You are on page 1of 11

Geosystem Engineering

ISSN: 1226-9328 (Print) 2166-3394 (Online) Journal homepage: http://www.tandfonline.com/loi/tges20

Optimization of truck-loader haulage systems in


an underground mine using simulation methods

Sebeom Park, Yosoon Choi & Han-su Park

To cite this article: Sebeom Park, Yosoon Choi & Han-su Park (2016): Optimization of truck-
loader haulage systems in an underground mine using simulation methods, Geosystem
Engineering, DOI: 10.1080/12269328.2016.1176538

To link to this article: http://dx.doi.org/10.1080/12269328.2016.1176538

Published online: 20 Apr 2016.

Submit your article to this journal

Article views: 10

View related articles

View Crossmark data

Full Terms & Conditions of access and use can be found at


http://www.tandfonline.com/action/journalInformation?journalCode=tges20

Download by: [University of Nebraska, Lincoln] Date: 10 June 2016, At: 10:21
Geosystem Engineering, 2016
http://dx.doi.org/10.1080/12269328.2016.1176538

Optimization of truck-loader haulage systems in an underground mine using


simulation methods
Sebeom Parka, Yosoon Choia and Han-su Parkb
a
Department of Energy Resources Engineering, Pukyong National University, Busan, Republic of Korea; bDaesung Mining Development INC.,
Seoul, Republic of Korea

ABSTRACT ARTICLE HISTORY


This study developed a program to simulate a haulage system with trucks and loaders for an Received 10 February 2016
underground mine using the GPSS/H simulation language. The Daesung MDI limestone mine Accepted 6 April 2016
located in Korea was selected as the study area. Using the developed program and parameter values
Downloaded by [University of Nebraska, Lincoln] at 10:21 10 June 2016

KEYWORDS
determined by a field survey, simulations of the truck-loader haulage system were performed to Truck-loader haulage
optimize the number of trucks dispatched at three loading points in the study area. The simulation system; underground mine;
results showed that maximum production can be expected by dispatching four, seven, and three simulation; GPSS/H
trucks to each loading point, respectively. Because the developed program was found to properly
simulate the haulage system, it could be used for practical purposes in the study area.

1. Introduction environments and haulage systems are more complicated


than those of open-pit mines. Among the few studies
The cost of haulage operations in mines is increasing
on underground mine simulation, Salama and Greberg
due to longer haul routes and increased fuel consump-
(2012) simulated the loading-haulage system with LHD
tion caused by deepening mines. Accordingly, design-
and trucks to optimize the number of trucks used in the
ing an efficient haulage system for ores and wastes is
haulage system for an underground mine. They also pro-
crucial when planning open-pit or underground mines
posed a plan of system operation to improve the efficiency
(Berkhimer, 2011; Choi, Sunwoo, & Park, 2007; Park
of the haulage system and satisfy production targets. Park,
& Choi, 2013). In mines, the ores and wastes are usu-
Choi, and Park (2014b) developed a program to simulate
ally hauled by trucks, conveyers, rails, shuttle cars, load
a truck-loader haulage system in an underground lime-
haulage dumps (LHDs), or skips. In particular, haulage
stone mine using the GPSS/H simulation language, and
systems with trucks and loaders are widely used in both
they proposed a measure to maximize the production of
open-pit and underground mines due to their advantages
the study area using the program. However, these studies
including haul route flexibility and high productivity
were only able to perform a simple form of simulation
(Salama, Greberg, & Schunnesson, 2014; Thomas, Gregg,
consisting of a single loading point, failing to represent the
& Hartman, 1987).
multiple loading points of the actual underground mines.
Various simulation techniques have been developed to
The objective of this study is to design a model for the
date by many researchers to prepare measures to increase
simulation of truck-loader haulage systems in an under-
the productivity of open-pit mine haulage systems (Aksoy
ground mine and develop a simulation program based
& Yalcin, 2000; Alarie & Gamache, 2002; Blackwell, 1999;
on the model using the GPSS/H simulation language.
Bonates, 1996; Choi, 2011; Ercelebi & Bascetin, 2009;
The Daesung MDI limestone mine located in Korea was
Krause & Musingwini, 2007; Niemann-Delius & Fedurek,
selected as the study area. Using the developed program,
2004; Oraee & Asi, 2004; Park, Choi, & Park, 2014a; Park,
simulations of the truck-loader haulage system were per-
Lee, Choi, & Park, 2014; Temeng, 1997; Yan & Lai, 2007;
formed to optimize the number of trucks dispatched at
Zhang, 2008). However, the research on simulations for
multiple loading points. This paper describes the details
underground mines is relatively lacking since their work

