Professional Documents
Culture Documents
Kebocoran
coalpipe 1D
Lokasi
Kabel Tray
Terbakar
The information contained in this document is strictly confidential. It is strictly forbidden to use, disclose, copy, modify,
or distribute this document without permission of PLN NUSANTARA POWER, PT 3
Kebakaran Kabel Tray di bawah Coal Feeder
The information contained in this document is strictly confidential. It is strictly forbidden to use, disclose, copy, modify,
or distribute this document without permission of PLN NUSANTARA POWER, PT 4
Kebutuhan Material (Listrik & Instrumen)
LISTRIK INSTRUMEN
NO SEPESIFIKASI PANJANG KETERANGAN No SPESIFIKASI Cable type PANJANG KETERANGAN
NYSY - 1 4 x 0,5 mm ZT-RVVP (serabut) 100 m
1
Cu/PVC/CTS/PVC 2 2 x 1,5 mm NYYHY (serabut) 100 m Ready
2x6mm serabut 100 m 3 2 x 2 x 1 mm ZRB-DJVP2VP2 (serabut) 100 m
4x4.5mm 100 m Ready 4 2 x 1 mm ZRB-DJVP2VP2 ( serabut ) 100 m
3x2mm serabut 100 m 5 2 x 2,5 mm ZRB-KVVP2-32 ( serabut ) 100 m
7x1.5mm serabut 100 m Ready 6 4 x 1 mm ZR-KVV ( serabut ) 100 m
4x1.5mm 100 m Ready 7 4 x 1,5 mm ZRB-KVVP2-32 ( serabut ) 100 m
14x1.5mm 100 m 8 4 x 2,5 mm NYMHY ( serabut ) 100 m
2 x 1.5 mm 100 m 9 6 x 1 mm ZRB-KVVP2-32 ( serabut ) 100 m
2 x 120 mm 100 m 10 7 x 1,5 mm ZRB-KVVP2-32 ( serabut ) 100 m
2 x 2 mm 100 m 11 10 x 1 mm ZR-KYJVP2 ( tunggal ) 100 m
2 x 2 x 1 mm 100 m 12 20 x 0,8 mm ( tunggal ) 100 m
2 x 4 mm 100 m 13 3 x 2 x 1 mm ZRB-DJVP2VP2 ( tunggal ) 100 m
3 x 2.5 mm 100 m 14 3 x 1,5 mm ZR-KYJVP2 ( tunggal ) 100 m
5 x 2 x 0.8 100 m 15 4 x 0,5 mm ZR-KYJVP2 ( tunggal ) 100 m
16 4 x 1,5 mm ZR-KYJVP2 ( tunggal ) 100 m
2 NYFGBY 4 x 4 mm 200 m Ready 17 4 x 2 mm ZR-KYJVP2 ( tunggal ) 100 m
3 NYFGBY 2 X 2.5 mm 1000 m 18 4 x 2,5 mm ZR-KYJVP2 ( tunggal ) 100 m
19 7 x 1,5 mm ZR-KYJVP2 ( tunggal ) 100 m
20 12 x 1,5 mm ZRB-KVVP2-32 (serabut) +-100m Ready
The information contained in this document is strictly confidential. It is strictly forbidden to use, disclose, copy, modify,
or distribute this document without permission of PLN NUSANTARA POWER, PT 5
Kebutuhan Material (Listrik & Instrumen)
Berdasarkan laporan kondisi terakhir unit, kemungkinan area terdampak pada area coal feeder
system baik Power supply dan control (cabinet CKA 03-05), igniting system, slag cooler
system dll akan terdampak juga, sehingga perlu dipastikan function test kondisi peralatan
sebelum start up.(ref dokumen: F305S-D1014, F305S-D1015, F305S-K0205-01
The information contained in this document is strictly confidential. It is strictly forbidden to use, disclose, copy, modify,
or distribute this document without permission of PLN NUSANTARA POWER, PT 6
Timeline recovery #1
The information contained in this document is strictly confidential. It is strictly forbidden to use, disclose, copy, modify,
or distribute this document without permission of PLN NUSANTARA POWER, PT 7
Rencana Perbaikan (Listrik)
1. Pola kerja menjadi 3 shift sesuai dengan operator (ada tambahan man power Kendala:
dari UMRO JP2) - Material belum semua ready
2. Tiap shift maksimal 4 personil dikarenakan area kerja yang terbatas - Area kerja yang terbatas
3. Re-isolasi kabel (yang belum putus)
4. Menyelesaikan identifikasi jenis kabel & tagging
5. Pemotongan kabel yang sudah teridentifikasi
6. Paralel kupas kabel yang sudah dipotong untuk persiapan penyambungan
