-07-2023 17-07-2023

Chequred Plate Fixing 7 18-07-2023 25-07-2023


Level 5

Insert Plate Fixing 5 20-06-2023 25-06-2023


Marking & Cutting MS Plate 10 19-06-2023 29-06-2023
Shifting MS Plate 8 24-06-2023 02-07-2023
Fabrication
Tacking 15 03-07-2023 18-07-2023
Welding (Fabrication Yard ) 15 19-07-2023 03-08-2023
Shifting to Location 7 04-08-2023 11-08-2023
Erection of Material (Preparation of
10 05-08-2023 15-08-2023
Derek / Scaffolding)
Position Welding 10 05-08-2023 15-08-2023
Chequred Plate Fixing 7 10-08-2023 17-08-2023