Professional Documents
Culture Documents
CHMI/OWL
4C Offshore | NOT FOR DISTRIBUTION “More huge waves” © Ronnie Robertson, Shetland, December 10. 2014
Housekeeping
Welcome to our 4C Offshore Webinar: Heavy Lift and Service Vessel Supply and Demand
Extensive Databases:
▪ 2700 offshore wind farms: project design, lifecycle updates,
supply chain, and finance
▪ 2000 vessels: past and future contracts and specifications
▪ Subsea cables, offshore platforms and interconnectors:
technology specifications, project updates
▪ GIS: interactive map, wind farm boundaries, cable
routes, turbine locations etc.
Monopile mass by offshore construction year Average turbine rating forecast Rotor diameter and modelled power density vs capacity
3000 18 300
Europe
Mass (t)
Americas
Average Turbine Rating (MW) 16
2500 APAC
15 MW 250
14 China
0.5 MW
TP-less
0 Year 0 50
1990 2000 2010 2020 2030 2010 12 14 16 18 20 22 24 26 28 2030 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Rated Capacity (MW)
4C Offshore | NOT FOR DISTRIBUTION 7
Supply and demand of foundation installation vessels
▪ Demand matches supply in 2025/2026 at 22 vessels ▪ Significant shortage of vessels in North America and
▪ Monopile demand is expected to increase, being the Asia
preferred solution due to lower CAPEX and supply chain ▪ The only WFIV in Asia is Green Jade which is due for
risk. delivery in 2023, and the US currently has no WFIVs.
▪ Vessel shortage in previous report is no longer observed ▪ European vessels may move to these markets to meet
due to near term project delays (see reconciliation demand
slide)
12-Jan-23 4C Offshore | NOT FOR DISTRIBUTION 8
Supply and demand of turbine installation vessels
Global Supply v Demand (exc. China) By GeoRegion Supply v Demand
Annual average 2025 - 2030
30
18
25 5 16 6 vessel
8 Under 10MW Demand
3 surplus
10 - 12MW Demand 14 12+ DEMAND
20 3
12+ SUPPLY
10 12-14MW Demand 12
2
15MW+ Demand
15 3 12 10
Total Fleet
18
26 8
4 4 12-14MW Supply
10 14 21 15MW+ Supply
19 6 12
4
8 7 7 14
4 2 vessel 4 vessel
5 9
5 shortage 5 shortage
2 4
3 3 3 2
2 1
0 0
2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 ASIA US EU
▪ Demand climbs steadily from 11 – 27 by 2027 ▪ Significant shortage of vessels in US and Asia
▪ Shortage in 12 – 14 MW capable vessels from 2028 ▪ The only vessel in the US is Charybdis, which is due for
▪ Shortage in 15MW + capable vessels from 2030 delivery in 2023
▪ Project delays will push back demand (see next slide) ▪ Without significant new-build capacity, US and Asia will
be dependent on European vessels.
25 vessels
24 vessels
22 vessels
17 vessels
Europe Analyst Offshore Start Europe Analyst Offshore Start
PROJECT MW Q1 2022 Q3 2022 REASON FOR DECREASED VESSEL DEMAND PROJECT MW Q1 2022 Q3 2022 REASON FOR DECREASED VESSEL DEMAND
Hornsea Three UK1K 2852 2024 2026 Grid connections moved from 2025 to Q4 2026 & 2028. Hornsea Three UK1K 2852 2024 2026 Grid connections moved from 2025 to Q4 2026 & 2028.
Seagreen 1A UK4P 500 2024 2025 Seagreen Extension did not secure CfD during AR4. Codling IE02 1500 2025 2026 Plans to submit planning consent in H2 2023.
Inch Cape UK54 1080 2024 2024 Turbine MW increased to 15 MW so reduced number of foundations. Baltica 3 PL21 1045.5 2025 2027 Delays to building permit and FID
Baltyk III PL17 720 2024 2026 Delays to building permit and FID. Norfolk Boreas UK69 1800 2025 2026 Developers revised schedule, installation expected 2026.
Baltyk III PL22 720 2024 2026 Delays to building permit and FID. East Anglia Hub – ONE North UK2Q 600 2025 2026 Consent challenged by judicial review, CfD anticipated H2 2023.
