Professional Documents
Culture Documents
A. UPAH
1 Pekerja Org/hari L. 01 105,000.00
2 Tukang Gali / Batu / Tembok / Kayu /Besi / Cat / Pipa / Cor / Semen / Listrik / Pancang Org/hari L. 02 125,000.00
3 Kepala Tukang Org/hari L. 03 145,000.00
4 Mandor Org/hari L. 04 155,000.00
5 Ahli alat berat (mekanik) Org/hari L. 07 125,000.00
6 Operator Alat Berat Org/hari L. 08 170,000.00
7 Pembantu Operator Org/hari L. 09 100,000.00
8 Supir Truk Org/hari L. 10 115,000.00
9 Kenek truk Org/hari L. 11 80,000.00
B. BAHAN PENGISI
1 Batu Kong M³ 300,000.00
2 Batu Sap Pinang M³ 320,000.00
3 Batu pecah 15-20 cm M³ 335,000.00
4 Batu pecah 10-15 cm M³ 350,000.00
5 Batu pecah 3-5 cm M³ 405,000.00
6 Batu pecah 2-3 cm M³ 435,000.00
7 Batu pecah 1-2 cm M³ 475,000.00
8 Batu pecah 0,5-1 cm M³ 500,000.00
9 Stone Dust M³ 350,000.00
10 Aspal Kg 13,790.00
11 Aspal Emulsi (Teak Coat) Kg 14,175.00
12 Aspal Emulsi (Prime Coat) Kg 14,175.00
13 Aspal Sealent Kg 36,000.00
14 Pasir Kasar M³ 125,000.00
15 Pasir Halus M³ 125,000.00
16 Semen PC Zak 75,000.00
17 Semen PC Kg 1,500.00
18 Tanah Ex. Peniraman M³ 190,000.00
19 Tanah Pilihan (Paladis) M³ 284,000.00
20 Paving Block Bh 3,750.00
21 Paving Stone Persegi Panjang (21 x 10,5 x 8) Bh 2,650.00
22 Paving Stone Persegi Panjang (21 x 10,5 x 10) Bh 3,750.00
23 Paving Stone Segi 5 (21 x 30 x 6) Bh 4,200.00
24 Paving Stone Diamond (Segi 6, 18 x 10.5 x 7 ) Bh 3,250.00
25 Batu Bata 5 x 11 x 22cm Bh 2,000.00
26 Bataco 15 x 30 x 7 cm Bh 1,800.00
27 Bataco 20 x 40 x 9 cm ( press ) Bh 2,500.00
28 Bataco 20 x 40 x 7 cm ( press ) Bh 2,300.00
29 Bata Ringan 20 x 60 x 10 Bh 18,000.00
30 Kerawang ( roster ) 18 x 18 cm Bh 20,000.00
31 Kerawang press ( roster ) 30 x 30 cm Bh 60,500.00
32 Keramik 20 x 20 cm Polished ex Roman Kotak 86,500.00
33 Keramik 20 x 20 cm Unpolished ex Roman Kotak 98,000.00
34 Keramik 30 x 30 cm Polished ex Roman Kotak 100,000.00
35 Keramik 30 x 30 cm Unpolished ex Roman Kotak 100,000.00
36 Keramik 40 x 40 cm Polished ex Roman Kotak 110,000.00
HARGA SATUAN DASAR
(TIDAK TERMASUK
NO MATERIAL SATUAN
PROFIT & OVERHEAD)
(Rp)
C. BAHAN KAYU
1 Ky. Belian tdk ketam Uk. 6/6 - 4 M M³ 11,805,000.00
2 Ky. Belian tdk ketam Uk. 7/7 - 4 M M³ 11,700,000.00
3 Ky. Belian tdk ketam Uk. 8/8 - 4 M M³ 8,950,000.00
4 Ky. Belian tdk ketam Uk. 8/16 - 4 M M³ 8,750,000.00
5 Ky. Belian tdk ketam Uk. 9/9 - 4 M M³ 9,567,900.00
6 Ky. Belian tdk ketam Uk. 10/10 - 4 M M³ 10,000,000.00
7 Ky. Belian tdk ketam Uk. 12/12 - 4 M M³ 13,020,900.00
8 Ky. Belian tdk ketam Uk. 18/18 - 4 M M³ 10,416,700.00
9 Ky. Belian tdk ketam Uk. 5/10 - 4 M M³ 11,500,000.00
10 Ky. Belian ketam Uk. 6/6 - 4 M M³ 12,800,000.00
11 Ky. Belian ketam Uk. 7/7 - 4 M M³ 12,500,000.00
12 Ky. Belian ketam Uk. 8/8 - 4 M M³ 11,015,700.00
13 Ky. Belian ketam Uk. 5/10 - 4 M M³ 11,000,000.00
14 Ky. Belian ketam Uk. 4/8 - 4 M M³ 11,718,750.00
15 Ky. klas I Bengkirai uk. 8/8 - 4 M ( tdk ketam ) M³ 7,421,875.00
16 Ky. klas I Bengkirai uk. 7/7 - 4 M ( tdk ketam ) M³ 7,500,000.00
17 Ky. klas I Bengkirai uk. 8/8 - 4 M ( ketam ) M³ 7,800,000.00
18 Ky. klas I Bengkirai uk. 7/7 - 4 M ( ketam ) M³ 7,840,000.00
19 Ky. klas I Bengkirai uk. 5/10 - 4 M ( ketam ) M³ 9,050,000.00
20 Kusen Ky Belian uk. 5/10 Meter 120,000.00
21 Kusen Ky Kelas I Bangkirai uk. 5/10 Meter 80,000.00
22 Kusen Ky Kelas II uk. 5/10 Meter 65,000.00
23 Ky. klas II Mabang uk. 8/8 - 4 M ( tdk ketam ) M³ 4,440,000.00
24 Ky. klas II Mabang uk. 7/7 - 4 M ( tdk ketam ) M³ 4,716,717.69
25 Ky. klas II Mabang uk. 4/6 - 4 M ( tdk ketam ) M³ 5,070,000.00
HARGA SATUAN DASAR
(TIDAK TERMASUK
NO MATERIAL SATUAN
PROFIT & OVERHEAD)
(Rp)
D. BAHAN CAT
1 Amplas Lbr 4,000.00
2 Minyak cat Kg 36,000.00
3 Cat kilat setara Dulux Kg 70,000.00
4 Cat kilat setara Avian Kg 70,000.00
5 Plamur Kg 31,500.00
6 Cat Dasar Alkali Kg 140,000.00
7 Cat Akhir Interior setara Dulux Kg 104,000.00
8 Cat Akhir Eksterior (weather shield) setara Dulux Kg 115,000.00
9 Cat Dasar setara Mowilex Kg 70,000.00
10 Cat Akhir Interior setara Mowilex Kg 100,000.00
11 Cat Akhir Eksterior (weather shield) setara Mowilex Kg 120,000.00
12 Cat Dasar setara Vinilex Kg 27,000.00
13 Cat Akhir Interior setara Vinilex Kg 28,000.00
14 Cat seng (Zinc Chromate) Kg 44,000.00
15 Plitur Kg 64,000.00
16 Thiner Ltr 25,000.00
17 Melamic Ltr 67,000.00
18 Vernis Ltr 45,000.00
19 Meni Kg 52,000.00
20 Oker / Semen Warna Kg 14,000.00
21 Lem Kayu Kg 20,000.00
22 Sealent Kg 107,700.00
23 Soda Api Kg 25,000.00
24 Sabun / cream pembersih kotoran Kg 15,700.00
25 Teak Oil Ltr 60,000.00
26 Ter / Residu Ltr 58,400.00
27 Kuas 4" Bh 25,000.00
28 Cat Marka (non Thermoplas) Kg 65,000.00
29 Cat Marka (Thermoplastic) Kg 95,000.00
30 Cat Kansteen (ex. Matex) Kg 53,750.00
31 Cat Trotoar (ex. Tenokote) Kg 41,250.00
32 Glass Bead Kg 30,000.00
33 Weatherbond Emulsion ( cat kerb ) Kg 39,000.00
34 Cat Water Proofing Kg 78,500.00
F. BAHAN PENGGANTUNG
1 Pintu PVC untuk WC Bh 266,000.00
2 Kait angin Bh 14,400.00
3 Handle Jendela Bh 15,400.00
4 Handle Pintu Bh 170,000.00
5 Engsel jendela Bh 18,800.00
6 Engsel pintu Bh 29,000.00
7 Slot pintu Bh 18,900.00
8 Slot jendela Bh 8,800.00
9 Kunci tanam 2 slag (setaraf Belluci) Bh 180,000.00
10 Kunci tanam 1 slag Besar Bh 230,000.00
11 Kunci tanam 1 slag Kecil Bh 150,000.00
12 Kunci silinder Bh 78,800.00
13 Door Closer Bh 250,000.00
14 Door Stoper Bh 88,750.00
HARGA SATUAN DASAR
(TIDAK TERMASUK
NO MATERIAL SATUAN
PROFIT & OVERHEAD)
(Rp)
G. BAHAN ATAP
1 Sirap belian Lbr 5,300.00
2 Asbes Lbr 57,200.00
3 Eternit M² 68,400.00
4 Genteng Metal Type Permata 0.30 Lbr 63,000.00
