Professional Documents
Culture Documents
Table of contents
1. Dismantling procedures
2. Installation procedures
3. Leak Test
4. Airbag Normalizing
5. Checklist
6. Safety Procedures
Prepared by:
Mohammad Hafiz
Head - Services
1) Before proceeding for dismantling, make sure all packagings available to pack
the material , also clean oil drums / skid tank available for transferring the oil.
All blanking plates should be readily available.
2) Close all the cooler valves top and bottom to the transformer.
3) Drain the oil from the bottom header to empty the oil from radiator and headers
and also drain the oil from the main tank until half oil level gauge on the tank to
empty the oil from conservator , turrets, pipings and approx. 100 mm below the
cover level. The oil to be drained into the clean drums/ clean oil tanks and their
opening to be sealed air tight.
4) Disconnect all the wiring to the instruments and pack it nicely to avoid water
entry. All the conduits used for joining to be separated out. The instrument
openings to be sealed air tight.
5) Disconnect the fan wiring and dismantle the fans along with its supports.
6) Dismantle the radiator ties and pack it properly.
7) Dismantle the radiators and headers (top and bottom) and close all the openings
with the gasket and blanking plate. Pack them in the wooden case with
sufficient dampers to take care of the vibration/impact during the transport.
8) Dismantle the conservator and its support and secure the conservator on the
steel support. Close all the openings and blank them air tight. MOG to be
installed with guard to avoid transit damage.
9) Dismantle the cable box and disconnecting chamber and mount them on the
steel supports.
10) Disconnect the bushings for HV, LV, TV and neutral and pack them properly
from inside as well as outside to avoid water entry and also in a manner to avoid
damage during transit.
11) Dismantle the HV turret for all the 3 phases , blank them and secure them on the
steel plate for transportation. Mark them for easy identification.
12) PRD to be separated from the drain pipe to avoid any damage during transit.
13) All the pipings for conservator , OLTC, Buchholz relay to be packed in wooden
case with all the openings sealed properly. Mark them for easy identification
14) All the valves to be fitted with valve guards.
15) OLTC DM to be covered with protection hood and OLTC on the cover also to
be protected with the hood. LCP to be covered with the enclosure for protection
16) All the supports for cable box, conservator to be packed properly. Mark them
for easy identification
17) All the fasteners to be packed in separate polythene packings and kept inside the
pipe case.
18) Instruments such as fans, buchholz relay to be packed in a separate case taking
care of the fragile nature of the instrument.
19) All the openings on the transformer to be blanked off, dry air/ nitrogen to be
filled at 0.2 bar and pressure monitored for 48 hrs with no leakage.
24) If transformer is dispatched gas filled then vacuuming has to be done and after
that oil filling under vacuum to be done, all the accessories on the main tank to
be installed after oil filling, installation of other accessories which does not
involve the releasing of the gas can be done parallely
25) Check the oil sample from the drums/bulk oil as per TNB specn for 8 tests (
1 sample only) as per clause 2A.2.1 at TNBR /other accredited laboratory
as approved by TNB – Already done at PMU Mersing
26) This inspection is required if there are heavy shocks observed as seen in the
shock recorder report.
Check the locating post on the cover to see if any movement of the core coil
assembly has actually taken.
Open the manhole inspection for doing the internal inspection if required or felt
necessary, The internal inspection is possible, if proper space available
otherwise inspection to be carried out from outside. During internal inspection,
make a list of things taken inside and while coming out should verify the same.
27) Before installing the main tank conservator , check the conservator at
ground level by opening the manhole inspection cover to verify the air bag
& float arm position of magnetic oil gauge. Also verify the MOG for OLTC
as well as main tank by moving the float up and down. Do not move the
pointer as it may get damaged.
28) Before any installation activity to be conducted or any cover to be opened on the
main tank, make sure the oil is filled until the core coil assembly level. Since the
transformer is gas filled dispatch hence fill up the oil after processing into
transformer under vacuum.
29) Install the HV turret followed by HV bushings. Check the IR value of the HV
bushings before installation.
30) Similarly install the LV turret and LV phase and neutral bushings . Check the IR
value of the bushings before installation.
31) Similarly install the TV bushings . Check the IR value of the bushings before
installation.
32) Install the HV neutral also check the IR value, followed by header supports,
headers , cooler pipes, radiators, conservator support, conservator, Buccholz
relay piping, radiators, conservator piping, OLTC piping and breather piping.
33) Install the LV DC and cable box. Verify the surge arrester installation inside the
cable box.
34) For internal connection for LV , TV and neutral bushings to connect the flexible
jumpers/leads from the winding , make sure the oil level is below the inspection
cover, open the cover during dry weather.
35) Connect all the conduit wiring to the instruments installed on the transformer
37) Immediately after inspection, close all the covers and check the tightness of all
flange openings, inspection covers, valves and all the joints to the
recommended torque with the torque wrench. Refer the torque table as below.
39) Raise the oil up to the conservator level and check for any leakage by applying
pressure up to 0.2 bar and monitor it for 4-6 hrs during which time the pressure
should be maintained (ambient temperature may cause the pressure to
40) If no leak observed , lower the oil from the transformer till the cover level.
Also after the blanking pressure test done , release the excess pressure and
then close the equalizing valve between main tank and OLTC.
41) Heat the oil through the filteration machine till the temperature reaches 60 deg
celcius. Heat it for a minimum of 24 hrs for 30 kl oil.
43) After having reached 70 mbar check the leak rate as per manual.
44) After leak rate is achieved, continue vacuuming to the full vacuum (less than 1.3
mbar or 1 torr) as per the manual , once 1 torr is achieved continue vacuuming
for 36 hrs for 132 kV transformers. Extended cycle of vacuum to be done since
the transformer was stored for long time under gas.
