You are on page 1of 6

Delivering a Light Rail System into Service – Considerations for

Effective Asset Management


Alan Knott BEng(Hons) CEng FIET MINCOSE*, Matthew Hack MSc CEng MIMechE†, Adrian
Cope MINCOSE#

* Technical Director, Parsons Brinckerhoff Ltd, UK, Email: knott@pbworld.com, † Asset Manager (Metrolink), Transport for
Greater Manchester, UK, matthew.hack@tfgm.com, Director Adrian Cope Project Management Ltd, acpmltd@gmail.com

Droylsden and Ashton to the East and, to Chorlton, Didsbury,


Keywords: Manchester Metrolink, Tram Systems, Wythenshawe and Manchester Airport to the Southeast of the
Operational Readiness, Configuration Management, BIM. City Centre. Figure 1 lists some of the significant figures
which demonstrate the scale of this endeavour.
Abstract Rochdale

Bury
Using experience gained from a number of rail and transit
projects the authors discuss how the engineering practices
Oldham
used throughout the lifecycle of a large, modern infrastructure
programme affect the delivery and transfer into service of
infrastructure assets and describe one particular, pragmatic Eccles
City
approach which has enabled Transport for Greater Centre
Ashton
Trafford
Manchester (TfGM) to successfully introduce a number of  £1.4 billion investment between 2009 and 2016. Park

new services on what is now the UK’s largest tram network. 



10 extensions to the network.
93 new and improved tram stops.
Didsbury
 Fleet of 104 new trams.
 Conversion to Line of Sight operation throughout.
1 Introduction City Centre Programme


Trebles the size of the current network to 103km.
Doubles passengers per year to 50m.
Altrincham

Manchester Airport

Once the design is completed, infrastructure project teams


tend to focus on the delivery of a new or upgraded set of Figure 1: Illustrating scale & complexity of the Metrolink
assets and often not so much on the operational and Extension Programme (MEP)
maintenance environment they are delivering into. However,
with forethought and through engagement with those that will Major contracts were let for the infrastructure extensions, a
need to support the assets over their long operational lifetime, second depot, a new fleet of light rail vehicles, a new
processes and management systems can be put in place during network-wide tram management system and management
the project lifecycle which can facilitate the smooth transfer centre and also to operate and maintain the expanded
into service and ease the integration into the Asset Managers’ network; all to be delivered as part of the Metrolink Extension
management systems. Programme (MEP). Due the scale of the MEP, and in order to
The paper introduces the engineering practices that have the start revenue service (return on investment) as soon as
greatest impact on the ‘back end’ of the project lifecycle and practical, the extensions were delivered in migration phases
‘front end’ of the operational lifecycle and describes a and the new trams in batches.
methodology specifically focussed on bringing an integrated
system through the operational readiness, or ‘Go-live’, 3 Delivering an Integrated Solution
process and into passenger service. It describes the
configuration management process that follows the entire Critical to the success of the MEP was the need to ensure the
asset lifecycle from the initial statement of requirements, various contracted packages together delivered an integrated
through design, build and transfer into operation, ensuring solution. This meant all parties needed to understand the
control of the information defining the assets at all times. relations between their deliverables and those of the other
parties. It was crucial that all of the associated technical and
non-technical interfaces were managed throughout the project
2 Metrolink Extension Programme lifecycle. The Integrated Delivery Team (IDT), comprising
Manchester’s modern tram system started operation in 1992 both TfGM staff and their Delivery Partner, Parsons
with the opening of Phase 1, serving Bury in the North and Brinckerhoff, also needed to ensure that at significant stages
Altrincham in the Southwest. The trams used the former in the lifecycle the configuration of the integrated system
heavy rail lines then travelled onto the streets in the heart of solution was defined and aligned with the schedule of works
the city. Phase 2 extended the service to Eccles in the West, and cost estimates, thus ensuring a balanced Project
opening in 2002. After a hiatus Phase 3 was initiated in 2007 Management Triangle [1] throughout (see Figure 2).
to deliver new services to Oldham and Rochdale to the North,

1
complete required system build for the EMN was achieved as
shown in Figure 4 [2].