5 Genteng Metal Type Prima 0.30 Lbr 66,600.00
6 Genteng Metal Type Royal 0.30 Lbr 66,600.00
7 Genteng Metal Type Classic 0.30 Lbr 66,600.00
8 Genteng Metal Type Permata 0.25 Lbr 51,800.00
9 Genteng Metal Type Classic 0.25 Lbr 51,800.00
10 Genteng Metal Type Royal 0.25 Lbr 51,800.00
11 Atap Genteng Onduline Transparan 2 x 0,95 m Lbr 275,000.00
12 Atap Genteng Onduline Warna 2 x 0,95 m (merah,hijau,coklat & hitam) Lbr 173,000.00
13 Atap Genteng Onduline Warna 2 x 0,95 m (Biru /Premium) Lbr 200,000.00
14 Atap Genteng Onduvilla Warna 1,06 x 0,4 m (merah,hijau,coklat & hitam) Lbr 59,000.00
15 Atap Genteng Onduvilla Warna 1,06 x 0,4 m (teracota 3D & florentino) Lbr 54,000.00
16 Perabung Onduline Warna 90 x 50 cm (merah, coklat, hijau & hitam) Lbr 100,000.00
17 Perabung Onduline Warna 90 x 50 cm (biru/premium) Lbr 110,000.00
18 Perabung Onduline Warna 90 x 50 cm (florentino) Lbr 110,000.00
19 Siku Onduline Warna 110 x 40 cm (merah,coklat,hijau & hitam) Lbr 93,000.00
20 Apron Piece Onduvilla 102 x 14 cm Lbr 89,500.00
21 Verge Piece Onduline/Onduvilla 104 x 10,5 cm tinggi 11,4 cm Lbr 89,500.00
22 Onduband M 57,000.00
23 Atap Seng Metal Soka Abadi Lbr 92,000.00
24 Atap Seng Metal Soka Jempol Lbr 67,000.00
25 Atap Seng Metal Soka Tiara Lbr 68,000.00
26 Genteng Metal Stone ( Type Classic 0.35 ) Lbr 80,000.00
27 Genteng Metal Stone ( Type Prima 0.35 ) Lbr 80,000.00
28 Atap Metal Supersheet 0.35 (polos) M² 81,300.00
29 Atap Metal Supersheet 0.35 (colour) M² 111,900.00
30 Atap Metal Supersheet 0.25 (polos) M² 47,000.00
31 Atap Metal Supersheet 0.25 (colour) M² 70,000.00
32 Atap Trim Deck 0.3 (polos) M² 100,000.00
33 Atap Trim Deck 0.35 (color) M² 112,300.00
34 Atap polycarbonat M² 78,300.00
35 Nok bubungan genteng metal 1/2 lingkaran 0.35 (pj 40cm) Bh 46,000.00
36 Nok bubungan genteng metal stone 1/2 lingkaran 0.35 (pj 40cm) Bh 75,000.00
37 Nok bubungan genteng metal kotak 0.35 M' 50,000.00
38 Nok bubungan genteng metal stone kotak 0.35 M' 96,900.00
39 Nok bubungan Trim Deck (polos) M' 109,500.00
40 Nok bubungan Trim Deck (color) M' 123,100.00
41 Seng Gelombang Bjls 30 Lbr 72,000.00
42 Seng Gelombang Bjls 20 Lbr 55,000.00
43 Seng Plat Bjls 20 Lbr 65,000.00
HARGA SATUAN DASAR
(TIDAK TERMASUK
NO MATERIAL SATUAN
PROFIT & OVERHEAD)
(Rp)
H. BAHAN KACA
1 Kaca Polos, t = 3 mm M² 150,000.00
2 Kaca Polos, t = 5 mm M² 200,000.00
3 Kaca Polos, t = 8 mm M² 398,000.00
4 Kaca Polos, t = 12 mm M² 640,000.00
5 Kaca Rayben, t = 3 mm M² 200,000.00
6 Kaca Rayben, t = 5 mm M² 200,000.00
7 Kaca Rayben, t = 8 mm M² 550,000.00
8 Kaca Rayben, t = 12 mm M² 900,000.00
9 Kaca Cermin t = 3 mm M² 275,000.00
10 Kaca Cermin t = 5 mm M² 418,000.00
11 Kaca Repsol, t = 5 mm M² 550,000.00
12 Sealent Kg 35,000.00
13 Nako + Bingkai (80 x 15) x 10 daun polos Bh 400,000.00
14 Nako + Bingkai (80 x 15) x 10 daun rayben Bh 469,000.00
15 Kaca Es, t = 3 mm M² 275,000.00
16 Kaca Es, t = 5 mm M² 267,500.00
17 Kaca Raindown, t = 5 mm M² 550,000.00
I. BAHAN TRIPLEK
1 Triplek t = 3 mm Lbr 70,000.00
5 Teakwood t = 3 mm Lbr 140,000.00
6 Formika t = 0,03 mm Lbr 115,000.00
7 Multiplex t = 6 mm Lbr 111,000.00
8 Multiplex t = 9 mm Lbr 220,000.00
HARGA SATUAN DASAR
(TIDAK TERMASUK
NO MATERIAL SATUAN
PROFIT & OVERHEAD)
(Rp)
J. BAHAN SANITASI
1 Wastafel setara Toto Bh 1,000,000.00
2 Kloset duduk monoblok Bh 2,962,700.00
3 Kloset duduk putih (setaraf TOTO) Bh 2,246,800.00
4 Kloset duduk warna (setaraf TOTO) Bh 2,500,000.00
5 Kloset jongkok (setaraf TOTO) Bh 330,000.00
6 Kloset jongkok (setaraf INA) Bh 200,000.00
7 Urinoir setaraf Toto Unit 2,000,000.00
8 Bak air fibreglass uk. 55x55x60 cm Bh 300,000.00
9 Shower Spray setara Toto Unit 350,000.00
10 Sliding rail setara Toto Unit 500,000.00
11 Floordrain stainless steel setara Toto Bh 400,000.00
12 Floordrain PVC Bh 35,000.00
13 Tempat Sabun Setara Toto Bh 120,000.00
14 Kran zink setara Toto Bh 307,000.00
15 Kitchenzink stainless steel 1 lubang Unit 650,000.00
16 Kran dinding setara Toto Bh 150,000.00
17 Kran air uk 1/2" Bh 32,500.00
18 Pipa PVC dia 1/2" AW ex Wavin Btg 23,400.00
19 Pipa PVC dia 3/4" AW ex Wavin Btg 32,500.00
20 Pipa PVC dia 1" AW ex Wavin Btg 44,400.00
21 Pipa PVC dia 2" AW ex Wavin Btg 100,000.00
22 Pipa PVC dia 3" AW ex Wavin Btg 203,500.00
23 Pipa PVC dia 4" AW ex Wavin Btg 335,500.00
24 Pipa PVC dia 8" AW ex Wavin Btg 1,306,800.00
25 Pipa PVC dia 3/4" D ex Wavin Btg 23,500.00
26 Pipa PVC dia 1" D ex Wavin Btg 30,000.00
27 Pipa PVC dia 2" D ex Wavin Btg 61,000.00
28 Pipa PVC dia 3" D ex Wavin Btg 111,000.00
29 Pipa PVC dia 4" D ex Wavin Btg 173,300.00
30 Stop kran dia 1/2" ex onda Bh 43,000.00
31 Stop kran dia 3/4" ex onda Bh 51,200.00
32 Stop kran dia 1" ex onda Bh 115,000.00
33 Tangki air 1000 liter Bh 2,500,000.00
34 Tangki air 500 liter Bh 1,500,000.00
35 Pelampung otomatis Bh 75,000.00
36 Roof Drain Metal Bh 75,000.00
37 Mesin Jet Pump kap.250 watt Unit 1,440,000.00
38 Mesin Pompa tekan kap. 150 watt Unit 550,000.00
L. BATU ALAM
1 Batu Andesit Ukuran 10 x 20 cm M² 170,000.00
2 Batu Andesit Ukuran 15 x 30 cm M² 200,000.00
3 Batu Andesit Ukuran 20 x 40 cm M² 230,000.00
4 Batu Andesit Ukuran 30 x 60 cm M² 260,000.00
5 Batu Candi Ukuran 10 x 20 cm M² 170,000.00
6 Batu Candi Ukuran 15 x 30 cm M² 200,000.00
7 Batu Candi Ukuran 20 x 40 cm M² 220,000.00
8 Batu Pacitoroso Ukuran 10 x 20 cm M² 190,000.00
HARGA SATUAN DASAR
(TIDAK TERMASUK
NO MATERIAL SATUAN
PROFIT & OVERHEAD)
(Rp)
15,750.00
56,250.00
6,525.00
1,240.00
79,765.00
414,792.00
6,000.00
420,792.00
500,557.00
75,083.55
575,640.55
Jumlah Harga
(Rp.)
