Professional Documents
Culture Documents
* Technical Director, Parsons Brinckerhoff Ltd, UK, Email: knott@pbworld.com, † Asset Manager (Metrolink), Transport for
Greater Manchester, UK, matthew.hack@tfgm.com, Director Adrian Cope Project Management Ltd, acpmltd@gmail.com
Bury
Using experience gained from a number of rail and transit
projects the authors discuss how the engineering practices
Oldham
used throughout the lifecycle of a large, modern infrastructure
programme affect the delivery and transfer into service of
infrastructure assets and describe one particular, pragmatic Eccles
City
approach which has enabled Transport for Greater Centre
Ashton
Trafford
Manchester (TfGM) to successfully introduce a number of £1.4 billion investment between 2009 and 2016. Park
Manchester Airport
1
complete required system build for the EMN was achieved as
shown in Figure 4 [2].
Project
Scope
All New Assets and
Assets that have
changed
Infrastructure Operations Metrolink Existing Network Phase 3 Project Systems Infrastructure Operations Figure 5: A typical Project ‘V’ Lifecycle is relatively short
compared to the lifetime of the asset.
2
required by each Operations and Maintenance (O&M) party to confirm that testing and commissioning had been
and controlling the definition of the System using completed satisfactorily.
Configuration Baselines, the appropriate asset information For the infrastructure to be handed into maintenance its
could be assembled for handover. configuration had to be known. The record of any
outstanding defects or incomplete work was appended to the
maintenance AMP form (AMP04), which when signed by the
Maintainer, Constructor and Asset Owner was the formal
acknowledgement of the state of the asset at handover.
Defects Liability
Environment (e.g. energisation of the infrastructure’s traction
AMP 03/04 AMP 04/03 AMP 05 power). Eventually the integration reached the System level
Handback Handback (& where there are also stage gates for Safety and System
IMSCC)
Construction Energisation Dynamic Testing SAT A (Test
Running)
SAT B
(Trial Ops)
SAT C
(Operate & Maintain)
Assurance.
Whole New Line
Driver
Training
Defects Liability The framework is shown in Figure 8 where the horizontal
AMP 03 AMP 04 AMP 05
bands represent the SBS and the vertical axis represents the
order in time when the stage gates (represented by diamond
Figure 7: TfGM’s AMP Process uses the exchange of forms shaped symbols) logically occur. Whilst the detail may not be
to record the status and transfer of responsibility for assets. clear in the figure at this scale it clearly shows the progressive
integration of the sub-systems and elements (blue diamonds)
The AMP form recording the transfer into operation (AMP03) as the project reaches the main milestones (stage gates) at
included separate sections associated with each sub-systems which a decision to proceed needs to be taken.
to be signed by the relevant constructor’s competent engineer
3
Stage Design Build Install Test & Commissioning Integration & Proving Putting in to Service
stakeholder communication, and discharge of legal, planning
Construction Site Operational Tramway when working on or near the line
and regulatory obligations.
S
R
C
Interim SRC submissions may be required dependent upon delivery staging S
R
C
Based on the experience from the initial migration phase it
KEY
System
S
B
R
T
R
R
was decided to start the Go-live process 16 weeks from the
Critical Path
P
R
O
S
R
R
S
R programmed dated for entry into Passenger Service.
