You are on page 1of 6

Doc.

No: SE-04-048
Doc.Type: Work Description
Page: 1 of 6
Author (sign): JRS Rev. date: 04.06.2012
Approved (sign): eei 2.2 x Static Load Test Davit Rev. no: 1
Verified (sign): SFL First publ.date: 15.05.2012

AMENDMENTS REGISTER:

Rev
Originator History Date Amendment Details
No.
Doc.No: SE-04-048
Doc.Type: Work Description
Page: 2 of 6
Author (sign): JRS Rev. date: 04.06.2012
Approved (sign): eei 2.2 x Static Load Test Davit Rev. no: 1
Verified (sign): SFL First publ.date: 15.05.2012

1 PROCESS FLOW

2 PURPOSE AND SCOPE


This procedure describes guidelines for conducting load test for winch.
The purpose of the procedure is to ensure that the davit structure and embedded foundation to the ship’s
structure can withstand the desired load

3 DEFINITIONS
LSA – Life Saving Appliance

2.2 x Static Load Test davit = 2.2 times the SWL of the lifeboat/rescue boat.

4 RESPONSIBILITY

Service Engineer
- (“A”)Who is Accountable for the activity or decision (Owner)
Only one accountable per activity

(Service Station)
- (“R”)Who is Responsible (Doer)
Role / area

Personnel
Shipyard
- (“C”)Who must be Consulted
- (“I”)Who must be Informed

Activity
Preparation of LSA and load weights AR
Load Test AC R

5 WORK METHOD
SN PROCESS T/E/PPE PICTURES
1 Hang up the lifting sling and PPE = Basic
shackles on the davit arm. Ensure to
protect slings against sharp edges.
Tools/
Equipment=
Slings
Doc.No: SE-04-048
Doc.Type: Work Description
Page: 3 of 6
Author (sign): JRS Rev. date: 04.06.2012
Approved (sign): eei 2.2 x Static Load Test Davit Rev. no: 1
Verified (sign): SFL First publ.date: 15.05.2012

SN PROCESS T/E/PPE PICTURES


2 Attach load cell PPE = Basic

Note: Verify that load cell


certificate is valid Tools/
Equipment=
Load cell

3 Zero digital reader where PPE = Basic


applicable, or record reading from
load cell reader. Photos can be Tools/
taken for recording purposes. Equipment=
Load cell

4 Attach water bags with load cells. PPE = Basic


Ensure the davit arms are fully
swung out. Tools/
Equipment=
Load cell,
water bag
Doc.No: SE-04-048
Doc.Type: Work Description
Page: 4 of 6
Author (sign): JRS Rev. date: 04.06.2012
Approved (sign): eei 2.2 x Static Load Test Davit Rev. no: 1
Verified (sign): SFL First publ.date: 15.05.2012

SN PROCESS T/E/PPE PICTURES


5 Connect hoses to bags / water PPE = Basic
weights.

Tools/
Equipment=
Load cell,
water bag

6 Fill bags / water weights to desired PPE = Basic


weight. Hold the load for 5 minutes

Tools/
Equipment=
Load cell,
water bag

7 Record full weight, photos can be PPE = Basic


taken for recording purposes.

Tools/
Equipment=
Load cell,
water bag
Doc.No: SE-04-048
Doc.Type: Work Description
Page: 5 of 6
Author (sign): JRS Rev. date: 04.06.2012
Approved (sign): eei 2.2 x Static Load Test Davit Rev. no: 1
Verified (sign): SFL First publ.date: 15.05.2012

SN PROCESS T/E/PPE PICTURES


8 Once the test has been completed, PPE = Basic
release and drain.

Tools/
Equipment=
Load cell,
water bag

9 Check the structure and PPE = Basic


foundation. There should be no
permanent deformation or
damage Tools/
Equipment=
N/A

6 SAFETY INITIATIVE
Service Engineers must wear Basic PPE
Ensure to barricade test areas

7 REFERENCES
A list of other QHSE documents
QHSE Doc.No Title
SE-07-058 Hazard Assessment for PPE.docx
SE-07-049 Commissioning- LH.docx
SE-07-050 Commissioning- HD-Free Fall lifeboat.docx
SE-07-051 Commissioning- conventional lifeboat and davit.docx
SE-07-052 Commissioning- NDA- Rescue Boat.docx
Doc.No: SE-04-048
Doc.Type: Work Description
Page: 6 of 6
Author (sign): JRS Rev. date: 04.06.2012
Approved (sign): eei 2.2 x Static Load Test Davit Rev. no: 1
Verified (sign): SFL First publ.date: 15.05.2012

SE-07-053 Commissioning- NDC.docx