CONTACT  Yosoon Choi  energy@pknu.ac.kr


© 2016 The Korean Society of Mineral and Energy Resources Engineers (KSMER)
2    S. Park et al.

of model and the results of applying the developed simu- regular intervals. When an empty truck returning to a
lation program to the study area. loading point after dumping the ore meets a loaded truck
heading to the crush site, it stops at the space and gives
way to the oncoming truck, causing a waiting time.
2.  Study area and field survey
Parameters required for simulating the truck-loader
In this study, we selected the Donghae Office of Daesung haulage system were also obtained from the field surveys.
MDI Co., Ltd to design the model and develop the pro- The time required for each work unit was repeatedly meas-
gram to simulate an underground mine haulage system. ured with a stopwatch up to 20 times and summarized in
This mine is located in Daepyeong-ri, Singi-myeon, the form of the mean ± standard deviation.
Samcheok-si, Gangwon-do, Korea, on administrative
divisions (see Figure 1). The Donghae Office operates as
3.  Design of simulation model
two districts, Daepyeong and Magyo, and produces 1.5
million tons of limestone per year. The produced lime- The simulation model is comprised of discrete events of
stone is mostly supplied to POSCO (KORES, 2011). objects (machinery)—including loading, traveling, dump-
To design a simulation model that represents the ing, and waiting—and it can be explained by the truck
field characteristics of the study area, we conducted cycle time theory proposed by Suboleski (1975) (see (1)).
Downloaded by [University of Nebraska, Lincoln] at 10:21 10 June 2016

field surveys of the study area. The haulage system at the


TCT = STL + LT + TL + STD + DT + TE + AD (1)
Daepyeong district in August of 2014 consisted of three
loading points (470, 540, and 590 ML), a crush site (two Here, TCT denotes the truck cycle time, STL (spotting
crushers with 200-tph capacity), a storage yard, and a time at the loader) denotes the time spent for a truck to
truck scale, as shown in Figure 2. A fixed number of trucks access a loader, LT (loading time) denotes the time spent
were dispatched to each loading point (i.e., four (470 ML), for loading the ore, TL (travel time of loaded truck)
six (540 ML), and four (590 ML)) to haul the limestone denotes the time spent for a loaded truck to move to a
ore. In addition, in the storage yard, loaders loaded and crusher, STD (spotting time at dumping area) denotes
hauled the stored ore to the crushers. the time spent for a truck to access a crusher or the stor-
The hauling tunnels leading from the mine portal to age yard, DT (dumping time) denotes the time spent for
each loading point are extremely narrow due to the char- dumping the ore, TE (travel time of empty truck) denotes
acteristics of the underground mine. Therefore, spaces the time spent for an empty truck that has finished dump-
to avoid oncoming trucks are provided in the tunnels at ing to return to a loading point, and AD (average delay

Figure 1. Aerial view of Daesung MDI underground limestone mine, Samcheok-si, Gangwon-do, Korea (image source: Vworld, http://
map.vworld.kr/map/maps.do).
Geosystem Engineering   3
Downloaded by [University of Nebraska, Lincoln] at 10:21 10 June 2016

Figure 2. Haulage system in the study area: (a) Haulage system from dumping area to portal, (b) Haulage system from portal to each
loading point.

time) denotes the time spent for a truck to wait during ore travels from the crusher to the portal and then travels to
loading or hauling. Here, AD includes the waiting time for the crossroad (TE). When trucks travel from the portal to
a truck in a queue at a loading point or crush site and the the crossroad and meet a loaded truck on the way, the time
waiting time for a truck to give way to oncoming trucks required to give way to the oncoming truck (waiting time)
in a hauling tunnel. is added. That is, AD occurs. When trucks travel from the
As shown in Figure 3, the simulation model can include crossroad to each loading point and meet a loaded truck
up to three loading points in the same condition as the on the way, both TE and AD occur.
study area. Once simulation begins, trucks are put in The trucks that arrive at a loading point determine
the fixed dispatch system in accordance with the initial whether loaders are available, and if they are, trucks access
dispatch interval for trucks. The truck put in the system the loaders and perform loading. In this process, STL and
4    S. Park et al.
Downloaded by [University of Nebraska, Lincoln] at 10:21 10 June 2016

Figure 3. Model for simulating truck-loader haulage systems in the study area.

