You are on page 1of 19

Coastal Engineering 183 (2023) 104334

Contents lists available at ScienceDirect

Coastal Engineering
journal homepage: www.elsevier.com/locate/coastaleng

Numerical investigation of scour around the monopile using CFD-DEM


coupling method
Shuye Zhang, Boen Li, Huihuan Ma *
School of Civil Engineering, Sun Yat-sen University, Southern Marine Science and Engineering Guangdong Laboratory (Zhuhai), 510275, China

A R T I C L E I N F O A B S T R A C T

Keywords: The risks posed by local scour around offshore monopile foundations are substantial and threaten the structural
Local scour safety of these installations. It is therefore essential to study the mechanisms of local scour to mitigate these risks.
Sediment transport Numerical simulation is an effective tool to help us understand the mechanisms of local scour. However, the
Monopile
accurate modeling of the local scour process remains to be challenging due to the complexity of sediment
Steady current
(CFD)
transportation, in which the continuity threatment of sediment phase is typically used, the discrete behavior of
Computational fluid dynamics the sediment is hard to be described. Therefore, in this paper, in order to conduct the deepin investigation into
(DEM) the mechanism of the local scour around monopile, a three-dimensional CFD-DEM model was established by
Discrete element method coupling the computational fluid dynamic method (CFD) and discrete element method (DEM). To increase the
(CGM) efficiency and accuracy of the CFD-DEM model, the coarse grain method (CGM) was used to decrease the number
Coarse grain method of required DEM particles in the simulation, and the angle of repose was used to calibrate the contact parameters
Seepage between DEM particles. During the validation process of the numerical model, it was found that the development
of the scour depth and the morphology of scour pit obtained by the CFD-DEM model showed good agreement
with the previously published results. The CFD-DEM simulation revealed that seepage-induced vertical drag force
plays a crucial role in the initial stage of local scour. Two sediment transportation processes, "Pile toe erosion-
Slope avalanche" and "Push-Accumulation-Wash", were observed and the relationship between bedload sedi­
ment flux and the Shields number was quantified. In the end of this paper, the critical evaluation of the CFD-DEM
method was conducted.

1. Introduction offer scientific guidance for engineering practice regarding the predic­
tion and prevention of scour.
In recent years, offshore wind power engineering has experienced The local scour around the marine monopile is a long-standing
rapid development. According to a recent investigation conducted by problem. As early as the 1960s, Chabert and Engeldinger (1956) con­
IRENA (2021), the total installed capacity of offshore wind turbines ducted some experimental studies on the monopile scour under different
worldwide reached 28308 MW by the end of 2020, with a growth rate of flow velocities, pile diameters, and sand diameters, and the equilibrium
nearly 30% over the past decade. Due to the advantages of simple scour depth is the focus of the study. After that, more scour experiments
structure, small land occupation, and high bearing capacity, the of the monopiles were conducted, and various formulas for predicting of
monopile foundation is the foundation form that is most widly used in scour depth when dealing with complex and variable scour conditions
offshore wind structures, according to the report by Wang et al. (2018). were also worked out, such as the 65-2 formula in Chinese Hydrological
Serious local scour problems are a significant challenge for the monopile Specifications for Survey and Design of Highway Engineering, HEC-18 for­
foundation. According to the research of Prendergast et al. (2013), the mula used by Federal Highway Administration, Melville formula by
effective embedment depth of the monopile is decreased by the local Melville and Sutherland (1988), S/M formula by Sheppard et al. (2014)
scour pit, which weakens the horizontal bearing capacity of the and so on.
monopile and affects the natural frequency of the support structure. With the development of computer technology, the numerical
Therefore, it is of great significance to study local scour’s development methods has become widely used for investigating the scour process and
process and mechanism in the vicinity of marine monopiles, in order to mechanism around monopiles. Olsen and Melaaen (1993) carried out

* Corresponding author.
E-mail address: mahh5@mail.sysu.edu.cn (H. Ma).

https://doi.org/10.1016/j.coastaleng.2023.104334
Received 18 November 2022; Received in revised form 28 April 2023; Accepted 7 May 2023
Available online 8 May 2023
0378-3839/© 2023 Published by Elsevier B.V.
S. Zhang et al. Coastal Engineering 183 (2023) 104334

the earliest numerical simulation on the monopile scour, which mainly be a useful and efficient numerical tool for investigating the mechanism
focus on the initial stage of the local scour. Roulund et al. (2005) of local scour around pipelines using a teo-dimensional approach. Zhang
simulated the whole process of monopile local scour, providing results et al. (2015) used the CFD-DEM method to simulate the initial stage of
that are valuable references for subsequent research, including the pipeline local scour, and identified that the large calculation resource
research by Zhao et al. (2010), Baykal et al. (2017), Song et al. (2022), consumption is the main factor that limits the engineering application of
Gautam et al. (2021), Song et al. (2022) and other researchers. To the CFD-DEM method. Yang et al. (2018) simulated the whole process of
consider the influence of the free water surface, Liu and García (2008) pipeline local scour using the CFD-DEM method, and the accuracy of
introduced the air phase into the CFD simulation by using the Volume of CFD-DEM method was validated using experimental data from Mao
Fluid (VoF) method, which enhances the feasibility for the research on (1988). Hu et al. (2019) used the CFD-DEM coupling method to simulate
local scour under wave conditions. the local scour around two pipelines, and employed the coarse grain
In most of the numerical simulation research, the shape of the sedi­ method to improve the simulation efficiency. In order to improve
ment surface was estimated through the morphologic model based on simulation accuracy, Song and Park (2022) calibrated the rolling friction
the empirical sediment transportation model, which is referred to as the coefficient of sediment particles based on the angle or repose, which
morphologic method. However, the morphologic method is over­ helps improve the accuracy of the prediction of scour pit morphology.
whelmingly dependent on the empirical equations that are mostly Simulating local scour around a monopile is a three-dimensional
derived under steady flow conditions and their applicability to complex problem that requires significantly more computational resources than
turbulent conditions around the pile needs futher investigation. In the cases under two-dimensional conditions. So far, only a few scholars
recent years, numerical models based on physical models rather than have investigated the local scour around monopile using the CFD-DEM
empirical formulas have gained significant attention and showen sig­ coupling method. Jaeho Shim (2016) simulated the local scour around
nificant advancement. Among these models, the Euler-Euler two-phase monopile using the CFD-DEM method for the first time, and the char­
flow model and Euler-Lagrange two-phase flow model are acteristics of the distribution of sediment particle velocities were
representative. analyzed. Liu et al. (2022) also conducted the simulation on monopile
The Euler-Euler two-phase flow model assumes that the sediment is local scour using the CFD-DEM method, it is proposed that the collision
continuity and represents sediment with the fluid that has unique between particles plays a dominant role in scour at the early stage of it.
rheological properties. It can consider the interactions between water Although promising efforts and attempts have been done based on the
and sediment particle, as well as the interactions between sediment CFD-DEM method, further research is needed to explore the application
particles. Significant improvements have been made to the sediment of the CFD-DEM method in the local scour simulation around the pile.
transportation model based on the Euler-Euler two-phase flow, partic­ In this paper, a three-dimensional CFD-DEM numerical model was
ularly in the areas of interface force and particle stress modeling. established to study the local scour around the monopile under steady
Amoudry et al. (2008) first discussed the Euler-Euler two-phase flow flow condition. In order to reduce computational resources consump­
model in the simulation of sediment transportation. After nearly a tion, the coarse grain method was utilized to decrease the number of
decade of optimization and improvement, Cheng et al. (2017) developed DEM particles. And the interaction parameters between the DEM par­
the opensource toolbox called ‘SedFoam’ to solve the sediment transport ticles were calibrated using a numerical test on the angle of repose to
problem using Euler-Euler two-phase flow model. Using the SedFoam achieve more accurate simulation of scour pit morphology. The CFD-
model, Nagel et al. (2020) conducted local scour simulation around the DEM model was validated by comparing its results with experimental
monopile under steady current and validated the effectiveness of the datas reported by Roulund et al. (2005) and the simulation results re­
Euler-Euler two-phase flow model for local scour simulation around ported by Nagel et al. (2020). Based on the validated numerical model,
monopiles. Although the Euler-Euler two-phase flow model has made an investigation into the local scour mechanism was conducted.
significant progress, based on the authors’ understanding and the
research of Chen et al. (2011) and Durán et al. (2012), it still has the 2. Theoretical background
following limitations, which are mainly owing to the assumption that
the sediment phase is continuous. In the CFD-DEM model, the computational fluid dynamic model and
discrete element model are used to simulate the fluid phase and particle
(i) The continuity assumption assumes that the sediment particles phase, respectively. To realize the coupling between the above two
suspended in the fluid are fluid that fills the entire space and is models, the data exchange between them is carried out at certain in­
completely void fraction-free. However, in practical conditions, tervals. Here is the detailed theoretical background of the CFD-DEM
when the concentration of sediment particles in the fluid is model.
relatively low, the number of sediment particles is insufficient to
form a continuous phase, therefore the continuity assumption is
no longer applicable; 2.1. Computational fluid dynamics (CFD)
(ii) The continuity assumption of the sediment phase ignores the
inherent material characteristics of the sediment particles that The N–S (Navier-Stokes) equations are used as the governing equa­
are discretely and randomly distributed, these characteristics tion to describe fluid motion. The equations include the continuity
play important roles in the determination of the critical starting equation and momentum equation. In the CFD-DEM model, considering
conditions of sediment; the contribution of particle interactions, the governing equations of
(iii) The model uses the binary collision assumption to consider the incompressible viscous fluid are as follows:
particle-particle interaction. However in the initial stage of local ∂( ) ( )
scour, the sediment motion is active and the binary collision α ρ + ∇ • αf ρf uf = 0 (1)
∂t f f
assumption is no longer applicable.
∂( ) ( ) ( )
α ρ u + ∇ • αf ρf uf uf = − αf ∇p + ∇ • αf τf + αf ρf g − Rf ,p (2)
To account for the discrete behavior of sediment, the CFD-DEM ∂t f f f
method has started to be used in the simulation of sediment trans­
portation. It is a kind of Euler-Lagrange two-phase flow model, which where the subscript f indicates the fluid phase; αf is the fluid volume
uses the computational fluid dynamics (CFD) method to solve the flow fraction; ρf , uf and p are the fluid density, velocity, and pressure,
field, and uses the discrete element method (DEM) to compute the respectively; g is the gravitational acceleration; τf is the fluid shear
motions of sediment particles. The CFD-DEM method has been proven to stress; and Rf,p is the momentum exchange term between fluid and

