You are on page 1of 1

PT.

BERKAT AIR HIDUP ABADI


TIME TABLE PROJECT TANK FOR POWDER HOPPER (12 UNIT)
KONTRAKTOR : PT.BERKAT AIR HIDUP ABADI
CLIENT : PT. TAIYO SINAR RAYA TEKNIK
PRIORITAS-2 : DELIVERY (EX-WORK, 28 SEP. 2023)
Apr 2023 May 2023 Jun 2023 Jul 2023 Aug 2023 Sep 2023
No Task Name Start Finish Total
W.3 W.4 W.1 W.2 W.3 W.4 W.1 W.2 W.3 W.4 W.1 W.2 W.3 W.4 W.1 W.2 W.3 W.4 W.1 W.2 W.3 W.4

1 Drawing Approval 18-Apr-2023 12-May-2023 3 Week

2 Pengadaan Material :
15-May-2023 6-Jun-2023 4 Week
Include Accecories

3 Material Reducing + Inspection 24-May-2023 8-Jun-2023 4 Week

4 Fabrication Proses : 5-Jun-2023 25-Sep-2023 18 Week

Marking + Cutting 5-Jun-2023 10-Jun-2023 1 Week

Rolling + Forming + Bending 12-Jun-2023 19-Jun-2023 1 Week

Fit Up + Welding 20-Jun-2023 12-Aug-2023 8 Week

QC Check 14-Aug-2023 19-Aug-2023 1 Week

Hydrotest 21-Aug-2023 26-Aug-2023 1 Week

Blasting 28-Aug-2023 2-Sep-2023 1 Week

Primer Coat 4-Sep-2023 9-Sep-2023 1 Week

Top Coat 11-Sep-2023 16-Sep-2023 1 Week

Cleaning + Packing 18-Sep-2023 25-Sep-2023 1 Week