8,400.00
100,000.00
11,600.00
620.00
120,620.00
908,700.00
908,700.00
1,029,320.00
154,398.00
1,183,718.00
A.2.2.1 Harga Satuan Pekerjaan Persiapan
A.2.2.1.2 (K3) Pembuatan 1 m2 pagar sementara dari seng gelombang tinggi 2 meter
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.200 105,000.00 21,000.00
Tukang Kayu L.02 OH 0.400 125,000.00 50,000.00
Kepala Tukang L.03 OH 0.020 145,000.00 2,900.00
Mandor L.04 OH 0.020 155,000.00 3,100.00
JUMLAH TENAGA KERJA 77,000.00
B BAHAN
Dolken Kayu 8-10/400 cm Batang 1.250 12,000.00 15,000.00
Semen Portland Kg 2.500 -
Seng gelombang Lbr 1.200 55,000.00 66,000.00
Pasir Beton m3 0.005 -
Koral Beton m3 0.009 -
Kayu 5/7 m3 0.072 4,755,000.00 342,360.00
Paku Biasa 2"-5" Kg 0.060 23,000.00 1,380.00
Mini besi Liter 0.450 52,000.00 23,400.00
JUMLAH HARGA BAHAN 448,140.00
C PERALATAN
A.2.2.1.3 (K3) Pembuatan 1 m2 pagar sementara dari kawat duri tinggi 1,8 meter
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.200 105,000.00 21,000.00
Tukang Kayu L.02 OH 0.300 125,000.00 37,500.00
Kepala Tukang L.03 OH 0.020 145,000.00 2,900.00
Mandor L.04 OH 0.020 155,000.00 3,100.00
JUMLAH TENAGA KERJA 64,500.00
B BAHAN
Dolken Kayu 8-10/400 cm Batang 1.000 12,000.00 12,000.00
Semen Portland Kg 2.000 1,500.00 3,000.00
Kawat duri m 25.000 4,000.00 100,000.00
Pasir Beton m3 0.005 1,500.00 7.50
Koral Beton m3 0.009 125,000.00 1,125.00
Paku Biasa 2"-5" Kg 0.060 23,000.00 1,380.00
JUMLAH HARGA BAHAN 117,512.50
C PERALATAN
A.3.2.1.10 Pemasangan 1m3 pondasi siklop, 60% beton campuran 1 SP : 2PB : 3 Kr dan 40% batu belah
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 3.400 105,000.00 357,000.00
Tukang batu L.02 OH 0.850 125,000.00 106,250.00
Kepala tukang L.03 OH 0.085 145,000.00 12,325.00
Mandor L.04 OH 0.170 155,000.00 26,350.00
JUMLAH TENAGA KERJA 501,925.00
B BAHAN
Batu belah (10-15 cm) m3 0.480 350,000.00 168,000.00
Semen Portland Kg 194.000 1,500.00 291,000.00
Pasir beton m3 0.312 125,000.00 39,000.00
Kerikil (1-2 cm) m3 0.468 475,000.00 222,300.00
Besi beton Kg 126.000 13,500.00 1,701,000.00
Kawat beton Kg 1.800 25,000.00 45,000.00
JUMLAH HARGA BAHAN 2,466,300.00
C PERALATAN
A.4.1.1.1 Membuat 1m3 beton mutu f'c = 7,4 Mpa ( K 100), slump (12 ± 2) cm ,w/c =0,87
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.650 105,000.00 173,250.00
Tukang batu L.02 OH 0.275 125,000.00 34,375.00
Kepala tukang L.03 OH 0.028 145,000.00 4,060.00
Mandor L.04 OH 0.083 155,000.00 12,865.00
JUMLAH TENAGA KERJA 224,550.00
B BAHAN
Semen Portland Kg 247.000 1,500.00 370,500.00
Pasir beton Kg 869.000 89.29 77,589.29
Kerikil (maks 30 mm) Kg 999.000 351.85 351,500.00
Air Liter 215.000
JUMLAH HARGA BAHAN 799,589.29
C PERALATAN
A.4.1.1.1.a Membuat 1m3 beton mutu f'c = 7,4 Mpa ( K 100), slump (12 ± 2) cm ,w/c =0,87 (menggunakan molen)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.323 105,000.00 138,915.00
Tukang batu L.02 OH 0.189 125,000.00 23,625.00
Kepala tukang L.03 OH 0.019 145,000.00 2,755.00
Mandor L.04 OH 0.066 155,000.00 10,230.00
JUMLAH TENAGA KERJA 175,525.00
B BAHAN
Semen Portland Kg 247.000 1,500.00 370,500.00
Pasir beton Kg 869.000 89.29 77,589.29
Kerikil (maks 30 mm) Kg 999.000 351.85 351,500.00
Air Liter 215.000
JUMLAH HARGA BAHAN 799,589.29
C PERALATAN
Sewa Molen sewa-hari 0.250 170,000.00 42,500.00
JUMLAH HARGA ALAT 42,500.00
D Jumlah (A + B + C) 1,017,614.29
E Overhead & Provit 15% x D 152,642.14
F Harga Satuan Pekerjaan ( D + E ) 1,170,256.43
A.4.1.1.2 Membuat 1m3 beton mutu f'c = 9,8 Mpa (K 125), slump (12 ± 2) cm ,w/c =0,78
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.650 105,000.00 173,250.00
Tukang batu L.02 OH 0.275 125,000.00 34,375.00
Kepala tukang L.03 OH 0.028 145,000.00 4,060.00
Mandor L.04 OH 0.083 155,000.00 12,865.00
JUMLAH TENAGA KERJA 224,550.00
B BAHAN
Semen Portland Kg 276.000 1500.00 414,000.00
Pasir beton Kg 828.000 89.29 73,928.57
Kerikil (maks 30 mm) Kg 1012.000 351.85 356,074.07
Air Liter 215.000
JUMLAH HARGA BAHAN 844,002.65
C PERALATAN
A.4.1.1.2.a Membuat 1m3 beton mutu f'c = 9,8 Mpa (K 125), slump (12 ± 2) cm ,w/c =0,78 (menggunakan molen)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.323 105,000.00 138,915.00
Tukang batu L.02 OH 0.189 125,000.00 23,625.00
Kepala tukang L.03 OH 0.019 145,000.00 2,755.00
Mandor L.04 OH 0.066 155,000.00 10,230.00
JUMLAH TENAGA KERJA 175,525.00
B BAHAN
Semen Portland Kg 276.000 1500.00 414,000.00
Pasir beton Kg 828.000 89.29 73,928.57
Kerikil (maks 30 mm) Kg 1012.000 351.85 356,074.07
Air Liter 215.000
JUMLAH HARGA BAHAN 844,002.65
C PERALATAN
Sewa Molen sewa-hari 0.250 170,000.00 42,500.00
JUMLAH HARGA ALAT 42,500.00
D Jumlah (A + B + C) 1,062,027.65
E Overhead & Provit 15% x D 159,304.15
F Harga Satuan Pekerjaan ( D + E ) 1,221,331.79
A.4.1.1.3 Membuat 1m3 beton mutu f'c = 12,2 Mpa (K 150), slump (12 ± 2) cm ,w/c =0,72
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.650 105,000.00 173,250.00
Tukang batu L.02 OH 0.275 125,000.00 34,375.00
Kepala tukang L.03 OH 0.028 145,000.00 4,060.00
Mandor L.04 OH 0.083 155,000.00 12,865.00
JUMLAH TENAGA KERJA 224,550.00
B BAHAN
Semen Portland Kg 299.000 1,500.00 448,500.00
Pasir beton Kg 799.000 89.29 71,339.29
Kerikil (maks 30 mm) Kg 1017.000 351.85 357,833.33
Air Liter 215.000
JUMLAH HARGA BAHAN 877,672.62
C PERALATAN
A.4.1.1.3.a Membuat 1m3 beton mutu f'c = 12,2 Mpa (K 150), slump (12 ± 2) cm ,w/c =0,72 (menggunakan molen)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.323 105,000.00 138,915.00