2
S. Zhang et al. Coastal Engineering 183 (2023) 104334

Fig. 1. Diagram of CFD-DEM coupling algorithm.

particles. αf , τf and Rf,p could be expressed as follows: turbulence model to obtain the turbulent viscosity coefficient. In this
np
study, the large eddy simulation (LES) model proposed by Smagorinsky
∑ /
αf = 1 − αp = 1 − Vp,i ΔV (3) (1963) is used to simulate the turbulence, which divides the turbulent
i=1 motion into large-scale vortices and small-scale vortices. The LES model
uses the direct numerical simulation (DNS) method to simulate the
[ )T ]
τf = −
2( )
v∇ • uf I + v ∇uf + ∇uf
(
(4) large-scale vortex motion and uses the sub-grid scale stress (SGS) to
3 consider the influence of small-scale vortex motion. The SGS can be
⃒ np ⃒ calculated as follows:
⃒ ∑ ( )⃒
⃒ f ⃒
⃒ d,i ⃒ ( ) 1
Rf ,p = i=1
⃒ ⃒ uf − 〈up 〉 (5) τ ij − τ kk δij − 2vsgs sij (12)
ρ ΔV ⃒uf − 〈up 〉⃒
f
3

where τij is the SGS; sij = (∂ui /∂xj +∂uj /∂xi )/2 is the resolved scale strain
where αp is the particles volume fraction; ΔV and Vp,i are the volume of a
rate tensor; vsgs is the sub-grid eddy-viscosity. In the solution of vsgs , the
computational cell and volume of particles inside this cell, respectively;
np is the number of particles inside the cell; v is the fluid viscosity; I is a one-equation eddy-viscosity sub-grid model from Yoshizawa and Horiuti
(1985) is adopted, which can can more accurately describe the
unit tensor; 〈up 〉 is the average velocity of particles in the computational
three-dimensional flow field under a high Reynolds number. The vsgs in
cell; f d,i is the fluid-particle force of particle i, which is mainly composed
the one-equation eddy-viscosity model is as follows:
of drag force, and can be calculated by the method proposed by Gidas­
√̅̅̅̅̅̅̅
pow (1994) as follows: vsgs = ck Δ ksgs (13)
β ( )
fd = Vp uf − up (6) ∂ksgs ( ) ( )
αf + ∇ • ksgs uf − ∇ • Dk ∇ksgs = G − εsgs (14)
∂t
When αf > 0.8,
where Δ is the sub-grid scale filter size; ksgs is the sub-grid scale turbulent
⃒ ⃒
3 ρf ⃒uf − up ⃒αf αp ψ kinetic energy; Dk = v + vsgs ; G = vsgs |sym(∇u)|2 ; εsgs = ce k1.5
sgs /Δ; ce , ck
β = Cd αf (7)
4 dp are both the parameters based on dynamic process.

where Cd is the drag force coefficient, dp is the diameter of particle, and 2.2. Discrete element method (DEM)
ψ = − 2.65.
For Re ≤ 1000: In DEM method, each sand particle is simplified as a sphere with
24 [ ( )0.687 ] specific property. The motion of each particle includes translation and
Cd = 1 + 0.15 αf Re (8) rotation, which are controlled by the following formula:
αf Re
dup,i ∑ nc
( )
For Re > 1000: mp = f n,ij + f t,ij + mp g + f d,i (15)
dt j=1
Cd = 0.44 (9)
dωp,i ∑ nc
[ ( )]
When αf ≤ 0.8, Ip = Ri × f n,ij + f t,ij (16)
dt j=1
( ) ⃒ ⃒
αp 1 − αf v ρf αp ⃒uf − up ⃒
β = 150 + 1.75 (10) where mp is the particle mass; up,i and ωp,i are the translational and
αf dp2 dp
angular velocity of particle i, respectively; f n,ij , f t,ij are the normal contact
where Re is the particle-based Reynolds number as follows: force and tangential contact force, respectively; Ri is the vector from the
center of particle i to the contact point; Ip is the rotational inertia of
ρf ⃒⃒ ⃒
Re = uf − up ⃒dp (11) particle; nc is the number of particles in contact with particle i.
v The computation of contact force is based on the contact model be­
To enclose the above N–S equation, it is necessary to introduce the tween particles. The Hertz-Mindlin non-slip softball model proposed by

3
S. Zhang et al. Coastal Engineering 183 (2023) 104334

Fig. 2. Computational settings of the local scour simulation.

Mindlin and Deresiewicz (1953) is applied to calculate the contact force, between the diameter of the coarse grain particle and the original par­
in which the contact force is simplified as the combination of string, ticle is defined as coarse grain ratio (kCG ).
damper, and slipper. The normal and tangential contact forces can be There are three assumptions of the coarse grain method according to
described as follows: the research of Takabatake et al. (2018): i) When the coarse grain par­
ticles collide with each other, all particles in one coarse particle collide
f n,ij = − ks δn − ηun,ij (17)
simultaneously; ii) The displacement and the velocities of the coarse
{ ⃒ ⃒ ⃒ ⃒ grain particles are assumed to be the average of those of the original
− ks δt ⃒− η⃒ut,ij ⃒ ⃒f t,ij ⃒ ⃒ ⃒
⃒ ≤ μ⃒ s f n,ij
f t,ij = ⃒ (18) particles; iii) The contact forces acting on the coarse particles are
− μs f n,ij t f t,ij > μs f n,ij ⃒
⃒ ⃒ ⃒ ⃒ ⃒
calculated by assuming that the kinetic energy of the coarse grain par­
ticles agrees with that of the original particles. The contact forces can be
where the subscripts n and t indicate the normal and tangential direction
calculated by the following formula:
of the tangent plane between two particle spheres, respectively; ks and η
( )
are the stiffness and damping coefficients, respectively; μs is the friction f n,ij,CG = CG3 f n,ij = CG3 − ks δn − ηun,ij (19)
coefficient; δ is the displacement vector between two contacting parti­
{ ⃒ ⃒ ⃒ ⃒
cles; u is the relative velocity vector between two contacted particles; − ks δt ⃒− ηu ⃒ ⃒ ⃒ ⃒
⃒ ⃒ f t,ij,CG = CG3 f t,ij = CG3 ⃒ ≤ μ⃒ s f n,ij,CGM
⃒ n,ij ⃒ f t,ij,CGM ⃒ (20)
and t = ut,ij /⃒ut,ij ⃒ is the unit tangent vector. − μs ⃒f n,ij ⃒t ⃒f t,ij,CGM ⃒ > μs ⃒f n,ij,CGM ⃒

Similarly, the drag force acting on the coarse particle can be derived
2.3. CFD-DEM coupling method
as:
The CFD-DEM coupling simulation is based on the CFDEMcoupling® β ( ) β ( )
f d,CG = Vp,CGM uf − up,CGM = Vp CG3 uf − up = CG3 f d (21)
project from Goniva et al. (2012), which is an object-oriented open-­ αf αf
source coupling Library based on the Linux platform and written in C++
language. Under the CFDEMcoupling® framework, the OpenFOAM® is Where the variables with subscript CG means the parameter of Coarse
used for fluid calculation, and the LIGGGHTS® is used for particles particle.
calculation, CFDEMcoupling® can couple the fluid phase and particle
phase by conducting the interaction force calculation and momentum 3. Numerical model validation
transfer between fluid and particles. The coupling process is summarized
in Fig. 1. 3.1. Numerical model settings

2.4. Coarse grain method The simulation domain is shown in Fig. 2(a). The main part is a
rectangular water flume with a submerged sand box arranged in the
The coarse grain method was used in this research to reduce the mid-rear of it. The sand box is filled with discrete particles to form a sand
computation consumption of the CFD-DEM simulation. A large-sized bed, and a monopile with the diameter (D) equal to 0.04m is located in
particle called coarse grain (CG) particle is used to replace a group of the center of the sand bed. The water flume extends along the x-axis,
particles in the coarse grain method, and the force applied on the with a total length of 60D, of which 50D is located in front of the pile and
original particles is accumulated to the large-sized particle. The ratio 10D is located behind it. The direction of water depth is along the z axis,

