Professional Documents
Culture Documents
examine various key flow parameters. For this example, These conditions drive production engineers to
conditions have been chosen based on efficient two-phase flow continuously look for solutions to help the completion maintain
for the existing completion ie. a successful completion design. gas flow.
Figure 2 shows a plot of the liquid and gas phase velocities Conventional Gas Well Dewatering Methods
in the completion.
Operators have employed a number of unique solutions to
350 manage water inflow when the original completion design can
Casing
Flow
no longer keep the well unloaded. Some of the most common
300
Tubing
of these are discussed.
Flow
250
Gas Velocity Strings
Velocity (in/sec)
Velocity
200
A velocity string is simply “the next size down” for the
completion. When a well is new, the production tubing is sized
150
Gas to handle initial gas flow rates and pressures. As wells deplete,
Dominant
pressure and flow rate decline and therefore a reasonable
100
Liquid solution is to similarly reduce the size of the completion to try
50
Liquid Dominant
to maintain the gas velocities required for liquid transport. This
Velocity
is achieved by hanging an appropriately sized coiled tubing
0
string inside the existing completion. Unfortunately, this results
0 1,000 2,000 3,000 4,000 5,000 6,000 7,000 8,000 9,000 10,000 in a more restrictive completion, which effectively chokes the
Depth (ft) well, reducing the overall flow rate.
Figure 2: Two-Phase Completion Flow Velocities Besides reduced flow capability, velocity strings are only
able to extend the life of a well for a limited period of time. As
We can see that, as expected, there is a dramatic increase in the reservoir further depletes, conditions will eventually drop
both phase velocities as the flow enters the tubing. Below this below those required for sustainable liquid transport in the
point, both velocities are relatively low, with the liquid velocity velocity string, and the well will again become critically loaded
ranging from 0.1 to 2.4 in/sec. With liquid velocities in this
range, this portion of the completion is not sustaining liquid Another issue for conventional velocity string completions
transport in the gas. Therefore the condition would be described is the fact that often the velocity string can not be run across, or
as liquid dominant, with gas percolating through the liquid below the perforations. Many velocity strings that have been
column. run across the producing interval quickly develop holes
wherever there are perforations in the completion. Later in this
There are a few consequences of this flow condition in the paper, further detail will be given on this phenomenon, and a
completion below the end of the tubing. One is that in wells validated solution will be presented.
with long casing intervals, there is significant hydrostatic
penalty due to the inefficient liquid transport characteristics. Velocity strings are simple and effective, but they are not
an ideal solution because they restrict the ultimate gas
Another arises from potential fluid impairment of the formation, production rate.
especially in zones that have been hydraulically fractured. This
phenomenon will be discussed later in this paper. Plunger Lift
4) Maturing Wells Another water management technique for mature gas wells is
the use of plunger lift systems. Plungers are a mechanical
Even with a properly designed completion, maturing gas wells interface between the produced liquids and gas which use the
face the following changes which can seriously alter liquid well's own energy for lift.
transport performance:
This is accomplished through the movement of an
declining gas rates independent piston / plunger traveling from the bottom of the
declining reservoir pressures tubing to the surface. Plunger drive pressure is provided by
formation gas stored in the casing annulus during a shut-in
increasing liquid rates period. When the well is opened, the shut-in tubing pressure is
bled-off and the pressurized gas in the casing annulus expands,
4 SPE 94193
pushing the plunger to the surface. This intermittent plunger produced water; with a second annulus needed for the gas flow
cycling is repeated several times throughout the day. path. Therefore, these completions are typically restricted to
applications where the gas can be produced up the casing
The main advantage of plunger lift systems is the low cost annulus.
of installation. However, there are several factors which restrict
its application. These are: Another challenge that this method faces is gas-locking of
the pump. As rod pumps are sensitive to gas-locking, it is
the need to use the wells drive energy for liquid lift important that the intake of the pump be sufficiently below the
lowest gas entry point in the well to prevent gas ingestion.
the tubing needs to be clean and uniform to avoid
plunger hold-up
Installing any type of tubular or mechanical component
plunger cycle optimization can be time consuming across perforations requires special considerations, which will
be addressed in the Corrosion section of this paper.
