Professional Documents
Culture Documents
PQC Bom
PQC Bom
BILL OF QUANTITIES
ITEM DESCRIPTION QTY UNIT MATERIAL COST LABOR COST WT % UNIT COST AMOUNT
2.0 Earthworks
2.1 Structural Excavation
a. Footings 21.50 cu.m 250.00 100.00 0.00375041 350.00 7525.00
b. Septic Tank 9.00 cu.m 250.00 100.00 0.00156994 350.00 3150.00
2.2 Backfilling & Compaction 14.00 cu.m 250.00 100.00 0.00244213 350.00 4900.00
2.3 Filling Works
a. Gravel Bedding Works 1.26 cu.m 1350.00 540.00 0.00118310 1890.00 2373.84
b. Soil Poisoning 0.00 lot 10000.00 4000.00 - 14000.00 0.00
c. Site Clearing , Hauling, Demolition & Disposal 1.00 lot 0.00 25000.00 0.01245982 25000.00 25000.00
SUB TOTAL 0.02140540 42948.84
BILL OF QUANTITIES
ITEM DESCRIPTION QTY UNIT MATERIAL COST LABOR COST WT % UNIT COST AMOUNT
d. Rebars -
-12mm diameter 55.00 pcs 270.00 108.00 0.01036159 378.00 20790.00
-10mm diameter 59.00 pcs 185.00 74.00 0.00761594 259.00 15281.00
e. GI Wire # 16 1.50 kgs 132.00 52.80 0.00013815 184.80 277.20
Formworks
a. 1/2 Phenolic Board 13.00 pcs 936.00 374.40 0.00849022 1310.40 17035.20
b. 2"x2"x8ft Coco Lumbers 89.00 pcs 92.80 37.12 0.00576286 129.92 11562.88
Scaffoldings
a. 2"x2"x8ft Coco Lumbers 88.00 pcs 92.80 37.12 0.00569811 129.92 11432.96
Miscellaneous 1.00 lot 5000.00 0.00 0.00249196 5000.00 5000.00
ARCHITECTURAL WORKS
6.0 Tileworks 173.90 sq.m 1308.19
a. Cement 55.00 bags 270.00 108.00 0.01036159 378.00 20790.00
b. Sand 5.00 cu.m 720.00 288.00 0.00251190 1008.00 5040.00
c. Tile Adhesive 23.00 bags 325.00 130.00 0.00521568 455.00 10465.00
d. Floor Tiles (60x60cm - Restroom & Multi-purpose Area) 532.00 pcs 250.00 100.00 0.09280076 350.00 186200.00
e. Floor Tiles (30x30cm - Office front) 0.00 pcs 120.00 48.00 - 168.00 0.00
f. Miscellaneous 1.00 lot 5000.00 0.00 0.00249196 5000.00 5000.00
BILL OF QUANTITIES
ITEM DESCRIPTION QTY UNIT MATERIAL COST LABOR COST WT % UNIT COST AMOUNT
9.0 Cabinetries
a. Bar Area 10.80 sq.m. 0.00 0.00 0.00747589 0.00 15000.00
BILL OF QUANTITIES
ITEM DESCRIPTION QTY UNIT MATERIAL COST LABOR COST WT % UNIT COST AMOUNT
LEXSHAS RESTAURANT
BECURAN, STA. RITA, PAMPANGA
MODERN FINISH
Item no. Description Unit Quantity Unit Cost Amount
Part A. General Requirements
Mobilization and Demobilization lot 1.00 ₱ 35,000.00 ₱ 35,000.00
Temporary Water and Electric Supply lot 1.00 16,000.00 ₱ 16,000.00
Temporary Fence and Board-ups lot 1.00 10,000.00 ₱ 10,000.00
Temporary Restroom lot 1.00 10,000.00 ₱ 10,000.00
Safety Productive Measure lot 1.00 ₱ 5,000.00 ₱ 5,000.00
