You are on page 1of 118

DEMOCRATIC SOCIALIST REPUBLIC OF SRI LANKA

SUPPORT TO COLOMBO URBAN REGENERATION PROJECT


(SCURP)

MONTHLY PROGRESS REPORT

MINISTRY OF URBAN DEVELOPMENT AND HOUSING


JANUARY 31, 2022

Prepared by: State Engineering Corporation of Sri Lanka


Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

CONTENT PAGE

1.0 General Information ……………………………………………………………………………... 01


1.1 Introduction ………………………………………………………………………………………... 01
1.2 Project structure …………………………………………………………………………………… 01
1.3 Construction Site Locations ……………………………………………………………………….. 02
1.4 Description of the site locations…………………………………………………………………… 03
1.5 Description of Projects…………………………………………………………………………….. 04

2.0 Progress of work ……………………………………………………………………………… 06


2.1 Physical and Design Progress……………………………………………………………………… 06
2.1.1 - Stadiumgama…………………………………………………………………………………... 06
2.1.1.1 Preliminary Work………………………………………………………………………….. 06
2.1.1.2 Design work………………………………………………………………………………... 06
2.1.1.3 Sub structure ………………………………………………………………………………. 07
2.1.1.4 Super structure……………………………………………………………………………... 08
2.1.1.5 Overall progress of site – Scheduled Vs. Achieved ………………………………………… 08

2.1.2 - Colombage Mawatha………………………………………………………………………….. 10


2.1.2.1 Preliminary Work …………………………………………………………………………..10
2.1.2.2 Design work ……………………………………………………………………………...10
2.1.2.3 Sub structure ………………………………………………………………………………..11
2.1.2.4 Super
structure………………………………………………………………………………11
2.1.2.5 Overall progress of site – Scheduled Vs. Achieved …………………………………………11

2.1.3 Obeysekarapura ………………………………………………………………………………….13


2.1.3.1 Preliminary Work ………………………………………………………………………….. 13
2.1.3.2 Design work …………………………………………………………………………..….13
2.1.3.3 Sub structure ………………………………………………………………………………..14
2.1.3.4 Super structure……………………………………………………………………………... 14
2.1.3.5 Overall progress of site – Scheduled Vs. Achieved…………………………………………14

2.1.4 Applewatta….……...……………………………………………………………………………. 16
2.1.4.1 Preliminary Work ………………………………………………………………………….. 16
2.1.4.2 Design work …………………………………………………………………………….. 16
2.1.4.3 Sub structure …………………………………………………………………………….… 17
2.1.4.4 Super structure……………………………………………………………………………... 17
2.1.4.5 Overall progress of site – Scheduled Vs. Achieved …………………………………………17

2.1.5 Furgusion Road …………………………………………………………………………………..19


2.1.5.1 Preliminary Work …………………………………………………………………………...19
2.1.5.2 Design work ……………………………………………………………………………...19
2.1.5.3 Sub structure ………………………………………………………………………………..20
2.1.5.4 Super structure………………………………………………………………………...……20
2.1.5.5 Overall progress of site – Scheduled Vs. Achieved…………………………………………20

2.1.6 Madampitiya……………………………………………………………………………………...22
2.1.6.1 Preliminary Work …………………………………………………………………………..22
2.1.6.2 Design work….………………………………………………………………………………22
2.1.6.3 Sub structure ………………………………………………………………………………..23
2.1.6.4 Super structure………………………………………………………...……………………23

Monthly Progress Report No. 07 (Month of January, 2022)


Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

2.1.6.5 Overall progress of site – Scheduled Vs. Achieved…………………………………………23

2.2 Resource Personnel…………………………………………………………………………….……25


2.2.1 Stadiumgama…………………………………………………………………………..................25
2.2.1.1 Labor Histogram…………………………………………………………………………..….25
2.2.1.2 Key Staff Personnel……………………………………………………………………….….25
2.2.2 Colombage Mawatha…………………………………………………………………..................27
2.2.2.1 Labor Histogram……………………………………………………………………….….….27
2.2.2.2 Key Staff Personnel………………………………………………………………….……….27
2.2.3 Obesekarapura…………………………………………………………………………................29
2.2.3.1 Labor Histogram…………………………………………………………………….……….29
2.2.3.2 Key Staff Personnel……………………………………………………………………….….29
2.2.4 Applewatta…..…………………………………………………………………………................31
2.2.4.1 Labor Histogram………………………………………………………………….……….….31
2.2.4.2 Key Staff Personnel……………………………………………………………………….….31
2.2.5 Ferguson Road….……...………………………………………………………………................33
2.2.5.1 Labor Histogram…………………………………………………………….…………….….33
2.2.5.2 Key Staff Personnel……………………………………………………………………….….33
2.2.6 Madampitiya….….……………………….……………………………………………................35
2.2.6.1 Labor Histogram………………………………………………………….……………….….35
2.2.6.2 Key Staff Personnel…………………………………………………………………………..35

2.3 Approvals…………...……………………………..………………………...………………………37
2.3.1 Material Approval Summary…………..……………………………..……………………..……37
2.3.1.1 Stadumgama………………………………………………………………..……………..….37
2.3.1.2 Colombage Mawatha………………………..……………………………..……………..…..44
2.3.1.3 Obesekarapura……...………………………..……………………………..……………..….50
2.3.1.4 Applewatta…………………………………..……………………………..…. ………….….53
2.3.1.5 Furgusion…………..………………………..……………………………..……………..…..57
2.3.1.6 Madampitiya……….…………………...…..……………………………..……………........59
2.3.1 Drawings Approval Summary…………..…..………………………..……………………..……63
2.3.2.1 Stadumgama………………………………………………………………..……………..….63
2.3.2.2 Colombage Mawatha………………………..……………………………..……………..…..66
2.3.2.3 Obesekarapura……...………………………..……………………………..……………..….71
2.3.2.4 Applewatta…………………………………..……………………………..…. ………….….75
2.3.2.5 Furgusion…………..………………………..……………………………..……………..…..79
2.3.2.6 Madampitiya……….………………………….…………………………..………………....83

Monthly Progress Report No. 07 (Month of January, 2022)


Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

2.4 Financial Progress…………………………………..………………………………………….……88


2.4.1Work done certificate…………………..……………………………..……………………..……88
2.4.1.1 Stadumgama………………………………………………………………..……………..….88
2.4.1.2 Colombage Mawatha………………………..……………………………..……………..…..89
2.4.1.3 Obesekarapura……...………………………..……………………………..……………..….90
2.4.1.4 Applewatta…………………………………..……………………………..…. ………….….91
2.4.1.5 Furgusion…………..………………………..……………………………..……………..…..92
2.4.1.6 Madampitiya……….………………………..………………………….....………………....92
2.4.2 Variation Log……………………………..……………………………..……………….…….....93
2.4.2.1 Stadumgama……………………………………………………………..…………………...93
2.4.2.2 Colombage Mawatha………………………..…………………………..…………………...93
2.4.2.3 Madampitiya……….………………………..……………...…………..……………………94
2.4.3 Claim Log-Cost………………………………………………………..…………………………..95
2.4.3.1 Stadumgama……………………………………………………………......………………...95
2.4.4 Claim Log-Extension of Time………...…………………….…………….…………………...….96
2.4.4.1 Stadumgama…………………………..……………………………………………..…...…..96
2.4.4.2 Colombage Mawatha………………………....………………………………………………97
2.4.4.3 Obesekarapura……...……………………..……………………..……………………….…..99
2.4.4.4 Applewatta………………………………….……………………………………..….…….100
2.4.5 Executive Summary……………..………...……………………………..…………………..…101
2.4.6 Major Achievements in last month………………………………………………...……………102

2.5 Progress of Health and safety provision and Implementation of Environmental provision......103

2.6 Progress photos………………………………………………………………………………….....106


2.6.1 Stadiumgama…………………………………………………………………………………....106
2.6.2 Colombage Mawatha……………………………………………………………………………107
2.6.3 Obeysekarapura……………………………………………………………………………...….108
2.6.4 Applewatta…………………………………...………………………………………………....109
2.6.5 Furgusion Road………………………………………………………………………………….110
2.6.6 Madampitiya………………………………………………………………………………….....111

3.0 Clearances and Building permits……………………………………………………………...…112

4.0 Prevailing drawbacks……………………………………………………………………………...114

Monthly Progress Report No. 07 (Month of January, 2022)


Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

1.0 GENERAL INFORMATION


1.1 INTRODUCTION
The objective of Support to Colombo Urban Regeneration Project (SCURP) is to improve
the housing conditions of low-income communities and increase land use efficiency in Colombo
through investments in the construction of affordable housing and redevelopment of land, along
with the associated enhancement of systems and policies. The proposed results indicators for these
objectives include: (i) number of low-income and lower-middle income households that move
from underserved settlements to newly construct housing units with improved utilities and
facilities, and under improved resettlement practice; and (ii) the increase in the land value of the
areas made available for redevelopment.
The proposed project will support through three main project components are outlined below.