Dieppe – Le Tréport FR33 496 2024 2025 Developers push back commissioning.
Oriel IE03 375 2024 2025 Procedural delays anticipated during 2023 RESS auction.
Asia
Arklow Bank - phase 2 IE07 800 2024 2028 Project upscaled so FID pushed back. PROJECT MW Q1 2022 Q3 2022 REASON FOR DECREASED VESSEL DEMAND
Incheon – KOSEP KR14 640 2025 2031 Public protests from fisheries.
Frederikshavn Offshore Wind
72 2024 2023 Consent recently awarded so construction brought forward a year.
Demo DK43
North America
Asia PROJECT MW Q1 2022 Q3 2022 REASON FOR DECREASED VESSEL DEMAND
PROJECT MW Q1 2022 Q3 2022 REASON FOR DECREASED VESSEL DEMAND Developer extended timeline by one year to mitigate supply chain
Greater Changhua TW76 337.1 2023 2024 Delayed FID due to knock-on effects from COVID Park City Wind US5W 804 2025 2026
bottlenecks and high commodity prices.
Onshore construction started this year so offshore construction Kitty Hawk Wind – phase 1 US1Y 1150 2025 2026 Increased capacity and extended timeline.
Taipower Iia TW49 300 2024 2023
moved forward to 2023.
Ulsan - SK KR19 136 2024 2026 Delays to permitting during the permitting stage.
Sinan – SK E&S Phase 1 KR55 99 2024 2023 Developers anticipate earlier construction start.
North America
PROJECT MW Q1 2022 Q3 2022 REASON FOR DECREASED VESSEL DEMAND
Empire Wind 1 US4J 816 2024 2025 Consent still not authorized so construction pushed back a year.
▪ Developers will find it increasingly difficult to secure the vessel assets needed to keep their projects on schedule and
meet planned commissioning dates, due to
▪ Unprecedented project delays
▪ Vessel incidents
▪ Lack of vessels capable of installing XXL monopiles and turbines
▪ European vessels will need to move to the US or Asian markets to enable them to meet their demand.
▪ Increasingly ambitious renewable energy targets adds pressure to the offshore wind industry to get projects built this
side of 2030.
▪ Demand will continue to increase post 2025, and vessel shortages are anticipated towards the end of the decade.
Monopile installation complete on Arcadis Ost 1, source: DEME Cadeler F-class vessel- Credit: https://www.cadeler.com/en/
Other News
▪ Top ten operators supplying ~66% of vessel days
▪ Windcat announced six hydrogen vessels
▪ Top five remain broadly the same but some shuffling in the
▪ N-O-S continues with diversification - has two W2W
other five
vessels and work outside of the sector
▪ Most vessel days supplied to the UK market
▪ Purus Marine acquired HST Marine, plus three hybrid
▪ SeaZip had a strong quarter since acquiring the WEM Damen FCS 2710s
vessels
▪ MRE acquired Opus Marine
▪ France and Germany providing opportunities to others
▪ 66% of the fleet of active vessels had work in Q3
operators
4C Offshore | NOT FOR DISTRIBUTION 13
Demand: CTVs Q3 2022 vs Q3 2021
5000
HST Marine
▪ UK the most disappointing
4000 World
Marine ▪ Germany and the Netherland holding up
3000 Offshore
2000
Offshore
Windservice
▪ France providing welcome demand
1000 Turner Iceni
0
Oct Jan Apr Jul Oct Jan Dec Mar Jun Sep Dec Mar Jun Sep
Construction demand increase offsets O&M losses
2018 2019 CTV Days by status, Q3 2021 vs Q3 2022
CTV days
9000 Q3 2022
15000 -8%
7000
10000 +2%
5000 +2%
5000 3000 +14% +784% 4.3k
-28% 3.2k
1000 +70%
0
Q1 Q2 Q3 Q4 -1000 Q3 2021 Q3 2022
UK Germany Netherlands France Denmark Belgium Finland
OPERATORS: Esvagt market share reduced Esvagt fleet maintains market lead New build news
Market share of SOV operators, Q3 2022 vessel days SOV Days by operator with number of active SOVs
900 DEME
▪ Steel cutting started on