4
S. Zhang et al. Coastal Engineering 183 (2023) 104334

Table 1
Summary of the geometry characteristics of the computational mesh.
Characteristics Value or Range

Total number of cells 291,708


Number of cells around the pile perimeter 36
Thickness of cells around the pile perimeter (m) 2 × 10− 3
Size of cells along the x axis (m) 6 × 10− 3
Size of cells along the y axis (m) 6 × 10− 3
Size of cells along the z axis (m) 4.5 × 10− 3

Range of y + on the bottom wall 20–45


Range of y + on the pile wall 13–61

Table 2
Summary of the discretization schemes used for simulation.
Discretization scheme

Time scheme Euler


Gradient scheme Gauss linear
Divergence scheme U: Gauss linearUpwind grad(U) k: Gauss linearUpwind grad
(k)
Laplacian scheme Gauss linear
Interpolation linear
scheme

(ii) At the outlet, zero gradient conditions (∂/∂n = 0) are specified for
Fig. 3. Mesh partition of the simulation domain. all quantities, except for the pressure, which is specified with the
total pressure condition (p0 = 0).
with a total height of 6D, of which 4D is located above the surface of (iii) At the top surface, slip condition (u • n = 0) is specified for u, zero
sand bed and 2D is located below it. And the width of the water flume is gradient conditions are specified for p, νt and k.
5D. (iv) At the pile surface and bottom surface, noslip condition (u • n = 0,
Along the x-axis, the water flume is divided into four sections: the ut = 0) is specified for u, zero gradient condition is specified for p.
preparatory section, transition section, scour section, and tail section. The boundary condition for νt and k is specified using the wall
The preparatory section is 35D long, with a 5 mm thick sediment layer function from OpenFOAM, with nutUSpaldingWallFunction for νt
consisting of discrete particles covering on the bottom, to ensure the and kqRWallFunction for k, respectively.
near-bottom turbulent boundary layer can be fully developed. The (v) At the sidewall surface, symmetry condition is specified for all
transition section is 7.5D long and has a variable cross-section, its bot­ quantities.
tom slope is 15◦ . The height of the water flume gradually increases from
4D to 6D with the increase of the x-axis coordinate, forming a smooth A structured mesh is used to discretize the computational domain, as
transition from the preparatory section to the scour section. The purpose shown in Fig. 3. To facilitate mapping the discrete phase properties into
of the transition section is to reduce the influence of the cross-section the Eulerian phase mesh and improves the numerical stability of CFD-
mutation on the flow field in front of the pile. DEM simulation, it is essential to ensure the particles’ size everywhere
The scour section is 10D long, with the sand box located at the smaller than the size of mesh cell, hence the minimum size of mesh cells
bottom of it. As shown in Fig. 2(b), the sand box contains two types of is limited above 2 mm. The mesh is refined around the pile, the refined
particles with diameters of 1 mm and 2 mm, respectively. The 1 mm area is a 3D diameter cylinder concentric with the pile. Other detailed
particles are placed in the active scour areas near the sediment bed information about the mesh is listed in Table 1.
surface and the pile, while the 2 mm particles are placed in the inactive The limitation of the CFD-DEM model on the minimum grid size
scour areas at the peripheral of the pile and deeper depth. The purpose of restricts the subdivision of the grid near the wall, making it difficult to
this configuration is to reduce the computational cost of the DEM directly analyze the flow in the viscous sublayer and buffer layer of the
simulation without affecting the simulation accuracy. boundary layer. Therefore, in this study, the wall functions were used to
The boundary conditions of the simulation are illustrated in Fig. 2(c), calculate the near-wall flow. The recommended condition for using wall
and the specific settings are as follows. functions is that the non-dimensional distance y+ > 15. From Table 1
and it can be seen that in this model, the y+ on the wall boundary can
(i) At the inlet, the velocities along the y direction and z direction are mostly satisfy the above condition, hence the wall functions are appli­
specified with zero, and the pressure p, turbulent kinetic energy k, cable to this model.
and turbulent viscosity νt are specified with zero gradient condi­ The finite volume method (FVM) was used to solve the governing
tions. The profile of x-direction velocity ux is specified based on equations of hydrodynamics and the discretization schemes used for the
the logarithmic law as follows: simulation are listed in Table 2. The time step for the CFD is determined
( ) by the courant number, and is set to 1 × 10− 3 s. The tim step for the DEM
uf 30z
ux (z) = ln (22) is determined by the Rayleigh time criterion given by GmbH (2014), and
κ Δ
is set to 1 × 10− 5 s. In the following article, several CFD-DEM local scour
where uf is the friction velocity; κ is the von Karman constant, in this simulations are conducted, for a CFD-DEM model with 0.5 million DEM
study, κ = 0.4; Δ is the bed roughness, which is usually taken as 2.5 particles, the average time consumption of 1s simulation is 3 h on the
times the sediment diameter d. AMD EPYC 7H12 with 128 processors.

5
S. Zhang et al. Coastal Engineering 183 (2023) 104334

Fig. 4. Diagram of repose angle test.

Table 3
Repose angles αr under different friction coefficients (μs is slide friction coefficient, μr is roll friction coefficient).
μs μr Accumulation shape αr (◦ ) μs μr Accumulation shape αr (◦ )
0.4 0.1 23.2 0.8 0.1 31.5

0.6 0.1 26.4 0.7 0.125 33.6

0.6 0.125 29.3 0.6 0.2 34.0

0.6 0.15 30.8 0.8 0.2 37.3

3.2. Calibration of the particle-particle contact parameters and behind the pile. Additionally, the slope angle in front of the pile
increases with the angle of repose, which is reasonable since the pit slope
The particle-particle contact parameters in DEM model include the is mainly influenced by the particles’ angle of repose. On the other hand,
slide friction coefficient (μs ) and roll friction coefficient (μr ). The slide the pit slope angle behind the pile decreases as the angle of repose in­
friction coefficient represents the surface roughness of particles, with the creases. This is because the formation of the scour pit behind the pile is
increase of slide friction coefficient, it needs a larger external force to not related to the avalanche of sediment particles. As the scour depth
drive the relative slip between particles, and the friction angle of par­ behind the pile decreases, the slope angle also decreases.
ticles increases correspondingly. The roll friction coefficient is carried It can be seen that the particle-particle contact parameters affect the
out to model the behavior of non-spherical particles, it has been reported morphology of the scour hole, including the scour slope angle and scour
by Ai et al. (2011) that the roll friction coefficient has an unignorable depth, by affecting the particle rest angle. Therefore, when comparing
influence on the accumulation shape of particles, and the friction angle with model experiments, the corresponding contact parameters can be
also increases with the increasing roll friction coefficient. calibrated from Table 3, which benefits the accuracy of scour pit
A numerical test on the angle of repose is designed in this section, it’s morphology prediction a lot.
diagram is shown in Fig. 4. At the beginning of the test, the particles are
initiated and stabilized in the funnel-shaped container; then the baffle at
3.3. Validation of the coarse grain method
the outlet is removed and the particles start to drop toward the rough
plane; finally, a conical accumulation is formed on the plane. The slope
The coarse grain method is used in this section to decrease the
angle of the accumulation is defined as the angle of repose (αr ). Based on
computational resource consumption of the CFD-DEM simulation. To
the results of several numerical tests, Table 3 is established to map the
verify the feasibility of coarse grain method in the CFD-DEM simulation,
contact parameters with the angle of repose, which can provide a
three simulation cases with different CG ratios (kCG = 1, 1.5 and 2) are
approach to calibrate the values of the contact parameters in the DEM
tested under the same working condition. In the case of kCG = 1, the
model by using the realistic angle of repose. From Table 3 it can be seen
coarse grain method is not used, and it is brought out to verify the other
that, with the increase of μs and μr , the angle of repose increases from
cases. Under different kCG , the development of the maximum scour
23.2◦ to 37.3◦ .
depth and the scour pit at the profile y = 0 are compared in Fig. 7 and
To further investigate the relationship between the angle of repose
Fig. 8, respectively.
and the scour pit morphology, three CFD-DEM coupling models with
The development of relative scour depth (S/D) upstream and
different angles of repose (23.2◦ , 33.6◦ , 37.3◦ ) are established. The scour
downstream the pile are shown in Fig. 7(a) and (b), respectively. It can
pit morphologies at profile y = 0 under different angles of repose are
be seen that the time dependent curves of relative scour depth under
shown in Fig. 5. It can be seen that the slope angle in front of the pile
kCG = 1.5 and kCG = 2 approach the same, while compared with the
varies with x/D, especially in the range within 1.5D to the pile center in
condition of kCG = 1, the scour depth is underestimated for 10%~20%
front of pile, where the concentration of horseshoe vortex causes the
using the coarse grain method. However, according to the scour pit
slope angle become larger there. Outside this range, the variation of
morphology at profile y = 0, as shown in Fig. 8, the underestimate of
slope angle becomes much smoother. Therefore, the terrain data within
scour depth is mainly distributed in the area cline to the pile, which only
the area of 1.0D ~1.5D to pile was selected to calculate the slope angle of
owns a small region in the scour pit, and does not affect the global shape
scour pit, as well as the slope angle behind it. The slope angle and
of the scour pit. Hence the difference in the scour depth induced by the
maximum scour depth of the scour pit are plotted in Fig. 6.
coarse grain method is acceptable in this research.
As the angle of repose increases, the frictional resistance between
The coarse grain method will be taken in the following research. By
particles also increases, which makes it more difficult for sediment to
setting kCG as 2, the number of DEM particles can be reduced to 12.5% of
start moving. This results in a decrease in the scour depth both in front of
the original model, which will largely decrease the computational

6
S. Zhang et al. Coastal Engineering 183 (2023) 104334

resource consumption of the CFD-DEM simulation.