Component 1: Housing Construction.


The component will support construction of about 5,500 housing units in multi-story apartment
buildings in eight or nine residential complexes (sub-projects) 5 with provision of full
infrastructure.
Component 2: Land Redevelopment.
This component will maximize the revenue from the land that has or will become available after
the households in the underserved settlements move into the new apartment units constructed.
Component 3: Technical Support and Project Management.
This component will support project management and other quality enhancement measures to
improve the implementation.
This report is prepared only for the progress of component 01 ongoing projects.

1.2 Project Structure

Funded by - AIIB

Employer - Ministry of
Urban Development &
Housing

Implementing Agency
- Urban Development
Authority

Engineer - PMU of
SCURP (AIIB)

Engineer’s Representative
- State Engineering Contractor
Corporation (SEC)

1
Monthly Progress Report No. 07 (Month of January, 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

1.3 Site Locations


Project Locations are marked in the below Map.

2
Monthly Progress Report No. 07 (Month of January, 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

1.4 Description of the Site Locations


PROJECT NAME ADDRESS SURROUNDED LAND MARKS

North – Port Access Road


No 475/1, Sirimawo
East – Sirimuthu Uyana Flats
STADIUMGAMA Bandaranayake
South – Access Road to Sirimuthu Uyana Flats
Mawatha,Colombo 14
West –Stadiumgama United Ground

North – Canal
No. 40/100, 5th Lane,
East – Canal
COLOMBAGE Colombage Mawatha,
South – HRL Site (Another low-income
MAWATHA Kiruolpone.
housing project)
West – 5th Lane, Colombage Mw.

No. 340, Arunodaya


North – Arunodaya mawatha
Mawatha,
OBEYSEKARAPURA East – Private Road
Obesekarapura
South – Canal
Rajagiriya
West – Private Road

North – Canal& Existing Building (Laksetha


Sewana)
No.130 , Temple East – R Premadasa International Cricket
APPLEWATTA Rd,Applewatta, Stadium
Colombo10 South – Kaleel playground & Canal
West – Sebestian Canal Road &
Maligawatta Place

North – Muwadora Uyana


East – Ferguson Road
FURGUSION ROAD Ferguson Road,
South – Kelani Bridge (Thotalanga)
Colombo 14.
West – Sanken Construction (Pvt) Ltd.

North – Madampitiya Road


No 320, Madampitiya East – Sri Jinarathanaramaya Buddhist Temple
MADAMPITIYA
Road, Colombo 14 South – Canal and CMC Aurvedic dispensary
West – Red bull Factory

3
Monthly Progress Report No. 07 (Month of January, 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

1.5 Description of Projects


Project Name Project Description
Contract Name Design and Construction of 1000 Housing Units at
Stadiumgama
Contract No SCURP/2019/C1-W/004
No. of Housing Units 1000 housing units
No. of Towers Four building Blocks
No. of Floors Fifteen (G+14) stories
Stadiumgama
Accepted Contract Price LKR 5,950,950,000.00 (5.95 Billion)
Contractor’s Name ACCESS Engineering PLC
Date of commencement 4th May 2020
Contract Period 1260 Days
Date of Completion 16th October 2023
Contract Name Design & Construction for Completion of Balance
work 624 Housing Units at Colombage Mawatha
Contract No SCURP/2019/C1-W/002

No. of Housing Units 624 housing units


No. of Towers Two building Blocks
No. of Floors Twelve (G+11) stories
Colambage
Mawatha Accepted Contract Price LKR. 3,126,568,267.17 (3.126 Billion)
Contractor is entitled a variation for existing pile test
Contractor’s Name MAGA Engineering (Pvt) Ltd.

Date of commencement 01st June 2020


Contract Period 1080 Days
Initial Date of Completion 16th May 2023
EOT Contractor is entitled for EOT for existing pile test
Contract Name Design & Construction of 300 housing units at
Obesekarapura Rajagiriya
Contract No SCURP/2019/C1-W/005
No. of Housing Units 300 housing units
No. of Towers 01 Block
Obeysekarapura No. of Floors Sixteen (G+15) stories
Accepted Contract Price LKR 1,723,347,855.00 (1.723 Billion)
Contractor’s Name Subasinghe Contractors (Pvt) Ltd.
Date of commencement 04th May 2020
Contract Period 900 Days
Date of Completion 21st October 2022

4
Monthly Progress Report No. 07 (Month of January, 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

Contract Name Design & Construction of 700 Housing Units at


Applewatta
Contract No SCURP/2019/C1-W/001
No. of Housing Units 700 housing units
No. of Towers 03 Blocks
No. of Floors Sixteen (G+15) stories
Applewatta Accepted Contract Price LKR.1,556,000,000.00 and USD 12,843,066.42
Contractor’s Name China Railway 25th Bureau Group Corporation
Ltd.
Date of commencement 27th October 2020

Contract Period 1086 Days


Date of Completion 17st October 2023

Contract Name Design & Construction of 750 Housing Units at


Ferguson Road, Colombo14
Contract No SCURP/2019/C1-W/003
No. of Housing Units 750 housing units
No. of Towers Three building Blocks
No. of Floors Sixteen (G+15) stories

Furgusion Road Accepted Contract Price LKR. 1,569,011,564.00 and USD 12,788,394.77

Contractor’s Name China Civil Engineering Construction Corporation


& China Railway 25th Group Joint Venture (Pvt)
Ltd.
Date of commencement 20th Jan 2021
Contract Period 1080 Days
Date of Completion 04th January 2024
Design & Construction of 700 housing units at No
Contract Name
320, Madampitiya Road, Colombo 14
Contract No SCURP/2019/C1-W/006
No. of Housing Units 700 housing units
No. of Towers Four building Blocks
Madampitiya No. of Floors Fifteen (G+15) stories
Accepted Contract Price LKR 3,936,638,501.87 (3.936 Billion)
Contractor’s Name Tudawe Brothers (Pvt.) Ltd
Date of commencement 20th of May 2021
Contract Period 1080 Days
Date of Completion 3rd of May 2024

5
Monthly Progress Report No. 07 (Month of January, 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

2. PROGRESS OF WORK
2.1 Physical & Design Progress
2.1.1 Stadiumgama
2.1.1.1 Preliminary Work
Total preliminary work progress is 53.34% which is tabulated in below table. All the
preliminaries have been implemented. But it includes Running cost and Final payment. Hence,
percentage of the progress increases with the time and 100% shall be achieved at the completion
of the project.
Item Progress
Insurance & Securities 100.00%
Engineer’s facilities 47.93%
Contractor’s facilities 59.41%
Contractor’s management and supervision 50.00%
Quality, Standards and Progress 71.58%
Health, Safety & Environment 54.48%
Security, Fencing & Protection 47.50%
Services and Facilities 42.49%
Miscellaneous 94.98%
Total 53.34%
2.1.1.2 Design Work
Total design progress is 82.50% which is tabulated in below table.
No Design / Drawing Preparation Progress

1 Architectural Services
i Concept Designs 100.00%
ii Council 70.00%
iii Construction Drawings 90.00%
2 Sub Structure
i Piles 100.00%
ii Pile caps & plinth beams 100.00%
iii Ground floor slab 100.00%
3 Super Structure 96.00%
4 Sump 90.00%
5 Plumbing
i Water supply 100.00%
ii Waste water 60.00%
6 Electrical 80.00%
7 Fire and LPG 86.00%
8 External 27.00%
CARRIED TO GRAND SUMMARY 82.50%

6
Monthly Progress Report No. 07 (Month of January, 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

2.1.1.3 Sub Structure


Total Sub structure progress is 86.30%, which is tabulated in below table.
Work Trade Progress
Piling (67 Piles) 100%
Pile Testing PIT -100% (67 Piles)
PDA -100% (4 Nos)
Block A Earth filling 62.3%
Pile caps 100%
Ground Beams 100%
Anti-termite Treat. & N/A
Ground Floor Slab
Piling (67 Piles) 100 %
Pile Testing PIT -100%
PDA -100% (4 Nos)
Block B Earth filling 62.3%
Pile caps 100%
Ground Beams 100%
Anti-termite Treat. & N/A
Ground Floor Slab
Piling (67 Piles) 100 %
Pile Testing PIT -100% (67 Piles)
PDA -100% (3 Nos)
Block C
Earth filling 64.6%
Pile caps 100%
Ground Beams 100 %
Anti-termite Treat. & N/A
Ground Floor Slab
Piling (68 Piles) 100 %
Pile Testing PIT -100% (68 Piles)
PDA -100% (3 Nos)
Block D Earth filling 62.4%
Pile caps 100%
Ground Beams 100 %
Anti-termite Treat. & N/A
Ground Floor Slab
Total Progress 86.30%