Large Infrastructure Project

Project
Scope
All New Assets and
Assets that have
changed

quality Assets that


Current System haven’t changed
Build Intermediate
Figure 2: The Project Management Triangle – balancing time Configuration System Build
Required System
Build Configuration
Configurations
cost and quality to ensure a consistent definition of the scope (RSBC)
at all times in the project lifecycle.
Figure 4: As a new Large Infrastructure System is delivered
3.1 System Breakdown Structure (SBS) in phases it creates a number of Interim System Build
Configurations comprising existing and new assets.
The product of the MEP was an integrated system, the
Expanded Metrolink Network (EMN), which now carries
4 Stages of the Asset Lifecycle
passengers across the Greater Manchester conurbation
(population circa 3 million). At each migration phase a new The project phase was only one part of the complete asset
system was delivered and integrated into the existing system. lifecycle and was relatively short compared with the expected
Figure 3 illustrates the system and its major elements, which life of most assets [3] (see Figure 5). However, defining the
are trams, infrastructure, control and operations, which align configuration of the new assets and the overall system at the
conveniently and directly with the contractual packaging of project phase was critical for effective operation of the system
the works. At the third level of this System Breakdown and for asset management.
Structure (SBS) are the main components of each element
such as the type of tram, control functions, structures,
utilities, the depot, operations resources, etc.

Highways Metrolink Expanded Network National Rail

Infrastructure Operations Metrolink Existing Network Phase 3 Project Systems Infrastructure Operations Figure 5: A typical Project ‘V’ Lifecycle is relatively short
compared to the lifetime of the asset.

Trams Control Infrastructure Operations


On the MEP the well-known ‘V’ Systems Engineering
M5000 M68 ATS TMS Interim NMC Depot Stops Civil & Utility PWay Comms Traction OLE Operators Rules & Infrastructure
lifecycle was applied during the project [4]; the left hand side
Structures Services Power & Drivers Procedures Managers
was where the system was defined and the right hand side
Shelters TVMs Validators

where the system was built, integrated, tested and


Figure 3: High level System Breakdown Structure for the commissioned into service. Once the high level system
expanding Metrolink network requirements and design had been defined and allocated in the
contract specifications, the middle part of the ‘V’ was
Continuing with this logical decomposition of the system developed and delivered by the contractors. It was thereafter
would end up with the detailed definition of the physical, important for the IDT to keep control of the scope of the
functional and human assets that together provide the required system, to ensure all parties developed their elements,
service. The SBS in Figure 3 indicates, even at the higher including the interfaces identified in the SBS, and that the
levels, how many interfaces need to be considered as the various parts were integrated and proven (verified and
system is specified, built and transferred into service. At all validated) to meet the requirements. This was achieved by
levels it is necessary to consider the other transportation defining the system configuration and baselining it in reviews
systems, roads and rail, with which the EMN interfaces. at key stage gates in the project lifecycle, as developed and
applied successfully on another project [5] and shown in
Figure 6.
3.2 System Configuration
The existing EMN was defined in various Asset Management
The configuration of the expanding network significantly Systems developed over the life of the network (more than 20
changed at each migration phase; as each new extension and years) by the organisations involved in delivering, operating,
the new service it provided entered operation. The built maintaining and managing the different parts. To obtain a
system’s configuration at each migration comprised the single, consistent definition of the existing system as shown
existing network assets and the new assets added until the in the SBS was therefore not feasible. However, by
understanding the requirements for the format and detail

2
required by each Operations and Maintenance (O&M) party to confirm that testing and commissioning had been
and controlling the definition of the System using completed satisfactorily.
Configuration Baselines, the appropriate asset information For the infrastructure to be handed into maintenance its
could be assembled for handover. configuration had to be known. The record of any
outstanding defects or incomplete work was appended to the
maintenance AMP form (AMP04), which when signed by the
Maintainer, Constructor and Asset Owner was the formal
acknowledgement of the state of the asset at handover.