Note :
Risiko :
1. Kontak listrik dengan kabel yang masih bertegangan, pada saat identifikasi, tagging dan
pemotongan kabel
2. Terjadi salah sambung atau tidak diketahui pasangan kabel yang dipotong
Mitigasi :
1. Menggunakan voltage detector
2. Melakukan tagging pada 2 sisi, penyamaan pemahaman tagging antar shift sehingga tidak ada
perbedaan dalam melakukan tagging antar shift
5 Penyambungan kabel 1%
The information contained in this document is strictly confidential. It is strictly forbidden to use, disclose, copy, modify,
or distribute this document without permission of PLN NUSANTARA POWER, PT 9
Progress (Listrik)
Note :
Risiko :
1. Kontak listrik dengan kabel yang masih bertegangan, pada saat identifikasi, tagging dan pemotongan kabel
2. Terjadi salah sambung core kabel atau tidak diketahui pasangan kabel yang dipotong
3. Terdapat warna kabel dalam satu kabel yang sama saat setelah pemotongan
4. Penggunaan kabel tidak standart eksisting (non armor copper) dapat mempengaruhi nilai pembacaan signal analog 4-20mA berdampak pada
transmitter, aktuator
Mitigasi :
1. Menggunakan voltage detector , Menggunakan sarung tangan listrik
2. Melakukan tagging pada 2 sisi, penyamaan pemahaman tagging antar personil shift sehingga tidak ada perbedaan dalam melakukan tagging
antar personil shift
3. Dilakukan pengupasan kabel dan memotong kabel satu per satu dengan di continuity lalu di tagging angka
4. Di orderkan kabel dengan spesifikasi yang sama atau secara emergensi menggunakan kabel biasa dengan menggunakan pelindung anti radiasi
(tape copper)
3 Pengupasan kabel 8%
4 Penyambungan kabel 5% Sekun kabel
kontrol kurang
The information contained in this document is strictly confidential. It is strictly forbidden to use, disclose, copy, modify,
or distribute this document without permission of PLN NUSANTARA POWER, PT 12
Progress (Instrumen)
The information contained in this document is strictly confidential. It is strictly forbidden to use, disclose, copy, modify,
or distribute this document without permission of PLN NUSANTARA POWER, PT 14
Rencana Tindak Lanjut Pencegahan
No Tindakan PIC Target Keterangan
1 Pemasangan plat bordes di atas grating Mesin1, Juni 2023 Material : bordes
Rendalhar, SOB tebal 2mm, estimasi
36 lembar per unit
2 Penambahan akses untuk cleaning SOB, Rendalhar Juni 2023 Sementara
menggunakan
scaffolding
3 Penambahan vaccum cleaner industrial Lingkungan, Juni 2023
Rendalhar
4 Penambahan cover cabel tray Harlis, Juli 2023 Material : Plat
Rendalhar
5 Cleaning kabel tray area boiler secara rutin Lingkungan Juni (rutin)
6 Penambahan line heat detector area kabel K3, Fire Juli 2023 Material : LHD
tray Engineer
The information contained in this document is strictly confidential. It is strictly forbidden to use, disclose, copy, modify,
or distribute this document without permission of PLN NUSANTARA POWER, PT 15
THANK YOU
TERIMA KASIH
The information contained in this document is strictly confidential. It is strictly forbidden to use, disclose, copy, modify,
or distribute this document without permission of PLN NUSANTARA POWER, PT 16
FDT (jangka pendek)
JANGKA PENDEK (PEMULIHAN KEGAGALAN )
No. Permasalahan Failure Defense Task PIC Target Penyelesaian
