Project Delay by Window

Baseline Baseline
Baseline

Window 1
Boiler Erection & Turbine Hall Steel +78 Days
(Jan. 16-Jul. 16)

Window 2
Turbine Hall Steel & ESP +25 Days
(Jul. 16-Nov.
Nov-1616)

Window 3
Alloy Approval
Alloy Piping Vendor Pipe & Delivery +50 Days
(Nov. 16-Sep. 17)
Window

Window 4
(Sep. 17-Feb. 18) AlloyAlloy
PipePipe
Delivery +124 Days

Window 5
FGD
FGD Fire
Fire +131 Days
(Feb. 18-Jul. 18)

Window 6
Close
Close Cycle
Cycle Cooling
Cooling Water
Water System
System +41 Days
(Jul. 18-Oct. 18)

Window 7
Construction Punchlist
Construction Punchlist &&System
SystemCloseout
Closeout +71 Days
(Oct. 18-Apr. 19)

Window 8
Commissioning +144 Days
(Apr. 19-Apr. 20)
to
2015

2017

May-19
May-18

Mar-20

May-20
Mar-19

Nov-19
Nov-18
Mar-18

Sep-19
Jan-19

Jan-20
Sep-18
Jan-18

Jul-19
Jul-18

2015-2017 2018 2019 2020