Won’t work with low BHP wells
plunger wear CT Pump Strings
reconverts the kinetic energy of the flowing liquid to potential Because many gas wells with liquid loading problems are
energy in the form of pressure. As the high velocity liquid pressure depleted it follows that the available flow area for the
stream exits the nozzle it generates a venturi suction effect gas production flow-path must be as large as practical to
which draws well-bore fluid into the jet stream. The co-mingled minimize friction losses and allow optimum production rates.
jet stream enters the shaped conduit where the regained This in turn requires the concentric coiled tubing string to be as
potential energy drives the co-mingled fluid stream to surface. small as practical but consistent with handling the produced
The high velocity liquid called “power fluid” is provided by a water volumes and the power fluid volumes required to operate
surface pump (typically a triplex pump) and is delivered a jet pump. Balancing these demands requires optimization
through a dedicated conduit to the down-hole jet pump. The between the gas production rate versus the power expended to
produced fluid in the wellbore is drawn into the power fluid drive the jet pump.
stream where they co-mingle and flow to surface in the annulus
outside the delivery conduit. The preferred choice of power Many tubing size configurations are available, but a
fluid is the produced liquid. practical combination that covers a significant number of
potential candidate wells uses 1” CT inside 1 ¾” CT.
Jet pumps are simple; they have no moving parts and their
design allows the internal parts exposed to the high velocity jet Pump Design
stream to be removed for servicing without having to pull the
completion with a service rig. Because of their simplicity they A key element behind the choice of jet pumps for low
are tolerant to the presence of solids in the fluid being produced. productivity gas wells is the need to have a liquid removal
method that is reliable and has low operating and servicing
Jet pumps offer many advantages, but they do have one costs. Therefore pump serviceability must be easy and
limitation, namely that the kinetic energy/potential energy inexpensive. This is achieved by designing the working part of
conversion efficiency through the device is typically less than the pump (the carrier – Figure 3) to be retrieved from the well
25%, and often significantly lower. For large volume pumping by reversing the direction of the power fluid and circulating the
operations this can be a significant limitation unless the “carrier” to surface for redress or replacement.
pressure requirements to lift the liquid are very low for
example, in shallow depth wells. The outside dimensions of the carrier must therefore be
able to pass through the inside of the 1” coiled tubing string
However, many of the North American gas wells with with sufficient clearance, allowing diameter & wall thickness
liquid loading problems are only producing relatively small variations, ovality and most importantly the longitudinal seam
volumes of liquid and thus the power requirements of a jet weld.
pump can be quite small and despite efficiency limitations are
still economically viable.
Since jet pumps need two liquid conduits (one for the
power fluid and a second for the co-mingled fluid returns) it
follows that an installation in a gas well will need three separate
flow paths, since a third path is needed for the produced gas. As
space is at premium in small diameter completions, one solution Figure 3: JPDS Carrier Assembly with Nozzle / Throat Inserts
is to convey the jet pump on concentric coiled tubing. This The preferred installation method is to attach the jet pump
allows for use of relatively small tubing sizes, and eliminates and it’s housing to the concentric coiled tubing on surface so
collars. the whole system can be tested before deploying it in the well.
To allow efficient deployment in the field therefore requires
In this configuration, the inner coiled tubing string carries that the pump assembly be no larger than the diameter of the
the power fluid and the annulus between the inner and outer outer CT string so that it can be stabbed through the injector and
coiled tubing strings conveys the co-mingled fluid return flow. tubing hanger. This sets the outside diameter limit for the pump
The annulus between the outer coiled tubing string and the housing at 1 ¾” which in turn determines the dimensions of the
well completion provides the flow path for the produced gas. pump body in which the carrier sits (Figure 4).
6 SPE 94193
Pump Depth
Samples of failed coiled tubing previously retrieved from It is not the purpose of this paper to provide detailed results
velocity string service have displayed numerous, regularly of the test program but only to summarize the important
spaced, round holes along the length of that section of the coiled findings. Corrosion rates on the 80 grade steel used for the jet
tubing that had been run opposite the perforations. Operators impingement test electrode increased with increasing wall shear
had reported that the holes were caused by erosion but no stress values but were generally in the range of 150 to 200 mpy.
serious investigation of this claim had been undertaken until the This clearly supports previous reports of coiled tubing
jet pump de-watering concept was proposed. Subsequent performance life of only a few months when located opposite
calculations of fluid velocity in the perforation tunnels did not producing perforations.
support the claim that erosion was the damage mechanism.
SPE 94193 7
Impingement tests on the chrome alloy showed no pitting scale inhibitors in the power fluid the tests were conducted with
and a calculated average wall loss of 7 mpy. these additives present.
Chrome alloy coiled tubing therefore seems suitable to be At the time of writing, these tests were still underway but
landed across a perforated interval for the range of brine and early results are encouraging.
CO2 conditions tested.
Surface Equipment
Other Corrosion Issues
The JPDS system requires a surface package to both deliver
Since both the pump and the lower end of the coiled tubing power fluid to the down hole jet pump and handle fluid returns
string will be immersed in produced formation brine it was also to surface. The fluid return system comprises a low pressure
necessary to test both for resistance to crevice & pitting attack separator which feeds the suction of the power fluid pump,
in low flow or stagnant conditions. The pump material and the while filtering solids and feeding produced liquid to surface
chrome alloy both performed well under these conditions. storage. Power fluid is typically supplied using a small triplex
pump, which is powered by casing gas, diesel fuel or electricity.
