METHOD OF STATEMENT
water proofing
Table of contents
PURPOSE
SCOPE
RESPONSIBILITY
MANPOWER
METHODS / PROCEDURES
SAFETY PRECAUTION
ATTACHMENT
ELKHOMRA PROJECT
- PURPOSE
The aim of this method statement is to execute the scope of work, provide and maintain an
effective quality control in compliance with standards and good practices at all stages/
activities for waterproofing work for roof deck opening area.
- SCOPE
This method statement covers all sequence of the waterproofing works to be carried
out for roof deck where required for this project. The objective of this method
statement is to produce waterproofing work for roof deck.
- RESPONSIBILITY
A full and detailed description of roles and responsibilities of all staff is included within
the project quality plan . for the works as covered this method statement , the following
personnel have specific duties
- Shall ensure that operatives comply with the relevant method statements, Toolbox
Talks and general site briefings.
- MANPOWER
The Civil Supervisor shall control the overall activities at site and he will be directly
reporting to the Site Superintendent. The basic manpower under him shall consist
but not limited to the following:
Lead Pre-Commissioning Engineer
Testing Engineer
Civil Lead Man
Senior Technicians
Technician
Vendor Represented (if need)
QC Engineer / Inspector
Safety Engineer
Company Representative
- Materials :
- Handling and placing of the approved /specified material will be done as per the
Instructions of the manufacturer. o The approved/specified materials must be
delivered and placed in specific time
- METHODS / PROCEDURES
The scope of this procedure covers the general construction plan for waterproofing work
for roof deck area. The purpose of the documentation is to implement the procedure & to
ensure that the quality control aspects are maintained and accurate records are
established. The objective is to ensure that the construction plan is executed, controlled
and documented in compliance with Contract Drawings & Specifications.
To apply (LIGHT WEIGHT FOAM CONCRETE) having 1% slope fall to drain with
50mm minimum thickness and 100 mm average thickness with density 350-450 kg/M3 as
a roof insulator and sloping screed. • To Supply and apply POLYURETHANE
(PU)FOAM SPRAYS 40 mm average thickness having the density of 40-45 kg/M3 on
top of LWFC roof deck area. • Supply and apply with two coats of Acrylic coating with
500 microns thickness (250+250). • Supply and lay Geo-textile sheet 140G/M2 as a
protection layer over the POLYURETHANE (PU ) System. • System will be covered&
ELKHOMRA PROJECT
protected by client by means of (Tiles, Gravel....ETC)
- SAFETY PRECAUTION