1 Kabel terbakar (instrumen) Identifikasi dan tagging kabel kontrol I&C 96%
2 Kabel terbakar (Listrik) Identifikasi dan tagging kabel power Harlis 96%
Re-isolasi kabel Harlis
The information contained in this document is strictly confidential. It is strictly forbidden to use, disclose, copy, modify,
or distribute this document without permission of PLN NUSANTARA POWER, PT 18
Kronologi #1 Kebakaran Kabel Tray unit 1
Kronologi Gangguan Temuan :
Kejadian tanggal 15 Juni 2023 pukul 02.42 WITA • Megger CF kabel power 1A & 1C short
• Terdapat indikasi PC unit 1 error (turbin, boiler dan common)
• DCS CHCB error
• Megger all fan 6KV (PA, SA, ID,HPFB &
• PC EWS 03.14 indikasi mati ESP Trafo) hasil normal
• Indikasi power loss sampai HUB switch (yang menghubungkan control ke PC, jadi tidak bisa komunikasi ke PC operator)
• PC server mati (tetapi masih bisa komunikasi dengan PC Operator)
• Operator melakukan pengecekan Ditindaklanjuti inspeksi pada area kabel tray
• Charger baterai → ok yang terbakar
• Pada 03.51 → CWP 1A trip indikasi butterfly valve close
• 04.25 → terdapat indikasi kabel terbakar dibawah greating coalpipe coal feeder
• Operator melakukan pengecekan DCS power suplay cabinet → dicoba dinyalakan oleh tim harlis
• server ok
• CF 1A trip VSD mati CF 1D trip indikasi motor open error
• CF 1F trip indikasi motor open error
• CF 1C trip VSD mati
• CF 1B trip PLC error
• Switch gear 6KV trip → CWP 1A failure
• Switch gear circulating water trafo mati
Temuan instrument :
• Panel CKA 52 controller mati indikasi breaker short (berpengaruh pada DCS control panel common CHCB, list terlampir)
The information contained in this document is strictly confidential. It is strictly forbidden to use, disclose, copy, modify,
or distribute this document without permission of PLN NUSANTARA POWER, PT
Kronologi #1 Kebakaran Kabel Tray unit 1
Kronologi Gangguan Kejadian tanggal 15 Juni 2023 pukul 02.42 WITA
Terdapat indikasi PC unit 1 error • Terdapat indikasi PC unit 1 error (turbin, boiler dan
common)
• DCS CHCB error
• PC EWS 03.14 indikasi mati
Turbin • Indikasi power loss sampai HUB switch (yang
menghubungkan control ke PC, jadi tidak bisa komunikasi
ke PC operator)
• PC server mati (tetapi masih bisa komunikasi dengan PC
Operator)
• Operator melakukan pengecekan
• Charger baterai → ok
Boiler • Pada 03.51 → CWP 1A trip indikasi butterfly valve close
• 04.25 → terdapat indikasi kabel terbakar dibawah greating
coalpipe coal feeder
• Operator melakukan pengecekan DCS power suplay
cabinet → dicoba dinyalakan oleh tim harlis
• server ok
• CF 1A trip VSD mati CF 1D trip indikasi motor
open error
CHCB • CF 1F trip indikasi motor open error
• CF 1C trip VSD mati
• CF 1B trip PLC error
• Switch gear 6KV trip → CWP 1A failure
• Switch gear circulating water trafo mati
Temuan instrument :
Common WTP • Panel CKA 52 controller mati indikasi breaker short
(berpengaruh pada DCS control panel common CHCB, list
terlampir)
The information contained in this document is strictly confidential. It is strictly forbidden to use, disclose, copy, modify, Setelah dilakukan mitigasi → common DCS normal
or distribute this document without permission of PLN NUSANTARA POWER, PT
Kronologi #1 Kebakaran Kabel Tray unit 1
Kronologi Gangguan Kejadian tanggal 15 Juni 2023 pukul 02.42 WITA
