RCFA

#1 Kebakaran Kabel Tray

Balikpapan, 16 Juni 2023


The information contained in this document is strictly confidential. It is strictly forbidden to use, disclose, copy, modify, or distribute this document
without permission of PLN NUSANTARA POWER, PT
Debu batubara
C6

Kebocoran
coalpipe 1D

Lokasi
Kabel Tray
Terbakar

The information contained in this document is strictly confidential. It is strictly forbidden to use, disclose, copy, modify,
or distribute this document without permission of PLN NUSANTARA POWER, PT 3
Kebakaran Kabel Tray di bawah Coal Feeder

Berdasarkan hasil inspeksi, secara visual


yang terdampak tray kabel 2-5 yang
meliputi kabel 6KV, 400V dan kabel control

The information contained in this document is strictly confidential. It is strictly forbidden to use, disclose, copy, modify,
or distribute this document without permission of PLN NUSANTARA POWER, PT 4
Kebutuhan Material (Listrik & Instrumen)
LISTRIK INSTRUMEN
NO SEPESIFIKASI PANJANG KETERANGAN No SPESIFIKASI Cable type PANJANG KETERANGAN
NYSY - 1 4 x 0,5 mm ZT-RVVP (serabut) 100 m
1
Cu/PVC/CTS/PVC 2 2 x 1,5 mm NYYHY (serabut) 100 m Ready
2x6mm serabut 100 m 3 2 x 2 x 1 mm ZRB-DJVP2VP2 (serabut) 100 m
4x4.5mm 100 m Ready 4 2 x 1 mm ZRB-DJVP2VP2 ( serabut ) 100 m
3x2mm serabut 100 m 5 2 x 2,5 mm ZRB-KVVP2-32 ( serabut ) 100 m
7x1.5mm serabut 100 m Ready 6 4 x 1 mm ZR-KVV ( serabut ) 100 m
4x1.5mm 100 m Ready 7 4 x 1,5 mm ZRB-KVVP2-32 ( serabut ) 100 m
14x1.5mm 100 m 8 4 x 2,5 mm NYMHY ( serabut ) 100 m
2 x 1.5 mm 100 m 9 6 x 1 mm ZRB-KVVP2-32 ( serabut ) 100 m
2 x 120 mm 100 m 10 7 x 1,5 mm ZRB-KVVP2-32 ( serabut ) 100 m
2 x 2 mm 100 m 11 10 x 1 mm ZR-KYJVP2 ( tunggal ) 100 m
2 x 2 x 1 mm 100 m 12 20 x 0,8 mm ( tunggal ) 100 m
2 x 4 mm 100 m 13 3 x 2 x 1 mm ZRB-DJVP2VP2 ( tunggal ) 100 m
3 x 2.5 mm 100 m 14 3 x 1,5 mm ZR-KYJVP2 ( tunggal ) 100 m
5 x 2 x 0.8 100 m 15 4 x 0,5 mm ZR-KYJVP2 ( tunggal ) 100 m
16 4 x 1,5 mm ZR-KYJVP2 ( tunggal ) 100 m
2 NYFGBY 4 x 4 mm 200 m Ready 17 4 x 2 mm ZR-KYJVP2 ( tunggal ) 100 m
3 NYFGBY 2 X 2.5 mm 1000 m 18 4 x 2,5 mm ZR-KYJVP2 ( tunggal ) 100 m
19 7 x 1,5 mm ZR-KYJVP2 ( tunggal ) 100 m
20 12 x 1,5 mm ZRB-KVVP2-32 (serabut) +-100m Ready

The information contained in this document is strictly confidential. It is strictly forbidden to use, disclose, copy, modify,
or distribute this document without permission of PLN NUSANTARA POWER, PT 5
Kebutuhan Material (Listrik & Instrumen)

Berdasarkan laporan kondisi terakhir unit, kemungkinan area terdampak pada area coal feeder
system baik Power supply dan control (cabinet CKA 03-05), igniting system, slag cooler
system dll akan terdampak juga, sehingga perlu dipastikan function test kondisi peralatan
sebelum start up.(ref dokumen: F305S-D1014, F305S-D1015, F305S-K0205-01
The information contained in this document is strictly confidential. It is strictly forbidden to use, disclose, copy, modify,
or distribute this document without permission of PLN NUSANTARA POWER, PT 6
Timeline recovery #1