7
Monthly Progress Report No. 07 (Month of January, 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

2.1.1.4 Super Structure


Total Super structure progress is 70.02%, which is tabulated in below table.
PROGRESS

Block A 43.67%

Block B 48.33%

Block C 93.75%

Block D 94.33%

Total 70.02%

2.1.1.5 Masonry and Finishes


Total Masonry and Finishes progress is 7.17%, which is tabulated in below table.
PROGRESS

Block A 0%

Block B 0%

Block C 11.67%

Block D 17.00%

Total 7.17%

2.1.1.5 Overall Progress of Site


Description Progress Details
Scheduled Achieved Delay Average
Labor
Count
Overall Cumulative 36.70% 39.61% 0 Days 410
progress as of 31st
of January 2022

8
Monthly Progress Report No. 07 (Month of January, 2022)
PROGRESS(%)

0
10
20
30
40
50
60
70
80
90
100
0.51
0.15
2.34
0.56
4.24
1.26
4.84
1.53
5.8
2.66
6.86
4.17
7.94
4.87
9.58
5.72
10.81
6.87
11.54
8.87
12.15
11.92
12.81
13.04
14.89
16.41
17.49
17.73
Scheduled

20.58
20.61
23.22
23.45
25.56
26.91
28.24
29.38
Actual
Support To Colombo Urban Regeneration Project (SCURP – AIIB)

31.02
31.38

Monthly Progress Report No. 07 (Month of January, 2022)


33.85
35.65
36.7
39.61
40.02
44.05
TIME (MONTHS) 47.44
Scheduled Series

52.14
STADIUMGAMA PROJECT

57.23
SCHEDULED VS ACHIEVED

62.46
68.68
74.05
Actual Series

78.78
82.44
85.95
88.86
91.16
93.14
Urban Development Authority, Sri Lanka

94.39
9

97.04
98.69
99.33
99.63
99.87
100
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

2.1.2 Colombage Mawatha


2.1.2.1 Preliminary Work
Total preliminary work progress is 56.19% which tabulated in below table. All the preliminaries
have been implemented and it includes Running cost and Final payment. Hence, percentage of the
progress increases with the time and 100% shall be achieved at the completion of the project.
Item Progress

Insurance & Securities 100.00%


Engineer’s facilities 58.10%
Contractor’s management and supervision 54.07%
Design, Quality, Standards and Progress 59.08%
Health, Safety & Environment 49.45%
Security, Fencing & Protection 54.05%
Services and Facilities 54.05%
Miscellaneous 88.20%
Total 56.19%

2.1.2.2 Design Work


Total design progress is 91.50% which is tabulated in below table.

No Design / Drawing Preparation Progress


1 Architectural Services
i Concept Designs 100.00%
ii Council 100.00%
iii Construction Drawings 100.00%
2 Sub Structure
i Piles 100.00%
ii Pile caps & plinth beams 100.00%
iii Ground floor slab 100.00%
3 Super Structure 95.00%
4 Sump 100.00%
5 Plumbing
i Water supply 100.00%
ii Waste water 100.00%
6 Electrical 100.00%
7 Fire 100.00%
8 External 25.00%
Total 91.50%

10
Monthly Progress Report No. 07 (Month of January, 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

2.1.2.3 Sub Structure


Total Sub structure progress is 89.65%, which is tabulated in below table.
Work Trade Progress
Piling (110 New Piles) 100.00 %
73.87 % (Hacking 80 new piles)
Pile Testing
75.00 % (PIT – 80 & PDA - 6)
Excavation, Earth works & Backfilling 95.96 %
Pile caps for 330 piles 90.91 %
Ground Beams 100.00 %
Anti-termite Treat. & Ground Floor Slab 100.00 %
Water Sump 10.50 %
Total 89.65 %

2.1.2.4 Super Structure


Total Super structure progress is 13.69%, which is tabulated in below table.
Block Progress
Block 1 13.02 %
Block 2 14.36 %
Total 13.69 %

2.1.2.5 Overall Progress of Site – Scheduled vs. Achieved


Progress Details
Description
Scheduled Achieved
st
Overall Cumulative progress as of 31
26.82%** 19.94%**
January 2022
100 additional days were granted after the EOT
No. of delay days as of 31st January
evaluation. However revised master program to be
2022
submitted by MAGA.
Average labor count for the month 105 Nos.
**Schedule and achieved progress have been calculated for the programme with 1080+176
days. Hence to be re-calculated after finalizing the master programme with 100 days of EOT.

11
Monthly Progress Report No. 07 (Month of January, 2022)
PROGRESS

10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
80.00%
90.00%
100.00%

0.00%
2020-Jun1.56% 1.68%
2020-Jul 1.95% 2.04%
2020-Aug 2.72% 2.60%
2020-Sep 3.48% 3.18%
2020-Oct 4.12% 3.75%
2020-Nov 4.94% 4.31%

2020-Dec 5.12% 4.88%


2021-Jan 6.14% 5.45%
2021-Feb 7.02% 6.34%
2021-Mar 8.79% 7.58%

2021-Apr 9.70% 8.93%

2021-May 10.42% 10.26%


10.91% 11.71%

Scheduled Progress
2021-Jun
2021-Jul 12.32% 12.78%

2021-Aug 12.59% 14.38%


2021-Sep 14.00% 16.15%
2021-Oct 14.90% 18.36%
Support To Colombo Urban Regeneration Project (SCURP – AIIB)

2021-Nov 16.45% 21.13%

Monthly Progress Report No. 07 (Month of January, 2022)


2021-Dec 18.06% 23.82%

Actual Progress
2022-Jan 19.94% 26.82%

2022-Feb 29.86%

2022-Mar 33.64%

2022-Apr 37.16%
41.08%
Colombage Mawatha

TIME (MONTH/YEAR)
2022-May
2022-Jun 45.28%

2022-Jul 49.97%
Scheduled Series 54.81%
2022-Aug
2022-Sep 59.56%
Scheduled Progress Vs. Achieved Progress

2022-Oct 63.06%

2022-Nov 66.30%

2022-Dec 69.53%

2023-Jan 72.77%
Actual Sereis

2023-Feb 75.77%

2023-Mar 78.61%

2023-Apr 81.47%
Urban Development Authority, Sri Lanka

2023-May 84.90%
12

2023-Jun 88.54%

2023-Jul 91.76%

2023-Aug 94.68%

2023-Sep 97.44%

2023-Oct 99.50%

2023-Nov 100.00%
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

2.1.3 Obeysekarapura
2.1.3.1 Preliminary Work
Total preliminary work progress is 52.53% which tabulated in below table. All the preliminaries
have been implemented. But it includes Running cost and Final payment. Hence, percentage of
the progress increases with the time and 100% shall be achieved at the completion of the project.
Item Progress
Insurance & Securities 93.25%
Engineer’s facilities 57.25%
Contractor’s facilities 63.26%
Contractor’s management and supervision 68.89%
Quality, Standards and Progress 34.92%
Health, Safety & Environment 43.68%
Security, Fencing & Protection 49.87%
Services and Facilities 15.57%
Miscellaneous 77.56%
Total 52.53%

2.1.3.2 Design Work


Total design progress is 48.61% which is tabulated in below table.

No Design / Drawing Preparation Progress


1 Architectural Services 68.33%
i Concept Designs 100.00%
ii Council 75.00%
iii Construction Drawings 30.00%
2 Sub Structure 75%
i Piles 100.00%
ii Pile caps & plinth beams 75.00%
iii Ground floor slab 50.00%
3 Super Structure 37.5%
4 Sump 50%
5 Plumbing 55%
i Water supply 55.00%
ii Waste water 55.00%
6 Electrical 20%
7 Fire 30%
8 External 20%
Total 48.61%

13
Monthly Progress Report No. 07 (Month of January, 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

2.1.3.3 Sub Structure


Total Sub structure progress is 84.92%, which is tabulated in below table.
Work Trade Progress
Piling (127 Piles) 100.00 %
Pile Testing
I. PIT 100 % (PIT – 127 piles out of 127)
II. PDA 33.33% (2 piles out of 6)
Excavation & Earth works 100 %
Pile caps 94.64 % (106 Pile caps out of 112)
Ground Beams 24.43 %
Anti-termite Treatment. & Ground Floor Slab 0%
Total 84.92%

2.1.3.4 Super Structure


The work of super structure is not yet commenced.