Operational Readiness Stage Gate
Review
5.5 Tracking Operational Readiness
R Sufficient trams of correct variant/configuration
F
Trams CC Construction Completion
I
DRT
IA
OSRR
With the logic defined and the basic principles established,
Drivers Ready for Training
Infrastructure Acceptance
Operational Service Readiness Review
R OR Operational Review
R PSRR
IRR
RFO
the next step was to identify the key activities associated with
Passenger Service Readiness Review
Infrastructure Readiness Review
Ready For Operation
Control
T
R
T
R
SRC
TRR date associated with the relevant stage gate. In deciding what
Safety Review Committee
Test Readiness Review
4
Executive Summary trajectory for each environment. This In order for maintenance to be undertaken from the day of
gave a powerful visual representation of progress towards handover a sub-set of certified marked-up as-built drawings
operational readiness, enabling all involved to quickly see any was required as a record of the infrastructure’s configuration
areas requiring attention. As more data became available it and to provide the necessary technical information needed to
became possible to plot an averaged ‘idealised’ trajectory, or deliver the routine maintenance. These included, for example,
flight path, for each stage gate which in turn provided a more electrical schematics, equipment connectivity and power
accurate way of assessing progress. feeding diagrams, stop layouts and drainage layouts. The
constructor’s signature on the maintenance AMP form
(AMP04) provided the assurance that the equipment handed
over was compliant with the design, had been shown by
testing to be safe to operate and was capable of being
maintained in a safe condition.
The GLR process captured the system configuration at the
point of handover to operation and hence provided a record of
any incomplete activities. This list of activities was appended
to the relevant AMP form together with a statement of any
associated operational restrictions; hence the AMP form was
Figure 9: The GLRT tool provides graphical indicators that the record of acknowledgement by the operator of any
allow managers to quickly see where there may be problems. incomplete activity and any restriction to operation.
There was no restriction on the continued development of the 5.7 Post Handover
GLRT for the associated migration phase; activities could be
removed or new activities included as agreed by the It was acknowledged that some activities did not need to be
responsible parties during the 16 week period. complete at the point at which operation commenced and,
The process and tool are now well established. The either needed to be completed as soon as practicable
developed Go Live format is embedded within the MEP and a thereafter, or could be completed at a later stage in the overall
key component of each Project Manager’s toolbox. The proof project. For example, a junction may be inserted into an
of its effectiveness is that it has been employed successfully existing line in preparation for the construction of a future
to track, monitor and report operational preparedness over diverging route. The junction would become partly
multiple migration phases. operational to allow the continuing passage of trams along the
existing route but would only become fully operational once
5.6 The Handover the branch line was completed. In this example the
intermediate configuration results in an operational
The preparations for operation made by the operator in restriction, in that the junction can only be traversed on the
collaboration with the constructor were tracked by the GLR through route. Once in operation there are still a number of
process. In parallel with these activities, the pre-existing Performance, Reliability, Availability, and Maintainability
system and new lines already brought into operation requirements which can only be proven after an extended
continued to operate. Although MRDL had a separate team to period of in-service operation and which the Project Team
manage network expansion there were still key activities needed to work with the O&M parties to conclude.
which needed to be carried out by the team doing the “day
job”, for example, all tram drivers needed to be trained on the 6 Tying up the ‘Loose Ends’
new route(s), new timetables and driver rosters needed to be
developed and customer facing staff needed to become Whilst the System for a particular migration phase might have
familiar with the characteristics of the new route. The been transferred into Service there will still be several items
network expansion team managed these preparations for needing to be completed before the Project has finished its
operation to meet the key stage gates so as to present a duties e.g. final issue of documentation, provision of all asset
coherent and consistent experience for customers. details required by the various maintenance Management
A coordinated asset register was developed as part of the Systems, clearance of caveats on AMP Forms, completion of
preparations for maintenance and based on this the non-critical outstanding works and snagging and defect
maintenance schedule and related maintenance instructions clearance. At this time the delivery organisations are under
were produced. Training, spares, tools and other logistical pressure to reassign their experienced resources and minimise
equipment were all required for maintenance to start. The remaining costs so there is a potential risk to the timely
need for the maintenance staff to undertake training on new completion of the transfer of all the assets and their associated