5% 2 LDA
Esvagt’s new SOV
800
10% ESVAGT
BS Offshore Bibby Marine ▪ SOV for BS Offshore is
5% 700
36% Acta Marine 1
Østensjø Rederi proposed for Hai Long projects
Østensjø Rederi
1,824
Bibby Marine
600 Acta Marine in Taiwan
15%
SOV Days
LDA
DEME
500 1 3
BS Offshore
▪ GC Reiber has ordered two
ESVAGT
400 SWATH SOVs from Cemre
15% 14%
300
2
▪ Keels laid on Shanghai Electric
200
5 3 SOVs
▪ Small increase days in Q3 2022 100 3
▪ North Star announced £140
▪ Esvagt lost 4% of share due to Edda 1 million investment for its SOV
0
Breeze (Edda Wind) starting operations <80 m 80-90 m >90 m fleet
LOA Group
▪ Esvagt is the market leader with 8 vessels ▪ New entrant Marco Polo
▪ Edda Wind (Østensjo Rederi) has three Marine – targeting Taiwan
vessels plus two to start soon market
1000 450
Q3 2021 350
800 +26% +22%
Q3 2022 250
600
150
400 -49.5% 50
200 -50
0
Q3 2021 Q3 2022
CLIENTS: SGRE maintains lead
SOV days supplied to clients since 2015
▪ Slight YoY improvement in overall vessel day 0 2,000 4,000 6,000 8,000 10,000 12,000
Client: Turbine OEMs take 74% share
Q3, 2022 market share of SOV days by client
demand SGRE
Vestas Equinor
▪ O&M improving while construction work Ørsted Esvagt 6%
Cumulative (turbines)
25,000
Annual (turbines)
APAC
1,500
20,000 Americas ▪ Steady growth but flattening out
1,000
15,000
Europe ▪ Limited demand in the Americas
Cumulative
10,000 ▪ Europe will continue to demand CTVs
500
5,000
Established markets stable; emerging markets driving demand
0 0 Europe: CTV demand by Country
2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035
534 537 542
Emerging markets will need their own supply chain 518 523 Others
Global CTV demand (ex. China) 452 467 Belgium
437
397 Poland
826 858 351
786 790 811 317
Ireland
92
704 91 292 287 293
89 83 87 Denmark
645 669
78
584 197 223 Americas France
73 72 179 184 190
515 63
159
437 62 135 146 APAC Netherlands
124
371 44
342 332 102 Europe Germany
2 28 75
10
36 49
518 523 534 537 542 United Kingdom
437 452 467
351 397
292 287 293 317
2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035
2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035
4C Offshore | NOT FOR DISTRIBUTION 17
Forecast : SOVs
32
40
5
7
5
7
68
74
83 86 91
higher for the lower confidence projects
26 3 4
22 23 2 59
2 53
1 1 44
31 36
23 27
21
2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 Minimal increases for high confidence projects
European SOV demand by Analyst Confidence 92
Germany and UK create demand 88
Europe: SOV demand by Country 84
15 76
14 Others 31
69 27
13 4 25
4 5 Belgium
19
10 4 5 61
13
7 4 5 Denmark 55 Low
1 15 15 8
6 4
1 14
11 Netherlands 45
5
Medium
5 4
1 9
3 United Kingdom 2 30 32 32
3 1 7 20 21 37 24 27 28 High
1 2
0 7 18 18 21
1 2
0 4 18 Germany 31 1 14
2
0
3 3 17 27 8
1
2
0 16 24 4
1
2 1
2
0 3 12 14 21 21 3
0
2 2 11 1
7 7 8 22 23 24 25
16 20
8 8 10 11 11 12 12 27 28 29 29 29 29 29 29 29 29
21 21 23 24
2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035
2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035
▪ What is an SOV?
▪ Purpose-built vessel for long
term operations and
maintenance work
▪ Market has evolved – need for
?
vessels with W2W capability in
construction plus short term
O&M
▪ Next report to include analysis
with W2W vessels and contracts
included
▪ Feedback welcome!
Get in touch
Contact us should you have any comments on the
content of this report, or suggestions for future content.
Orbis Energy Centre, Wilde Street, Lowestoft, NR32 1XH
The team at 4C is always happy to help. Tel +44 (0)1502 307037 Email info@4coffshore.com Web www.4coffshore.com