Supervision Cost months 3.00 ₱ 20,000.00 ₱ 60,000.00
Design Fees lot 1.00 ₱ 70,000.00 ₱ 70,000.00
Sub-Total ₱ 206,000.00
Part B. Earthworks
Clearing/Demolition lot 1.00 ₱ 20,000.00 ₱ 20,000.00
Structural Excavation cu.m 30.50 ₱ 350.00 ₱ 10,675.00
Structural Backfill and Compaction cu.m 14.00 ₱ 350.00 ₱ 4,900.00
Gravel Bedding cu.m 1.26 ₱ 1,620.00 ₱ 2,034.72
Sub-Total ₱ 37,609.72
Part C. Concrete Works
Footings cu.m 6.97 ₱ 5,744.40 ₱ 40,049.96
Tie beams & Masonry Beams cu.m 2.50 ₱ 5,744.40 ₱ 14,361.00
Columns cu.m 2.10 ₱ 5,744.40 ₱ 12,063.24
Sub-Total ₱ 66,474.20
Part D. Formworks and Falseworks
Formworks l.s 1.00 ₱ 46,486.72 ₱ 46,486.72
Falseworks / Shorings l.s 1.00 ₱ 27,669.12 ₱ 27,669.12
Sub-Total ₱ 74,155.84
Part E. Reinforcing Steel Bars
10mm Reinforcing Bars (Gr.33) pcs 236.00 ₱ 285.20 ₱ 67,307.20
12mm Reinforcing Bars (Gr.40) pcs 190.00 ₱ 397.34 ₱ 75,494.60
Sub-Total ₱ 142,801.80
Total ₱ 1,765,274.07
SAY 1,760,000.00
Prepared By:
________________________________
Jan Lawrence T. Alberto, RCE. RMP
Prequal Constructions, Quantity Engineer
Approved by:
_______________________________
Kim Prince B. Payumo, RCE
Prequal Constructions, General Manager
I. FOUNDATION
A. ISOLATED FOOTING
INPUTS
B. WALL FOOTING
Commercial Bar length 6000 mm
Assumed splice length 300 mm
Dowel Bar Height 600 mm
INPUTS
Wall Ftg Tag Width Linear Mtr Thickness Depth Footing Bar Dia
16 7 7
SUMMARY
1 Reinforcements
16
2 Concrete
Volume
Cement
Sand
Gravel
3 Gravel Bedding
4 GI Wire
5 Excavation
6 Backfilling
Volume Multiplier
Cement 9.1
Sand 0.5
Gravel 1
INPUTS
Dowel
Traverse bars n bars Bars
spacing (Longitudinal) n bars (Traverse) Dowel Bar Dia Spacing
400 3 58 10 800
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
SUMMARY
1 Reinforcements
10
2 Concrete
Volume
Cement
Sand
Gravel
3 Gravel Bedding
4 GI Wire
5 Excavation
6 Backfilling
REINFORCEMENT
Footing Tag Bar Dia Cut length (L) N pcs (L) Cut length (W)
F1 16 1050 20 1050
0 0 -150 0 -150
0 0 -150 0 -150
0 0 -150 0 -150
0 0 -150 0 -150
0 0 -150 0 -150
0 0 -150 0 -150
0 0 -150 0 -150
0 0 -150 0 -150
0 0 -150 0 -150
0 0 -150 0 -150
Quantity
42 pcs
5.04 m3
49 bags
3.5 m3
6 m3
0.756 cu.m
5 kgs
15.5 m3
10 m3
REINFORCEMENTS
Bar Dia N bars N bars Total Footing
(Longitudinal) (Transverse) bars
12 13 4 17
0 0 #DIV/0! #DIV/0!
0 0 #DIV/0! #DIV/0!
0 0 #DIV/0! #DIV/0!
0 0 #DIV/0! #DIV/0!
0 0 #DIV/0! #DIV/0!
0 0 #DIV/0! #DIV/0!
0 0 #DIV/0! #DIV/0!
0 0 #DIV/0! #DIV/0!
0 0 #DIV/0! #DIV/0!
0 0 #DIV/0! #DIV/0!