5.2 Establishing an Operational Readiness (Go-live)


Process
Having established the System Configuration Baseline
defining what was to be delivered (the product of each
delivery project), how it was to be delivered (the engineering
process) and having a well-defined asset transfer mechanism,
the IDT’s focus turned to the final stages of the project
lifecycle and start of the operational service. Both the IDT
Figure 6: The MEP defined 4 Stage Gates where the System and the O&M organisations were finding the transfer into the
Configuration was verified, validated and then baselined. operation extremely demanding and somewhat inefficient. An
extensive checklist of activities that had been imposed served
5 Transfer into Service to complicate and increase the burden on the various teams
during this critical period and it was clear that the transfer
5.1 Transferring Responsibility for Assets into service needed to be streamlined. The IDT therefore went
back to basic principles, took notice of the way the System
The formal mechanism for recording the transfer of the Configuration was being managed and, in consultation with
system into operation and maintenance was the the stakeholders, developed an Operational Readiness process
Handover/Handback process, which was part of TfGM’s based on the progressive integration of the levels in the SBS
Safety Management System (SMS). This controlled the and the stage gates in the project lifecycle where key
transfer of responsibility for the new or modified assets from decisions needed to be taken.
the Constructor to the Operator and the Infrastructure This led to a process which considered activities in two
Manager. The Handover/Handback process recorded the “Environments” which:-
acknowledgement of the relevant parties to the change in the 1. Delivered the Project scope
status of the system using a series of signed forms, known as 2. Prepared the O&M Environment for the delivery
AMP forms. There were separate, interdependent AMP forms
for the transfer of operation (AMP03) and for the transfer of
5.3 Delivering the Project
maintenance responsibilities (AMP02 and AMP04), see
Figure 7. The parties involved were the Asset Owner and The logic structure for the Project Environment of the
Manager, TfGM, the System Operator, MRDL, and the Operational Readiness, or “Go-live”, process was naturally
Infrastructure Maintainer, depending on the location, either biased towards the back end of the ‘V’ lifecycle. As the point
MPT (for the new extensions) or MRDL (for the changes to for delivering the constructed system into operation
the pre-existing network) and the constructor. approached, the scale of the project integration increased.
Handover Handback Handback
The Go-live process was set out using a framework starting
Asset in Operate
Operate &
Maintain
Engineering Operate Operate & Maintain with the stage gates where significant integration occurred
& Maintain Defects Liability between the 4 SBS elements (e.g. testing of the dynamic
AMP 01
AMP 02 AMP 03 AMP 04 AMP 05 envelope provided by the infrastructure for the trams) and/or
Handback Handback
an aspect of one of the elements started to affect the O&M
New Asset
Construction Operate or Maintain Operate & Maintain

Defects Liability
Environment (e.g. energisation of the infrastructure’s traction
AMP 03/04 AMP 04/03 AMP 05 power). Eventually the integration reached the System level
Handback Handback (& where there are also stage gates for Safety and System
IMSCC)
Construction Energisation Dynamic Testing SAT A (Test
Running)
SAT B
(Trial Ops)
SAT C
(Operate & Maintain)
Assurance.
Whole New Line
Driver
Training
Defects Liability The framework is shown in Figure 8 where the horizontal
AMP 03 AMP 04 AMP 05
bands represent the SBS and the vertical axis represents the
order in time when the stage gates (represented by diamond
Figure 7: TfGM’s AMP Process uses the exchange of forms shaped symbols) logically occur. Whilst the detail may not be
to record the status and transfer of responsibility for assets. clear in the figure at this scale it clearly shows the progressive
integration of the sub-systems and elements (blue diamonds)
The AMP form recording the transfer into operation (AMP03) as the project reaches the main milestones (stage gates) at
included separate sections associated with each sub-systems which a decision to proceed needs to be taken.
to be signed by the relevant constructor’s competent engineer

3
Stage Design Build Install Test & Commissioning Integration & Proving Putting in to Service
stakeholder communication, and discharge of legal, planning
Construction Site Operational Tramway when working on or near the line
and regulatory obligations.
S
R
C
Interim SRC submissions may be required dependent upon delivery staging S
R
C
Based on the experience from the initial migration phase it
KEY

System
S
B
R
T
R
R
was decided to start the Go-live process 16 weeks from the
Critical Path
P

R
O
S
R
R
S
R programmed dated for entry into Passenger Service.
Operational Readiness Stage Gate

R Technical Assurance Stage Gate


R

Safety Assurance Activity

Review
5.5 Tracking Operational Readiness
R Sufficient trams of correct variant/configuration
F
Trams CC Construction Completion