Tukang batu L.02 OH 0.189 125,000.00 23,625.00
Kepala tukang L.03 OH 0.019 145,000.00 2,755.00
Mandor L.04 OH 0.066 155,000.00 10,230.00
JUMLAH TENAGA KERJA 175,525.00
B BAHAN
Semen Portland Kg 299.000 1,500.00 448,500.00
Pasir beton Kg 799.000 89.29 71,339.29
Kerikil (maks 30 mm) Kg 1017.000 351.85 357,833.33
Air Liter 215.000
JUMLAH HARGA BAHAN 877,672.62
C PERALATAN
Sewa Molen sewa-hari 0.250 170,000.00 42,500.00
JUMLAH HARGA ALAT 42,500.00
D Jumlah (A + B + C) 1,095,697.62
E Overhead & Provit 15% x D 164,354.64
F Harga Satuan Pekerjaan ( D + E ) 1,260,052.26
A.4.1.1.4 Membuat 1m3 lantai kerja beton mutu f'c = 7,4 MPa slump (3-6) cm, w/c =0,87
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.200 105,000.00 126,000.00
Tukang batu L.02 OH 0.200 125,000.00 25,000.00
Kepala tukang L.03 OH 0.020 145,000.00 2,900.00
Mandor L.04 OH 0.060 155,000.00 9,300.00
JUMLAH TENAGA KERJA 163,200.00
B BAHAN
Semen Portland Kg 230.000 1,500.00 345,000.00
Pasir beton Kg 893.000 89.29 79,732.14
Kerikil (maks 30 mm) Kg 1027.000 351.85 361,351.85
Air Liter 200.000
JUMLAH HARGA BAHAN 786,083.99
C PERALATAN
A.4.1.1.5 Membuat 1m3 beton mutu f'c = 14,5 MPa (K 175), slump (12 ± 2) cm ,w/c = 0,66
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.650 105,000.00 173,250.00
Tukang batu L.02 OH 0.275 125,000.00 34,375.00
Kepala tukang L.03 OH 0.028 145,000.00 4,060.00
Mandor L.04 OH 0.083 155,000.00 12,865.00
JUMLAH TENAGA KERJA 224,550.00
B BAHAN
Semen Portland Kg 326.000 1,500.00 489,000.00
Pasir beton Kg 760.000 89.29 67,857.14
Kerikil (maks 30 mm) Kg 1029.000 351.85 362,055.56
Air Liter 215.000
JUMLAH HARGA BAHAN 918,912.70
C PERALATAN
A.4.1.1.5.a Membuat 1m3 beton mutu f'c = 14,5 MPa (K 175), slump (12 ± 2) cm ,w/c = 0,66 (menggunakan molen)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.323 105,000.00 138,915.00
Tukang batu L.02 OH 0.189 125,000.00 23,625.00
Kepala tukang L.03 OH 0.019 145,000.00 2,755.00
Mandor L.04 OH 0.066 155,000.00 10,230.00
JUMLAH TENAGA KERJA 175,525.00
B BAHAN
Semen Portland Kg 326.000 1,500.00 489,000.00
Pasir beton Kg 760.000 89.29 67,857.14
Kerikil (maks 30 mm) Kg 1029.000 351.85 362,055.56
Air Liter 215.000
JUMLAH HARGA BAHAN 918,912.70
C PERALATAN
Sewa Molen sewa-hari 0.250 170,000.00 42,500.00
JUMLAH HARGA ALAT 42,500.00
D Jumlah (A + B + C) 1,136,937.70
E Overhead & Provit 15% x D 170,540.65
F Harga Satuan Pekerjaan ( D + E ) 1,307,478.35
A.4.1.1.6 Membuat 1m3 beton mutu f'c = 16,9 Mpa (K 200), slump (12 ± 2) cm ,w/c = 0,61
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.650 105,000.00 173,250.00
Tukang batu L.02 OH 0.275 125,000.00 34,375.00
Kepala tukang L.03 OH 0.028 145,000.00 4,060.00
Mandor L.04 OH 0.083 155,000.00 12,865.00
JUMLAH TENAGA KERJA 224,550.00
B BAHAN
Semen Portland Kg 352.000 1,500.00 528,000.00
Pasir beton Kg 731.000 89.29 65,267.86
Kerikil (maks 30 mm) Kg 1031.000 351.85 362,759.26
Air Liter 215.000
JUMLAH HARGA BAHAN 956,027.12
C PERALATAN
A.4.1.1.6.a Membuat 1m3 beton mutu f'c = 16,9 Mpa (K 200), slump (12 ± 2) cm ,w/c = 0,61 (menggunakan molen)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.323 105,000.00 138,915.00
Tukang batu L.02 OH 0.189 125,000.00 23,625.00
Kepala tukang L.03 OH 0.019 145,000.00 2,755.00
Mandor L.04 OH 0.066 155,000.00 10,230.00
JUMLAH TENAGA KERJA 175,525.00
B BAHAN
Semen Portland Kg 352.000 1,500.00 528,000.00
Pasir beton Kg 731.000 89.29 65,267.86
Kerikil (maks 30 mm) Kg 1031.000 351.85 362,759.26
Air Liter 215.000
JUMLAH HARGA BAHAN 956,027.12
C PERALATAN
Sewa Molen sewa-hari 0.250 170,000.00 42,500.00
JUMLAH HARGA ALAT 42,500.00
D Jumlah (A + B + C) 1,174,052.12
E Overhead & Provit 15% x D 176,107.82
F Harga Satuan Pekerjaan ( D + E ) 1,350,159.93
A.4.1.1.7 Membuat 1m3 beton mutu f'c = 19,3 Mpa (K 225), slump (12 ± 2) cm ,w/c = 0,58
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.650 105,000.00 173,250.00
Tukang batu L.02 OH 0.275 125,000.00 34,375.00
Kepala tukang L.03 OH 0.028 145,000.00 4,060.00
Mandor L.04 OH 0.083 155,000.00 12,865.00
JUMLAH TENAGA KERJA 224,550.00
B BAHAN
Semen Portland Kg 371.000 1,500.00 556,500.00
Pasir beton Kg 698.000 89.29 62,321.43
Kerikil (maks 30 mm) Kg 1047.000 351.85 368,388.89
Air Liter 215.000
JUMLAH HARGA BAHAN 987,210.32
C PERALATAN
A.4.1.1.8 Membuat 1m3 beton mutu f'c = 21,7 Mpa (K 250), slump (12 ± 2) cm ,w/c = 0,56
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.650 105,000.00 173,250.00
Tukang batu L.02 OH 0.275 125,000.00 34,375.00
Kepala tukang L.03 OH 0.028 145,000.00 4,060.00
Mandor L.04 OH 0.083 155,000.00 12,865.00
JUMLAH TENAGA KERJA 224,550.00
B BAHAN
Semen Portland Kg 384.000 1,500.00 576,000.00
Pasir beton Kg 692.000 89.29 61,785.71
Kerikil (maks 30 mm) Kg 1039.000 351.85 365,574.07
Air Liter 215.000
JUMLAH HARGA BAHAN 1,003,359.79
C PERALATAN
A.4.1.1.8.a Membuat 1m3 beton mutu f'c = 21,7 Mpa (K 250), slump (12 ± 2) cm ,w/c = 0,56 (menggunakan molen)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.323 105,000.00 138,915.00
Tukang batu L.02 OH 0.189 125,000.00 23,625.00
Kepala tukang L.03 OH 0.019 145,000.00 2,755.00
Mandor L.04 OH 0.066 155,000.00 10,230.00
JUMLAH TENAGA KERJA 175,525.00
B BAHAN
Semen Portland Kg 384.000 1,500.00 576,000.00
Pasir beton Kg 692.000 89.29 61,785.71
Kerikil (maks 30 mm) Kg 1039.000 351.85 365,574.07
Air Liter 215.000
JUMLAH HARGA BAHAN 1,003,359.79
C PERALATAN
Sewa Molen sewa-hari 0.250 170,000.00 42,500.00
JUMLAH HARGA ALAT 42,500.00
D Jumlah (A + B + C) 1,221,384.79