45) During the vacuuming, filter the oil in the skid tank for two cycles at a
temperature of about 55-60 degree Celcius and keep the oil prepared to be filled
back into the main tank under vacuum.
48) After the filteration is complete, Check the oil parameters for the acceptance
criteria.
49) Allow settling time for oil, do leak test with nitrogen gas at 5 psi or 0.3 bar and
check all the gasketted joints for any oil spills, leaks or seepage. The PRD
should be locked or oil level in the conservator to be lowered otherwise PRD
may operate. Refer the procedure as below.
Introduction
The purpose of this test is to prove that no oil leaks exist on the Transformer tank, cooler
bank and all other oil compartment. The Test shall be carried out upon completion of the
erection work, whereby all fittings, i.e. conservator, radiators etc are in place and all
valve open/close as required in the service.
The additional test pressure of 0.35 bar as per FAT requirement shall be measured at the
base of the tank and this pressure will be in addition to the normal static head pressure.
Test Procedure
Note :
1) Since there is considerable variations of ambient temperature throughout the
day , its very important to take into account the pressure increase / drop
because of the same. The pressure at the start and at final stage after 24
hours should be approximately same if the ambient is almost the same.
2) Pressure should be checked only at the flange opening of PRD and not at the
spring side.
50) After leak test found to be ok, do air venting & nitrogen processing for Air bag.
Refer the procedure below.
Proceed as follows:
- Inflate airbag to 0.1 maximum bar, letting the air vent on the conservator open.
-Maintain the device at a constant temperature and verify if exist a loss of pressure for a
period of 24 hours. If there is no loss of pressure, then you can considered that the air bag
and the conservator have been perfectly mounted. (This step may be done if airbag found
leaking)
- Inject oil at low pressure by the lower part of the conservator until it escapes through the
airvent plugs in the upper part.
- Close the air vent plugs and fill the oil in the conservator through the lower part, while
letting the air bag deflated progressively.
- Conclude with the fill up when the oil reaches the level of operation temperature.
Proceed as follows:
-Open equalizing valve and Create vacuum inside the airbag as well as conservator.
-Open the valve at the lower part to fill oil. Due to vacuum in the conservator, the oil
level will rise automatically. Stop filling oil once the volume required in the conservator
is reached
-Maintain conservator under vacuum, but let dry air or nitrogen enter airbag, then this
will inflate by itself and will take all the free space because the conservator was not
completely full. Inflate the airbag to a maximum pressure of 0.1 bar
-Check that in the air venting plugs appear oil, guaranteeing that the conservator does not
have anymore air.
-Close the air venting plugs and if it is necessary adjust the level.
IMPORTANT: CAUTIONS
When the device is ready and working, never open the valve/vent plugs in the upper part.
Such opening would create an air current in the upper part of the device creating a drop
in the oil level that is compensated by a drop in the volume of the airbag.
If you think that air has entered the conservator, first, you must inflate the airbag
below 0.1 bar and after that open the venting plugs to bleed oil.
52) All the tests on the transformer for site acceptance will be done.
a) Physical Inspection
1) During the filter processing it is very important to have the breathers fitted on
transformer , skid tank, vacuum break should be done preferably with nitrogen
gas or dry air.
3) Also make sure the skid tank is clean from the inside, the filter cartridge is
clean.
1. INTRODUCTION
This method of statement is meant for the installation of power transformer in general.
All workers shall wear minimum PPE during the whole work duration.
While working in a live substation, barricading the work area with a suitable
means (red/ white tape, plastic chain, etc) and put necessary and sufficient
warning sign. Ensure that the work is restricted inside the confined area.
If crane usage is required, ensure that the crane is properly parked and secured.
Ensure clear communication between the driver and the team supervisor to avoid
miscommunication. Inspect all lifting units are in good condition.
All machines and tools that going to be used must be in good working condition.
Carefully check for any damaged or broken parts.
When working with filteration machines, ensure all hoses having no leaks,
properly connected and sealed. Should there any oil leak, immediate action to
clean up must be taken to avoid any accident due to slippage.
When working at height, ensure that the area below is clear. Carefully not to drop
any tools/ items that may hit others.
When lifting part/ accessories, ensure that the item is properly secured. Do not
stand directly below the item being lifted.
All lifting equipment e.g sling wires, shackles shall be visually inspected prior to
any lifting works being carried out.
For any lifting work, the instruction to commence lifting originates from the
supervisor/signal man after getting acceptance from project site supervisor.
DO’S :
1. IMP. : Insulating oil and insulation for windings and connections are inflammable.
Watch for fire hazards.
2. Replace Nitrogen gas completely with air if it was filled in main unit for
transport/storage.
3. Make sure that nothing is kept inside the pockets before one enters inside main unit.
Also take off the wrist watches and shoes.
4. List up all the tools and material to be taken inside and check it after coming out to
make it sure that no tools is left inside.
5. There must be a protective guard for lamp to be taken inside.
DON’TS :
1. Do not take any fibrous material such as cotton waste inside while repairing.
2. Do not drop any tools/materials inside.
3. Do not stand on leads/cleats.
4. Do not weld, braze or solder inside the tank.
5. Do not weld anything to tank wall from outside.
6. Do not weld anything to conservator vessel if bag is inside.
7. Do not Smoke on or near the transformer.
8. Do not use Fibrous cleaning material, as it can deteriorate oil if mixed with it.
9. Do not leave off circuit tap switch handle unlocked.
10. Do not use low capacity lifting jacks on transformer for jacking.
11. Do not change the settings of WTI and OTI alarm and trip frequently. The setting
should be done as per the site condition.
12. Do not leave any connection loose.
13. Do not meddle with the protection circuits.
14. Do not leave Thermojunction box/M.Box doors open, they must be locked.
Prepared By