The information contained in this document is strictly confidential. It is strictly forbidden to use, disclose, copy, modify,
or distribute this document without permission of PLN NUSANTARA POWER, PT 7
Rencana Perbaikan (Listrik)
1. Pola kerja menjadi 3 shift sesuai dengan operator (ada tambahan man power Kendala:
dari UMRO JP2) - Material belum semua ready
2. Tiap shift maksimal 4 personil dikarenakan area kerja yang terbatas - Area kerja yang terbatas
3. Re-isolasi kabel (yang belum putus)
4. Menyelesaikan identifikasi jenis kabel & tagging
5. Pemotongan kabel yang sudah teridentifikasi
6. Paralel kupas kabel yang sudah dipotong untuk persiapan penyambungan

Note :
Risiko :
1. Kontak listrik dengan kabel yang masih bertegangan, pada saat identifikasi, tagging dan
pemotongan kabel
2. Terjadi salah sambung atau tidak diketahui pasangan kabel yang dipotong
Mitigasi :
1. Menggunakan voltage detector
2. Melakukan tagging pada 2 sisi, penyamaan pemahaman tagging antar shift sehingga tidak ada
perbedaan dalam melakukan tagging antar shift

Opsi lain : sambung kabel langsung (mengubah jalur kabel).


Note : sudah dicoba namun sulit untuk menarik kabel karena posisi kabel yang bertumpuk-
tumpuk dan jalur kabel tray yang panjang
The information contained in this document is strictly confidential. It is strictly forbidden to use, disclose, copy, modify,
or distribute this document without permission of PLN NUSANTARA POWER, PT 8
Progress (Listrik)
Kendala:
No Tindakan Progr Keterangan 1. Masih ada kabel
yang kondisi berteganga
es n karena tidak semua
1 Identifikasi dan tagging 96% Terkendala sumber power boiler #1
kabel power kabel masih ada dapat di OFF karena ada
yang terhubung dengan
yang bertegangan sistem common.
2 Re-isolasi kabel
3. Masih banyak
3 Pemotongan kabel yang 96% Terkendala kabel tumpukan debu BB di
sudah ditagging masih ada yang ber tray kabel
tegangan
4 Pengupasan kabel 15%

5 Penyambungan kabel 1%

2. Ada kabel yg terbakar dan 4. Kondisi kabel tray yang penuh


masih bertegangan. baru dengan kabel menyulitkan identifikasi
direisolasi dan ditagging

The information contained in this document is strictly confidential. It is strictly forbidden to use, disclose, copy, modify,
or distribute this document without permission of PLN NUSANTARA POWER, PT 9
Progress (Listrik)

kabel sudah ditagging

Tagging kabel sudah sampai


kabel sudah L102 (102 kabel)
ditagging. dan baru
dpotong 1 sisi. perlu
potong 1 sisi lagi, dan
dikupas agar siap
sambung

kabel sudah ditagging, inspeksi kabel yang kondisi


dipotong, dan dikupas. masih bagus dan tidak perlu
siap proses sambung dpotong
The information contained in this document is strictly confidential. It is strictly forbidden to use, disclose, copy, modify,
or distribute this document without permission of PLN NUSANTARA POWER, PT 10
Rencana Perbaikan (Instrumen)
1. Pola kerja menjadi 3 shift sesuai dengan operator (ada tambahan man power dari UMRO JP2)
2. Tiap shift maksimal 4 personil dikarenakan area kerja yang terbatas Kendala:
3. Menyelesaikan identifikasi jenis kebel & tagging
4. Material kabel kontrol khusus analog yg kabelnya spesifik full armor (Cable type ZRB-DJVP2VP2 - material belum semua
2x2x1mm) tidak ada di jual umum. Akan dicoba menggunakan Cable type NYYHY 2x1,5mm non ready
armor (standart perumahan) yang akan di balut/dilapisi tape copper atau tape alumunium foil utk - Area kerja yang terbatas
melindungi radiasi elektromagnetik dari kabel bertegangan

Note :
Risiko :
1. Kontak listrik dengan kabel yang masih bertegangan, pada saat identifikasi, tagging dan pemotongan kabel
2. Terjadi salah sambung core kabel atau tidak diketahui pasangan kabel yang dipotong
3. Terdapat warna kabel dalam satu kabel yang sama saat setelah pemotongan
4. Penggunaan kabel tidak standart eksisting (non armor copper) dapat mempengaruhi nilai pembacaan signal analog 4-20mA berdampak pada
transmitter, aktuator
Mitigasi :
1. Menggunakan voltage detector , Menggunakan sarung tangan listrik
2. Melakukan tagging pada 2 sisi, penyamaan pemahaman tagging antar personil shift sehingga tidak ada perbedaan dalam melakukan tagging
antar personil shift
3. Dilakukan pengupasan kabel dan memotong kabel satu per satu dengan di continuity lalu di tagging angka
4. Di orderkan kabel dengan spesifikasi yang sama atau secara emergensi menggunakan kabel biasa dengan menggunakan pelindung anti radiasi
(tape copper)

Opsi lain : sambung kabel langsung (mengubah jalur kabel).