For economic reasons it is proposed to run the jet pump
system using produced water which means the inside of the
concentric coiled tubing strings will be continuously exposed to
reduced pH formation brine. For precautionary reasons and
unless individual tests determine otherwise it is proposed to
treat the power fluid with corrosion and scale inhibitors. These
production chemicals might typically be run at levels around 50
ppm and since the produced liquid volumes are so low the
chemical costs are minimal.
The manufacturer of the chrome alloy coiled tubing 1) Completion Flow Efficiency
developed the welding procedures to join chrome alloy to
conventional grade material. The test program included a series Previously, we have discussed the issues associated with two-
of bend fatigue tests on the weld as part of the weld phase flow in gas wells, and the resultant inefficiency created
characterization. A procedure was developed that gave due to hydrostatic loading and liquid slip. The JPDS has been
performance comparable to existing girth welds on regular shown to provide a means of removing water from the gas flow
grades of coiled tubing. path, achieving ‘dry gas flow’ conditions.
Finally, a series of galvanic corrosion tests have been The benefit of this is best shown comparing IPR / TPR
undertaken to test the suitability of attaching chrome alloy analysis for a sample well.
coiled tubing to regular grade coiled tubing. Certain types of
corrosion inhibitor have been shown to promote conditions for For demonstration purposes, consider a sample well with
galvanic corrosion. Since it is proposed to use corrosion & the following parameters:
8 SPE 94193
evaluation of the liquid-lift performance of the well. Gas Production Rate [MMscf/day]
900
Now, assessing JPDS for this case, the system removes
800
liquid from the wellbore through a separate flow path, allowing
700
near-dry gas flow up the CCT / tubing annulus.
600
500
Modeling this condition to obtain a TPR, we can see the
400
following IPR / TPR relationship:
300
200 IPR & TPR Analysis:
100 Current IPR Completion TPR 1.5” CT TPR AquaLift TPR
0
1.25” CT TPR
0.05 0.10 0.15 0.20 0.25 0.30 0.35 0.40 0.45 0.50 0.55 0.60 1000
Bottom Hole Flowing Pressure [psi]
with two CT TPR plots included (for 1.5” and 1.25” CT): Gas Production Rate [MMscf/day]
with significant on-going future decline in the IPR (as shown by At this time, it is expected that the JPDS will reduce or
the green TPR line above). even eliminate this flow impairment. Additional study and
testing will be required to fully validate this claim.
Still working with the above example, we can see that the
only two viable completion options are the 1.25” velocity string 3) Increased Recoverable Reserves
(limited lifespan), and the JPDS. However, the production rate
for the 1.25” string is showing to only reach about 170 Earlier in this paper, the benefit of JPDS was shown with
Mscf/day, whereas the JPDS provides about 360 Mscf/day. The respect to IPR decline (Figure 10). Taking liquid out of the gas
difference is 190 Mscf/day, or more than double the rate of the stream, allows these wells to continue to produce even with
velocity string. significantly reduced IPR characteristics, which results in
greater reserve recovery. Any improvement in recoverable
Overall, as a result of removing completion liquid loading reserve ratios will have a significant economic impact.
and liquid slip problems, more efficient flow is achieved.
Applications for JPDS
Near Dry Gas Flow
As the JPDS is a new use for jet pump technology, the range of
The above analysis was based on the claim that the JPDS applications has yet to be fully explored. Based on what has
creates near-dry gas flow conditions in the tubing. A more been seen so far, there appear to be a number of completion
detailed analysis is required to fully prove that, in most types that should benefit greatly from its use.
situations, little, if any liquid will be present in the tubing gas
flow, but the following rationalization can be considered to help Slimhole / Tubing completed Wells
support this claim.
The design of the JPDS has been adapted to allow installation in
We have already looked at the two-phase flow conditions small diameter completions. The current downhole pump can be
in the casing interval and have seen that typically, because of operated with 1” inner CT and 1.75” outer CT – while still
low liquid velocities, the interval is liquid dominant, and gas is permitting the nozzle / throat carrier to be circulated to surface.
percolating through the slow moving liquid column. As a In most cases, this size configuration will suit completions of 2
result, in a conventional gas well completion, we do see liquid ⅞" and larger.
pick-up and transport in the tubing because it is supported by
the column of fluid in the casing. In some cases, this completion system can be run in 2 ⅜”,
but the flow friction of the gas starts to become significant.
Using the JPDS, the casing liquid column is drawn down Ideally, if the initial trial phase of this technology continues to
well below the end of the tubing; even down below the lowest show success, a smaller downhole pump configuration is
set of perforations. Therefore there will be little encouragement planned, which will allow the use a ⅞” inner / 1.5” outer CCT
for any significant quantity of liquid to be transported up to the string, while still maintaining the ability to circulate the carrier
high velocity gas flow in the tubing. to surface.