Quantity
24 pcs
1.93 m3
18 bags
1.0 m3
2.0 m3
0.50 cu.m
2.00 kgs
6.00 m3
4.00 m3
CONCRETE GI WIRE
Sand, Gravel
N pcs (W) Total pcs Volume, Cement, Gravel, m3 kgs
m3 Bedding, m2
m3 bags
20 40 5.04 46 3 5.5 14.4 4
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
CONCRETE GI WIRE
Total Cement, Sand, Gravel
Bar Dia Volume Gravel, m3 kgs
Dowel Bars bags m3 Bedding
10 5 1.84 17.00 0.92 1.84 9.20 0.98
0 #DIV/0! 0.00 0.00 0.00 0.00 0.00 #DIV/0!
0 #DIV/0! 0.00 0.00 0.00 0.00 0.00 #DIV/0!
0 #DIV/0! 0.00 0.00 0.00 0.00 0.00 #DIV/0!
0 #DIV/0! 0.00 0.00 0.00 0.00 0.00 #DIV/0!
0 #DIV/0! 0.00 0.00 0.00 0.00 0.00 0.00
0 #DIV/0! 0.00 0.00 0.00 0.00 0.00 0.00
0 #DIV/0! 0.00 0.00 0.00 0.00 0.00 0.00
0 #DIV/0! 0.00 0.00 0.00 0.00 0.00 0.00
0 #DIV/0! 0.00 0.00 0.00 0.00 0.00 0.00
0 #DIV/0! 0.00 0.00 0.00 0.00 0.00 0.00
Excavation Backfilling
m3 m3
14.4 9.36
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
Excavation Backfilling
m3 m3
5.52 3.68
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
Commercial Bar Length 6000
Formworks Width 1.2 m
Length 2.4 m
Coco Lumber Size 2x2
D1 2 inches
D2 2 inches
Length 8 ft
Thickness of Board 1/2 inches
Allowance
SUMMARY
MAIN REINFORCEMENTS STIRRUPS CONCRETE
Allowance 1.05
SUMMARY
Reinforcements Quantity Unit
10 59 pcs
12 55 pcs
Concrete
Volume 2.50 m3
Cement 21 bags
Sand 1.5 m3
Gravel 2.5 m3
Scaffoldings
2x2 Coco Lumber 88 pcs
CRETE GI WIRE FORMWORKS Scaffoldings
Column Tag C1
Column Height 5 m
MAIN REINFORCEMENT
N pcs of rebar/column 6 pcs
Total No. of rebar 36 pcs
STIRRUPS
Stirrup Cut Length 930 mm
No. of stirrups / column 34 pcs
No. of cuts per commercial length 6 pcs
No. of bar required per column 6 pcs
Total No. of bar required 36 pcs
CONCRETE
Volume 2.10 m3
FORMWORKS
Phenolic Board
Board Size (W) 1.2 m
Board Size (L) 2.4 m
No. of pcs 7 pcs
Wood Frame
Table 5-1 Board Foot of Wood Frame for Column and Beam per plywood Form
Thickness of Plywood Form
Size of Wood Frame Columns Beams
1/4 1/2 1/4
2x2 29.67 20.33 25.06
2x3 44.5 30.5 37.6
SCAFFOLDINGS
Commercial Length
Allowance for lap splices of main bars
Phenolic Board Dimension D1
D2
Coco Lumber Size
D1
D2
L
Thickness of plywood form
SUMMARY
Reinforcements
12
10
Concrete
Cement
Sand
Gravel
GI Wire
Formworks
1/2'' phenolic board
2x2x8 ft Cocolumber
Scaffoldings
2x2x8 ft Cocolumber
lywood Form
wood Form
Beams
1/2
18.66
28
48
Volume Multiplier
6 m Cement 9
10 % Sand 0.5
1.2 m Gravel 1
2.4 m
2x2 inches
2 inches
2 inches
8 feet
1/2 inches
INPUTS
No. of Columns D1 D2 Main Dia N bars Hook length Stirrups Dia Spacing
3 4 5 6 7 8 9 10
6 200 350 12 6 150 10 150
6 200 350 12 6 150 10 150
1.05
Quantity
38 pcs
38 pcs
20 bags
1.5 m3
2.5 m3
8.00 kgs
8 pcs
57 pcs
0 pcs