Note : sudah dicoba namun sulit untuk menarik kabel karena posisi kabel yang bertumpuk-tumpuk dan jalur kabel tray yang panjang
The information contained in this document is strictly confidential. It is strictly forbidden to use, disclose, copy, modify,
or distribute this document without permission of PLN NUSANTARA POWER, PT 11
Progress (Instrumen)
Kendala:
N Tindakan Progres Keterangan 1. Masih ada kabel
yang kondisi berteganga
o n karena tidak semua
Terkendala kabe sumber power boiler #1
1 Identifikasi dan tagging 96% dapat di OFF karena ada
kabel kontrol l masih ada yang yang terhubung dengan
bertegangan sistem common.

2 Pemotongan kabel 96% Terkendala kabe


3. Masih banyak
kontrol yg sudah l masih ada yang tumpukan debu BB di
ditagging bertegangan tray kabel

3 Pengupasan kabel 8%
4 Penyambungan kabel 5% Sekun kabel
kontrol kurang

2. Ada kabel yg terbakar dan 4. Kondisi kabel tray yang penuh


masih bertegangan. baru dengan kabel menyulitkan identifikasi
direisolasi dan ditagging

The information contained in this document is strictly confidential. It is strictly forbidden to use, disclose, copy, modify,
or distribute this document without permission of PLN NUSANTARA POWER, PT 12
Progress (Instrumen)

Kabel kontrol sudah


dipotong

Tagging kabel sudah sampai


L102 (102 kabel)
Proses Tagging kabel
sisi unit Kabel Kontrol analog dengan
armor copper

kabel sudah ditagging, inspeksi kabel yang kondisi


dipotong, dan dikupas. masih bagus dan tidak perlu
siap proses sambung dpotong
The information contained in this document is strictly confidential. It is strictly forbidden to use, disclose, copy, modify,
or distribute this document without permission of PLN NUSANTARA POWER, PT 13
Progress Pekerjaan (Instrumen)
Kendala:
1. Material belum
semua ready
2. Area kerja yang
terbatas

The information contained in this document is strictly confidential. It is strictly forbidden to use, disclose, copy, modify,
or distribute this document without permission of PLN NUSANTARA POWER, PT 14
Rencana Tindak Lanjut Pencegahan
No Tindakan PIC Target Keterangan
1 Pemasangan plat bordes di atas grating Mesin1, Juni 2023 Material : bordes
Rendalhar, SOB tebal 2mm, estimasi
36 lembar per unit
2 Penambahan akses untuk cleaning SOB, Rendalhar Juni 2023 Sementara
menggunakan
scaffolding
3 Penambahan vaccum cleaner industrial Lingkungan, Juni 2023
Rendalhar
4 Penambahan cover cabel tray Harlis, Juli 2023 Material : Plat
Rendalhar
5 Cleaning kabel tray area boiler secara rutin Lingkungan Juni (rutin)
6 Penambahan line heat detector area kabel K3, Fire Juli 2023 Material : LHD
tray Engineer

The information contained in this document is strictly confidential. It is strictly forbidden to use, disclose, copy, modify,
or distribute this document without permission of PLN NUSANTARA POWER, PT 15
THANK YOU
TERIMA KASIH

The information contained in this document is strictly confidential. It is strictly forbidden to use, disclose, copy, modify,
or distribute this document without permission of PLN NUSANTARA POWER, PT 16
FDT (jangka pendek)
JANGKA PENDEK (PEMULIHAN KEGAGALAN )
No. Permasalahan Failure Defense Task PIC Target Penyelesaian