2.1.3.5 Overall Progress of Site – Scheduled vs. Achieved

Progress Details
Scheduled
Description Average
Master Mitigation program Delay
Achieved Labor
program submitted on (Days)
Count
02/10/2021
Overall
Cumulative 59.2 %
33.0 %
(Program not 11.9% 235 25
progress as of 31st
approved yet)
January 2022

14
Monthly Progress Report No. 07 (Month of January, 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

SCHEDULED VS ACHIEVED
OBESEKARAPURA PROJECT
Schedule Series4 Schedule Series3
100
100 97.0

90 86.0

79.4
80 75.7
72.2
68.6
70 66.3
62.5
59.2
60 55.3
PROGRESS(%)

50.6
50
44.9

40 38.1

31.0
30
24.0
20.2
20 18.0
14.0
12.0 11.5 11.9
8.0 9.07 8.1 8.2 8.3 8.3 8.4 8.5 9.5 10.2 10.5
10
5.04.5 6.05.5 6
2.0 3.0 3.02 4.03
0 0 1.00.2 0.5 1
0

TIME (MONTHS)

15
Monthly Progress Report No. 07 (Month of January, 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

2.1.4 Applewatta
2.1.4.1 Preliminary Work
Total preliminary work progress is 79% which tabulated in below table. All the preliminaries
have been implemented.
Item Progress

Providing Site Office with facilities for the Engineers Representatives 100%

Maintenance of Provided Office for the Engineers Representatives 56%


Providing Vehicle for the Engineer 100%
Maintenance of the provided Vehicle for the Engineer 58%

Establishing Contractor’s Site Office with facilities 100%

Maintenance of Contractor’s Site Office with Required facilities 62%

Total 79%

2.1.4.2 Design Work


Total design progress is 76% which is tabulated in below table.

No Design / Drawing Preparation Progress


1 Architectural Services
i Concept Designs 100%
ii Council 90%
iii Construction Drawings 80%
2 Sub Structure
i Piles 100.00%
ii Pile caps & plinth beams 95.00%
iii Ground floor slab 100.00%
3 Super Structure 85%
4 Sump 100%
5 Plumbing
i Water supply 75%
ii Waste water 95%
6 Electrical 75%
7 Fire 50%
8 External 27%
CARRIED TO GRAND SUMMARY 76%

16
Monthly Progress Report No. 06 (Month of December 2021)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

2.1.4.3 Sub Structure


Total Sub structure progress is 85.5%, which is tabulated in below table.
Work Trade Progress
Piling (160 piles) 100.00 %
Pile Testing
I. PIT 100.00 % (PIT – 160 Out of 160)
II. PDA 100% (PDA – 9 Out of 9)
III. MLT 65% (PDA -3 out 3)
Excavation & Earth works 80.00 %
Pile caps for 160 piles 68%
Ground Beams 50%
Anti-termite Treatment. & Ground Floor N/A
Slab
Total 85.5%

2.1.4.4 Super Structure


Construction of super structure is not yet commenced.

2.1.4.5 Overall Progress of Site – Scheduled vs. Achieved

Progress Details

Description Scheduled According


Delay Average Labor
Scheduled to Recovery Achieved
(Days) Count
Programme*
Overall
Cumulative
progress as
38.49% 15.84% 14.48% 140 Days 53
of 31st of
January,
2022

* As per the UDA approved recovery programme effective from 18.01.2022 (DOC/354R1)

17
Monthly Progress Report No. 06 (Month of December 2021)
No. of Labours

0%
20%
40%
60%
80%
100%
120%
Oct-20 1%

Nov-20 1.49%

0% 1.31%
Dec-20 2.39%

Jan-21 4.19%

2% 3.87%
Feb-21 5.59%

Mar-21 8.09%

Apr-21 10.19%

5.70%6.70%7.06%
May-21 11.73%

Jun-21 12.78%

Jul-21 13.72%

8.60% 10%11.10%
Aug-21 15.72%

18.51%

11.41%
Sep-21

12.52%
Oct-21 25.52%

Forecasted
Nov-21 30.00%

Dec-21 35.13%

Jan-22 38.49%
13.58%

Actual
Support To Colombo Urban Regeneration Project (SCURP – AIIB)

Feb-22 41.80%
13.25%13.27% 14.48%

Monthly Progress Report No. 06 (Month of December 2021)


Mar-22 45.69%

Apr-22 48.70%
Applewatta Project

Month
May-22 50.49%

51.87%
Forecasted Vs. Actual Progress

Jun-22
Forecasted Series

Jul-22 54.03%

Aug-22 58.49%

Sep-22 62.48%

Oct-22 65.28%

Nov-22 67.90%
Actual Series

Dec-22 72.19%

Jan-23 79.88%

Feb-23 82.32%

Mar-23 86.43%

Apr-23 89.16%
Urban Development Authority, Sri Lanka

May-23 92.13%
18

Jun-23 94.22%

Jul-23 96.63%
99.49%
Aug-23

Sep-23 99.96%

Oct-23
100.00%
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

2.1.5 Ferguson Road


2.1.5.1 Preliminary Work
Total preliminary work progress is 21.24 % which is tabulated in below table.

Item Progress
Insurance & Securities 0.00%
Engineer’s facilities 29.03%
Contractor’s facilities 41.18%
Contractor’s management and supervision 19.67%
Quality, Standards and Progress 24.81%
Health, Safety & Environment 24.40%
Security, Fencing & Protection 42.69%
Services and Facilities 25.97%
Miscellaneous 71.37%
Total 21.24%

2.1.5.2 Design Work


Total design progress is 24.93% which is tabulated in below table.

No Design / Drawing Preparation Progress


1 Architectural Services
i Concept Designs 90.00 %
ii Council 30.00 %
iii Construction Drawings 5.00 %
2 Sub Structure
i Piles 95.00 %
ii Pile caps & plinth beams 20.00%
iii Ground floor slab 0.00%
3 Super Structure 15.00%
4 Sump 15.00%
5 Plumbing
i Water supply 8.00%
ii Waste water 3.00%
6 Electrical 8.00%
7 Fire 0.00%
8 External 5.00%
Total 24.93%

19
Monthly Progress Report No. 07 (Month of January, 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

2.1.5.3 Sub Structure


Total Sub structure progress is 13.55 %, which is tabulated in below table.
Work Trade Progress
Piling (174 Piles) 33.90 %
Pile Testing 0.00 %
Excavation & Earth works 0.00 %
Pile caps 0.00 %
Ground Beams 0.00 %
Anti-termite Treat. & Ground Floor Slab 0.00 %
Total 13.55 %

2.1.5.4 Super Structure


Construction of super structure is not yet commenced.

2.1.5.5 Overall Progress of Site – Scheduled vs. Achieved

Progress Details
Scheduled Planned
Description (Rev. 2.0 (Rev. 2.1
Achieved
Baseline program – Not
program) approved)
Overall Cumulative progress as of
19.54 % 14.36 % 6.59 %
31st January 2022
Delay days 186 days
Average labour count 4

20
Monthly Progress Report No. 07 (Month of January, 2022)
Progress (%)

100

0
10
20
30
40
50
60
70
80
90
Jan-21 0.32
0.35

Feb-21 1.82
0.90

Mar-21 3.56
1.58

Apr-21 4.81
2.44

May-21 5.77
3.28

Jun-21 7.13
4.26

Jul-21 9.36
5.21

Aug-21 11.40
5.82

Sep-21 12.98
6.29

Oct-21 15.43
6.45

Nov-21 18.59
6.50
19.10

Scheduled
Dec-21 6.50

Jan-22 19.54
6.59

Feb-22 20.72

Mar-22 21.95

Apr-22 24.12
Support To Colombo Urban Regeneration Project (SCURP – AIIB)

May-22 27.32

Monthly Progress Report No. 07 (Month of January, 2022)


Achieved
Jun-22 32.08

Jul-22 37.79

Aug-22 45.13

Time (Month-Year)
Sep-22 55.11

Oct-22 63.64

Scheduled
Nov-22 70.24
750 Housing units at Ferguson Road

Dec-22 76.61
Scheduled Progress Vs Achieved Progress

Jan-23 83.15

Feb-23 87.69

Mar-23 91.24
Achieved

Apr-23 93.05

May-23 94.37

Jun-23 95.48

Jul-23 95.98
Urban Development Authority, Sri Lanka

Aug-23 96.24
21

Sep-23 97.25

Oct-23 98.23

Nov-23 99.18

Dec-23 99.94

Jan-24 100.00
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

2.1.6 Madampitiya
Note: All the progress percentages were calculated according to revised construction program
(Submittal No: MADM/TBL/DOC 16 R2) which approved on 10.12.2021.
2.1.6.1 Preliminary Work
Total preliminary work progress is 30.64% which tabulated in below table

Item Progress
Insurance & Securities 100.00%
Engineer’s facilities 24.34%
Contractor’s management and supervision 22.57%
Quality, Standards and Progress 20.58%
Health, Safety & Environment 22.98%
Security, Fencing & Protection 22.79%
Services and Facilities 22.73%
Miscellaneous 9.09%
Total 30.64%

2.1.6.2 Design Work


Total design progress is 37.80% which is tabulated in below table.

