You are on page 1of 1

ECE Project Planner

CSC308 Report Project - Security Risks Associated with OS Updates - Dr. Xiaojie Zhu Period Highlight: 12 Plan Duration Actual Start % Complete Actual (beyond plan) % Complete (beyond plan)

PLAN
ACTIVITY Assigned Team Member PLAN ACTUAL
DURATI START
ACTUAL PERCENT COMPLETE
START DURATION PERIODS
ON
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40

Alia Alneyadi 100%


Abstract 3 2 2 1
Alia Alneyadi 100%
Summary 3 2 3 1
Methodolog Alia Alneyadi 100%
y 3 2 2 1
Alia Alneyadi 100%
Motivation 3 2 3 2
Literature 100%
review Ahmed Zaitoun 3 2 2 2
recommend 100%
ations Hadeel Al-Rifa'i 3 2 2 2
100%
Background Ahmed Zaitoun 3 2 3 3
Problem 100%
statement Ahmed Zaitoun 3 2 3 1
100%
Results Ahmed Zaitoun 3 2 4 2
Whole Hadeel Al-Rifa'i 100%
Conclusion 3 2 4 3
Requirement Hadeel Al-Rifa'i 100%
s 3 2 3 2
Hadeel Al-Rifa'i 100%
Objectives 3 2 4 1
Presentation Hadeel Al-Rifa'i 100%
template 3 2 5 3
Project Hadeel, Sana 100%
Cover 3 2 6 2
Hadeel Al-Rifa'i 100%
Lessons Lear 3 2 5 1
Team Hadeel AlRifa'i 100%
Dynam 3 2 4 2
1000%
Gantt Hadeel Al-Rifa'i 3 11 3 11
100%
Multisim Hadeel Al-Rifa'i 4 3 6 7
100%
TinkerCad Hadeel Al-Rifa'i 5 6 5 8
0%
Circuit Both Members 14 5 14 6
44%
Activity 21 Team Member 1 14 8 14 2
0%
Activity 22 Team Member 2 14 7 14 3
12%
Activity 23 Team Member 1 15 4 15 8
5%
Activity 24 Team Member 2 15 5 15 3
0%
Activity 25 Team Member 3 15 8 15 5

You might also like