I
DRT
IA
OSRR
With the logic defined and the basic principles established,
Drivers Ready for Training
Infrastructure Acceptance
Operational Service Readiness Review
R OR Operational Review
R PSRR
IRR
RFO
the next step was to identify the key activities associated with
Passenger Service Readiness Review
Infrastructure Readiness Review
Ready For Operation

each environment and to identify each activity’s completion


C R I
Infrastructure RR Readiness Review
C T A RRR Route Readiness Review
RTE Ready To Energise
SBR System Baseline Review

Control
T
R
T
R
SRC
TRR date associated with the relevant stage gate. In deciding what
Safety Review Committee
Test Readiness Review

activities to include, it was important that the process did not


Operations
O
R
O
R
revert to being onerous or be perceived by participants as
micro-management. It had to encourage engagement and add
Figure 8: Illustrating the Project Environment in the value to existing processes. The activities were divided into
Operational Readiness Process those relating to the delivery of the project and those relating
to the operational preparedness and grouped under the
At the System level (grey) the decision to proceed at the relevant stage gate.. A management tool, the Go Live
Safety Assurance gates (orange diamonds) was made by the Readiness Tracker (GLRT), was used to monitor progress.
Safety Review Committee (SRC). The first Safety Assurance The GLRT used spreadsheets to display the status of the
stage gate was before the Ready to Energise (RTE) stage gate activities in the Project Environment and the O&M
within the Infrastructure element. The System Assurance Environment. Additional worksheets were used to record
process is represented by the green diamonds. Having critical issues and actions, and record the document status for
completed the System Baseline Review (SBR), at which the version control purposes.
Configuration Baseline content was confirmed as representing Prior to the start of the Go-live process at T-16 weeks (where
the System Build that has been planned and specified (i.e. the T is the date for the start of passenger services) a meeting was
scope of the system has been defined), the next System held with the team members responsible for project delivery,
Assurance stage gate was passed if the integrated elements for preparing the O&M environment and for managing the
are ready for the System Acceptance Tests. This was the Test system when in operation. At this meeting all the functional
Readiness Review (TRR) stage gate. The System Acceptance leads would identify the programme outputs within their
Tests lead to the Route Readiness Review (RRR) stage gate at domain appropriate for inclusion in the GLRT, which
which it was decided whether the infrastructure, trams and required a judgement to be made about the level of detail to
control elements are sufficiently integrated to permit driver be included and collectively agreed by relevant attendees.
training to start. The System Acceptance Testing continued This form of collaborative working, engaging all disciplines
during the Driver Training stage after which there is a stage as it did, ensured an early commitment to the process and a
gate to decide whether to hand the System to the Operator for sense of ownership from each of the responsible parties. The
final proving that it will deliver the service required during a agreed activities were added to the relevant environment
period of Shadow Running. This was the Operational Service worksheets and grouped under generic functional areas for
Readiness Review (OSRR) and was where the System each stage gate. This structure ensured that timely progress
Assurance and Operational Readiness processes met. The was easily monitored and that there was early identification of
successful completion of Shadow Running lead to the stage activities that were at risk of delay.
gate to decide to start to carry passengers, the Passenger As an assurance tool it was important for the MEP that the
Service Readiness Review (PSRR). This marked the point at GLRT provided a repository of evidence to support the Case
which the project was deemed to have delivered the scope for for Safety and aligned with the status of the items in the
the associated migration phase and that the system had been Configuration Baselines. It was therefore agreed that
successfully brought into the O&M Environment. completion could only be recorded using agreed validation
criteria, and the type of assurance evidence depended on the
5.4 Preparing the O&M Environment for Delivery nature of each separate activity. As the process matured a
further innovation was developed for the GLRT. The initial
The Go-live Process involved the O&M parties in the Red-Amber-Green (RAG) indication of status was found to
Transfer into Service Stage hence ensuring they understood be too coarse a measure of progress and was replaced with a
the System that they were getting and were ready to receive it. measure in ten percentile increments.
However, it also ensured that the Project Team understood the Go Live Working Group (GLWG) meetings were held
expectations for the System they needed to deliver to satisfy regularly (fortnightly from T-16 to T-8 and then weekly
sufficient O&M requirements to gain acceptance. thereafter) where the activities in each stage gate in each of
Activities considered in the O&M Environment included the the two environments were updated. The trajectory towards
operating and maintenance procedures, timetables, passenger the completion of each activity associated with the respective
information, revenue, fares, marketing, existing operations, stage gate was presented graphically and a combined