E Overhead & Provit 15% x D 183,207.72
F Harga Satuan Pekerjaan ( D + E ) 1,404,592.51
A.4.1.1.9 Membuat 1m3 beton mutu f'c = 24,0 Mpa (K 275), slump (12 ± 2) cm ,w/c = 0,53
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.650 105,000.00 173,250.00
Tukang batu L.02 OH 0.275 125,000.00 34,375.00
Kepala tukang L.03 OH 0.028 145,000.00 4,060.00
Mandor L.04 OH 0.083 155,000.00 12,865.00
JUMLAH TENAGA KERJA 224,550.00
B BAHAN
Semen Portland Kg 406.000 1,500.00 609,000.00
Pasir beton Kg 684.000 89.29 61,071.43
Kerikil (maks 30 mm) Kg 1026.000 351.85 361,000.00
Air Liter 215.000 -
JUMLAH HARGA BAHAN 1,031,071.43
C PERALATAN
A.4.1.1.9.a Membuat 1m3 beton mutu f'c = 24,0 Mpa (K 275), slump (12 ± 2) cm ,w/c = 0,53 (menggunakan molen)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.323 105,000.00 138,915.00
Tukang batu L.02 OH 0.189 125,000.00 23,625.00
Kepala tukang L.03 OH 0.019 145,000.00 2,755.00
Mandor L.04 OH 0.066 155,000.00 10,230.00
JUMLAH TENAGA KERJA 175,525.00
B BAHAN
Semen Portland Kg 406.000 1,500.00 609,000.00
Pasir beton Kg 684.000 89.29 61,071.43
Kerikil (maks 30 mm) Kg 1026.000 351.85 361,000.00
Air Liter 215.000 -
JUMLAH HARGA BAHAN 1,031,071.43
C PERALATAN
Sewa Molen sewa-hari 0.250 170,000.00 42,500.00
JUMLAH HARGA ALAT 42,500.00
D Jumlah (A + B + C) 1,249,096.43
E Overhead & Provit 15% x D 187,364.46
F Harga Satuan Pekerjaan ( D + E ) 1,436,460.89
A.4.1.1.10 Membuat 1m3 beton mutu f'c = 26,4 Mpa (K 300), slump (12 ± 2) cm ,w/c = 0,52
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.650 105,000.00 173,250.00
Tukang batu L.02 OH 0.275 125,000.00 34,375.00
Kepala tukang L.03 OH 0.028 145,000.00 4,060.00
Mandor L.04 OH 0.083 155,000.00 12,865.00
JUMLAH TENAGA KERJA 224,550.00
B BAHAN
Semen Portland Kg 413.000 1,500.00 619,500.00
Pasir beton Kg 681.000 89.29 60,803.57
Kerikil (maks 30 mm) Kg 1021.000 351.85 359,240.74
Air Liter 215.000
JUMLAH HARGA BAHAN 1,039,544.31
C PERALATAN
A.4.1.1.10.a Membuat 1m3 beton mutu f'c = 26,4 Mpa (K 300), slump (12 ± 2) cm ,w/c = 0,52 (menggunakan molen)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.323 105,000.00 138,915.00
Tukang batu L.02 OH 0.189 125,000.00 23,625.00
Kepala tukang L.03 OH 0.019 145,000.00 2,755.00
Mandor L.04 OH 0.066 155,000.00 10,230.00
JUMLAH TENAGA KERJA 175,525.00
B BAHAN
Semen Portland Kg 413.000 1,500.00 619,500.00
Pasir beton Kg 681.000 89.29 60,803.57
Kerikil (maks 30 mm) Kg 1021.000 351.85 359,240.74
Air Liter 215.000
JUMLAH HARGA BAHAN 1,039,544.31
C PERALATAN
Sewa Molen sewa-hari 0.250 170,000.00 42,500.00
JUMLAH HARGA ALAT 42,500.00
D Jumlah (A + B + C) 1,257,569.31
E Overhead & Provit 15% x D 188,635.40
F Harga Satuan Pekerjaan ( D + E ) 1,446,204.71
A.4.1.1.11 Membuat 1m3 beton mutu f'c = 28,8 Mpa (K 325), slump (12 ± 2) cm ,w/c = 0,49
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 2.100 105,000.00 220,500.00
Tukang batu L.02 OH 0.350 125,000.00 43,750.00
Kepala tukang L.03 OH 0.035 145,000.00 5,075.00
Mandor L.04 OH 0.105 155,000.00 16,275.00
JUMLAH TENAGA KERJA 285,600.00
B BAHAN
Semen Portland Kg 439.000 1,500.00 658,500.00
Pasir beton Kg 670.000 89.29 59,821.43
Kerikil (maks 30 mm) Kg 1006.000 351.85 353,962.96
Air Liter 215.000
JUMLAH HARGA BAHAN 1,072,284.39
C PERALATAN
A.4.1.1.12 Membuat 1m3 beton mutu f'c = 31,2 Mpa (K 350), slump (12 ± 2) cm ,w/c = 0,48
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 2.100 105,000.00 220,500.00
Tukang batu L.02 OH 0.350 125,000.00 43,750.00
Kepala tukang L.03 OH 0.035 145,000.00 5,075.00
Mandor L.04 OH 0.105 155,000.00 16,275.00
JUMLAH TENAGA KERJA 285,600.00
B BAHAN
Semen Portland Kg 448.000 1,500.00 672,000.00
Pasir beton Kg 667.000 89.29 59,553.57
Kerikil (maks 30 mm) Kg 1000.000 351.85 351,851.85
Air Liter 215.000
JUMLAH HARGA BAHAN 1,083,405.42
C PERALATAN
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
1 Pekerja L.01 OH 1.000 105,000.00 105,000.00
2 Tukang L.02 OH 0.250 125,000.00 31,250.00
3 Kepala Tukang L.03 OH 0.025 145,000.00 3,625.00
4 Mandor L.04 OH 0.100 155,000.00 15,500.00
JUMLAH TENAGA KERJA 155,375.00
B BAHAN
1 Beton Ready Mix K 100 m³ 1.020 1,072,500.00 1,093,950.00
JUMLAH HARGA BAHAN 1,093,950.00
C PERALATAN
1 Pompa Ready mix Sewa-hari 0.120 3,300,000.00 396,000.00
JUMLAH HARGA ALAT 396,000.00
D Jumlah (A+B+C) 1,645,325.00
E Overhead & Profit (Contoh 15%) 15% x D 246,798.75
F Harga Satuan Pekerjaan (D+E) 1,892,123.75
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
1 Pekerja L.01 OH 1.000 105,000.00 105,000.00
2 Tukang L.02 OH 0.250 125,000.00 31,250.00
3 Kepala Tukang L.03 OH 0.025 145,000.00 3,625.00
4 Mandor L.04 OH 0.100 155,000.00 15,500.00
JUMLAH TENAGA KERJA 155,375.00
B BAHAN
1 Beton Ready Mix K 100 m³ 1.020 1,072,500.00 1,093,950.00
JUMLAH HARGA BAHAN 1,093,950.00
C PERALATAN
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
1 Pekerja L.01 OH 1.000 105,000.00 105,000.00
2 Tukang L.02 OH 0.250 125,000.00 31,250.00
3 Kepala Tukang L.03 OH 0.025 145,000.00 3,625.00
4 Mandor L.04 OH 0.100 155,000.00 15,500.00
JUMLAH TENAGA KERJA 155,375.00
B BAHAN
1 Beton Ready Mix 125 m³ 1.020 1,108,250.00 1,130,415.00
JUMLAH HARGA BAHAN 1,130,415.00
C PERALATAN
1 Pompa Ready mix Sewa-hari 0.120 3,300,000.00 396,000.00
JUMLAH HARGA ALAT 396,000.00
D Jumlah (A+B+C) 1,681,790.00
E Overhead & Profit (Contoh 15%) 15% x D 252,268.50
F Harga Satuan Pekerjaan (D+E) 1,934,058.50
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
1 Pekerja L.01 OH 1.000 105,000.00 105,000.00