1 Kabel terbakar (instrumen) Identifikasi dan tagging kabel kontrol I&C 96%

Pemotongan kabel kontrol yg sudah ditagging I&C 8%

Penyambungan kabel kontrol I&C 5%

2 Kabel terbakar (Listrik) Identifikasi dan tagging kabel power Harlis 96%
Re-isolasi kabel Harlis

Pemotongan kabel yang sudah ditagging Harlis 96%


Pengupasan kabel Harlis 15%
Penyambungan kabel Harlis 1%
3 Debu batubara Pengecekan coalpipe all feeder M1, SOB Juni 2023
Bahan bakar,
Pengecekan jalur C6 Juni 2023
SOC
M1,
4 Debu batubara pada kabel tray Pemasangan plat bordes di atas grating elevasi 9 Juni 2023
Renhar,SOB
Penambahan akses untuk cleaning kabel tray SOB, Renhar Juni 2023
Lingkungan,
Penambahan vaccum cleaner industrial Juni 2023
Rendalhar
Harlis,
Penambahan cover cabel tray Juli 2023
Rendalhar
Cleaning kabel tray area boiler secara rutin Lingkungan (rutin)
The information contained in this document is strictly confidential. It is strictly forbidden to use, Penambahan
K3, Fire
line
disclose, copy, modify, heat detector area kabel tray Juli 2023
or distribute this document without permission of PLN NUSANTARA POWER, PT Engineer 17
FDT (jangka panjang)
JANGKA PENDEK (PEMULIHAN KEGAGALAN )
No. Permasalahan Failure Defense Task PIC Target Penyelesaian

The information contained in this document is strictly confidential. It is strictly forbidden to use, disclose, copy, modify,
or distribute this document without permission of PLN NUSANTARA POWER, PT 18
Kronologi #1 Kebakaran Kabel Tray unit 1
Kronologi Gangguan Temuan :
Kejadian tanggal 15 Juni 2023 pukul 02.42 WITA • Megger CF kabel power 1A & 1C short
• Terdapat indikasi PC unit 1 error (turbin, boiler dan common)
• DCS CHCB error
• Megger all fan 6KV (PA, SA, ID,HPFB &
• PC EWS 03.14 indikasi mati ESP Trafo) hasil normal
• Indikasi power loss sampai HUB switch (yang menghubungkan control ke PC, jadi tidak bisa komunikasi ke PC operator)
• PC server mati (tetapi masih bisa komunikasi dengan PC Operator)
• Operator melakukan pengecekan Ditindaklanjuti inspeksi pada area kabel tray
• Charger baterai → ok yang terbakar
• Pada 03.51 → CWP 1A trip indikasi butterfly valve close
• 04.25 → terdapat indikasi kabel terbakar dibawah greating coalpipe coal feeder
• Operator melakukan pengecekan DCS power suplay cabinet → dicoba dinyalakan oleh tim harlis
• server ok
• CF 1A trip VSD mati CF 1D trip indikasi motor open error
• CF 1F trip indikasi motor open error
• CF 1C trip VSD mati
• CF 1B trip PLC error
• Switch gear 6KV trip → CWP 1A failure
• Switch gear circulating water trafo mati

Temuan instrument :
• Panel CKA 52 controller mati indikasi breaker short (berpengaruh pada DCS control panel common CHCB, list terlampir)

Pukul 06.42 beban unit 1 30MW net


Pukul 07.19 beban unit 1 25MW gross
• Temuan MCC ke feeder trip (1A & 1C)

Setelah dilakukan mitigasi → common DCS normal

Proses pemadaman pada temuan kabel tray

The information contained in this document is strictly confidential. It is strictly forbidden to use, disclose, copy, modify,
or distribute this document without permission of PLN NUSANTARA POWER, PT
Kronologi #1 Kebakaran Kabel Tray unit 1
Kronologi Gangguan Kejadian tanggal 15 Juni 2023 pukul 02.42 WITA
Terdapat indikasi PC unit 1 error • Terdapat indikasi PC unit 1 error (turbin, boiler dan
common)
• DCS CHCB error
• PC EWS 03.14 indikasi mati
Turbin • Indikasi power loss sampai HUB switch (yang
menghubungkan control ke PC, jadi tidak bisa komunikasi
ke PC operator)
• PC server mati (tetapi masih bisa komunikasi dengan PC
Operator)
• Operator melakukan pengecekan
• Charger baterai → ok
Boiler • Pada 03.51 → CWP 1A trip indikasi butterfly valve close
• 04.25 → terdapat indikasi kabel terbakar dibawah greating
coalpipe coal feeder
• Operator melakukan pengecekan DCS power suplay
cabinet → dicoba dinyalakan oleh tim harlis
• server ok
• CF 1A trip VSD mati CF 1D trip indikasi motor
open error
CHCB • CF 1F trip indikasi motor open error
• CF 1C trip VSD mati
• CF 1B trip PLC error
• Switch gear 6KV trip → CWP 1A failure
• Switch gear circulating water trafo mati