LT occur. If a loader is performing another truck’s loading, mean of 25 tons and a standard deviation of 5 tons,
the truck that arrives later should wait in the queue until and only the ore that has been crushed or dumped
the loading is over, in which case AD occurs. The truck in the storage yard is included in the production.
loaded with the ore travels through a hauling tunnel and • The maximum capacity of the storage yard is 5,000
along a road to the crush site (TL). When the loaded truck tons, and when the yard contains more than 200
arrives at the truck scale, the time required to weigh the tons of dumped ore, the ore is hauled to a crusher
ore occurs additionally (AD). by a loader located in the yard. At this time, the
Upon arriving at the crush site, trucks determine hauling amount of the loader (in tons) has a normal
whether crushers are available for use at the time. If they distribution with a mean of 8 tons and a standard
are, trucks perform dumping (AD, STD, DT). If crushers deviation of 1.6 tons.
are not available, they travel to the storage yard to store the
ore (AD, STD, DT). The trucks that have completed dump-
ing check the simulation time, and determine whether 4.  Development of simulation program
they should travel back to the loading point or finish the
The previously designed simulation model was imple-
simulation.
mented into a program using the GPSS/H simulation
The following additional conditions are put forth to
language. The language provides a powerful simulation
incorporate the specific conditions of the study area.
environment, and it is used in various industries, includ-
• At a loading point, only one truck can perform ing transportation, logistics, and mining (Choi, 2011).
loading at a time, however at the crush site with GPSS/H is one of the specialized simulation languages,
two crushers, two trucks can perform dumping at and it can write a logic into an easy-to-understand, fast,
a time. and concise program. Compared to Fortran, a procedural
• The trucks that are put in the system have the same programming language, GPSS/H has several advantages
performance. (e.g., simulator implementation time, execution time, ease
• The section between the crush site and the portal is of changing programs, and length of program code), as
a two-lane road, and the section between the portal shown in Table 1. Simulation programs can be devel-
and the loading points is a single-lane road. A sin- oped with text editing programs such as Notepad (see
gle-lane road does not allow multiple trucks to pass Table 2). In other words, GPSS/H commands are written
a point simultaneously. in an ASCII-type text file with parameters that compose a
• The weight (in tons) of the ore that can be hauled by simulation algorithm. The simulation results can be shown
a truck is said to have a normal distribution with a as an output on the PC screen using a Windows 32 console
Geosystem Engineering   5

Table 1. Comparison of GPSS/H and FORTRAN for simulator implementation (Sturgul, 2000).
GPSS/H FORTRAN
Time to implement a simulator Few days Many months
Ease of changing program Trivial Up to a week
Execution time <1 min 3–4 h
Lines of computer code 300–400 20,000–50,000
User friendly? Yes No

Table 2. Part of GPSS/H program for simulating truck-loader haulage systems in an underground mine.
GENERATE &TDIA,,0,&TRUCKA
BLET &ODD1=0
ENTER RCP
GTA ADVANCE RVNORM(1,4.28,0.77)
LEAVE RCP
RCA BLET &NTJP=S(RJP)
BLET &NDJPA=&NDJPA+S(RJP)
BLET &DTPJA=&NTJP*RVNORM(1,0.62,0.12)
ENTER RPJ
ADVANCE RVNORM(1,4.54,0.72)
Downloaded by [University of Nebraska, Lincoln] at 10:21 10 June 2016

ADVANCE &DTPJA
LEAVE RPJ
BLET &NTAJ=W(RAC)
BLET &NDAJ=&NDAJ+W(RAC)
BLET &DTJA=&NTAJ*RVNORM(1,0.62,0.12)
ADVANCE RVNORM(1,6.88,0.60)
ADVANCE &DTJA
QUEUE QLPA
TEST E FNU(SHOVELA),1,WSQA
SEIZE SHOVELA
DEPART QLPA
ADVANCE RVNORM(1,0.49,0.09)
ADVANCE RVEXPO(1,2.94/3)
ADVANCE RVEXPO(1,2.94/3)
ADVANCE RVEXPO(1,2.94/3)
RELEASE SHOVELA
TRANSFER ,RAC
(the rest is omitted)