It was previously shown that even with efficient two-phase flow Although the JPDS has been adapted for small diameter
in the production tubing, it is common that in the cased interval completions, it is well suited for use in completion sizes larger
below the end of the tubing, there will be a liquid dominant than 2 7/8”. A number of pending applications are planned for
condition with gas streaming through the liquid column. This casing completions. Some of these will still utilize a CCT
means that over this interval, the perforations will be string, while others will combine CT and production tubing for
submerged, as will any proppant fractured intervals. Other the final completion.
studies have identified this condition and have determined that
the resultant flow condition is that of gas flow through the top Horizontal Wells
of the proppant fractured interval, with near-static liquid in the There are aspects of the JPDS that should allow it to be applied
bottom. “Consequently, water (or oil) saturation in rock in horizontal wells.
immediately adjacent to the faces of the affected part of the
fracture will be very high and relative permeability to gas may First of all, jet pumps function the same, whether orientated
be zero in the case of low reservoir permeability”(5). This vertically or horizontally - unlike rod pumps. There are no
condition will result in a pseudo-skin, limiting overall well down hole moving parts, and the pump’s power is delivered
production. through fluid energy, eliminating the problems with rods run
through a build section.
10 SPE 94193
Jet pumps are also much more ‘forgiving’ for gas ingestion. a test package, to a permanent installation. During that process,
Rod pumps can easily get gas-locked when gas enters the debris was accidentally left in one of the new surface lines, and
intake, but up to a point, jet pumps will continue to perform. when it was pumped downhole, it plugged the jet pump
assembly. This being an early test well, a conventional,
While still being evaluated, it is anticipated that the best commercially available jet pump was used. This did not allow
candidate wells will have been drilled ‘down-dip’, with the the carrier to be reversed up 1” CT, and therefore the system
pump installed at the toe of the well. This will provide an was temporarily suspended pending a work-over to install the
effective gravity separation interval, creating a sump for the new generation jet pump.
pump to work in.
A number of commercial applications are being engineered
Other candidates have been evaluated which have been and planned, but at the time of writing this paper, they had not
drilled up-dip. In these cases it is anticipated that the pump will yet been installed.
work best if landed in the lowest inflection point of the well. In
these cases it may be found that the system will work best if Conclusion
operated intermittently, allowing a reasonable volume of fluid
to build up prior to start-up. The JPDS has shown great early promise to deal with the
problem of gas well liquid loading. Benefits for this new
New Wells system include:
Most discussions about gas well dewatering have focused on 1. Lifting water through a separate flow path allows for
aging, or maturing wells. However, given the unique fluid increased gas production rates
management solution that JPDS has shown, there is significant
justification for consideration of the system in new completions. 2. Near-dry gas flow results in extended well production
performance, even as the reservoir continues to deplete
Completion design in new wells is still a compromise (higher reserve recovery)
between gas flow maximization and liquid transport
performance. Typically, tubing is selected to achieve this 3. Mixed-material strings allow JPDS completions to be
compromise, but the fact is that the flow performance will installed below perforations
always be suppressed by flow hydrostatics and friction. As
well, it has already been shown that the flow dynamics in the 4. Ability to handle solids
perforated / casing interval of the well will in most cases be a
liquid dominant two-phase mixture, both increasing the 5. Ability to handle gas (won’t gas-lock)
hydrostatic flow penalty, and hampering the frac performance.
6. Dewater casing and frac wings
Because the JPDS is run to a point below the perforations,
both of these conditions will be eliminated. This allows the 7. Basic pump service operations can be performed without
well to deliver gas at its ideal maximum rate, through its entire needing rig (pump carrier circulated to surface)
life span. Also, it has been shown that we anticipate that the
JPDS will greatly increase the economic life span of a gas well. 8. In the event that production operations require the well to
be shut in, the new process can be immediately restarted
Test Well Results without needing blow down, or any other form of
intervention to re-initiate production
Early in the development of the JPDS, a test installation was run
in an East Texas gas well for evaluation. 9. Can be applied to a wide range of gas well completion
types
The well had a dual completion and the side that the JPDS
was installed in had 2 ⅞” and was unable to sustain flow. The
JPDS string consisted of 1” CT inside of 1.75” CT, and was run
below the last set of perforations at about 7,500 ft.
Acknowledgements
References
2. Misselbrook, J., Wilde, G., Falk, K., “The Development and Use
of a Coiled-Tubing Simulator for Horizontal Applications”, SPE
22822 presented at the Annual Technical Conference and
Exhibition, Dallas, TX, 6-9 October 1991