No Design / Drawing Preparation Progress


1 Architectural Services
i Concept Designs 75%
ii Council 0%
iii Construction Drawings 0%
2 Sub Structure
i Piles 100%
ii Pile caps & plinth beams 87.5%
iii Ground floor slab 87.5%
3 Super Structure
i Transfer floor - level 1 general 56.25%
arrangements, slab rf, beam rf
ii Typical floor general arrangements, slab 23%
rf, beam rf
iii Roof top level general arrangement 0%
iv Water tank details, lift machine room 0%
details etc
v Shear wall details, column details 38%
vi Staircase details 75%

22
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

4 Plumbing
i Water supply system 0%
ii Sewer and waste water disposal system 6%
5 Electrical
i Electrical system 0%
ii Lift system 0%
iii Generator system 0%
iv Lighting protection system 75%
6 Fire
i Fire protection detection and sprinkler 0%
system
ii LP gas system 0%
7 External
i Storm water discharge system 0%
ii Landscape details 0%
CARRIED TO GRAND SUMMARY 37.8%

2.1.6.3 Sub Structure


Total Sub structure progress is 72.9%, which is tabulated in below table.
Work Trade Progress
Piling (178 out of 178 New Piles) 100%
Pile Testing
 PIT( 127 out of 178) 71.3%

 PDA( 6 out of 13) 46.2%

Excavation & Earthworks 73%


Pile caps 29.5%
Ground Beams 13.75%
Anti-termite Treat. & Ground Floor Slab 7%
Total 72.9%

2.1.6.4 Super Structure


Construction of super structure is not yet commenced.
2.1.6.5 Overall Progress of Site – Scheduled vs. Achieved
Progress Details
Description Average Labor
Scheduled Achieved Delay (Days)
Count
Overall Cumulative
progress as of 31st 12.16% 9.78% 40 127
Jan 2022

23
Monthly Progress Report No. 07 (Month of January 2022)
PROGRESS %

0.00
10.00
20.00
30.00
40.00
50.00
60.00
70.00
80.00
90.00
100.00
May/21 0.63
0.63
Jun/21 0.95
0.92
Jul/21 1.62
1.34
Aug/21 2.69
2.55
Sep/21 4.15
3.95
Oct/21 7.04
6.88
Nov/21 8.41
8.14
Dec/21 10.80
8.59
Jan/22 12.16
9.78
Feb/22 13.40

Scheduled Progress %
Mar/22 14.33

Apr/22 15.20

May/22 16.48

Jun/22 18.07

Jul/22 19.98

Aug/22 21.93

Actual Progress %
Sep/22 24.21
Support To Colombo Urban Regeneration Project (SCURP – AIIB)

26.71

Monthly Progress Report No. 07 (Month of January 2022)


Oct/22
Nov/22 29.37

Axis Title
Dec/22 32.76

Jan/23 36.52

Feb/23 40.09

Mar/23 44.31

Scheduled Progress %
Apr/23 47.21

May/23 51.49

Jun/23 55.71

Jul/23 60.96

Aug/23 66.52

Sep/23 71.95

Oct/23 77.88
Actual Progress %

Nov/23 84.39

Dec/23 88.73
Scheduled Progress Vs Actual Progress of Madampitiya Housing Project

Jan/24 93.08

Feb/24 97.77
Urban Development Authority, Sri Lanka

Mar/24 99.16
24

Apr/24 99.81

May/24 100.00
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

2.2 Resource Personnel


2.2.1 Stadiumgama
2.2.1.1 Labor Histogram

Labour Histogram (Forecasted vs. Actual)


Stadiumgama
450
400
350 412 421 402 410
No. of Labours

300 368 355 355 355 354


329
250 282 298 297
276
200 247 245
226
150 190 181
100 167
50 119
209 5912 8317 101
52 9868 5876 5755 7134 9057 101
64 94
0

Month

Forecasted Actual Forecasted Series Actual Series

Total Scheduled man dated for Actual man dated up to 31st


whole project January 2022

294,450 96,272

2.2.1.2 Key Staff Personnel

S/N Position Requirement


Actual
1 Senior Project Manager 1
2 Chartered Architect 1 1
3 Chartered Structural Engineer 1 1
4 Chartered Mechanical Engineer 1 1
5 Chartered Electrical Engineer 1 1
Senior Manager-Construction
6
Administration 1
7 Project Manager 1 1
8 Construction Manger 1
9 Planning Engineer 1
10 QA/QC Engineer 1
11 Assistant Planning Engineer 1
12 Quantity Surveyor 1 1
13 Assistant Quantity Surveyor 4
14 Site Engineer 1 2
15 Site Manager 4

25
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

16 QS Monitoring 1
17 HR/Admin officer 1
18 Assistant Engineer 6
19 MEP Engineer 1 3
20 Assistant MEP Engineer 2
21 MEP Technical Officer 1
22 MEP Storekeeper 1
23 MEP Draftsman 1
24 MEP Supervisor 3
25 Surveyor 1
26 Assistant Surveyor 1
27 Technical Officer 4
28 HR Assistant 1
29 Accountant 1
30 Account. Assistant 1
31 Purchasing officer 1
32 Asst. Purchasing officer 1
33 Environmental officer 1
34 Safety Officer 2
35 Draftsman 1 1
36 Supervisor 8
37 QA/QC technical officer 1
38 Store keeper 1
39 Asst. store keeper 1
40 Welfare officer 1
41 Document controller 1
42 Data Entry operator 1
43 Lab technician 1
44 Foreman 1

Key Personnel of the Project

26
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

2.2.2 Colombage Mawatha


2.2.2.1 Labor Histogram

Labor Histogram (Forecasted Vs. Actual)


Colombage Mawatha
250

203
200
173
Number of Labors

150 132
140
114
99
100 90 99 105
83
72 85 91 88
67 80
52 58 58 58 58
50 57
34 36 46 49
39 42 40
12 14 18
11 20
13 15 15 12 16
0 0

Month/Year

Forecasted Actual Forecasted Series Actual Series

Total Scheduled man dated for whole Actual man dated up to 31st January
project 2022

** 244,373 32,218

**Labor histogram has been forecasted as per the master programme with 1080+176 days. 100 additional
days were granted after the EOT evaluation. However revised labor histogram is still to be
submitted by MAGA after finalizing the master program.

2.2.2.2 Key Staff Personnel

S/N Position Requirement Actual


1 Project Director 1 1
2 Charted Architect 1 1
3 Structural Design Engineer 1 1
4 Electrical Design Engineer 1 1
5 Quality, Health, Safety & Environmental Officer 1 1
6 Project Manager 1 1
7 Deputy Project Manager 1 1
8 Construction Manger - 1
9 M & E Engineer 1 1
10 Quantity Surveyor 1 3
11 Trainee Quantity Surveyor 1 3

27
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

12 Civil Engineer 1 4
13 Engineer Assistant - 1
14 Construction Superintendent - Rebar 1 -
15 Foreman - Carpentry work 1 2
16 Foreman - General Work - 2
17 Foreman Finishing work - -
18 Technical Officer - 2
19 Supervisor 1 3
20 Engineer Assistant (MEP) - 1
21 Forman - Electrical Work 1 1
22 Forman - Services Work - 1
23 Draft Person 1 2
24 Assistant Draft Person - -
25 HES Officer 1 1
26 Account Assistant 1 1
27 Time Keeper - -
28 Store Keeper 1 1
29 Admin & ERP DPO 1 1
30 ERP Data Processing - -
Key Personnel of the Project

28
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

2.2.3 Obesekarapura
2.2.3.1 Labor Histogram

Labour Histogram (Forecasted vs. Actual)


Obesekarapura
140
129

120
110

100 95

80 75

60

36 36 39
40
30
25 2725 26 27 25 25
17 20 2121 2117 2223 2220 23 20 19 22
18 21
20 1312 14 16
10 12 10
78 7 8

-
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan

Plan Actual Plan Actual

Total schedule man dated for Actual man dated up to 31


whole project January -2022

56,436 12,531

2.2.3.2 Key Staff Personnel

S/N Position Requirement


Actual
1 Senior Project Manager
2 Chartered Architect 1 1
3 Chartered Structural Engineer 1 1
4 Chartered Mechanical Engineer 1 1
5 Chartered Electrical Engineer 1 1
Senior Manager-Construction
6
Administration
7 Project Manager 1 1
8 Construction Manger 1
9 Planning Engineer 1
10 QA/QC Engineer
11 Assistant Planning Engineer
12 Quantity Surveyor 1 1
13 Assistant Quantity Surveyor