4
Executive Summary trajectory for each environment. This In order for maintenance to be undertaken from the day of
gave a powerful visual representation of progress towards handover a sub-set of certified marked-up as-built drawings
operational readiness, enabling all involved to quickly see any was required as a record of the infrastructure’s configuration
areas requiring attention. As more data became available it and to provide the necessary technical information needed to
became possible to plot an averaged ‘idealised’ trajectory, or deliver the routine maintenance. These included, for example,
flight path, for each stage gate which in turn provided a more electrical schematics, equipment connectivity and power
accurate way of assessing progress. feeding diagrams, stop layouts and drainage layouts. The
constructor’s signature on the maintenance AMP form
(AMP04) provided the assurance that the equipment handed
over was compliant with the design, had been shown by
testing to be safe to operate and was capable of being
maintained in a safe condition.
The GLR process captured the system configuration at the
point of handover to operation and hence provided a record of
any incomplete activities. This list of activities was appended
to the relevant AMP form together with a statement of any
associated operational restrictions; hence the AMP form was
Figure 9: The GLRT tool provides graphical indicators that the record of acknowledgement by the operator of any
allow managers to quickly see where there may be problems. incomplete activity and any restriction to operation.

There was no restriction on the continued development of the 5.7 Post Handover
GLRT for the associated migration phase; activities could be
removed or new activities included as agreed by the It was acknowledged that some activities did not need to be
responsible parties during the 16 week period. complete at the point at which operation commenced and,
The process and tool are now well established. The either needed to be completed as soon as practicable
developed Go Live format is embedded within the MEP and a thereafter, or could be completed at a later stage in the overall
key component of each Project Manager’s toolbox. The proof project. For example, a junction may be inserted into an
of its effectiveness is that it has been employed successfully existing line in preparation for the construction of a future
to track, monitor and report operational preparedness over diverging route. The junction would become partly
multiple migration phases. operational to allow the continuing passage of trams along the
existing route but would only become fully operational once
5.6 The Handover the branch line was completed. In this example the
intermediate configuration results in an operational
The preparations for operation made by the operator in restriction, in that the junction can only be traversed on the
collaboration with the constructor were tracked by the GLR through route. Once in operation there are still a number of
process. In parallel with these activities, the pre-existing Performance, Reliability, Availability, and Maintainability
system and new lines already brought into operation requirements which can only be proven after an extended
continued to operate. Although MRDL had a separate team to period of in-service operation and which the Project Team
manage network expansion there were still key activities needed to work with the O&M parties to conclude.
which needed to be carried out by the team doing the “day
job”, for example, all tram drivers needed to be trained on the 6 Tying up the ‘Loose Ends’
new route(s), new timetables and driver rosters needed to be
developed and customer facing staff needed to become Whilst the System for a particular migration phase might have
familiar with the characteristics of the new route. The been transferred into Service there will still be several items
network expansion team managed these preparations for needing to be completed before the Project has finished its
operation to meet the key stage gates so as to present a duties e.g. final issue of documentation, provision of all asset
coherent and consistent experience for customers. details required by the various maintenance Management
A coordinated asset register was developed as part of the Systems, clearance of caveats on AMP Forms, completion of
preparations for maintenance and based on this the non-critical outstanding works and snagging and defect
maintenance schedule and related maintenance instructions clearance. At this time the delivery organisations are under
were produced. Training, spares, tools and other logistical pressure to reassign their experienced resources and minimise
equipment were all required for maintenance to start. The remaining costs so there is a potential risk to the timely
need for the maintenance staff to undertake training on new completion of the transfer of all the assets and their associated
equipment, the logistics of which were not at first well information. Recognising this could present a significant
planned, was managed as part of the GLR process. The need potential risk to the O&M parties and particularly to the Asset
to release front-line maintenance staff from the “day job” Owner and Manager, a process to manage Project Close-out
without affecting their ability to deliver reactive and was developed. The Close-out Process firstly defined the
preventative maintenance required careful planning. grouping of projects and work packages that constituted a
logical complete achievement of an objective of the initial