2 Tukang L.02 OH 0.250 125,000.00 31,250.00
3 Kepala Tukang L.03 OH 0.025 145,000.00 3,625.00
4 Mandor L.04 OH 0.100 155,000.00 15,500.00
JUMLAH TENAGA KERJA 155,375.00
B BAHAN
1 Beton Ready Mix K 125 m³ 1.020 1,108,250.00 1,130,415.00
JUMLAH HARGA BAHAN 1,130,415.00
C PERALATAN
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
1 Pekerja L.01 OH 1.000 105,000.00 105,000.00
2 Tukang L.02 OH 0.250 125,000.00 31,250.00
3 Kepala Tukang L.03 OH 0.025 145,000.00 3,625.00
4 Mandor L.04 OH 0.100 155,000.00 15,500.00
JUMLAH TENAGA KERJA 155,375.00
B BAHAN
1 Beton Ready Mix 175 m³ 1.020 1,194,050.00 1,217,931.00
JUMLAH HARGA BAHAN 1,217,931.00
C PERALATAN
1 Pompa Ready mix Sewa-hari 0.120 3,300,000.00 396,000.00
JUMLAH HARGA ALAT 396,000.00
D Jumlah (A+B+C) 1,769,306.00
E Overhead & Profit (Contoh 15%) 15% x D 265,395.90
F Harga Satuan Pekerjaan (D+E) 2,034,701.90
B. 13.c.2 Membuat 1 m³ beton ready mix K 175 tidak menggunakan pompa
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
1 Pekerja L.01 OH 1.000 105,000.00 105,000.00
2 Tukang L.02 OH 0.250 125,000.00 31,250.00
3 Kepala Tukang L.03 OH 0.025 145,000.00 3,625.00
4 Mandor L.04 OH 0.100 155,000.00 15,500.00
JUMLAH TENAGA KERJA 155,375.00
B BAHAN
1 Beton Ready Mix 175 m³ 1.020 1,194,050.00 1,217,931.00
JUMLAH HARGA BAHAN 1,217,931.00
C PERALATAN
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
1 Pekerja L.01 OH 1.000 105,000.00 105,000.00
2 Tukang L.02 OH 0.250 125,000.00 31,250.00
3 Kepala Tukang L.03 OH 0.025 145,000.00 3,625.00
4 Mandor L.04 OH 0.100 155,000.00 15,500.00
JUMLAH TENAGA KERJA 155,375.00
B BAHAN
1 Beton Ready Mix 225 m³ 1.020 1,329,800.00 1,356,396.00
JUMLAH HARGA BAHAN 1,356,396.00
C PERALATAN
1 Pompa Ready mix Sewa-hari 0.120 3,300,000.00 396,000.00
JUMLAH HARGA ALAT 396,000.00
D Jumlah (A+B+C) 1,907,771.00
E Overhead & Profit (Contoh 15%) 15% x D 286,165.65
F Harga Satuan Pekerjaan (D+E) 2,193,936.65
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
1 Pekerja L.01 OH 1.000 105,000.00 105,000.00
2 Tukang L.02 OH 0.250 125,000.00 31,250.00
3 Kepala Tukang L.03 OH 0.025 145,000.00 3,625.00
4 Mandor L.04 OH 0.100 155,000.00 15,500.00
JUMLAH TENAGA KERJA 155,375.00
B BAHAN
1 Beton Ready Mix 225 m³ 1.020 1,329,800.00 1,356,396.00
JUMLAH HARGA BAHAN 1,356,396.00
C PERALATAN
JUMLAH HARGA ALAT -
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
1 Pekerja L.01 OH 1.000 105,000.00 105,000.00
2 Tukang L.02 OH 0.250 125,000.00 31,250.00
3 Kepala Tukang L.03 OH 0.025 145,000.00 3,625.00
4 Mandor L.04 OH 0.100 155,000.00 15,500.00
JUMLAH TENAGA KERJA 155,375.00
B BAHAN
1 Beton Ready Mix 250 m³ 1.020 1,372,800.00 1,400,256.00
JUMLAH HARGA BAHAN 1,400,256.00
C PERALATAN
1 Pompa Ready mix Sewa-hari 0.120 3,300,000.00 396,000.00
JUMLAH HARGA ALAT 396,000.00
D Jumlah (A+B+C) 1,951,631.00
E Overhead & Profit (Contoh 15%) 15% x D 292,744.65
F Harga Satuan Pekerjaan (D+E) 2,244,375.65
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
1 Pekerja L.01 OH 1.000 105,000.00 105,000.00
2 Tukang L.02 OH 0.250 125,000.00 31,250.00
3 Kepala Tukang L.03 OH 0.025 145,000.00 3,625.00
4 Mandor L.04 OH 0.100 155,000.00 15,500.00
JUMLAH TENAGA KERJA 155,375.00
B BAHAN
1 Beton Ready Mix 250 m³ 1.020 1,372,800.00 1,400,256.00
JUMLAH HARGA BAHAN 1,400,256.00
C PERALATAN
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
1 Pekerja L.01 OH 1.000 105,000.00 105,000.00
2 Tukang L.02 OH 0.250 125,000.00 31,250.00
3 Kepala Tukang L.03 OH 0.025 145,000.00 3,625.00
4 Mandor L.04 OH 0.100 155,000.00 15,500.00
JUMLAH TENAGA KERJA 155,375.00
B BAHAN
1 Beton Ready Mix 300 m³ 1.020 1,430,000.00 1,458,600.00
JUMLAH HARGA BAHAN 1,458,600.00
C PERALATAN
1 Pompa Ready mix Sewa-hari 0.120 3,300,000.00 396,000.00
JUMLAH HARGA ALAT 396,000.00
D Jumlah (A+B+C) 2,009,975.00
E Overhead & Profit (Contoh 15%) 15% x D 301,496.25
F Harga Satuan Pekerjaan (D+E) 2,311,471.25
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
1 Pekerja L.01 OH 1.000 105,000.00 105,000.00
2 Tukang L.02 OH 0.250 125,000.00 31,250.00
3 Kepala Tukang L.03 OH 0.025 145,000.00 3,625.00
4 Mandor L.04 OH 0.100 155,000.00 15,500.00
JUMLAH TENAGA KERJA 155,375.00
B BAHAN
1 Beton Ready Mix 300 m³ 1.020 1,430,000.00 1,458,600.00
JUMLAH HARGA BAHAN 1,458,600.00
C PERALATAN
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
1 Pekerja L.01 OH 1.000 105,000.00 105,000.00
2 Tukang L.02 OH 0.250 125,000.00 31,250.00
3 Kepala Tukang L.03 OH 0.025 145,000.00 3,625.00
4 Mandor L.04 OH 0.100 155,000.00 15,500.00
JUMLAH TENAGA KERJA 155,375.00
B BAHAN
1 Beton Ready Mix 350 m³ 1.020 1,530,100.00 1,560,702.00
JUMLAH HARGA BAHAN 1,560,702.00
C PERALATAN
1 Pompa Ready mix Sewa-hari 0.120 3,300,000.00 396,000.00
JUMLAH HARGA ALAT 396,000.00
D Jumlah (A+B+C) 2,112,077.00
E Overhead & Profit (Contoh 15%) 15% x D 316,811.55
F Harga Satuan Pekerjaan (D+E) 2,428,888.55
B. 13.g.2 Membuat 1 m³ beton ready mix K 350 tidak menggunakan pompa
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
1 Pekerja L.01 OH 1.000 105,000.00 105,000.00
2 Tukang L.02 OH 0.250 125,000.00 31,250.00
3 Kepala Tukang L.03 OH 0.025 145,000.00 3,625.00
4 Mandor L.04 OH 0.100 155,000.00 15,500.00
JUMLAH TENAGA KERJA 155,375.00
B BAHAN
1 Beton Ready Mix 350 m³ 1.020 1,530,100.00 1,560,702.00
JUMLAH HARGA BAHAN 1,560,702.00
C PERALATAN
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
1 Pekerja L.01 OH 1.000 105,000.00 105,000.00
2 Tukang L.02 OH 0.250 125,000.00 31,250.00
3 Kepala Tukang L.03 OH 0.025 145,000.00 3,625.00