• Terdapat indikasi PC unit 1 error (turbin, boiler dan
common)
PC server mati (tetapi masih bisa komunikasi • DCS CHCB error
• PC EWS 03.14 indikasi mati
dengan PC Operator) • Indikasi power loss sampai HUB switch (yang
menghubungkan control ke PC, jadi tidak bisa komunikasi
ke PC operator)
• PC server mati (tetapi masih bisa komunikasi dengan PC
Operator)
• Operator melakukan pengecekan
• Charger baterai → ok
• Pada 03.51 → CWP 1A trip indikasi butterfly valve close
• 04.25 → terdapat indikasi kabel terbakar dibawah greating
coalpipe coal feeder
• Operator melakukan pengecekan DCS power suplay
cabinet → dicoba dinyalakan oleh tim harlis
• server ok
• CF 1A trip VSD mati CF 1D trip indikasi motor
open error
• CF 1F trip indikasi motor open error
• CF 1C trip VSD mati
• CF 1B trip PLC error
Indikasi power loss sampai HUB switch (yang • Switch gear 6KV trip → CWP 1A failure
• Switch gear circulating water trafo mati
menghubungkan control ke PC, jadi tidak bisa komunikasi Temuan instrument :
ke PC operator) • Panel CKA 52 controller mati indikasi breaker short
(berpengaruh pada DCS control panel common CHCB, list
terlampir)
The information contained in this document is strictly confidential. It is strictly forbidden to use, disclose, copy, modify, Setelah dilakukan mitigasi → common DCS normal
or distribute this document without permission of PLN NUSANTARA POWER, PT
Kronologi #1 Kebakaran Kabel Tray unit 1
Kronologi Gangguan Kejadian tanggal 15 Juni 2023 pukul 02.42 WITA
• Terdapat indikasi PC unit 1 error (turbin, boiler dan
common)
• DCS CHCB error
• PC EWS 03.14 indikasi mati
• Indikasi power loss sampai HUB switch (yang
menghubungkan control ke PC, jadi tidak bisa komunikasi
ke PC operator)
• PC server mati (tetapi masih bisa komunikasi dengan PC
Operator)
• Operator melakukan pengecekan
• Charger baterai → ok
• Pada 03.51 → CWP 1A trip indikasi butterfly valve close
• 04.25 → terdapat indikasi kabel terbakar dibawah greating
coalpipe coal feeder
• Operator melakukan pengecekan DCS power suplay
cabinet → dicoba dinyalakan oleh tim harlis
• server ok
• CF 1A trip VSD mati CF 1D trip indikasi motor
Operator melakukan pengecekan open error
Charger baterai → ok • CF 1F trip indikasi motor open error
• CF 1C trip VSD mati
• CF 1B trip PLC error
• Switch gear 6KV trip → CWP 1A failure
• Switch gear circulating water trafo mati
Temuan instrument :
• Panel CKA 52 controller mati indikasi breaker short
(berpengaruh pada DCS control panel common CHCB, list
terlampir)
The information contained in this document is strictly confidential. It is strictly forbidden to use, disclose, copy, modify, Setelah dilakukan mitigasi → common DCS normal
or distribute this document without permission of PLN NUSANTARA POWER, PT
Kronologi #1 Kebakaran Kabel Tray unit 1
Kronologi Gangguan Kejadian tanggal 15 Juni 2023 pukul 02.42 WITA
• Terdapat indikasi PC unit 1 error (turbin, boiler dan
common)
• DCS CHCB error
• PC EWS 03.14 indikasi mati
• Indikasi power loss sampai HUB switch (yang
04.25 → terdapat indikasi kabel terbakar menghubungkan control ke PC, jadi tidak bisa komunikasi
ke PC operator)
dibawah greating coalpipe coal feeder • PC server mati (tetapi masih bisa komunikasi dengan PC
Operator)
• Operator melakukan pengecekan
• Charger baterai → ok