Temuan instrument :
Common WTP • Panel CKA 52 controller mati indikasi breaker short
(berpengaruh pada DCS control panel common CHCB, list
terlampir)

Pukul 06.42 beban unit 1 30MW net


PC EWS 03.14 indikasi mati Pukul 07.19 beban unit 1 25MW gross
• Temuan MCC ke feeder trip (1A & 1C)

The information contained in this document is strictly confidential. It is strictly forbidden to use, disclose, copy, modify, Setelah dilakukan mitigasi → common DCS normal
or distribute this document without permission of PLN NUSANTARA POWER, PT
Kronologi #1 Kebakaran Kabel Tray unit 1
Kronologi Gangguan Kejadian tanggal 15 Juni 2023 pukul 02.42 WITA
• Terdapat indikasi PC unit 1 error (turbin, boiler dan
common)
PC server mati (tetapi masih bisa komunikasi • DCS CHCB error
• PC EWS 03.14 indikasi mati
dengan PC Operator) • Indikasi power loss sampai HUB switch (yang
menghubungkan control ke PC, jadi tidak bisa komunikasi
ke PC operator)
• PC server mati (tetapi masih bisa komunikasi dengan PC
Operator)
• Operator melakukan pengecekan
• Charger baterai → ok
• Pada 03.51 → CWP 1A trip indikasi butterfly valve close
• 04.25 → terdapat indikasi kabel terbakar dibawah greating
coalpipe coal feeder
• Operator melakukan pengecekan DCS power suplay
cabinet → dicoba dinyalakan oleh tim harlis
• server ok
• CF 1A trip VSD mati CF 1D trip indikasi motor
open error
• CF 1F trip indikasi motor open error
• CF 1C trip VSD mati
• CF 1B trip PLC error
Indikasi power loss sampai HUB switch (yang • Switch gear 6KV trip → CWP 1A failure
• Switch gear circulating water trafo mati
menghubungkan control ke PC, jadi tidak bisa komunikasi Temuan instrument :
ke PC operator) • Panel CKA 52 controller mati indikasi breaker short
(berpengaruh pada DCS control panel common CHCB, list
terlampir)

Pukul 06.42 beban unit 1 30MW net


Pukul 07.19 beban unit 1 25MW gross
• Temuan MCC ke feeder trip (1A & 1C)

The information contained in this document is strictly confidential. It is strictly forbidden to use, disclose, copy, modify, Setelah dilakukan mitigasi → common DCS normal
or distribute this document without permission of PLN NUSANTARA POWER, PT
Kronologi #1 Kebakaran Kabel Tray unit 1
Kronologi Gangguan Kejadian tanggal 15 Juni 2023 pukul 02.42 WITA
• Terdapat indikasi PC unit 1 error (turbin, boiler dan
common)
• DCS CHCB error
• PC EWS 03.14 indikasi mati
• Indikasi power loss sampai HUB switch (yang
menghubungkan control ke PC, jadi tidak bisa komunikasi
ke PC operator)
• PC server mati (tetapi masih bisa komunikasi dengan PC
Operator)
• Operator melakukan pengecekan
• Charger baterai → ok
• Pada 03.51 → CWP 1A trip indikasi butterfly valve close
• 04.25 → terdapat indikasi kabel terbakar dibawah greating
coalpipe coal feeder
• Operator melakukan pengecekan DCS power suplay
cabinet → dicoba dinyalakan oleh tim harlis
• server ok
• CF 1A trip VSD mati CF 1D trip indikasi motor
Operator melakukan pengecekan open error
Charger baterai → ok • CF 1F trip indikasi motor open error
• CF 1C trip VSD mati
• CF 1B trip PLC error
• Switch gear 6KV trip → CWP 1A failure
• Switch gear circulating water trafo mati

Temuan instrument :
• Panel CKA 52 controller mati indikasi breaker short
(berpengaruh pada DCS control panel common CHCB, list
terlampir)

Pukul 06.42 beban unit 1 30MW net


Pukul 07.19 beban unit 1 25MW gross
• Temuan MCC ke feeder trip (1A & 1C)