depending on the user settings, or it can be saved as a text system using the developed simulation program by incor-
file (see Figure 4). porating the conditions of the study area (Table 3).
Figure 5 shows a schematic view of the input and out- The simulation period was set to 1,000 days based
put data of the simulation program. Generally, program on 8.5 h a day for work, and the initial truck dispatch
input data have the following parameter sets: parameters interval was set to 3 min (i.e., one truck is put in every
to execute a simulation (e.g., number of machines, simu- three minutes sequentially once simulation begins).
lation period, number of work hours per day), and time This was to prevent the excessive queues and waiting
parameters (e.g., truck dispatch interval, required time times caused by putting in all trucks at the beginning
for each work unit). The output data show the following of the simulation. The number of loaders put in the
parameters: the mean number of times trucks give way system was set to four (i.e., one loader at each loading
to other trucks, average utilization of machinery, average point (470, 540, 590 ML), and one loader at the storage
queue length per machine, average waiting time, average yard). Because the study area has 14 trucks, the number
number of hauls, and average amount of hauled ore per of trucks that could be put in for each loading point
day. was set to 0–14.
As a result, a total of 120 simulations were conducted
that represent the total number of applicable combinations
5. Application
considering the number of trucks suggested in the simula-
To reduce hauling cost, which accounts for a significant tion conditions. The simulation results were sorted based
portion of mining cost, the layout of the haulage sys- on the average daily production, and part of the results are
tem components and the number and performance of shown in Table 4. The haulage system in the study area was
machines allocated in the system must be properly inte- most productive when each loading point had four trucks
grated. In this study, we conducted simulations to opti- (470 ML), nine trucks (540 ML), and one truck (590 ML) put
mize the number of trucks for the truck-loader haulage in, respectively. However, this result may not be applicable to
6    S. Park et al.
Downloaded by [University of Nebraska, Lincoln] at 10:21 10 June 2016

Figure 4. View of Win32 console for displaying simulation results on PC.

Figure 5. Input and output data of simulation program developed in this study.

the actual site, because the utilizations (%) of the loader at the The simulation results suggest that production increases
540 ML loading point and the crushers are very high. Because when a relatively large number of trucks are dispatched
the loaders and crushers require some time for maintenance, to the 540 ML loading point, which is the closest loading
their utilizations are restricted up to 70% according to the point, and vice versa. In addition, it was found that when
regulations in the study area. Therefore, it is believed to be trucks were concentrated to a specific loading point, the
reasonable to put in four (470 ML), seven (540 ML), and machinery utilization and truck waiting time for the load-
three trucks (590 ML) by restricting the utilization of appli- ing point increased.
cable machinery to 70%. With this setting, 3,588 tons of A validation of the simulation program was performed
ore can be produced daily. by comparing between the simulation results and real
Downloaded by [University of Nebraska, Lincoln] at 10:21 10 June 2016

Table 3. Parameter settings for truck-loader haulage simulations in the study area.
Parameter Value
Simulation parameter Number of days to simulate for 1000 (day)
Daily working time for each day 510 (min)
Truck dispatch interval 3 (min)
Capacity of each truck 25 ± 5 (ton)
Capacity of each loader 8 ± 1.6 (ton)
Time parameter At loading point Spotting time (wait in the queue) .80 ± .16 (min)
Spotting time (no wait in the queue) .49 ± .09 (min)
Loading time 2.94 ± .58 (min)
At crusher Waiting time in the queue .84 ± .16 (min)
Spotting time (wait in the queue) .87 ± .17 (min)
Spotting time (no wait in the queue) .47 ± .09 (min)
Dumping time .59 ± .11 (min)
At storage yard Spotting time .76 ± .15 (min)
Dumping time .59 ± .11 (min)
On hauling tunnel and road Loaded truck Travel time (loading point 470 ML – crossroad) 10.45 ± .44 (min)
Travel time (loading point 540 ML – crossroad) 7.10 ± .90 (min)
Travel time (loading point 590 ML – crossroad) 12.78 ± .79 (min)
Travel time (crossroad-portal) 7.59 ± .84 (min)
Travel time (portal-dumping area) 6.26 ± .70 (min)
Empty truck Return time (dumping area-portal) 4.28 ± .77 (min)
Return time (portal-crossroad) 4.54 ± .72 (min)
Return time (crossroad-loading point 470 ML) 6.88 ± .60 (min)
Return time (crossroad-loading point 540 ML) 5.00 ± .61 (min)
Return time (crossroad-loading point 590 ML) 9.80 ± .43 (min)
Etc. Time for measuring the weight of ore or cleaning the wheels .37 ± .07 (min)
Waiting time for a truck to give way to oncoming trucks .62 ± .12 (min)
Geosystem Engineering 
 7
Downloaded by [University of Nebraska, Lincoln] at 10:21 10 June 2016