equipment, the logistics of which were not at first well information. Recognising this could present a significant
planned, was managed as part of the GLR process. The need potential risk to the O&M parties and particularly to the Asset
to release front-line maintenance staff from the “day job” Owner and Manager, a process to manage Project Close-out
without affecting their ability to deliver reactive and was developed. The Close-out Process firstly defined the
preventative maintenance required careful planning. grouping of projects and work packages that constituted a
logical complete achievement of an objective of the initial
5
business case e.g. provision of a 12 minute passenger service the installed assets. Reviewing and assessing the information
from the City Centre to Rochdale via Oldham. It then for quality and content was an onerous task carried out
considered the Close-out in terms of completing the transfer typically during and after the point of handover. In the future,
of all the assets into the O&M Environment and the contractual arrangements should be structured so that delivery
completion of all associated commercial aspects. of as-built information takes place continuously throughout
By analysing the work streams and functions responsible for the project and is aligned with stage payments. To achieve
closing out either the Asset Transfer or Commercial aspects a this definition of the Configuration of the System needs to be
number of metrics were identified that could be quantified readily translated into the Configuration Management
and tracked to completion. A tracking tool was created with a Systems of the O&M parties who would also need to provide
dashboard front end for monitoring close-out progress for a clear set of requirements for asset information which would
each Grouping in the following major categories:- need to be cascaded throughout the supply chain [6]. The
Asset Transfer improvements in this area do not need to be developed from
Safety Assurance scratch as the specifications for Building Information
Modelling (BIM) provide just the kind of structured
Operational
framework needed for the management of asset information
Financial / Contract Completion through a project lifecycle. It is proposed that future projects
Completion of Close-out for all categories was set for the adopt BIM principles which would make the transfer of
expected end of contractual liability (e.g. end of the defect information much more efficient whilst also reducing
liability or the warranty period). Responsibilities for the redundancy in the information provided and improve its
close-out of each sub-category were assigned and progress accuracy [7].
monitored at monthly intervals. A RAG indication was used The increasing use of digital technology in design, project
to highlight deviations from the expected rate of clearance so control, communication and asset management is helping
as to provide a simple but effective way to signal to senior make the delivery and maintenance of new infrastructure
management the areas that required further investigation and systems more effective and efficient. BIM has matured into
attention. an industry standard [8] and systems can be captured,
visualised, modelled, rendered, refined and recorded
throughout their life from concept to decommissioning.
Assets can now be said to have a digital life as well as a
physical one and it is a digital legacy the delivery project
provides for the Asset Managers of the future.
References
[1] INCOSE, “Guide for the Application of Systems
Engineering in Large Infrastructure Projects” INCOSE-
TP-2010-007-01 version 3.0 (2012).
[2] Knott, A., “Applying Configuration Management
Principles on a Large Scale Operational Railway
Infrastructure, Railway Engineering Conference (2004).
[3] INCOSE UK, “Applying Systems Engineering to In-
Figure 11: A dashboard showing the progress towards close- Service Systems – Supplementary Guidance to the
out of relevant functional areas of the project. INCOSE SE Handbook”, ls-tr-005, Issue 1.0 (2010).
[4] INCOSE, “Systems Engineering Handbook – A Guide
7 Lessons for the Future Extensions for System Life Cycle Processes and Activities”,
INCOSE-TP-2003-002-03.2.2 (2011).
Metrolink continues to expand with a second city crossing, [5] Knott A. & Stubbs M. Q., “Innovative Systems
which will significantly increase capacity across the network, Engineering Practices that help manage the
and a line through the rejuvenated Trafford Park area. This Organisational and Technical Complexity of a Modern
continuing development, combined with the opportunities Railway Project”, International Conference on Railway
presented by the need to enter a new arrangement for O&M Engineering (ICRE2008), Hong Kong, (2008).
services when the current franchise expires in 2017, [6] Ross Dentten, “Enabling Quality Asset Information to
encourages TfGM to continue to learn lessons from the past support the Crossrail Smart Railway”, Asset
and to keep abreast of the latest industry practices and Information and Data Management for Smart Rail
technologies. (2014)
The success of the Go-live Process depended on being able to [7] HM Government, “Building Information Modelling”,
identify key activities for the transfer from project to O&M URN 12/1327 (2010)
and bring them further forward in the programme. During [8] Institute of Asset Management, “An Anatomy of Asset
successive iterations of the process it became apparent that an Management”, Issue 1.1 (2012).
area for improvement was the transfer of information about