1. What is the advantage of construction planning for a project least five points? (10 pts)
Answer
Answer
6.Given 15 m3 of c-25 concrete with mix ratio of 1:2;3 with 30% shrinkage and 5% wastage
Assume density of cement 1400kg/m3,sand 1840kg/m3 and gravel 2250kg/m3 (40 pts)
a) Calculate the amount of cement (kg), sand (m3) and gravel (m3)
b) Calculate the cost preparing for the above volume of concrete
Sand 50 birr/m3
Gravel 250birr/m3
Sand 50 birr/m3
Gravel 50birr/m3
c) How many days required to accomplish the above work if a mason and 6 labourers work
2m3/day
d) Calculate the weightag of the above work if the total time of the project is 180 days and the
total cost of the project is 1,000,000 birr.