8 
  S. Park et al.

Table 4. Simulation results for truck-loader haulage systems in the study area.
At hauling tunnel At loading point
Avg. number of times trucks give way
Number of trucks to other trucks 470 ML 540 ML 590 ML At crusher At storage yard Avg.
amount
Avg. Avg. Avg. Avg. Avg. Avg. Avg. Avg. of hauled
Avg. wait- waiting queue Utili- waiting queue Utili- waiting queue waiting queue ore per
Crossroad – Crossroad Crossroad Utiliza- ing time Avg. queue Utiliza- time length zation time length zation time length time length day
Case ID 470 ML 540 ML 590 ML 470 ML – 540 ML – 590 ML tion (%) (min) length (unit) tion (%) (min) (unit) (%) (min) (unit) (%) (min) (unit) (min) (unit) (tons)
1 4 9 1 2.57 3.42 .00 28.10 .71 .06 71.79 2.22 .44 6.76 .00 .00 72.74 .01 .00 .21 .03 3615.69
2 4 8 2 2.53 3.20 2.05 28.07 .71 .06 64.40 1.76 .32 13.62 .27 .01 71.09 .01 .00 .24 .04 3608.46
3 3 9 2 2.33 3.41 2.10 21.20 .51 .03 71.81 2.22 .44 13.59 .27 .01 72.00 .01 .00 .22 .03 3606.78
4 5 8 1 2.85 3.25 .00 35.11 .89 .09 64.35 1.72 .31 6.75 .00 .00 72.37 .01 .00 .21 .03 3604.37
5 5 9 0 2.92 3.46 .00 35.06 .87 .09 71.79 2.20 .44 .00 .00 .00 73.78 .01 .00 .18 .03 3603.47

11 4 7 3 2.48 2.98 2.14 28.07 .71 .06 56.86 1.41 .23 20.27 .50 .03 69.30 .01 .00 .25 .04 3588.15
12 5 7 2 2.77 3.00 2.02 35.02 .88 .09 56.79 1.38 .22 13.60 .28 .01 70.37 .01 .00 .24 .04 3587.25
13 6 7 1 3.15 3.07 .00 41.74 1.03 .12 56.88 1.37 .22 6.73 .00 .00 71.79 .01 .00 .20 .03 3586.21
14 2 10 2 2.20 3.61 2.15 14.16 .27 .01 78.78 2.83 .62 13.55 .28 .01 72.95 .01 .00 .18 .03 3583.64
15 3 7 4 2.28 3.01 2.37 21.04 .50 .03 56.83 1.40 .22 26.86 .72 .06 69.00 .01 .00 .23 .04 358.48
16 2 8 4 2.13 3.22 2.42 14.21 .25 .01 64.64 1.73 .31 26.81 .73 .06 70.00 .01 .00 .20 .03 3579.77
17 1 9 4 .00 3.43 2.43 7.16 .00 .00 71.94 2.18 .44 26.88 .74 .06 70.86 .01 .00 .17 .03 3566.53
18 7 7 0 3.49 3.10 .00 48.49 1.19 .16 57.05 1.36 .22 .00 .00 .00 72.90 .01 .00 .17 .03 3563.95
19 1 8 5 .00 3.25 2.68 7.13 .00 .00 64.56 1.70 .31 33.14 .90 .09 69.45 .01 .00 .18 .03 3559.62
20 4 6 4 2.47 2.80 2.34 28.05 .70 .06 49.22 1.11 .15 26.93 .69 .05 67.50 .01 .00 .24 .04 3557.53
21 1 10 3 .00 3.60 2.27 7.12 .00 .00 78.82 2.83 .62 20.42 .53 .03 72.25 .01 .00 .16 .02 3557.40
22 2 7 5 2.12 3.04 2.66 14.28 .28 .01 57.07 1.39 .22 33.08 .89 .08 68.39 .01 .00 .20 .03 3556.29
23 5 6 3 2.74 2.79 2.11 34.92 .86 .09 49.19 1.11 .15 20.41 .52 .03 68.27 .01 .00 .25 .04 3554.14
24 6 6 2 3.09 2.82 2.00 41.75 1.02 .12 49.13 1.12 .16 13.60 .30 .01 69.75 .01 .00 .23 .03 3551.09
25 3 11 0 2.44 3.76 .00 21.16 .47 .03 84.97 3.78 .88 .00 .00 .00 74.62 .01 .00 .15 .02 3550.11