4 Mandor L.04 OH 0.100 155,000.00 15,500.00
JUMLAH TENAGA KERJA 155,375.00
B BAHAN
1 Beton Ready Mix 400 m³ 1.020 1,601,600.00 1,633,632.00
JUMLAH HARGA BAHAN 1,633,632.00
C PERALATAN
1 Pompa Ready mix Sewa-hari 0.120 3,300,000.00 396,000.00
JUMLAH HARGA ALAT 396,000.00
D Jumlah (A+B+C) 2,185,007.00
E Overhead & Profit (Contoh 15%) 15% x D 327,751.05
F Harga Satuan Pekerjaan (D+E) 2,512,758.05
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
1 Pekerja L.01 OH 1.000 105,000.00 105,000.00
2 Tukang L.02 OH 0.250 125,000.00 31,250.00
3 Kepala Tukang L.03 OH 0.025 145,000.00 3,625.00
4 Mandor L.04 OH 0.100 155,000.00 15,500.00
JUMLAH TENAGA KERJA 155,375.00
B BAHAN
1 Beton Ready Mix 400 m³ 1.020 1,601,600.00 1,633,632.00
JUMLAH HARGA BAHAN 1,633,632.00
C PERALATAN
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
1 Pekerja L.01 OH 1.000 105,000.00 105,000.00
2 Tukang L.02 OH 0.250 125,000.00 31,250.00
3 Kepala Tukang L.03 OH 0.025 145,000.00 3,625.00
4 Mandor L.04 OH 0.100 155,000.00 15,500.00
JUMLAH TENAGA KERJA 155,375.00
B BAHAN
1 Beton Ready Mix 450 m³ 1.020 1,673,100.00 1,706,562.00
JUMLAH HARGA BAHAN 1,706,562.00
C PERALATAN
1 Pompa Ready mix Sewa-hari 0.120 3,300,000.00 396,000.00
JUMLAH HARGA ALAT 396,000.00
D Jumlah (A+B+C) 2,257,937.00
E Overhead & Profit (Contoh 15%) 15% x D 338,690.55
F Harga Satuan Pekerjaan (D+E) 2,596,627.55
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
1 Pekerja L.01 OH 1.000 105,000.00 105,000.00
2 Tukang L.02 OH 0.250 125,000.00 31,250.00
3 Kepala Tukang L.03 OH 0.025 145,000.00 3,625.00
4 Mandor L.04 OH 0.100 155,000.00 15,500.00
JUMLAH TENAGA KERJA 155,375.00
B BAHAN
1 Beton Ready Mix 450 m³ 1.020 1,673,100.00 1,706,562.00
JUMLAH HARGA BAHAN 1,706,562.00
C PERALATAN
A.4.2.1.19 Pemasangan 1 m' talang 1/2 lingkaran D-15 cm, seng pelat bjls 30 lebar 45 cm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.150 105,000.00 15,750.00
Tukang L.03 OH 0.300 125,000.00 37,500.00
Kepala tukang L.03 OH 0.030 145,000.00 4,350.00
Mandor L.04 OH 0.008 155,000.00 1,240.00
JUMLAH TENAGA KERJA 58,840.00
B BAHAN
Seng pelat m 1.050 42,500.00 44,625.00
Paku 1cm - 2,5 cm Kg 0.010 23,000.00 230.00
Besi strip m3 0.500 -
JUMLAH HARGA BAHAN 44,855.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 103,695.00
E Overhead & Provit 15% x D 15,554.25
F Harga Satuan Pekerjaan ( D + E ) 119,249.25
A.4.4.1 Harga Satuan Pekerjaan Pasangan Dinding
A.4.4.1.3 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 4PP
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.600 105,000.00 63,000.00
Tukang batu L.02 OH 0.200 125,000.00 25,000.00
Kepala tukang L.03 OH 0.020 145,000.00 2,900.00
Mandor L.04 OH 0.030 155,000.00 4,650.00
JUMLAH TENAGA KERJA 95,550.00
B BAHAN
Bata merah Buah 140.000 2,000.00 280,000.00
Semen portland Kg 26.550 1,500.00 39,825.00
Pasir pasang m3 0.093 125,000.00 11,625.00
JUMLAH HARGA BAHAN 331,450.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 427,000.00
E Overhead & Provit 15% x D 64,050.00
F Harga Satuan Pekerjaan ( D + E ) 491,050.00
A.4.6.1.1 Pembuatan dan pemasangan 1m3 kusen pintu dan kusen jendela, kayu kelas I
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 7.000 105,000.00 735,000.00
Tukang Kayu L.03 OH 21.000 125,000.00 2,625,000.00
Kepala Tukang L.03 OH 2.100 145,000.00 304,500.00
Mandor L.04 OH 0.350 155,000.00 54,250.00
JUMLAH TENAGA KERJA 3,718,750.00
B BAHAN
Kusen Kayu Kelas 1 (bengkirai) m3 1.100 16,000,000.00 17,600,000.00
Paku 10cm kg 1.250 23,000.00 28,750.00
Lem kayu kg 1.000 20,000.00 20,000.00
JUMLAH HARGA BAHAN 17,648,750.00
C PERALATAN
A.4.6.1.1.a Pembuatan dan pemasangan 1m3 kusen pintu dan kusen jendela, kayu belian
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 7.000 105,000.00 735,000.00
Tukang Kayu L.03 OH 21.000 125,000.00 2,625,000.00
Kepala Tukang L.03 OH 2.100 145,000.00 304,500.00
Mandor L.04 OH 0.350 155,000.00 54,250.00
JUMLAH TENAGA KERJA 3,718,750.00
B BAHAN
Kusen Kayu Belian m3 1.100 24,000,000.00 26,400,000.00
Paku 10cm kg 1.250 23,000.00 28,750.00
Lem kayu kg 1.000 20,000.00 20,000.00
JUMLAH HARGA BAHAN 26,448,750.00
C PERALATAN
A.4.6.1.2 Pembuatan dan pemasangan 1m3 kusen pintu dan kusen jendela, kayu kelas II
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 6.000 105,000.00 630,000.00
Tukang Kayu L.03 OH 18.000 125,000.00 2,250,000.00
Kepala Tukang L.03 OH 1.800 145,000.00 261,000.00
Mandor L.04 OH 0.300 155,000.00 46,500.00
JUMLAH TENAGA KERJA 3,187,500.00
B BAHAN
Kusen Kayu Kelas II m3 1.200 13,000,000.00 15,600,000.00
Paku 10cm kg 1.250 23,000.00 28,750.00
Lem kayu kg 1.000 20,000.00 20,000.00
JUMLAH HARGA BAHAN 15,648,750.00
C PERALATAN
A.4.6.1.5 Pembuatan dan pemasangan 1m2 daun pintu panel, kayu kelas I
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.000 105,000.00 105,000.00
Tukang Kayu L.03 OH 3.000 125,000.00 375,000.00
Kepala Tukang L.03 OH 0.300 145,000.00 43,500.00
Mandor L.04 OH 0.050 155,000.00 7,750.00
JUMLAH TENAGA KERJA 531,250.00
B BAHAN
Papan kayu kelas 1 (bengkirai) m3 0.040 11,188,300.00 447,532.00
Lem kayu kg 0.500 20,000.00 10,000.00
JUMLAH HARGA BAHAN 457,532.00
C PERALATAN
A.4.6.1.5.a Pembuatan dan pemasangan 1m2 daun pintu panel, kayu belian
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.000 105,000.00 105,000.00
Tukang Kayu L.03 OH 3.000 125,000.00 375,000.00
Kepala Tukang L.03 OH 0.300 145,000.00 43,500.00
Mandor L.04 OH 0.050 155,000.00 7,750.00
JUMLAH TENAGA KERJA 531,250.00
B BAHAN