5
business case e.g. provision of a 12 minute passenger service the installed assets. Reviewing and assessing the information
from the City Centre to Rochdale via Oldham. It then for quality and content was an onerous task carried out
considered the Close-out in terms of completing the transfer typically during and after the point of handover. In the future,
of all the assets into the O&M Environment and the contractual arrangements should be structured so that delivery
completion of all associated commercial aspects. of as-built information takes place continuously throughout
By analysing the work streams and functions responsible for the project and is aligned with stage payments. To achieve
closing out either the Asset Transfer or Commercial aspects a this definition of the Configuration of the System needs to be
number of metrics were identified that could be quantified readily translated into the Configuration Management
and tracked to completion. A tracking tool was created with a Systems of the O&M parties who would also need to provide
dashboard front end for monitoring close-out progress for a clear set of requirements for asset information which would
each Grouping in the following major categories:- need to be cascaded throughout the supply chain [6]. The
 Asset Transfer improvements in this area do not need to be developed from
 Safety Assurance scratch as the specifications for Building Information
Modelling (BIM) provide just the kind of structured
 Operational
framework needed for the management of asset information
 Financial / Contract Completion through a project lifecycle. It is proposed that future projects
Completion of Close-out for all categories was set for the adopt BIM principles which would make the transfer of
expected end of contractual liability (e.g. end of the defect information much more efficient whilst also reducing
liability or the warranty period). Responsibilities for the redundancy in the information provided and improve its
close-out of each sub-category were assigned and progress accuracy [7].
monitored at monthly intervals. A RAG indication was used The increasing use of digital technology in design, project
to highlight deviations from the expected rate of clearance so control, communication and asset management is helping
as to provide a simple but effective way to signal to senior make the delivery and maintenance of new infrastructure
management the areas that required further investigation and systems more effective and efficient. BIM has matured into
attention. an industry standard [8] and systems can be captured,
visualised, modelled, rendered, refined and recorded
throughout their life from concept to decommissioning.
Assets can now be said to have a digital life as well as a
physical one and it is a digital legacy the delivery project
provides for the Asset Managers of the future.

References
[1] INCOSE, “Guide for the Application of Systems
Engineering in Large Infrastructure Projects” INCOSE-
TP-2010-007-01 version 3.0 (2012).
[2] Knott, A., “Applying Configuration Management
Principles on a Large Scale Operational Railway
Infrastructure, Railway Engineering Conference (2004).
[3] INCOSE UK, “Applying Systems Engineering to In-
Figure 11: A dashboard showing the progress towards close- Service Systems – Supplementary Guidance to the
out of relevant functional areas of the project. INCOSE SE Handbook”, ls-tr-005, Issue 1.0 (2010).
[4] INCOSE, “Systems Engineering Handbook – A Guide
7 Lessons for the Future Extensions for System Life Cycle Processes and Activities”,
INCOSE-TP-2003-002-03.2.2 (2011).
Metrolink continues to expand with a second city crossing, [5] Knott A. & Stubbs M. Q., “Innovative Systems
which will significantly increase capacity across the network, Engineering Practices that help manage the
and a line through the rejuvenated Trafford Park area. This Organisational and Technical Complexity of a Modern
continuing development, combined with the opportunities Railway Project”, International Conference on Railway
presented by the need to enter a new arrangement for O&M Engineering (ICRE2008), Hong Kong, (2008).
services when the current franchise expires in 2017, [6] Ross Dentten, “Enabling Quality Asset Information to
encourages TfGM to continue to learn lessons from the past support the Crossrail Smart Railway”, Asset
and to keep abreast of the latest industry practices and Information and Data Management for Smart Rail
technologies. (2014)
The success of the Go-live Process depended on being able to [7] HM Government, “Building Information Modelling”,
identify key activities for the transfer from project to O&M URN 12/1327 (2010)
and bring them further forward in the programme. During [8] Institute of Asset Management, “An Anatomy of Asset
successive iterations of the process it became apparent that an Management”, Issue 1.1 (2012).
area for improvement was the transfer of information about

You might also like