TIME TABLE PROJECT TANK FOR POWDER HOPPER (12 UNIT) KONTRAKTOR : PT.BERKAT AIR HIDUP ABADI CLIENT : PT. TAIYO SINAR RAYA TEKNIK PRIORITAS-2 : DELIVERY (EX-WORK, 28 SEP. 2023) Apr 2023 May 2023 Jun 2023 Jul 2023 Aug 2023 Sep 2023 No Task Name Start Finish Total W.3 W.4 W.1 W.2 W.3 W.4 W.1 W.2 W.3 W.4 W.1 W.2 W.3 W.4 W.1 W.2 W.3 W.4 W.1 W.2 W.3 W.4
1 Drawing Approval 18-Apr-2023 12-May-2023 3 Week
2 Pengadaan Material : 15-May-2023 6-Jun-2023 4 Week Include Accecories
3 Material Reducing + Inspection 24-May-2023 8-Jun-2023 4 Week
4 Fabrication Proses : 5-Jun-2023 25-Sep-2023 18 Week
Marking + Cutting 5-Jun-2023 10-Jun-2023 1 Week
Rolling + Forming + Bending 12-Jun-2023 19-Jun-2023 1 Week