29
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

14 Site Engineer 1 2
15 Site Manager
16 QS Monitoring
17 HR/Admin officer 1
18 Assistant Engineer
19 MEP Engineer 1
20 Assistant MEP Engineer
21 MEP Technical Officer
22 MEP Store Keeper
23 MEP Draftsman
24 MEP Supervisor
25 Surveyor
26 Assistant Surveyor
27 Technical Officer 1
28 HR Assistant
29 Accountant 1
30 Account. Assistant
31 Purchasing officer
32 Asst. Purchasing officer
33 Environmental officer
34 Safety Officer
35 Draftsman 1
36 Supervisor
37 QA/QC technical officer
38 Store keeper 1
39 Asst. store keeper
40 Welfare officer
41 Document controller
42 Data Entry operator
43 Lab technician
44 Foreman
Key Personnel of the Project

30
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

2.2.4 Applewatta
2.2.4.1 Labor Histogram

Labor Histogram (Forecasted Vs. Actual)


Applewatta Project
180
158
160
134
140 124
No. of Labours

120
95
100 83
80 64
60 53
43 57 53
36 36 36 47 44
40 25 27 40 37 43
20 22 31 35 36
20 20 23
12 15
0 6

Month
Forecasted Actual Forecasted Series Actual Series

Total Scheduled Man Dated for Whole Actual man Dated up to 31st January
Project 2022
171,960 14,970

2.2.4.2 Key Staff Personnel

S/N Position Requirement Actual

1 Senior Project Manager


2 Chartered Architect 1 1
3 Chartered Structural Engineer 1 1
4 Chartered Mechanical Engineer 1 1
5 Chartered Electrical Engineer 1 1
6 Senior Manager-Construction Administration
7 Project Manager 1 1
8 Construction Manger 1
9 Planning Engineer
10 QA/QC Engineer 1
11 Assistant Planning Engineer
12 Quantity Surveyor 1 1
13 Assistant Quantity Surveyor
14 Site Engineer 1 2
15 Site Manager 1
16 QS Monitoring
17 HR/Admin officer 2
18 Assistant Engineer

31
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

19 MEP Engineer 1 1
20 Assistant MEP Engineer
21 MEP Technical Officer 1
22 MEP Store Keeper 1
23 MEP Draftsman
24 MEP Supervisor
25 Surveyor 1
26 Assistant Surveyor 1
27 Technical Officer 1
28 HR Assistant 1
29 Accountant
30 Account. Assistant 1
31 Purchasing officer 2
32 Asst. Purchasing officer
33 Environmental officer 1 1
34 Safety Officer 1 1
35 Draftsman 1 1
36 Supervisor 2
37 QA/QC technical officer
38 Store keeper 1
39 Asst. store keeper
40 Welfare officer
41 Document controller 2
42 Data Entry operator
43 Lab technician
44 Foreman 1
Key Personnel of the Project

32
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

2.2.5 Ferguson Road


2.2.5.1 Labor Histogram

Labour Histogram (Forecasted vs. Actual)


Ferguson Road

231
229
240

208
220
200
Number of Labours

180

155
160
140
120

87
100

64
80

51
60

40
40

23
20

20
17

17
16

15
13

13

12
12

12

10

10
11

20
7

4
0
Feb-21

Mar-21

May-21

Jun-21

Sep-21
Jan-21

Jul-21

Oct-21

Dec-21

Jan-22
Apr-21

Aug-21

Nov-21
Planned Actual Planned Actual

Total scheduled man dated for Actual man dated upto 31th
whole project January 2022

214,419 4,895

2.2.5.2 Key Staff Personnel

S/N Position Requirement Actual


1 Senior Project Manager
2 Chartered Architect 1 1
3 Chartered Structural Engineer 1 1
4 Chartered Mechanical Engineer 1 1
5 Chartered Electrical Engineer 1 1
Senior Manager-Construction
6
Administration
7 Project Manager 1
8 Construction Manger
9 Planning Engineer 1
10 QA/QC Engineer 1
11 Assistant Planning Engineer
1 (Pending
12 Quantity Surveyor 1
approval)
13 Assistant Quantity Surveyor
14 Site Engineer 1 1

33
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

15 Site Manager
16 QS Monitoring
17 HR/Admin officer
18 Assistant Engineer
19 MEP Engineer 1 1
20 Assistant MEP Engineer
21 MEP Technical Officer
22 MEP Store Keeper
23 MEP Draftsman
24 MEP Supervisor
25 Surveyor 1
26 Assistant Surveyor
27 Technical Officer 1
28 HR Assistant
29 Accountant
30 Account. Assistant
31 Purchasing officer
32 Asst. Purchasing officer
33 Environmental officer
34 Safety Officer 1
35 Draftsman 1 1
36 Supervisor 2
37 QA/QC technical officer
38 Store keeper
39 Asst. store keeper
40 Welfare officer
41 Document controller 1
42 Data Entry operator
43 Lab technician
44 Foreman
Key Personnel of the Project

34
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

2.2.6 Madampitiya
2.2.6.1 Labor Histogram

Labour Histogram (Forecasted vs. Actual)


Madampitiya
140 127
121
120
100
Avg. Labours

80
84 54 55
60
40 64
49 52 53 58 64 58
20
25
0 15 15 32
Jun-21 Jul-21 Aug-21 Sep-21 Oct-21 Nov-21 Dec-21 Jan-22
Month

Forecasted Actual Forecasted Series Actual Series

Total Scheduled man dated for Actual man dated up to 31st


whole project January 2022
204,727 11,481

2.2.6.2 Key Staff Personnel

S/N Position Requirement Actual

1 Senior Project Manager


2 Chartered Architect 1 1
3 Chartered Structural Engineer 1 1
4 Chartered Mechanical Engineer 1 1
5 Chartered Electrical Engineer 1 1
Senior Manager-Construction
6
Administration
7 Project Manager 1 1
8 Construction Manger
9 Planning Engineer 1 1
10 QA/QC Engineer 1
11 Assistant Planning Engineer
12 Quantity Surveyor 1 1
13 Assistant Quantity Surveyor 1 1
14 Site Engineer 1 1
15 Site Manager 1 1
16 QS Monitoring 1
17 HR/Admin officer 1
18 Assistant Engineer 1
19 MEP Engineer 1 1

35
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

20 Assistant MEP Engineer


21 MEP Technical Officer
22 MEP Store Keeper
23 MEP Draftsman
24 MEP Supervisor
25 Surveyor 1 1
26 Assistant Surveyor
27 Technical Officer 1
28 HR Assistant
29 Accountant
30 Account. Assistant
31 Purchasing officer
32 Asst. Purchasing officer
33 Environmental officer 1
34 Safety Officer 1 1
35 Draughtsman 1 1
36 Supervisor 1 1
37 QA/QC technical officer
38 Store keeper 1 1
39 Asst. store keeper
40 Welfare officer
41 Document controller
42 Data Entry operator
43 Lab technician
44 Foreman
Key personnel of the project

36
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

2.3 APPROVALS
2.3.1 Material Approval Summary
2.3.1.1 Stadiumgama
Project: Construction of 1000 Housing
Consultant: State Engineering Corporation
units at Stadiumgama
No of floors : G+14 Contractor:Access Engineering PLC
Warran
Country ty/ Material Submission Approved Remark
Sr Trade Name (if of Origin Guaran for Approval (Y-Yes/N-N0) Date s
Item Description Manufacture / Local Supplier
No relevant) ty
Specs Sample Date
B Base Materials
B5 Reinforcment Steel
B5.1 Tor steel Ceylon
reinforcement Sri Lanka Ceylon steel cooporation Limited Y 10/9/2020 6/10/2020
steel
Captain steel Sri Lanka Captai steel (pvt) Ltd Y 19/08/2020 1/9/2020
Melwa Sri Lanka Melwire Rolling (pvt) Ltd Y 10/9/2020 24/09/2020
GTB Sri Lanka GTB Steel Corporation (pvt) Ltd Y 23/11/2020 4/1/2021
B5.2 Mild steel Ms water bar Y 4/1/2021 19/01/2021

B6 Ready mix concrete


B7 Masonary
B7.1 Cement Ultratech Sri Lanka Ultratech cement Lanka (pvt) Ltd Y 20/07/2020 14/08/2020
INSEE
MAHAWELI Sri Lanka Siam city cement (Lanka) Ltd Y 10/2/2021 23/02/2021
MARINE
INSEE
SANSTHA Sri Lanka Siam city cement (Lanka) Ltd Y 10/2/2021 23/02/2021
MARINE

37
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

Tokyo cement company (Lanka)