REINFORCEMENTS
Hook length Column Tag Bar Dia N pcs (Main) Bar Dia
11 1 2 3 4
75 C1 12 36 10
75 C1 10
0 #N/A #N/A #N/A
0 #N/A #N/A #N/A
CONCRETE
GI Wire
N bars (Stirrups) Volume Cement Sand Gravel
5 6 7 8 9 10
36 2.10 19.00 1.05 2.10 6.928302
36 2.10 19 1.05 2.10 6.93
#N/A #N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A #N/A
Formworks Scaffoldings
Board Lumber Lumber
11 12 13
7 54 0
7 54 0
#N/A #N/A 0
#N/A #N/A 0
A. On-Grade
Commercial length 6 m
Lap Splice 0.3 m
Elevation of Flooring from NGL 0 m
Allowance for discrepancy 0 %
Inputs Reinfo
Spacing Spacing
Thickness Dimension X Dimension Y Bar Dia Bar dia
Along-X Along-Y
mm m m mm m m mm
100 25 10.8 10 0.3 0.3 10
0
SUMMARY
Reinforcements Quantity
10 0.00 pcs
Concrete
Volume 0.00 m3
Cement 0.00 bags
Sand 0.00 m3
Gravel 0.00 m3
Elevation of Slab-
on-Grade from 0.00 m3
NGL
Volume Multiplier
Cement 9.1
Sand 0.5
Gravel 1
Reinforcements Concrete
Elevation
n bars GI Wire of slab-
n bars along X
along Y Total bars Volume
Cement Sand Gravel
on-grade
pcs pcs pcs m3 bags m3 m3 kgs m3
158 158 316 27.00 246 14 27 0.00 0.00
#DIV/0! #DIV/0! #DIV/0! 0 0 0 0
TABLE 2-2 QUANTITY OF CEMENT AND SAND FOR CHB MORTAR PER
SQUARE METER
TABLE 2-4 QUANTITY OF CEMENT AND SAND FOR PLASTER PER SQUARE
METER AREA
Cement in Bags
Class Mix Thickness of plaster
8 12 16 20 25
A 0.144 0.216 0.288 0.36 0.45
B 0.096 0.144 0.192 0.24 0.3
C 0.072 0.108 0.144 0.18 0.225
D 0.06 0.09 0.12 0.15 0.188
Sand 0.008 0.12 0.016 0.02 0.025
MASONRY
SUMMARY
CHB Unit Total Area Quantity
4'' 59.28 779 pcs
5'' 115.75 1520 pcs
Mortar
Cement 127.00 bags
Sand 18.50 m3
Plaster
Cement 74.0 bags
Sand 6.5 m3
Reinforcement
10 115 pcs
TABLE 2-1 QUANTITY OF CEMENT
AND SAND FOR MORTAR AND
PLASTER IN CUBIC METER
Class Mixture Proportion
A 1:02
B 1:03
C 1:04
D 1:05
Material
Total Length
Quantity
E. Roof Purlins
Material
Spacing
Splice Length
Commercial Length
Effective Length
Allowance for discrepancy
F. Roofing Sheet
Allowance for discrepancy
Slanted length
Roof total width
Effective width of a sheet
Total linear meter
G. Plain GI Sheets
Allowance for discrepancy
Roof Gutter
Gutter length
Gutter length + allowance
End Flashing
Total length
Length + Allowance
HT-1
7 pcs
6 m
1.05 %
2x2x1/4
21.67 m
27 pcs
TRUSS SUMMARY
L 2 x 2x 1/4
2'' Ø Schedule 40
7 pcs
C 2''x3''x1.2mm
0.6 m
0.5 m recommended is 15% of span
6 m
5.5 m
1.05
3 m assumed conservatively
25 m
13.1 m
22 pcs
5.00 pcs
110 pcs
1.05
13.1 m
25 m
1 m
343.875 m
1.10
24'' GI Sheet
0 m
0.0 m
16" GI Sheet
21 m (Rear only)
23.1 m
27
No. of SEPTIC TANK 1
A. Excavation
Volume 9 m3
B. CHB Units
CHB Specs 6 inches
Total Perimeter + Baffle Walls 12 m
Total Area of Walls 24 m²
Total CHB required 300 pcs
C. CHB Reinforcements