• Pada 03.51 → CWP 1A trip indikasi butterfly valve close
• 04.25 → terdapat indikasi kabel terbakar dibawah greating
coalpipe coal feeder
• Operator melakukan pengecekan DCS power suplay
cabinet → dicoba dinyalakan oleh tim harlis
• server ok
• CF 1A trip VSD mati CF 1D trip indikasi motor
open error
• CF 1F trip indikasi motor open error
• CF 1C trip VSD mati
• CF 1B trip PLC error
• Switch gear 6KV trip → CWP 1A failure
• Switch gear circulating water trafo mati
Temuan instrument :
• Panel CKA 52 controller mati indikasi breaker short
(berpengaruh pada DCS control panel common CHCB, list
terlampir)
The information contained in this document is strictly confidential. It is strictly forbidden to use, disclose, copy, modify, Setelah dilakukan mitigasi → common DCS normal
or distribute this document without permission of PLN NUSANTARA POWER, PT
Kronologi #1 Kebakaran Kabel Tray unit 1
Kronologi Gangguan Kejadian tanggal 15 Juni 2023 pukul 02.42 WITA
• Terdapat indikasi PC unit 1 error (turbin, boiler dan
common)
• DCS CHCB error
• PC EWS 03.14 indikasi mati
• Indikasi power loss sampai HUB switch (yang
menghubungkan control ke PC, jadi tidak bisa komunikasi
ke PC operator)
• PC server mati (tetapi masih bisa komunikasi dengan PC
Operator melakukan pengecekan DCS power suplay cabinet → dicoba dinyalakan oleh Operator)
tim harlis • Operator melakukan pengecekan
• server ok • Charger baterai → ok
• CF 1A trip VSD mati CF 1D trip indikasi motor open error • Pada 03.51 → CWP 1A trip indikasi butterfly valve close
• CF 1F trip indikasi motor open error • 04.25 → terdapat indikasi kabel terbakar dibawah greating
• CF 1C trip VSD mati coalpipe coal feeder
• CF 1B trip PLC error • Operator melakukan pengecekan DCS power suplay
• Switch gear 6KV trip → CWP 1A failure cabinet → dicoba dinyalakan oleh tim harlis
• Switch gear circulating water trafo mati • server ok
• CF 1A trip VSD mati CF 1D trip indikasi motor
open error
• CF 1F trip indikasi motor open error
• CF 1C trip VSD mati
• CF 1B trip PLC error
• Switch gear 6KV trip → CWP 1A failure
• Switch gear circulating water trafo mati
Temuan instrument :
• Panel CKA 52 controller mati indikasi breaker short
(berpengaruh pada DCS control panel common CHCB, list
terlampir)
The information contained in this document is strictly confidential. It is strictly forbidden to use, disclose, copy, modify, Setelah dilakukan mitigasi → common DCS normal
or distribute this document without permission of PLN NUSANTARA POWER, PT
Saran
1. Tambahkan standard yang dilengkapi Form uji sehingga dapat dijadikan prosedur yang
tetap dan history data
2. Strategic spare part diperlukan untuk mengurangi waktu downtime
3. Perlu mencari referensi standar penggantian rutin Fuse berdasarkan lifetimenya
4. Rutin melakukan asesmen peralatan proteksi
5. Perlu di evaluasi juga terkait proteksi motor 6KV
The information contained in this document is strictly confidential. It is strictly forbidden to use, disclose, copy, modify,
or distribute this document without permission of PLN NUSANTARA POWER, PT 25
The information contained in this document is strictly confidential. It is strictly forbidden to use, disclose, copy, modify, or distribute this document
without permission of PLN NUSANTARA POWER, PT
26