LOKASI PROYEK DS. CIPEUTEUY - BANDUNGAN BANDUNGAN SUKABUMI, JAWA BARAT
TOTAL PRICE HOUSE (DOUBLE)
NO DESCRIPTION QTY Satuan MATERIAL SUB TOTAL PRICE MATERIAL PRICE A PEKERJAAN PERSIAPAN 1 Mobiltsasi Dan DemobtTisasi 3,00 Lot 2 Barak Kerja 1,00 Lot 3 lisatrik Kerja 1,00 Lot 4 Pengukuran & Boupiank 344,00 m2 Sub Total A B PEKERJAAN TANAH 1 Galian Tanah Foot Plate @ 1000mm x 1000mm x 1000 mm (85 titik) + Urug 85 m3 2 Galian Tanah Foot Plate$ @ 800mm x 800mm x 1000 mm (95 titik) ♦ Urug 60,8 m3 3 Galian sloof @ 200mm x 300mm x (261 meter) + Urug 15,66 m3 4 Galian Drainase @ 60cm x 50cm (275 meter) * Urug 96,25 m3 Sub Total B C PEKERJAAN BETON 1 Pondasi Setapak 800mm x 800mm x 1000mm (85 Titik) K-175 20,4 m3 2 Pondasi Setapak 600mm x 600mm x 1000mm (95 Titik) K-175 15,2 m3 3 Sloof Gantung @ 15cm x 25cm (561.6 meter) k-175 21,0563 m3 4 Plate Lantai Bawah @T 10cm k-225 (1566.4 m2) 156,64 m3 a. Plastik Cor b. Wire mess M81 Layer c. Trowel d. Begistmg 5 Plate Lantai Atas @T 10cm k- 250 (1598 m2) 159,8 m3 a. Seng Bondek @ 0,75 mm b. Besi Wiremesh @8 mm (1 layer) c Besi Baja ringan Tipe U d. Trowel 6 Selasar (Tebal 100mm) Luas 228.8 m2 K-125 22,88 m3 Sub Total C D PEKERJAAN PASANGAN DINDING REBEL Pekerjaan dinding Hebei + Plesteran + Acian 263 m2 a. Bata Hebei 100mm x 200mm x 600mm b. MU-380 @40 kg PerekatT.3mm c. MU-301 @40 kg PlesterT. 15mm d. MU - 200 @ 40 kg Adan T. 2mm Sub Total D E PEKERJAAN DRAINASE Pekerjaan Pasangan Bata Merah + Plesteran+Acian 286 ml Sub Total E F PEKERJAAN KONTRUKSI BAJA a. Baja IWF 200x100 x 5.5 x8 15.528 kg b. Baja IWF 150 x 75 x 5 x7 12.146 kg c. Plat Simpul 2.992 Kg d. Ikatan Angin Rb @ 12 mm 895 kg e.ClemBakel @5/8x8inc 84 pcs f. Stud Gordeng Rb @ 10mm 520 pcs g. Angkur Baut @ 5/8 x 20cm 176 pcs h. Baut Hitam @ 12mm x 2,5 inc 1.800 pcs LBautHitam @ 10mm x 2,5 inc 700 pcs j. Baut Hitam @ 10mm x 2 inc 400 pcs k.CNP 125,50,20,-2 2.772 Kg 1. Angkur Baut @5/8 x 600mm 720 Pcs
RENCANA ANGGARAN BIAYA (RAB) PER UNIT
PROYEK KANDANG AYAM TYPE - CLOSE HOUSE LOKASI PROYEK DS. CIPEUTEUY - BANDUNGAN BANDUNGAN SUKABUMI, JAWA BARAT
G PEKERJAAN DINDING KANDANG
a. Holo @ 40mm x 40mm t2,5mm 6196,85 kg b. Siku @ 30mm x 30mm t3mm 708,76 kg c. Plat strip @ 4mcm t.3mm 1526,04 kg d. Kawat Harmonika @ 2mm - 20mm x 20mm H 1500mm 480 meter e.Zeng Piesing Galvalum@Tiknes 0,35mm H 400mm 240 meter f.Zeng Piesing Galvalum @ Tilcnes 0,35mm H 600mm 240 meter f. Sleef Driling @ 5mm x 35 mm 1800 pcs Sub Total G H PEKERJAAN DINDING GUDANG a. CNP @100,40,20,13 154 kg b.Holo 100 x 50 x 23 544 kg b. Zengzingalum@t.0,30 80 m2 c. Sleef Driling @ 5mm x 60mm 420 pcs Sub Total H 1 PEKERJAAN ATAP a. Atap Sandwict Panel 1900 m2 b. CNP 125,50,20,3.2 1941,6 m2 c. Sleef Driling @ 5mm x 60mm 5400 pcs d. Sleef Driling @ Smm x 2,5mm 1440 pcs e. Zeng ringalum @ 1030 H 800mm 173 meter Sub Total 1 J Pekerjaan Pintu (kusenUNP 100/RangkaHolo 40x40 t2,5/palt 2mm) a. Pintu Gudang @ L 2,4meter x T 2meter 2 set b. Pintu Kandang @ L 1,2 meter x 2 meter 6 set c. Pintu Kolingpat @ L 0,9 meter x 1,8 meter 4 set Sub Total J K PEKERJAAN TANG6A 3 Unit a. UNP150 X 73 X 6 X7 b. Siku 50 x 50 x5 c. Plate Bordes 3mm (Besi) d. Relling Pipa 3/4 inc & Hand Refling + Tiang 13 Inc Sub Total K L PEKERJAAN GANTUNGAN PAKAN a. HoHo 50 x 50 x2 780 kg b. Hunger 70mm dia 8mm 1681 Pcs Sub Total A s/d L Jasa Kontruksi Kontraktor Pelaksana Grand Total