TOKYO SUPER Sri Lanka Y 10/2/2021 23/02/2021
PLC
NIPPON Tokyo cement company (Lanka)
Sri Lanka Y 18/02/2021 9/3/2021
CEMENT PRO PLC
INSEE EXTRA Sri Lanka Siam city cement (Lanka) Ltd Y 23/02/2021 4/3/2021
INSEE RAPID
Sri Lanka Siam city cement (Lanka) Ltd Y 18/02/2021 4/3/2021
FLOW PLUS
INSEE RAPID
Sri Lanka Siam city cement (Lanka) Ltd Y 18/02/2021 4/3/2021
FLOW
Singhe Sri Lanka Penna cement industries ltd Y 25/11/2021 7/12/2021
B7.2 Tile mortar Swisstek Sri Lanka Swissteck (Ceylon) plc Y 10/8/2021 25/11/2021
lanka tile grout manufacturing
B7.3 Tile grout Buidco Sri Lanka Y 27/09/2021 16/11/2021
(pvt) ltd
B8 Cement Blocks
Ct.Sand Solid block
B8.1 AMTRAD Sri Lanka Amtrad Ltd Y 3/2/2021 13/02/2021
150x190x390mm
DHARA Sri Lanka Dhara International pvt ltd Y 8/2/2021 23/02/2021
WAPCO Sri Lanka W.A.PAERER & co pvt ltd Y 31/03/2021 21/04/2021
ELS Sri Lanka ELS construction pvt ltd Y 5/10/2021 27/10/2021
B9 Non Shrink Grout DAVCO UK Davco construction company Ltd Y 15/12/2020 9/1/2021
Stocrete Germony Sto SEA Pvt Ltd Y 27/01/2021 3/2/2021
Chryso Excem
V1 India Chryso lanka pvt ltd Y 16/11/2021 30/11/2021
Chryso SL GP
B10 Water Proofing chemicals
B10.
for lift Mixguard CW Sri Lanka HE Engineering (pvt) ltd 10 Yrs Y 16/12/2020 9/1/2021
1
SOLICO Sri Lanka Solico International (pvt) ltd 10 Yrs Y 16/12/2020 9/1/2021
BRUSHBOND N Chandrarathne Decorators
Y 20/01/2021
TGP (pvt) ltd

38
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

B10. Nile waterproofing materials Co.


Roof slab NILOBIT PN Egypt 10 Yrs Y 27/01/2021 3/2/2021
2 S.A.E.
Bitumode flex (- Bitumode Qatar Waterproofing
Qatar 10 Yrs Y 9/2/2021 23/01/2021
10) Factory
Gulf Membrane and coating
Bituflame Bahrain 10 Yrs Y 9/2/2021 23/02/2021
industries WLL
B10.
Toilet /Balcony Mixguard AC Australia Aura Polymers Australia pvt ltd Y 10/2/2021 23/02/2021
3
B10.
Sump Mixguard CW Sri Lanka HE Engineering (pvt) ltd 10 Yrs Y 16/12/2020 9/1/2021
4
SOLICO Sri Lanka Solico International (pvt) ltd 10 Yrs Y 16/12/2020 9/1/2021
B10. Chopped stand China National Building
Fiber mesh Sri Lanka Y Y 17/06/2021 22/7/2021
5 Mat Materials (Group) Corp
B11 Expantion Joint Material
B11.
Sealant Polyseal PS PG UAE Henkel Polybit industries ltd Y 11/3/2021 12/3/2021
1
M Finishing Material

M1 Door Shutters

M1.1 Main door - D1 Superwood Sri Lanka Superwood Exports (Pvt) Ltd. 10 Yrs Y Y 29/07/2021 27/01/2022
Lanka
Aluminium
M1.2 Toliet Door -D3 sri lanka Lanka Aluminium Industries PLC Y Y 9/9/2021 16/11/2021
Romet
Engineering
M1.3 Fire door ASP Enterprises China ASP Enterprises Y Y 29/03/2021 13/05/2021

M2 Timber /Aluminium Door Frame

M2.1 Main Door - D1 Superwood Sri Lanka Superwood Exports (Pvt) Ltd. 10 Yrs Y Y 29/07/2021 27/01/2022
M2.2 Bed Room - D2 Superwood Sri Lanka Superwood Exports (Pvt) Ltd. 5 Yrs Y Y 29/07/2021 27/01/2022
San Trading Sri Lanka San trading Enterprises (Pvt) Ltd. 5 Yrs Y Y 28/10/2021 26/01/2022
Lanka
Aluminium
M2.3 Toliet Door -D3 sri lanka Lanka Aluminium Industries PLC Y Y 9/9/2021 16/11/2021
Romet
Engineering

39
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

M3 Aluminum Window
Lanka
Powder Coated Aluminium - Aluminium
M3.1 sri lanka Lanka Aluminium Industries PLC Y Y 9/9/2021 16/11/2021
Fan Light Romet
Engineering
Lanka
Powder coated Aluminium Aluminium
M3.2 sri lanka Lanka Aluminium Industries PLC Y Y 9/9/2021 16/11/2021
windows Romet
Engineering
M3.5 Window accessories Kinglong China Romet Engineering pvt ltd 5Yrs Y Y 10/1/2022 20/1/2022
M4 Aluminium Door Sealent Fittings
M4.1 Guangdong Archie Hardware Co.
Tower Bolt Bob Hardware China Y Y 3/11/2021 16/11/2021
Ltd
M4.2 Guangdong Archie Hardware Co.
Hinges Bob Hardware China Y Y 3/11/2021 16/11/2021
Ltd
M4.3 Guangdong Archie Hardware Co.
door lock Bob Hardware China Y Y 3/11/2021 16/11/2021
Ltd
M4.4 Silicone Masense 801 China Gunuo Tianjin Industrial Co.Ltd Y Y 9/12/2021 16/12/2021
M5 Bath Room
M5.1 Foshan Jiexia Sanitory ware Co.
Wall hung wash basin GISMO China 5 Yrs Y Y 22/03/2021 5/9/2021
Ltd
M5.2 Foshan Jiexia Sanitory ware Co.
Water closet GISMO China 5 Yrs Y Y 22/03/2021 5/9/2021
Ltd
M5.3 Shower rose ONIDA India IBIBO Metal master (pvt) ltd 5 Yrs Y Y 28/09/2021 13/10/2021
M5.4 Pillar tap ONIDA India IBIBO Metal master (pvt) ltd 5 Yrs Y Y 28/09/2021 13/10/2021
M5.5 Bib tap ONIDA India IBIBO Metal master (pvt) ltd 5 Yrs Y Y 28/09/2021 13/10/2021
M6 Paint Materials
M6.1 N. Chandrarathna Decorators pvt
Skim coat ENDMIX sri lanka Y 14/09/2021 10/11/2021
ltd
SK sri lanka St.Anthany's Coatings pvt ltd Y 22/07/2021 26/08/2021
Aero flex sri lanka Colouright Industries (Pvt) Ltd Y 19/07/2021 26/08/2021
Singhe sri lanka Fair Mate Y 3/12/2021 9/12/2021
M7 Tiles

40
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

Bathroom floor tile-300 Ranjanas


M7.1 India Ranjanas Ceramic (Pvt) Ltd Y Y 6/7/2021 3/9/2021
mm*300mm Ceremic
Bathroom wall tile -300mm *200 Ranjanas
M7.2 India Ranjanas Ceramic (Pvt) Ltd Y Y 6/7/2021 3/9/2021
mm Ceremic
F Fire system
F1 GI pipe & fittings, heavy duty SURYA India Surya Roshni Ltd Y 26/11/2020 7/1/2021
F2 Valves Valve IT Italy Global drive industries solution Y 20/05/2021 6/9/2021
Steel Recon Industries/Unitech
F3 Butterfly valve SRI Malaysia Y 26/11/2020 7/1/2021
fire and security system (pvt) ltd
Steel Recon Industries/Unitech
F4 Flexible Coupling(For pumps) SRI Malaysia Y 26/11/2020 7/1/2021
fire and security system (pvt) ltd