116 2 0 12 1.91 .00 4.39 14.48 .26 .01 .00 .00 .00 75.63 2.73 .57 51.87 .00 .00 .10 .01 2999.17
117 0 1 13 .00 .00 4.61 .00 .00 .00 8.49 .00 .00 80.75 3.38 .76 51.82 .00 .00 .09 .01 2956.69
118 1 0 13 .00 .00 4.58 7.31 .00 .00 .00 .00 .00 80.97 3.42 .76 51.04 .00 .00 .08 .01 2906.80
119 14 0 0 4.90 .00 .00 89.24 5.34 1.30 .00 .00 .00 .00 .00 .00 60.68 .00 .00 .05 .00 2898.67
120 0 0 14 .00 .00 4.72 .00 .00 .00 .00 .00 .00 85.66 4.39 1.03 49.76 .00 .00 .06 .01 2796.53
Geosystem Engineering   9

Table 5. Comparison between measured and simulated values.


Measured value Simulated value Absolute error value
Avg. waiting time of trucks at each loading point (min) At 470 ML .32 .70 .38
At 540 ML .79 1.11 .32
At 590 ML .88 .69 .19
Avg. amount of loaded ore (tons/day) 3,575 3,558 17

data measured in the study area. As of the field survey future work, it needs to be developed into a user-friendly
in August of 2014, four (470  ML), six (540  ML), and Windows-based program.
four trucks (590 ML) were operating at the three loading
points. Table 5 shows the daily production and average
Disclosure statement
waiting time for trucks at each loading point, which were
measured at the study area. The study area was producing No potential conflict of interest was reported by the authors.
3,575 tons of ore at 8.5  h of work per day. This is very
similar to the simulation result (3,558 tons) when four,
Funding
six, and four trucks were dispatched to the 470, 540, and
Downloaded by [University of Nebraska, Lincoln] at 10:21 10 June 2016

590 ML loading points, respectively. In addition, the wait- This work was supported by the Korea Institute of Ener-
gy Technology Evaluation and Planning [grant number
ing times of the trucks measured at the loading points
2013T100100021].
(.32 min (470 ML), .79 min (540 ML), .88 min (590 ML))
were found to be similar to the simulation results (.70 min
(470 ML), 1.11 min (540 ML), .69 min (590 ML)). References
Aksoy, M., & Yalcin, E. (2000). A computer program for
6. Conclusions open pit mine equipment selection: TruckMac. In G. N.
Panagiotou & T. N. Michalakopoulos (Eds.), Mine planning
In this study, we designed a model for the simulation of and equipment selection 2000 (pp. 499–503). Rotterdam:
truck-loader haulage systems in an underground lime- Balkema.
stone mine, Korea and developed a simulation program Alarie, S., & Gamache, M. (2002). Overview of solution
strategies used in truck dispatching systems for open pit
using the GPSS/H simulation language. Using the devel-
mines. International Journal of Surface Mining, Reclamation
oped program, simulations of the truck-loader haulage and Environment, 16, 59–76.
system were performed to optimize the number of trucks Berkhimer, E. N. (2011). Selection and sizing of excavating,
dispatched at three loading points. Results showed that loading, and hauling equipment. In P. Darling (Ed.), SME
considering the number of trucks retained in the study mining engineering handbook (3rd ed., pp. 931–939).
area currently, the largest amount of ore (3,616 tons) Englewood, CO: Society for Mining, Metallurgy, and
Exploration.
could be produced within the range of 70% of utiliza- Bonates, E. J. L. (1996). Interactive truck haulage simulation
tion of machinery when four (470 ML), seven (540 ML), program. In W. T. Hennies, L. A. Ayres Da silva, & A. P.
and three trucks (590 ML) were dispatched to respective Chaves (Eds.), Mine planning and equipment selection 1996
loading points. In addition, considering that the simula- (pp. 51–57). Rotterdam: Balkema.
tion results and the measured results from the field survey Blackwell, G. H. (1999). Estimation of large open pit haulage
truck requirements. CIM Bulletin, 92, 143–149.
conducted in August of 2014 were similar, the simulation
Choi, Y. (2011). New software for simulating truck-shovel
program is believed to properly simulate the haulage sys- operation in open pit mines. Journal of the Korean Society
tem of the study area. for Geosystem Engineering, 48, 448–459.
This study is significant, in that it simulated a truck- Choi, Y., Sunwoo, C., & Park, H. D. (2007). Analysis of optimal
loader haulage system by expanding to underground haulage routes for dump trucks in large open pit mines.
mines for which research has been scarce, and it presented Journal of the Korean Society for Geosystem Engineering,
44, 477–491.
the optimal combination of machinery for production Ercelebi, S. G., & Bascetin, A. (2009). Optimization of shovel-
improvement of the study area. The simulation program truck system for surface mining. The Journal of the Southern
developed in this study can be used for practical purposes African Institute of Mining and Metallurgy, 109, 433–439.
in actual mining sites, because the program was found KORES (Korea Resources Corporation). (2011). Technical
to simulate by properly representing the haulage system data analysis of Donghae Mine of Daesung MDI Co., Ltd.
[PDF]. Retrieved from http://http://www.kores.net/main.do
in the site. However, the developed program has limita-
Krause, A., & Musingwini, C. (2007). Modelling open pit
tions; for example, users must enter commands line by line shovel-truck systems using the machine repair model. The
and conduct simulations repeatedly, because it conducts Journal of the Southern African Institute of Mining and
simulations using a Windows console. Therefore, in the Metallurgy, 107, 469–476.
10    S. Park et al.