3.4. Validation of local scour model

To validate the CFD-DEM method in the simulation of local scour


around the monopile, a CFD-DEM model was established based on the
experimental parameters from Roulund et al. (2005). In the experiment,
the pile diameter (D) is 0.1 m, the median particle size (d50 ) is 0.26 mm,
the bulk flow velocity (Ub ) is 0.46 m/s, and the depth of water (h) is
0.4m. In the CFD-DEM model, the above parameters are modified to
avoid the huge amount of DEM particles, hence ensuring the feasibility
of DEM calculation. Under the premise that the test conditions are
equivalent, the D, d50 , Ub and h are set to 0.04m, 1 mm, 0.66 m/s, and
0.16m, respectively. The detailed parameters settings are shown in
Table 4. In which the equivalence principles come from the research of
Roulund et al. (2005) and are listed as follows:

(i) The same relative velocities (U/Ucr ), or the same relative Shields
numbers (θ/θcr , as shown in Eqs. (23)–(25));
(ii) The relative pile diameters (D/d50 ) that are greater than or equal
to 40, it is indicated by Melville and Sutherland (1988) that when
the ratio D/d50 ≥ 40, the scour depth is almost independent of the
D/d50 ;
(iii) The Reynolds numbers (Re) with the same order of magnitude,
within the same order of magnitude, the difference in Reynolds
numbers can only lead to a small difference in the size of the
horseshoe vortex and therefore can be disregarded.
(iv) The fairly small Froude numbers (Fr), when the value of Fr is
small, the influence of the free water surface is limited, hence the
influence of Fr can be disregarded.

u2f
θ= (23)
g(s − 1)d50

0.3
θcr = + 0.055[1 − exp (− 0.02D∗ )] (24)
1 + 1.2D∗

Where uf is the friction velocity, s = ρs /ρw is the relative density of


sediment, g is the acceleration of gravity, d50 is the median diameter of
Fig. 5. Scour pit morphology at profile y = 0 under different angles of repose. sediment particles, D∗ is the dimensionless diameter of sediment parti­
cles, which can be calculated by the following formula:
[ ](1/3)
(s − 1)g
D∗ = 2
d50 (25)
v
The detailed parameters settings of the CFD-DEM model are listed in
Table 5. With the above parameters settings, the simulation was con­
ducted and run for 200s of real-time, which spends 25 days on the AMD
EPYC 7H12 with 128 processors. The consumption of computational
resource is about 76800 CPU hours, which needs 8.8 years for a single
processor to complete the simulation.
The time scale is the parameter to describe the time consuming of a
physical process. It is essential in the prediction of the monopile local
scour, using which the time dependent development of local scour can
be predicted. Owing to the difference in the dimension between the CFD-
DEM numerical simulation and the experiment, the time scale of the case
in CFD-DEM is about 1/47.1 times that in Roulund’s case. To ensure the
comparability between the time dependent curves of the above two
cases, as showen in Eq. (26), the dimensionless time t∗ by Sumer et al.
(1992) as is used.
[ ]
Fig. 6. Variation of the slope angle and maximum scour depth in front and
3 0.5 − 2
t∗ = t g(s − 1)d50 D (26)
behind the pile under different angles of repose.
Where t ∗ is the dimensionless time, t is the scour time, and D is the pile
diameter.
The relative scour depth (S/D) - dimensionless time (t∗ ) curve in front
of the pile is plotted in Fig. 9. By comparing it with the results of

7
S. Zhang et al. Coastal Engineering 183 (2023) 104334

Fig. 7. Development of the scour depth with different kCG .

Fig. 8. Scour pit morphology at the profile y = 0 with different kCG .

Table 4
Parameters settings of the experiment and CFD-DEM model.
h (m) Ub (m/ uf (m/ θ θcr θ/θcr
s) s)

Roulund et al. 0.4 0.46 0.021 0.105 0.050 2.12


(2005)
CFD-DEM 0.16 0.66 0.040 0.066 0.031 2.12

D d50 D/d50 ◦
αr ( ) Re ( × Fr
(m) (mm) 104 )

0.1 0.26 385 32.7 4.6 0.23


Roulund et al.
(2005)
CFD-DEM 0.04 1 40 33.6 2.64 0

Table 5
The parameters settings of the CFD-DEM model.
Model Parameters value

DEM Number of particles Np 515,966


Particle diameter d50 (m) 0.001
Particle Density ρs (kg/m3) 2 650 Fig. 9. Development of the maximum scour depth in front of the pile.
Poisson’s ratio μ 0.45
Young’s modulus E (Pa) 5 × 106
Coarse grain ratio kcg 2.0 experiment and simulation conducted by Roulund et al. (2005). It can be
Slide friction coefficient μs 0.7 seen that the CFD-DEM model established in this study can precisely
Roll friction coefficient μr 0.125 predict the development of the scour depth and accurately predict the
Time step ΔtDEM (s) 1 × 10− 5 equilibrium relative scour depth of ds /D = 1.2. It can also be seen that,
CFD Fluid density (kg/m3) 1 000 the development of scour depth can be divided into the following three
Viscosity (m2/s) 1.002 × 10− 3
stages:
Mean flow velocity (m/s) 0.66
Flow depth (m) 0.16
Reynolds number of pile 2.64 × 104
(i) The initial stage: when t ∗ ≤ 1.3, the scour depth in front of the
Time step ΔtCFD (s) 1 × 10− 3 pile increased rapidly, reaching almost 2/3 of the equilibrium
scour depth within 1/7 of the equilibrium scour time;

8
S. Zhang et al. Coastal Engineering 183 (2023) 104334

Fig. 10. Development of the scour pit morphology at the profile y =


0 over time.

Fig. 12. Comparison of the vertical profiles of the dimensionless Reynolds


stress R = uUu2 at the end of pre-simulation between CFD-DEM model and
′ ′

DNS model.

4. Results and discussion

4.1. Flow field around the pile

A pre-simulation is conducted to provide sufficient time for the


turbulent boundary layer fully develop. During this stage, the DEM
particles are frozen, and their velocity and external forces are set to 0.
However, momentum transfer from the particles to the flow remains
effective.
Fig. 11. Vertical profiles of the mean relative horizontal velocity 〈Ux 〉/ U at the The presence of particles induces near-bottom turbulence, causing
location 0.8 m upstream of the pile at different times. the thickening of the turbulent boundary layer during pre-simulation.
Fig. 11 shows the curves of the mean relative horizontal flow velocity 〈
(ii) The deceleration stage: when 1.3 < t ∗ ≤ 7, the development rate Ux 〉/Ub distribution along the depth measured 0.8 m upstream of the pile
of the scour depth decreased gradually with time. Compared with at different times. The curves indicate that the development of flow
the initial stage, the time consumption to reach a certain incre­ velocity distribution is processed rapidly within the initial 5 s and then
ment of scour depth was greatly increased. And because of the tends to slow down, and the vertical profile of flow velocity increasingly
repetitive process of "Pile toe erosion-Slope avalanche" (which converged to the logarithmic law. Finally, the vertical profile of flow
will be discussed in 4.2), the scour depth also fluctuated with velocity appeared to stabilize after 40 s, hence the pre-simulation was
time; stopped after that time.
(iii) The equilibrium stage: when t ∗ > 7, the maximum scour depth To further validate the results of the pre-simulation, the distribution
had nearly reached equilibrium, and the development of local of Reynolds stress (R) along the depth at the final moment of the pre-
scour pit in front of the pile tended to stop. simulation was compared with the data obtained by Kempe et al.
(2014), who utilized the direct numerical simulation (DNS) method and
The development of scour pit morphology at profile y = 0 is plotted the submerged boundary method to investigate the flow field in the open
in Fig. 10. It can be observed that at the initial stage, when t∗ = 0.4, the channel with a sandy bottom. The comparison of Reynolds stress be­
scour pit in front of the pile had already taken shape, and the sediment tween the results of our research and DNS simulation is shown in Fig. 12.
accumulation behind the pile had appeared. The scour depth increased It is proved that the values and distribution of Reynolds stress of
with the enlargemnet of scour pit over time, and it was observed that the CFD-DEM simulation are both consistent with the results of DNS simu­
scour depth in front of the pile was consistently greater than that behind lation, which shows the accuracy of the turbulent flow field in the
the pile; By t∗ = 8, the development of the scour pit in front of the pile pre-simulation.
had nearly reached equilibrium, while the scour behind the pile was still After the pre-simulation, the local scour simulation was conducted.
very active. Between t∗ = 8 and t ∗ = 16, the scour depth in front of the Fig. 13 displays the vertical profiles of the relative horizontal flow ve­
pile only increased by 4%, while the scour depth behind the pile locity 〈Ux 〉/U, the sediment particle fraction αp , and the sediment par­
increased by nearly 22%. ticle velocity Us when t∗ = 4, t ∗ = 8, t ∗ = 16 at three locations around
In summary, the CFD-DEM method can accurately predict the the pile, specifically, in front of the pile, to the side and front of the pile,
development of local scour around the pile. Compared with the tradi­ and behind the pile. In front of the pile, where x/D = − 0.75, we use the
tional numerical simulation method, it is able to provide more location where αp = 0.01 to represent the water-sediment interface
comprehensive insight into the sediment’s initiation and movement (indicated by the dotted line in Fig. 13), above the interface, the flow
during the local scour process, This detailed information will be dis­ velocity is positive and follows a similar distribution pattern at different
cussed in sections 4.2 and 4.3, and it can aid in conducting more thor­ times, and there is no sediment particle here, so it’s velocity is 0. Below
ough investigations into the local scour mechanism around the pile. the interface, the downward flow in front of the pile drives the formation