Papan Kayu Belian m3 0.040 14,814,000.00 592,560.00
Lem kayu kg 0.500 20,000.00 10,000.00
JUMLAH HARGA BAHAN 602,560.00
C PERALATAN
A.4.6.1.5.b Pembuatan dan pemasangan 1m2 daun pintu panel, kayu kelas II
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.000 105,000.00 105,000.00
Tukang Kayu L.03 OH 3.000 125,000.00 375,000.00
Kepala Tukang L.03 OH 0.300 145,000.00 43,500.00
Mandor L.04 OH 0.050 155,000.00 7,750.00
JUMLAH TENAGA KERJA 531,250.00
B BAHAN
Papan Kayu Kelas II (mabang) m3 0.040 8,300,000.00 332,000.00
Lem kayu kg 0.500 20,000.00 10,000.00
JUMLAH HARGA BAHAN 342,000.00
C PERALATAN
A.4.6.1.6.a Pembuatan dan pemasangan 1m2 pintu dan jendela kaca, kayu kelas II
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.800 105,000.00 84,000.00
Tukang Kayu L.03 OH 2.400 125,000.00 300,000.00
Kepala Tukang L.03 OH 0.240 145,000.00 34,800.00
Mandor L.04 OH 0.040 155,000.00 6,200.00
JUMLAH TENAGA KERJA 425,000.00
B BAHAN
Papan kayu kelas II (mabang) m3 0.024 8,300,000.00 199,200.00
Lem kayu kg 0.300 20,000.00 6,000.00
JUMLAH HARGA BAHAN 205,200.00
C PERALATAN
A.4.6.1.7 Pembuatan dan pemasangan 1m2 pintu dan jendela jalusi kayu kelas I
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.000 105,000.00 105,000.00
Tukang Kayu L.03 OH 3.000 125,000.00 375,000.00
Kepala Tukang L.03 OH 0.300 145,000.00 43,500.00
Mandor L.04 OH 0.050 155,000.00 7,750.00
JUMLAH TENAGA KERJA 531,250.00
B BAHAN
Papan kayu kelas I m3 0.064 11,188,300.00 716,051.20
Lem kayu kg 0.500 20,000.00 10,000.00
JUMLAH HARGA BAHAN 726,051.20
C PERALATAN
A.4.6.1.8 Pembuatan dan pemasangan 1m2 pintu plywood rangkap, rangka kayu kelas II tertutup (lebar sampai 90cm)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.700 105,000.00 73,500.00
Tukang Kayu L.03 OH 2.100 125,000.00 262,500.00
Kepala Tukang L.03 OH 0.210 145,000.00 30,450.00
Mandor L.04 OH 0.035 155,000.00 5,425.00
JUMLAH TENAGA KERJA 371,875.00
B BAHAN
Papan kayu Kelas II m3 0.025 8,300,000.00 207,500.00
Paku 1cm-2,5 cm kg 0.030 23,000.00 690.00
Lem kayu kg 0.500 20,000.00 10,000.00
Plywood tebal 4 mm ukuran (90x220) cm Lembar 1.000 120,000.00 120,000.00
JUMLAH HARGA BAHAN 338,190.00
C PERALATAN
A.4.6.1.9 Pembuatan 1m2 pintu plywood rangkap, rangka expose kayu kelas I
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.800 105,000.00 84,000.00
Tukang Kayu L.03 OH 2.100 125,000.00 262,500.00
Kepala Tukang L.03 OH 0.240 145,000.00 34,800.00
Mandor L.04 OH 0.040 155,000.00 6,200.00
JUMLAH TENAGA KERJA 387,500.00
B BAHAN
Papan kayu kelas I m3 0.0256 11,188,300.00 286,420.48
Paku 1cm-2,5 cm kg 0.030 23,000.00 690.00
Lem kayu kg 0.500 20,000.00 10,000.00
Plywood tebal 4 mm ukuran (90x220) cm Lembar 1.000 120,000.00 120,000.00
JUMLAH HARGA BAHAN 417,110.48
C PERALATAN
A.4.6.1.13.a Pemasangan 1m3 konstruksi kuda-kuda konvensional, kayu kelas II bentang 6 meter
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 4.000 105,000.00 420,000.00
Tukang Kayu L.03 OH 12.000 125,000.00 1,500,000.00
Kepala Tukang L.03 OH 1.200 145,000.00 174,000.00
Mandor L.04 OH 0.200 155,000.00 31,000.00
JUMLAH TENAGA KERJA 2,125,000.00
B BAHAN
Balok kayu kelas II uk. 6/12 m3 1.100 11,000.00 12,100.00
Paku 12 cm kg 5.600 23,000.00 128,800.00
JUMLAH HARGA BAHAN 140,900.00
C PERALATAN
A.4.6.1.25 Pemasangan 1m2 dinding pemisah plywood rangkap, rangka kayu kelas II
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.200 105,000.00 21,000.00
Tukang Kayu L.03 OH 0.600 125,000.00 75,000.00
Kepala Tukang L.03 OH 0.060 145,000.00 8,700.00
Mandor L.04 OH 0.010 155,000.00 1,550.00
JUMLAH TENAGA KERJA 106,250.00
B BAHAN
balok kayukelas II uk. 6/12 m3 0.028 4,224,000.00 118,272.00
Paku 5 dan 10 Kg 0.150 23,000.00 3,450.00
Plywood 4 mm,120 x 240 Lembar 0.860 120,000.00 103,200.00
Lem kayu Kg 0.560 20,000.00 11,200.00
JUMLAH HARGA BAHAN 236,122.00
C PERALATAN
A.4.7.1.5 1m2 Pengecatan bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 3 lapis cat penutup)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.070 105,000.00 7,350.00
Tukang cat L.02 OH 0.105 125,000.00 13,125.00
Kepala tukang L.03 OH 0.004 145,000.00 580.00
Mandor L.04 OH 0.003 155,000.00 465.00
JUMLAH TENAGA KERJA 21,520.00
B BAHAN
Cat menie Kg 0.200 52,000.00 10,400.00
Plamuur Kg 0.150 31,500.00 4,725.00
Cat dasar Kg 0.170 70,000.00 11,900.00
Cat penutup Kg 0.350 100,000.00 35,000.00
Kuas buah 0.010 25,000.00 250.00
Pengencer Kg 0.030 25,000.00 750.00
Ampelas Lbr 0.200 4,000.00 800.00
JUMLAH HARGA BAHAN 63,825.00
C PERALATAN
A.4.7.1.10 1m2 Pengecatan tembok baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup) Interior setara Vinilex
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.020 105,000.00 2,100.00
Tukang cat L.02 OH 0.063 125,000.00 7,875.00
Kepala tukang L.03 OH 0.0063 145,000.00 913.50
Mandor L.04 OH 0.003 155,000.00 465.00
JUMLAH TENAGA KERJA 11,353.50
B BAHAN
Plamuur Kg 0.100 31,500.00 3,150.00
Cat dasar Kg 0.100 27,000.00 2,700.00
Cat penutup Kg 0.260 28,000.00 7,280.00
JUMLAH HARGA BAHAN 13,130.00
C PERALATAN
A.4.7.1.11 1m2 Pengecatan tembok lama (1 lapis cat dasar, 2 lapis cat penutup) Interior setara Vinilex
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.028 105,000.00 2,940.00
Tukang cat L.02 OH 0.042 125,000.00 5,250.00
Kepala tukang L.03 OH 0.0042 145,000.00 609.00
Mandor L.04 OH 0.003 155,000.00 465.00
JUMLAH TENAGA KERJA 9,264.00
B BAHAN
Cat dasar Kg 0.120 27,000.00 3,240.00
Cat penutup Kg 0.180 28,000.00 5,040.00
JUMLAH HARGA BAHAN 8,280.00
C PERALATAN