Vertical Spacing 800 mm
Horizontal bar layer spacing 3 layer
Rebar Dia 10 mm
Commercial length of rebar 6 m
D. Mortar
Mixture Class B Refer to Table 2-1
Cement 25 bags
Sand 2.5 m3
E. Plastering
Mixture Class B Refer to Table 2-4
Thickness 20 mm
No. of faces to plaster 2
Cement 12 bags
Sand 0.5 m3
E. Foundation Reinforcement
Rebar Dia 12 mm
Spacing Along L 200 mm
Spacing Along W 200 mm
F. Cover Reinforcement
Rebar Dia 12 mm
Spacing Along L 200 mm
Spacing Along W 200 mm
TOTAL COST
TOTAL COST
TABLE 2-2 QUANTITY OF CEMENT AND SAND FOR CHB MORTAR PER SQUAR
Cement in Bags
Class Mix Thickness of plaster
8 12 16
A 0.144 0.216 0.288
B 0.096 0.144 0.192
C 0.072 0.108 0.144
D 0.06 0.09 0.12
Sand 0.008 0.12 0.016
CEMENT AND SAND FOR
ND FOR CHB MORTAR PER SQUARE METER MORTAR AND PLASTER IN
CUBIC METER
ment Mixture Class Mixture Proportion
Sand
D A 1:02
0.328 0.0435 B 1:03
0.4805 0.1279 C 1:04
0.633 0.0844 D 1:05
Horizontal Rebar
length per sq.m.
3.3
2.15
1.72
ND FOR PLASTER PER SQUARE METER AREA
Cement in Bags
ckness of plaster
20 25
0.36 0.45
0.24 0.3
0.18 0.225
0.15 0.188
0.02 0.025
A. Ceiling Works
B. Wall Cladding
Allowance for discrepancy 0.00
Total linear meter of wall to clad m approximately
Wall height m +0.40 m allowance
Total Area 0 m²
C. Cabinetries
Location Area, m² Remarks
Bar Area 6 1
Bar Area 5.5 2
Bar Area 4.5 shelves
16.00
Carrying channel 60 cm spacing
metal furring 40 cm spacing
A. Cabinetries
Location Area, m² Remarks
Bar Area 6 1
Bar Area 5.5 2
Bar Area 4.5 shelves
16.00
A. Tiling Works
Allowance for tile breakage 1.10
Allowance for mortar 1.05
Tile Dimension 0.6 m
0.6 m
Area Multiplier
Cement 0.3 bags
Sand 0.025 m3
Tile Adhesive 0.125 bags
532 55 5
Tiles Cement, bags Sand, m3
0 0 0
Tiles Cement, bags Sand, m3
Tile Adhesive Remarks
18.9375
2.8
23
Tile Adhesive, bags
0
Tile Adhesive, bags
A. Ceiling Finishes
I. Metal Frame Assembly - Groundfloor
A. Wall Finishes
I. Metal Frame Assembly - Wall Design
Allowance for discrepancy 1.05
No. of panels 9 pcs
Commercial length 6 m
Total Area,
Per panel Unit Qty
sqm
SUMMARY
1/2" Blue pipe 69.70 l.m.
1 '' Blue Pipe 24.53 l.m.
4'' PVC Pipe 62.4 l.m.
2'' PVC Pipe 0 l.m.
D. Fixtures
Description per Unit Unit
1 Water Closet 6 pcs
2 Lavatory 5 pcs
3 Urinal 2 pcs
4 Kitchen Sink 1 pcs
5 Floor Drain 7 pcs
6 Clean-out 2 pcs
7 Gate Valve 5 pcs
8 pcs
B. Sanitary
Remarks Description
approximate (+20% allowance for bends and connection to fixture) 4'' PVC Pipe
approximate (+20% allowance for bends and connection to fixture) 4'' PVC Pipe
C. Vent
F. Electrical Wirings
Description Total
2.5 mm² 444 l.m. for lightings 111 l.m x 4
2.5 mm² 94 l.m. for outlets 47 l.m x 2
3.5 mm² 94 l.m. for outlets 47 l.m x 2