9
S. Zhang et al. Coastal Engineering 183 (2023) 104334

Fig. 13. Vertical profiles of relative mean horizontal velocity 〈Ux 〉/U, particles’ volume fraction αp and sediment particles’ velocity Us at different locations around
the pile when t ∗ = 4, t ∗ = 8, and t ∗ = 16.

of the horseshoe vortex, with its peripheral flow moving in the direction vortex. Moreover, at all times, the flow velocity fluctuated along the
away from the pile, leading to the negative flow velocity. And the water depth due to the asynchronous shedding of the wake vortex.
sediment particle fraction increases with the decrease of z/H, until Concerning the sediment particle velocity, two peaks appear on the
reaching a steady value of around 0.55. Within the sediment layer be­ velocity curve when t∗ = 8, they were located above and below the
tween αp = 0.01 and αp = 0.55, the sediment particle velocity initially water-sediment interface, representing the suspended load and bedload
increases and then decreases with the decrease of z/H, the maximum components of sediment transportation, respectively. When t ∗ = 16, the
sediment particle velocity occurs below the water-sediment interface, peak of the sediment velocity curve appeared to be slightly higher than
indicating that bedload is the primary form of sediment transportation. the water-sediment interface, indicating a tendency of the trans­
To the side and front of the pile, where x/D = − 0.53 and y/D = − 0.55, formation from bedload to suspended load. Hence, behind the pile, the
the flow velocity below the water-sediment interface increases signifi­ suspended load is active during the development stage of scour process.
cantly compared with that in front of the pile, resulting in higher sedi­ To visualize the cohesive vortex structure surrounding the pile, we
ment particle velocity and the fluctuation of sediment particle fraction have employed the Q-criterion, which involves calculating the second-
near the water-sediment interface. order invariant of the velocity gradient tensors using Eq. (27). This
Behind the pile, where x/D = 0.75, significant differences are criterion identifies regions with positive Q values as being dominated by
observed. Regarding the flow velocity, when t∗ = 4, negative velocity vorticity, while regions with negative Q values are dominated by strain
occurred at the location z/H > 0.18 due to the backflow of the wake rate. By plotting the iso-surface of Q values, we can visualize the vortex

10
S. Zhang et al. Coastal Engineering 183 (2023) 104334

wake vortex, The wake vortex was elongated in length and its shedding
frequency experiences a significant decrease. And with the further
decrease of z/D, the influence of sediment particles further increased,
and the vortex structure turned from regular to irregular.
The CFD-DEM method can depict the seepage behavior inside sedi­
ment, which is often neglected in other simulation methods. Fig. 16 il­
lustrates the seepage field at the x = 0 profile at different times,
revealing that the seepage starts from the scour pit’s bottom, where the
pressure concentrates due to the horseshoe vortex. The pressure drives
the flow to seep horizontally away from the pile’s periphery, exhibiting
varied seepage patterns at different depths. In the shallow layer, the flow
maintains high vorticity, thus rotating and seeping out of the sediment
surface after a certain horizontal displacement. In contrast, the deeper
layer experiences lower vorticity and is driven by gravity to seep deeper
during horizontal movement.
Fig. 17 illustrates the relative vertical drag force Fd,z /Fg acting on
individual particles in the early stage of scour. The maximum vertical
drag force attained a magnitude equivalent to that of gravity, and the
closer a particle is to the water-sand surface, the greater the vertical drag
force acting on it. This vertical drag force diminishes part of the gravity
acting on sediment particles, making them easier to start up. Hence the
seepage-induced vertical drag force can be a crucial factor in the early
Fig. 14. Coherent structure of vortex structure around the pile. stage of local scour.

regions, as depicted in Fig. 14. 4.2. Development of local scour pit


1 ( ⃒ ⃒ ⃒ ⃒)
Q = ⃒Ωij ⃒ − ⃒Sij ⃒ (27) In this section, the morphological characteristics and development
2
process of the local scour pit under steady current are investigated and
Where Ωij is the magnitude of vorticity tensor, Sij is the magnitude of discussed in detail, as well as the mechanism of sediment particles
strain-rate tensor. The calculation formula of Ωij , Sij are as follows: movement behind the development of the scour pit.
( ) In the initial period of the local scour process, the morphology of the
1 ∂ui ∂uj
Ωij = − (28) scour pit in front of the pile obtained by CFD-DEM simulation is
2 ∂xj ∂xi
compared with the simulation results obtained by Nagel et al. (2020).
( ) Under the same relative scour depth, the comparison of scour pits be­
1 ∂ui ∂uj
Sij = + (29) tween the CFD-DEM model and the Euler-Euler two-phase flow model is
2 ∂xj ∂xi
presented in Fig. 18, the black lines represent the sediment surface ob­
Behind the pile, the alternately shedding of the wake vortex and the tained from the Euler-Euler multiphase flow simulation, and the colored
unregular near-bottom vortex due to the interaction between water and particles represent the results obtained from the CFD-DEM simulation.
sediment particles can be observed in Fig. 14. With the development of Fig. 18 reveals that both models share a common feature of scour pit: a
the flow field, the wake vortex behind the pile entered the stable platform with a width of roughly 0.2D in front of the pile, and the
shedding state, as depicted in Fig. 15 which displays the plane distri­ maximum scour depth occurs at the position of about 0.1D from the pile
bution of vorticity at different relative water depths z/D. It is observable wall. Outside the platform, as the distance from the pile increases, the
that at z/D = 2 and z/D = 4, the wake vortex shaded regularly and slope angle of the scour pit initially increases and then decreases before
alternately. Based on the flow velocity and the distance between vortex eventually stabilizing. The comparison results show that the two models
cores, the period of vortex shedding can be calculated as Lcore / U = produce comparable results in terms of scour morphologies and
0.283s, which is in agreement with the result estimated by the Strouhal maximum scour depths, providing further validation for the CFD-DEM
number D/(St • U) = 0.303s. At z/D = 1, the stable vortex shedding can method’s accuracy.
no longer maintain due to the interaction between flow and sediment Fig. 19 illustrates the elevation distribution of the scour pit at
particles behind the pile, which significantly affected the flow pattern of different times. When t∗ = 0.4, the maximum scour depth had reached
nearly 50% of the equilibrium scour depth only in the initial 2.5%

Fig. 15. Graph of vorticity at the profiles vertical to z axis at different z/D.

11
S. Zhang et al. Coastal Engineering 183 (2023) 104334

Fig. 16. Seepage field at the x = 0 profile at different times.

duration of the scour process. And the scour pit to the side and front of at the position about 0.75 times the pile diameter from the pile center.
the pile had initially formed, with a shape similar to the horseshoe and This phenomenon can be more clearly observed through the slope angle
symmetric about the x-z plane. The maximum scour depth was located of the terrain, as shown in Fig. 20. For the sake of description, we define
in the position adjacent to the outer surface of the pile where the center the distance to the pile center as R. In the region of R < 0.6Dp , the slope
angle β is approximately 45◦ . When t∗ = 2, the area of scour pit angle is small and the surface of scour pit is nearly flat; In the region of
expanded significantly, the scour pit not only developed toward the 0.6Dp < R < 0.9Dp , the slope angle increases significantly, with the
periphery of the pile but also developed toward the back of the pile. As maximum slope angle reaching 70◦ , far exceeding the angle of repose
the scour pit continued to develop, when t∗ = 8, the scour pit had αr = 33◦ , in this region, the friction between sediment particles can no
already connected behind the pile, and the wake flow drove the scour pit longer maintain the stability of particles, the slope avalanche as shown
to extend downstream along the x-axis, causing the shape of scour pit in Fig. 21 occurred under the drive of gravity.
turning from the horseshoe-shaped to the spoon-shaped. In front of the pile, the evolution of scour pit morphology and the
It can be observed that with the development of scour, as shown in velocity vectors of sediment particles at the profile y = 0 are illustrated
Fig. 19(c) and (d), there is a rapid change in the elevation of the scour pit in Fig. 21. Fig. 21(a) shows the slope avalanche caused by excessive