The information contained in this document is strictly confidential. It is strictly forbidden to use, disclose, copy, modify, Setelah dilakukan mitigasi → common DCS normal
or distribute this document without permission of PLN NUSANTARA POWER, PT
Kronologi #1 Kebakaran Kabel Tray unit 1
Kronologi Gangguan Kejadian tanggal 15 Juni 2023 pukul 02.42 WITA
• Terdapat indikasi PC unit 1 error (turbin, boiler dan
common)
• DCS CHCB error
• PC EWS 03.14 indikasi mati
• Indikasi power loss sampai HUB switch (yang
04.25 → terdapat indikasi kabel terbakar menghubungkan control ke PC, jadi tidak bisa komunikasi
ke PC operator)
dibawah greating coalpipe coal feeder • PC server mati (tetapi masih bisa komunikasi dengan PC
Operator)
• Operator melakukan pengecekan
• Charger baterai → ok
• Pada 03.51 → CWP 1A trip indikasi butterfly valve close
• 04.25 → terdapat indikasi kabel terbakar dibawah greating
coalpipe coal feeder
• Operator melakukan pengecekan DCS power suplay
cabinet → dicoba dinyalakan oleh tim harlis
• server ok
• CF 1A trip VSD mati CF 1D trip indikasi motor
open error
• CF 1F trip indikasi motor open error
• CF 1C trip VSD mati
• CF 1B trip PLC error
• Switch gear 6KV trip → CWP 1A failure
• Switch gear circulating water trafo mati

Temuan instrument :
• Panel CKA 52 controller mati indikasi breaker short
(berpengaruh pada DCS control panel common CHCB, list
terlampir)

Pukul 06.42 beban unit 1 30MW net


Pukul 07.19 beban unit 1 25MW gross
• Temuan MCC ke feeder trip (1A & 1C)

The information contained in this document is strictly confidential. It is strictly forbidden to use, disclose, copy, modify, Setelah dilakukan mitigasi → common DCS normal
or distribute this document without permission of PLN NUSANTARA POWER, PT
Kronologi #1 Kebakaran Kabel Tray unit 1
Kronologi Gangguan Kejadian tanggal 15 Juni 2023 pukul 02.42 WITA
• Terdapat indikasi PC unit 1 error (turbin, boiler dan
common)
• DCS CHCB error
• PC EWS 03.14 indikasi mati
• Indikasi power loss sampai HUB switch (yang
menghubungkan control ke PC, jadi tidak bisa komunikasi
ke PC operator)
• PC server mati (tetapi masih bisa komunikasi dengan PC
Operator melakukan pengecekan DCS power suplay cabinet → dicoba dinyalakan oleh Operator)
tim harlis • Operator melakukan pengecekan
• server ok • Charger baterai → ok
• CF 1A trip VSD mati CF 1D trip indikasi motor open error • Pada 03.51 → CWP 1A trip indikasi butterfly valve close
• CF 1F trip indikasi motor open error • 04.25 → terdapat indikasi kabel terbakar dibawah greating
• CF 1C trip VSD mati coalpipe coal feeder
• CF 1B trip PLC error • Operator melakukan pengecekan DCS power suplay
• Switch gear 6KV trip → CWP 1A failure cabinet → dicoba dinyalakan oleh tim harlis
• Switch gear circulating water trafo mati • server ok
• CF 1A trip VSD mati CF 1D trip indikasi motor
open error
• CF 1F trip indikasi motor open error
• CF 1C trip VSD mati
• CF 1B trip PLC error
• Switch gear 6KV trip → CWP 1A failure
• Switch gear circulating water trafo mati

Temuan instrument :
• Panel CKA 52 controller mati indikasi breaker short
(berpengaruh pada DCS control panel common CHCB, list
terlampir)

Pukul 06.42 beban unit 1 30MW net


Pukul 07.19 beban unit 1 25MW gross
• Temuan MCC ke feeder trip (1A & 1C)

The information contained in this document is strictly confidential. It is strictly forbidden to use, disclose, copy, modify, Setelah dilakukan mitigasi → common DCS normal
or distribute this document without permission of PLN NUSANTARA POWER, PT
Saran
1. Tambahkan standard yang dilengkapi Form uji sehingga dapat dijadikan prosedur yang
tetap dan history data
2. Strategic spare part diperlukan untuk mengurangi waktu downtime
3. Perlu mencari referensi standar penggantian rutin Fuse berdasarkan lifetimenya
4. Rutin melakukan asesmen peralatan proteksi
5. Perlu di evaluasi juga terkait proteksi motor 6KV

The information contained in this document is strictly confidential. It is strictly forbidden to use, disclose, copy, modify,
or distribute this document without permission of PLN NUSANTARA POWER, PT 25
The information contained in this document is strictly confidential. It is strictly forbidden to use, disclose, copy, modify, or distribute this document
without permission of PLN NUSANTARA POWER, PT
26