Niemann-Delius, C., & Fedurek, B. (2004). Computer-aided approach using SimMine. Proceedings of MassMin 2012
simulation of loading and transport in medium and small (6th international Conference & Exhibition on Mass
scale surface mines. In M. Hardygora, G. Paszkowska, & M. Mining), Sudbury, Canada.
Sikora (Eds.), Mine planning and equipment selection 2004 Salama, A., Greberg, J., & Schunnesson, H. (2014). The use of
(pp. 579–584). London: Taylor & Francis Group. discrete event simulation for underground haulage mining
Oraee, K., & Asi, B. (2004). Fuzzy model for truck allocation equipment selection. International Journal of Mining and
in surface mines. In M. Hardygora, G. Paszkowska, & M. Mineral Engineering, 5, 256–271.
Sikora (Eds.), Mine planning and equipment selection 2004 Suboleski, S. C. (1975). Mine systems engineering. Lecture
(pp. 585–591). London: Taylor & Francis Group. notes. State College, PA: The Pennsylvania State University-
Park, S., & Choi, Y. (2013). Simulation of shovel-truck haulage University Park.
system by considering truck dispatch methods. Journal Sturgul, J. R. (2000). Mine design: Examples using simulation.
of the Korean Society of Mineral and Energy Resources Littleton, CO: Society for Mining, Metallurgy and
Engineers, 50, 543–556. Exploration.
Park, S., Choi, Y., & Park, H. S. (2014a). Simulation of shovel- Temeng, V. A. (1997). A computerized model for truck
truck haulage systems in open-pit mines by considering dispatching in open pit mines (Doctoral dissertation).
breakdown of trucks and crusher capacity. Tunnel & Michigan Technological University, Houghton, MI.
Underground Space, 24(1), 1–10. Thomas, N., Gregg, A. J., & Hartman, H. L. (1987). Comparative
Park, S., Choi, Y., & Park, H. S. (2014b). Simulation of truck- performance study of diesel and electric face-haulage
loader haulage systems in an underground mine using vehicles. International Journal of Mining and Geological
Downloaded by [University of Nebraska, Lincoln] at 10:21 10 June 2016

GPSS/H. Tunnel & Underground Space, 24, 430–439. Engineering, 5, 405–417.


Park, S., Lee, S., Choi, Y., & Park, H. S. (2014). Development Yan, S., & Lai, W. (2007). An optimal scheduling model for
of a windows-based simulation program for selecting ready mixed concrete supply with overtime considerations.
equipments in open-pit shovel-truck haulage systems. Automation in Construction, 16, 734–744.
Tunnel & Underground Space, 24, 111–119. Zhang, H. (2008). Multi-objective simulation-optimization for
Salama, A., & Greberg, J. (2012). Optimization of truck-loader earthmoving operations. Automation in Construction, 18,
haulage system in an underground mine: A simulation 79–86.

You might also like