12
S. Zhang et al. Coastal Engineering 183 (2023) 104334

Fig. 17. Relative vertical drag force Fd,z /Fg acting on particles due to seepage at the profile x = 0 at different times.

to an increase in the slope angle, which in turn triggers the slope


avalanche. Then, during the slope avalanche, the sediment particles
separate from the slope move downward and supply into the pile toe,
resulting in the decrease of scour depth and the enlargement of scour pit.
Subsequently, the sediment at the pile toe continues to experience
erosion, then the above process repeats, resulting in the fluctuating
growth of scour depth and the enlargement of scour pit. Similar sedi­
ment movement mechanisms had been brought out in the studies by
Roulund et al. (2005) and Nagel et al. (2020), who suggested that the
erosion at the pile toe is responsible for the deepening of scour pit, while
the slope avalanche is responsible for the sediment transportation from
the periphery to the pile toe and the enlargement of scour pit.
The scour pit morphology and its formation mechanism on the pile
side have key differences from those in front of the pile. Fig. 22 illus­
trates the evolution of scour pit morphology at the profile x = 0, as can
be observed, a terrain mutation appeared on the slope of the scour pit,
with the slope angle greater than 90◦ , which is significantly larger than
the angle of repose. However the slope avalanche did not happen in this
area. It is believed that the maintenance of this special scour
morphology is related to the additional force provided by the water-
sediment interaction, and its formation mechanism is illustrated in
Fig. 23.
The formation process of the above scour morphology can be
concluded as the “Push-Accumulation-Wash” process, with the expla­
nations as follows.

(i) Push: As shown in Fig. 23(a), in the plane perpendicular to the x


direction, the bottom flow of the horseshoe vortex pushed the
sediment on the bottom of scour pit to move outward along the
surface of scour pit;
(ii) Accumulation: With the increase of the slope angle, the sediment
particles received greater resistance, which made them stop and
accumulated on the surface of scour pit. The accumulation body
was located at 0.3 ∼ 0.6 Dp from the pile wall, with the width
equal to 0.3 Dp and the height equal to 0.5 Dp ;
(iii) Wash: In the accumulation body, the interaction forces between
particles were much lower because the gravity is partly balanced
by the force from the bottom flow, the resistance acting on par­
ticles was lower accordingly, hence making the sediment easier to
start up. As shown in Fig. 23(b), when the concentrated flow on
Fig. 18. Comparison of the scour pit profile y = 0 in front of the pile at the the pile side passed through the accumulation body, a large
initial stage of local scour.
amount of sediment is carried by concentrated flow and removed
from the scour hole, forming a motion trajectory as shown in the
slope angle, and Fig. 21(b) shows the sediment supplement from the white curve frame.
slope avalanche and the erosion at pile toe. It is observed that during the
development of scour, the slope avalanche and the scour at the pile toe The "Pile toe erosion-Slope avalanche" process reveals the mecha­
occur alternately. Firstly, the increase in scour depth at the pile toe leads nism of sediment transportation in front of the pile, while the "Push-

13
S. Zhang et al. Coastal Engineering 183 (2023) 104334

Fig. 19. Eevation of the scour pit around the pile at different times.

Fig. 20. Slope angle of scour pit around the pile under different times.

Accumulation-Wash" process explains the mechanism of sediment 4.3. The sediment flux – shields number relationship curve
transportation besides the pile side. Among which the "Push-Accumu­
lation-Wash" process is firstly observed in the existing studies, this may The sediment flux - Shields number relationship curve is an impor­
be a special phenomenon that occurs under larger sediment particle tant component of the sediment transport model. However, in the CFD-
sizes, but due to the lack of the mesoscopic data of sediment movement DEM model, the sediment flux and Shields number parameters, which
during the local scour process, the correctness and universality of this are applicable to the assumption that the seabed is continuous, can’t be
phenomenon remain to be verified. directly extracted due to the discrete nature of the DEM particles.
Therefore, in this section, a conversion method is proposed to convert
particle velocity, drag force, particle phase fraction, and other

14
S. Zhang et al. Coastal Engineering 183 (2023) 104334

Fig. 21. Evolution of the scour pit morphology and the velocity vectors of sediment particles at y = 0 profile in front of the pile.

Fig. 22. Evolution of the scour pit morphology and the velocity vectors of sediment particles at x = 0 profile beside the pile.

parameters of discrete phase into the continuous phase parameters such Shields number, the sediment flux is integrated along the depth z to
as sediment flux and Shields number, and based on this, the relationship obtain the depth-integrated sediment flux. The dimensionless calcula­
between sediment flux and Shields number is analyzed and quantified. tion formulas for the total sediment flux and the bedload sediment flux
Based on the drag force applied on each particle, the Shields number are shown in Eq. (31) and Eq. (32), respectively.
at the water-sand interface can be calculated, where the water-sand ∫ / √̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅
⃦ ⃦
interface is defined as the equivalent surface with αp = 0.7. In the q∗ = ⃦αp up • t⃦dz (s − 1)gd350 (31)
calculation process, the sediment region was sliced in the x-y plane and
divided into several calculation cells. For each calculation cell, the ∫
⃦ ⃦
/ √̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅
average Shields number is calculated using Eq. (30). Here, q∗b = ⃦αp up,b • t⃦dz (s − 1)gd350 (32)

∬ f d • tdSα /Sα ⃒αp =α0 converts the drag forces on the water-sand interface
in each calculation cell into the tangential forces parallel to the water- Where q∗ is the dimensionless total sediment flux, q∗b is the dimension­
sand interface and integrates them to the total tangential force. Based less bedload sediment flux, up is the velocity vector of particles, up,b is
on this, the average shear stress is obtained by dividing the total the velocity vector of particles with z ≤ 0.
tangential force to the area of the water-sand interface. Fig. 24 shows the distributions of the Shields number, total sediment
⃦ ∫∫
⃦ / ⃒ ⃦
⃦ flux, and bedload sediment flux at the x-y plane when t∗ = 0.4 and t ∗ =
u2f τ2 ⃦ f d • tdSα Sα ⃒αp =α0 ⃦ 2.0. It can be seen that around the pile, the distribution of sediment flux
θ= = = ( ) (30)
g(s − 1)d50 gρf (s − 1)d50 g ρ − ρf d50 and Shields number exhibit similar patterns, a circular ring around the
pile with the maximum values located behind the side of the pile. And
Where θ is the Shields number, θcr is the critical Shields number, f d is the influenced by the high-pressure gradient at the pile toe and the wake
vector of drag force, t is the tangential vector on the water-sand surface, vortex at the pile tail, the circular ring is broken at the pile toe and tail,
αp is the volume fraction of sediment particles, α0 is the critical sediment respectively. This pattern is particularly visible in the bedload sediment
particles’ volume fraction on the water-sand surface, and Sα is the area flux distribution but is weakened in the total sediment flux distribution
of the water-sand surface in the calculation cell. due to the interference of the suspended load.
The sediment flux can be obtained by calculating the average ve­ When t ∗ = 0.4, it can be seen from Fig. 24(c) and (e) that, a signif­
locity and volume fraction of particles in each CFD grid, but the sedi­ icant increase in the sediment flux at the pile tail occurred due to the
ment flux obtained in this way is a three-dimensional distributed emergence of the suspended load. However, due to the differences in the
variable. To make it comparable with the two-dimensional distributed motion mechanisms between suspended load and bedload sediment, as

15
S. Zhang et al. Coastal Engineering 183 (2023) 104334

Fig. 23. Forming mechanism of the scour pit morphology at x = 0 profile beside the pile.

shown in Fig. 24(a) and (c), no clear correlation was observed between sediment flux and the Shields number around the pile at different times
the Shields number and the total sediment flux at the pile tail. Therefore, before the scour reached equilibrium (t∗ < 7). According to Eq. (33), the
this study focuses on the bedload sediment flux and its relationship with fitting between the above two parameters was conducted, and the
the Shields number rather than the suspended load sediment flux. When empirical parameters a and b are fitted to 19.8 and 2, respectively, with
t ∗ = 2.0, the maximum Shields number and sediment flux around the the fitted curve plotted as the solid line in Fig. 26. In the research of
pile decreased compared with that when t∗ = 0.4, and their distribution Nagel et al. (2020), the ranges of a and b were estimated as 26.14–31.06
also changed. Comparing Fig. 24(a), (b), (e), and (f), it can be seen that and 1.57–2.09, respectively, which are in good accordance with the
the location of the maximum Shields number and bedload sediment flux results obtained in this research. The curves with a = 40, b = 2 and a =
moved downstream with time, which was consistent with the down­ 10, b = 2 are also plotted in Fig. 26 with dotted lines to represent the
stream extension of the scour pit. upper boundary and lower boundary of data points. It can be seen that
The MPM formula is a kind of bedload sediment flux equation based the curve of a = 10, b = 2 is a suitable lower boundary. And for the
on the experimental data, which is brought out by Meyer-Peter and upper boundary, the curve of a = 40, b = 2 can cover most of the data
Müller (1948). It can describe the relationship between the bedload points with θ ≥ 0.15, while for the data points with θ < 0.15, the curve
sediment flux and the Shields number, with the standard formation as tends to underestimate the sediment flux, especially for the data points
Eq. (33), in which the parameters a and b are empirically dependent on with lower Shields number that approaches the critical Shields number.
the experimental data, the values of a and b in previous studies are listed The possible reason is the ignorance of the effect of the slope angle. On
in Table 6. the slope of scour pit surface, the gravity component along the slope
makes the sediment particles easier to be started up. Under a low Shields
q∗b = a(θ − θcr )b (33) number, the bed shear stress acting on the sediment is much lower,
hence the effect of gravity increases relatively. This leads to a more
Where θ is the Shields number, θcr is the critical Shields number, a and b
significant increase in sediment flux due to gravity.
are the empirical parameters.
The Shields number and the dimensionless bedload sediment flux
4.4. Discussion of the CFD-DEM method
were sampled from the points in the scour active area. The specific
sampling locations are shown in Fig. 25. Based on the sediment flux
4.4.1. Advantages of the CFD-DEM method
distribution in Fig. 24, most of the sampling points are arranged behind
The biggest advantage of the CFD-DEM method is that it treats the
the side of the pile. Because these locations have high values of sediment
sediment as a discrete phase and uses the discrete element method
flux and Shields number, hence can cover a wider range of the sediment
(DEM) to calculate the movement of sediment particles. Therefore, it is
flux and Shields number, which makes them more representative.
capable of analyzing the motion and forces of each sediment particle,
Considering the complexity of the sediment initiation mechanism under
and based on this, we can analyze the individual and collective dynamic
the influence of vortex shedding, as shown in the dark area, the wake
characteristics of sediment particles, which can help us to understand
area was avioded in the selection of sampling points.
the mesoscopic mechanism of the local scour. Secondly, the CFD-DEM
Fig. 26 shows the sampled data of the dimensionless bedload
method can capture the behaviors such as collision, cohesion,

16
S. Zhang et al. Coastal Engineering 183 (2023) 104334

Fig. 24. Distribution of Shields number, dimensionless integrated depth total sediments flux, and integrated depth bedload sediments flux at the water-sand surface.

coordination between the calculation efficiency and accuracy, which is


Table 6 also pointed out in the research by Liu et al. (2022). For the un-resolved
The values of empirical parameters a and b in previous studies. CFD-DEM method, in order to map the discrete phase properties into the
Researchers a b Eulerian phase mesh and improve the numerical stability of simulation,
Meyer-Peter and Müller (1948) 8 1.5 the size of CFD grid cells should be larger than the size of sediment
Wong and Parker (2006) 3.97–4.93 1.5–1.6 particle, which means that the CFD grid near the wall can’t be finely
Nagel et al. (2020) 26.14–31.06 1.57–2.09 divided, the near-wall flow needs to be estimated using the wall func­
This research 19.8 2
tions, and some flow details inside the boundary layer may be ignored.
This may bring unavoidable errors to the local scour simulation around
separation, and so on between sediment particles, which is helpful in the pile. For the resolved CFD-DEM method, the immersed boundary
achieving a more accurate simulation of the seabed evolution during the method is used to resolve the shape of each particle, which requires the
local scour. Furthermore, the CFD-DEM method can specify random size of CFD grid cells to be less than 1/10 times the particle diameter.
non-uniform particle properties for the discrete phase, hence can The required number of cells in the CFD grid is so huge that even the
simulate the scour in non-uniform and layered sediment conveniently. simulation containing hundreds of particles also needs a long time to
Overall, the CFD-DEM method provides a tool for simulating and complete.
revealing the microscopic phenomena of sediment motion in the process Currently, research on local scour problems is mainly based on the
of sediment transportation and has great potential in the study of local un-resolved CFD-DEM method. However, how to carry out efficient
scour mechanisms. cross-scale simulation has always been an unresolved problem.
Although the coarse grain method and the enlargement of particle size in
4.4.2. Limitations of the CFD-DEM method the lower layer of sediment are helpful in reducing the number of
However, due to the incomplete development of the CFD-DEM sediment particles, the consumption of computational resources to
coupling algorithm and the limitations of the DEM method itself, the simulate the whole process of local scour is still very high.
main limitation of the CFD-DEM method is the difficulty to achieve the Therefore, the authors believe that in the research of local scour

17
S. Zhang et al. Coastal Engineering 183 (2023) 104334

uses CFD to solve the flow of water and DEM to calculate the movement
of sediment particles. To enhance computational efficiency, the study
employed the coarse grain method in the CFD-DEM simulations, which
reduced computational resource consumption by 87.5% while main­
taining accurate results in local scour simulation. Furthermore, this
study investigated the relationship between the scour pit morphology
and the angle of repose, it’s pointed out that, inside the scour pit, the
slope angle and scour depth are closely related to the angle of repose,
which is determained by the contact parameters between DEM particles.
Therefore, in order to improve the accuracy in the prediction of scour pit
morphology, a numerical test of the angle of repose is proposed in this
study, and the angle of repose is used to calibrate the contact parameters
between DEM particles.
Through the time dependent curves of scour depth in front of the
pile, it is observed that the CFD-DEM model can accurately predicted the
equilibrium scour depth obtained from exprimentand reproduced the
three stages of scour depth development, including the initial stage,
deceleration stage, and equilibrium stage. And the scour pit morphology
is also in good agreement with that obtained from Euler-Euler two-phase
flow simulation, Therefore, the CFD-DEM model has been validated to
be effective in the simulation of local scour around monopile.
Through analyzing the simulation results of the CFD-DEM model
established above, the following conclusions about the local scour
around the monopile can be drawn.

i). The seepage-induced vertical drag force is a crucial factor in the


Fig. 25. Sampling locations of sediment flux and Shields number. early stage of local scour. In the early stage of local scour, due to
the seepage inside the sediment, the maximum vertical drag force
acting on the sediment particles can reach 0.2 times the gravity,
which diminishes part of the gravity acting on sediment particles,
and makes them easier to start up;
ii). Under the working condition in this study, the "Pile toe erosion-
Slope avalanche" process is the main mechanism of sediment
transportation in front of the pile. And the "Push-Accumulation-
Wash" process is the main mechanism of sediment transportation
beside the pile. Among which the "Push-Accumulation-Wash"
process is firstly observed in the existing studies, this may be a
special phenomenon that occurs under larger sediment particle
sizes, but due to the lack of the mesoscopic data of sediment
movement during the local scour process, the correctness and
universality of this phenomenon remains to be verified;
iii). The relationship between the bedload sediment flux and Shields
number can be quantified using the MPM formula, in this study,
the empirical parameters a and b are fitted to 19.8 and 2 in the
MPM formula, respectively, which are in good accordance with
the results obtained by Nagel et al. (2020). However, the bedload
sediment flux was always underestimated at a low Shields num­
ber, which is because of its neglect of the additional sediment
transportation induced by gravity.
Fig. 26. Relationship curve between the dimensionless bedload sediment flux
and Shields number.
At present, the main limitation of the CFD-DEM method is the dif­
ficulty to achieve the coordination between the calculation efficiency
around the pile, a potential application of the CFD-DEM method is to and accuracy. The cross-scale simulation based on the CFD-DEM method
explore the mesoscopic mechanism of scour based on small-scale is very expensive for the current computing power. In this research,
simulation. This means using a DEM simulation domain with a size although some methods were taken to reduce the number of sediment
much smaller than the pile size to investigate the mesoscopic mechanism particles in CFD-DEM simulation, its consumption of computational
of the scour in a certain location around the pile. The small-scale char­ resources to simulate the whole process of local scour was still very high.
acteristic can reduce the number of particles and allow the size of par­ In the future, a potential application of the CFD-DEM method is to
ticles to be smaller, hence the CFD grid division near the wall can be explore the mesoscopic mechanism of scour based on the small-scale
finer, and the balance between computational efficiency and accuracy simulation, some work relevant to this has recently been brought out
can be obtained. by Yazdanfar et al. (2021) and more applications of the CFD-DEM
method are yet to be discovered.
5. Conclusion
Author credit statement
In this study, a three-dimensional CFD-DEM coupled model was
developed to simulate the local scour around the monopile. This model
Shuye Zhang: Conceptualization, Methodology, Investigation,

18
S. Zhang et al. Coastal Engineering 183 (2023) 104334

Software, Validation, Dates analysis, Writing – original draft. Boen Li: Muktiphas Flow 58, 214–235. https://doi.org/10.1016/j.
ijmultiphaseflow.2013.09.008.
Methodology, Investigation, Software, Dates analysis. Huihuan Ma:
Liu, X., García, M.H., 2008. Three-dimensional numerical model with free water surface
Investigation, Writing – review & editing, Visualization, Funding and mesh deformation for local sediment scour. J. Waterw Port Coast. 134 (4),
acquisition, Resources, Supervision. 203–217. https://doi.org/10.1061/(ASCE)0733-950X(2008)134:4(203).
Liu, Q., Wang, Z., Zhang, N., Zhao, H., Liu, L., Huang, K., Chen, X., 2022. Local scour
mechanism of offshore wind power pile foundation based on CFD-DEM. J. Mar. Sci.
Declaration of competing interest Eng. 10 (11), 1724. https://doi.org/10.3390/jmse10111724.
Mao, Y., 1988. The Interaction between Vibrating Pipe and Erodible Bed. Technical
The authors declare that they have no known competing financial University of Denmark, Lyngby, Denmark.
Melville, B.W., Sutherland, A.J., 1988. Design method for local scour at bridge piers.
interests or personal relationships that could have appeared to influence J. Hydraul. Eng. 114 (10), 1210–1226. https://doi.org/10.1061/(ASCE)0733-9429
the work reported in this paper. (1988)114:10(1210).
Meyer-Peter, E., Müller, R., 1948. Formulas for Bed-Load Transport. IAHSR 2nd meeting.
Stockholm, appendix 2. http://resolver.tudelft.nl/uuid:4fda9b61-be28-4703-ab06
Data availability -43cdc2a21bd7.
Mindlin, R.D., Deresiewicz, H., 1953. Elastic spheres in contact under varying oblique
The authors do not have permission to share data. forces. J. Appl. Mech. 20 (3), 327–344. https://doi.org/10.1115/1.4010702.
Nagel, T., Chauchat, J., Bonamy, C., Liu, X., Cheng, Z., Hsu, T.-J., 2020. Three-
dimensional scour simulations with a two-phase flow model. Adv. Water Resour.
Acknowledgment 138, 103544 https://doi.org/10.1016/j.advwatres.2020.103544.
Olsen, N.R., Melaaen, M.C., 1993. Three-dimensional calculation of scour around
cylinders. J. Hydraul. Eng. 119 (9), 1048–1054. https://doi.org/10.1061/(ASCE)
This research was supported by the National Key R&D Program of
0733-9429(1993)119:9(1048).
China (grant no. 2021YFC3100800, 2021YFC3100803), and Natural Prendergast, L.J., Hester, D., Gavin, K., O Sullivan, J.J., 2013. An investigation of the
Science Foundation of Guangdong Province of China (grant no. changes in the natural frequency of a pile affected by scour. J. Sound Vib. 332 (25),
2023A1515011022). 6685–6702. https://doi.org/10.1016/j.jsv.2013.08.020.
Roulund, A., Sumer, B.M., Fredsøe, J., Michelsen, J., 2005. Numerical and experimental
investigation of flow and scour around a circular pile. J. Fluid Mech. 534, 351–401.
References https://doi.org/10.1017/S0022112005004507.
Sheppard, D.M., Melville, B., Demir, H., 2014. Evaluation of existing equations for local
Amoudry, L., Hsu, T.-J., Liu, P.-F., 2008. Two-phase model for sand transport in sheet scour at bridge piers. J. Hydraul. Eng. 140 (1), 14–23. https://doi.org/10.1061/
flow regime. J. Grophys. Res-Oceans 113 (C3). https://doi.org/10.1029/ (ASCE)HY.1943-7900.0000800.
2007JC004179. Smagorinsky, J., 1963. General circulation experiments with the primitive equations: I.
Ai, J., Chen, J., Rotter, J.M., Ooi, J.Y., 2011. Assessment of rolling resistance models in The basic experiment. Mon. Weather Rev. 91 (3), 99–164. https://doi.org/10.1175/
discrete element simulations. Powder Technol. 206 (3), 269–282. https://doi.org/ 1520-0493(1963)091<0099:GCEWTP>2.3.CO;2.
10.1016/j.powtec.2010.09.030. Song, S., Park, S., 2022. Unresolved CFD and DEM coupled simulations on scour around a
Baykal, C., Sumer, B.M., Fuhrman, D.R., Jacobsen, N.G., Fredsøe, J., 2017. Numerical subsea pipeline. J. Mar. Sci. Eng. 10 (5), 556. https://doi.org/10.3390/
simulation of scour and backfilling processes around a circular pile in waves. Coast jmse10050556.
Eng. 122, 87–107. https://doi.org/10.1016/j.coastaleng.2017.01.004. Song, Y., Xu, Y., Ismail, H., Liu, X., 2022. Scour modeling based on immersed boundary
Chabert, J., Engeldinger, P., 1956. Etude Des Affouillements Autour Des Piles De Ponts. method: a pathway to practical use of three-dimensional scour models. Coast Eng.
Laboratoire National d’Hydraulique, Chatou, France. 171, 104037 https://doi.org/10.1016/j.coastaleng.2021.104037.
Chen, X., Li, Y., Niu, X., Li, M., Chen, D., Yu, X., 2011. A general two-phase turbulent Sumer, B.M., Christiansen, N., Fredsoe, J., 1992. Time Scale of Scour Around a Vertical
flow model applied to the study of sediment transport in open channels. Int. J. Pile. The Second International Offshore and Polar Engineering Conference, San
Multiphas. Flow 37 (9), 1099–1108. https://doi.org/10.1016/j. Francisco, USA.
ijmultiphaseflow.2011.05.013. Takabatake, K., Mori, Y., Khinast, J.G., Sakai, M., 2018. Numerical investigation of a
Cheng, Z., Hsu, T.J., Calantoni, J., 2017. SedFoam: a multi-dimensional Eulerian two- coarse-grain discrete element method in solid mixing in a spouted bed. Chem. Eng. J.
phase model for sediment transport and its application to momentary bed failure. 346, 416–426. https://doi.org/10.1016/j.cej.2018.04.015.
J. Coast Eng. 119, 32–50. https://doi.org/10.1016/j.coastaleng.2016.08.007. Wang, X., Zeng, X., Li, J., Yang, X., Wang, H., 2018. A review on recent advancements of
Durán, O., Andreotti, B., Claudin, P., 2012. Numerical simulation of turbulent sediment substructures for offshore wind turbines. Energy Convers. 158, 103–119. https://doi.
transport, from bed load to saltation. Phys. Fluids 24 (10), 103306. https://doi.org/ org/10.1016/j.enconman.2017.12.061.
10.1063/1.4757662. Wong, M., Parker, G., 2006. Reanalysis and correction of bed-load relation of Meyer-
Gautam, S., Dutta, D., Bihs, H., Afzal, M.S., 2021. Three-dimensional computational fluid Peter and Müller using their own database. J. Hydraul. Eng. 132 (11), 1159–1168.
dynamics modelling of scour around a single pile due to combined action of the https://doi.org/10.1061/(ASCE)0733-9429(2006)132:11(1159).
waves and current using level-set method. Coast Eng. 170, 104002 https://doi.org/ Yang, J., Low, Y.M., Lee, C., Chiew, Y., 2018. Numerical simulation of scour around a
10.1016/j.coastaleng.2021.104002. submarine pipeline using computational fluid dynamics and discrete element
Gidaspow, D., 1994. Multiphase Flow and Fluidization. Academic Press, San Diego, USA. method. Appl. Math. Model. 55, 400–416. https://doi.org/10.1016/j.
Gmbh, D.C., 2014. Cfdemcoupling Manual. https://www.cfdem.com/media/CFDEM/do apm.2017.10.007.
cu/CFDEMcoupling_Manual.html/. (Accessed 15 November 2022). Yazdanfar, Z., Lester, D., Robert, D., Setunge, S., 2021. A novel CFD-DEM upscaling
Goniva, C., Kloss, C., Deen, N.G., Kuipers, J.A.M., Pirker, S., 2012. Influence of rolling method for prediction of scour under live-bed conditions. Ocean Eng. 220, 108442
friction on single spout fluidized bed simulation. Particuology 10 (5), 582–591. https://doi.org/10.1016/j.oceaneng.2020.108442.
https://doi.org/10.1016/j.partic.2012.05.002. Yoshizawa, A., Horiuti, K., 1985. A statistically-derived subgrid-scale kinetic energy
Hu, D., Tang, W., Sun, L., Li, F., Ji, X., Duan, Z., 2019. Numerical simulation of local model for the large-eddy simulation of turbulent flows. J. Phys. Soc. Jpn. 54 (8),
scour around two pipelines in tandem using CFD–dem method. Appl. Ocean Res. 93, 2834–2839.
101968 https://doi.org/10.1016/j.apor.2019.101968. Zhang, Y., Zhao, M., Kwok, K.C.S., Liu, M.M., 2015. Computational fluid
Irena, 2021. Renewable Capacity Statistics (Abu Dhabi, United Arab Emirates). dynamics–discrete element method analysis of the onset of scour around subsea
Jaeho Shim, J.D.H.J., 2016. Simulating Sediment Transport Around a Bridge Pier Using pipelines. Appl. Math. Model. 39 (23–24), 7611–7619. https://doi.org/10.1016/j.
Open Foam Software. World Environmental and Water Resources Congress 2016, apm.2015.03.058.
West Palm Beach, Florida. https://doi.org/10.1061/9780784479872.037. Zhao, M., Cheng, L., Zang, Z., 2010. Experimental and numerical investigation of local
Kempe, T., Vowinckel, B., Fröhlich, J., 2014. On the relevance of collision modeling for scour around a submerged vertical circular cylinder in steady currents. Coast Eng. 57
interface-resolving simulations of sediment transport in open channel flow. Int. J. (8), 709–721. https://doi.org/10.1016/j.coastaleng.2010.03.002.

19

You might also like