F5 Landing valve Steel Recon Industries/Unitech


SRI Malaysia fire and security system (pvt) ltd Y 26/11/2020 7/1/2021
F6 4 way Breaching Inlet Steel Recon Industries/Unitech
SRI Malaysia fire and security system (pvt) ltd Y 26/11/2020 7/1/2021
F7 19mm × 45 m Fire hose reel Steel Recon Industries/Unitech
SRI Malaysia fire and security system (pvt) ltd Y 26/11/2020 7/1/2021
Steel Recon Industries/Unitech
F8 Jet /Spray Nozzle
SRI Malaysia fire and security system (pvt) ltd Y 26/11/2020 7/1/2021
F9 Fire Cable Cable solutions Sri Lanka Cable solutions Y Y 22/12/2021 31/12/2021
P
P1 Plumbing System
P2 uPVC pipes & fittings National Sri Lanka Central Industries PLC Y Y 2/11/2021 9/11/2021
SLON Sri Lanka SLON Lanka (pvt) Ltd Y Y 31/12/2020 7/1/2021
P3 Unit valves / accessories Valve IT Italy Global drive industries solution 5 Yrs Y 2/12/2021 13/12/2021
P4 Angle Valve ONIDA India IBIBO Metal master (pvt) ltd 5 Yrs Y Y 28/09/2021 13/10/2021
P5 Concealed valve ONIDA India IBIBO Metal master (pvt) ltd 5 Yrs Y Y 28/09/2021 13/10/2021
P6 Flexible Hose ONIDA India IBIBO Metal master (pvt) ltd 5 Yrs Y Y 28/09/2021 13/10/2021
P7 Water Pumps MAS-DAF Turkey Mas DAF 3Yrs Y 19/11/2021 13/12/2021

P8 Water Meter Zenner International GmbH &


Zenner Germany Co. KG 1 Year Y 22/11/2021 1/12/2021
P9 Rain water side outlet … sri lanka DJ Fabricators (pvt) ltd Y Y 2/11/2021 9/11/2021

41
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

D
D1 Drainage systems
D2 Floor Gully ERA China Yanggao Co. Ltd Y Y 10/12/2020 1/1/2021
D3 Manhole covers EDNA EDNA Engineering pvt ltd Y 11/5/2021 21/05/2021
Auscar Engineering services pvt
Auscar(C250) Y 16/06/2021 8/1/2021
ltd
D4 Gully trap ERA China ERA Piping systems Y Y 2/7/2021 27/7/2021
D5 PVC puddle collar … sri lanka Maaz lanka industries Y 21/09/2021 12/10/2021
S
S1 Sanitary ware
S2 Kitchen sink Mascons Sri Lanka Mascons(pvt) Ltd Y 16/07/2021
S3 Bottled Trap- Kitchen Sink Pakai A300 Malaysia Pakai Industries Berhad Y Y 4/10/2021 1/11/2021
Pakai A301 Malaysia Pakai Industries Berhad Y Y 4/10/2021 1/11/2021
E
E1 Electrical System
E2 Electrical Cable Orange Sri Lanka Orange Electric Y 29/09/2021 12/11/2020
sierra Sri Lanka sierra cables PLC Y 21/09/2021 22/10/2021
E3 Cable Tray/ Trunking/ Ladder Obo Bettermann German Saw Engineering pvt ltd Y 5/3/2021 12/3/2021
E4 Polycrome Electrical Industries
Conduit Polycrome Sri Lanka (pvt) ltd Y Y 25/01/2021 2/2/2021
Polycrome Electrical Industries
Polycrome Sri Lanka (pvt) ltd Y 26/03/2021 30/03/2021
S-Lon Sri Lanka S-Lon lanka pvt ltd Y Y 19/07/2021 28/07/2021
Kevilton Electrical products pvt
Kevilton Sri Lanka ltd Y Y 19/07/2021 28/07/2021
E5 Flexible conduit material S-Lon Sri Lanka S-Lon lanka pvt ltd Y 12/8/2021 8/9/2021
E6 Polycrome Electrical Industries
Junction Box Polycrome Sri Lanka (pvt) ltd Y Y 25/01/2021 2/2/2021
E7 Switch boxes Polycrome Electrical Industries
Polycrome Sri Lanka (pvt) ltd Y Y 25/01/2021 2/2/2021
E8 Switches & Socket outlets CHINT China Chint Energy (pvt) ltd lifetime Y 4/12/2020
ACL Sri Lanka ACL Cables PLC 20Yrs Y Y 19/04/2021 23/04/2021

42
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

Chech
E9 Electrical Door bell Bonega Bonega, spol.s r o 3Yrs Y 16/11/2020 4/1/2021
Republic
ACL Sri Lanka ACL Cables PLC 20Yrs Y Y 15/12/2020 22/01/2021
Kevilton Electrical products pvt
Kevilton Sri Lanka Y 18/01/2022 26/01/2022
ltd
Polycrome Electrical Industries
E10 Light fittings/ holders Polycrome Sri Lanka Y Y 25/01/2021 2/2/2021
(pvt) ltd
Kevilton Electrical products pvt
Kevilton Sri Lanka Y Y Y 29/03/2021 5/4/2021
ltd
Polycrome Electrical Industries
E11 Ceiling roses Polycrome Sri Lanka Y Y 25/01/2021 2/2/2021
(pvt) ltd
Kevilton Electrical products pvt
Kevilton Sri Lanka Y Y Y 29/03/2021 5/4/2021
ltd
Polycrome Electrical Industries
E12 Pendent holders Polycrome Sri Lanka Y Y 25/01/2021 2/2/2021
(pvt) ltd
Polycrome Electrical Industries
E13 Enclosure Polycrome Sri Lanka Y Y 25/01/2021 22/02/2021
(pvt) ltd
E14 Breakers (MCB, RCCB) CHINT China Chint Energy (pvt) ltd lifetime Y 4/12/2020
E15 Elevator Mitsubishi Japan Mitsubishi elevator Asia Co.Ltd 1 Year Y 28/10/2021 1/12/2021

E16 Lightning Protection System Wallis UK A.N.Wallis & Co. Ltd Y Y 29/03/2021 5/4/2021
E17 Earth Electrode (Earth rod) Kingsmill UK Kingsmill Industries (UK) Ltd Y 18/09/2021 29/9/2021
E18 Insulation board Insutech … … Y Y 4/1/2022 18/01/2022
E19 LP Gas system
E19.
Heavy duty pipes Surya India Surya Roshni Ltd Y 26/11/2021 3/12/2021
1

43
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

2.3.1.2 Colombage Mawatha

Draft Past
Country SLSI Test SUBMITTAL
Material BRAND SUPPLIAR Warranty Project Samples STATUS
of Origin Certificates reports NO.
certificate References

Reinforcement Material

Ceylon Steel Ceylon Steel


Ceylon Steel Sri Lanka -    -
Corporation Limited Corporation Limited
GTB Steel Accepted with
GTB Steel GTB Steel Sri Lanka -    - EMSF/003
Corporation (Pvt) Ltd. comments.
Melwire Rollig (Pvt) Melwire Rolling (Pvt)
Melwire Sri Lanka -    -
LTD Ltd.
Captain Steel (Pvt) Captain Steel (Pvt) Accepted with
Captain Steel Sri Lanka -    - EMSF/005
Ltd. Ltd. comments.

Cement

Ordinary Portland
India     - EMSF/030 Approved.
Cement (OPC) Ultra Tech Ultra Tech Cement
Portland Fly Ash Cement Lanka Accepted with
India    - EMSF/031
Cement (PFC/PPC) comments

Waterproofing Material

Water Bar (3mm MS


plate- Hot rolled steel JSW Steel, India India Relax Steel, Sri Lanka - - - -  EMSF/033 Approved.
plates/ Sheets)
Mixguard AC Mixguard, UAE U.A.E.     - EMSF/037 Approved.
Mixguard CW Mixguard, UAE U.A.E.     - EMSF/038 Approved.
Polyseal PS PG Polyseal, UAE U.A.E. H.E. Engineering, Sri     - EMSF/039 Approved.
Lanka
Rockal Plus Egypt - -   - EMSF/046R3 Approved.
Torch on Membrane
Nilobit 5 PY Egypt - -  - - EMSF/046R1 Resubmission

44
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

Formwork

Column System TECON Construction


Accepted with
Formwork (To TECON China Technology Co. Ltd., - -    EMSF/011
comments.
Import) China

Petrokem Lanka (Pvt)


Form Oil - Sri Lanka - -  - - EMSF/022 Approved.
Ltd

Plumbing Material

EMSF/006
S-LON Lanka (Pvt)
S-LON Sri Lanka      EMSF/023 Approved
Ltd.
PVC Pipes & Fittings EMSF/026

Central Industries
NATIONAL Sri Lanka    -  EMSF/007 Approved
PLC
S-LON Lanka (Pvt) EMSF/008
Solvent Cement S-LON Sri Lanka      Approved
Ltd. EMSF/023
Brass Valves (Gate
Valves, Pressure
PEX UK PEX, UK - - - -  EMSF/50 Approved
reducing Valves and
Ball Float Valves)
uPVC Balcony Floor
YONGGAO.CO.LTD,
Trap Gully with SS ERA China - - - -  EMSF/51 Approved
China
Grating
uPVC Trap Floor
S-LON Lanka (Pvt)
Gully (For S-LON Sri Lanka - - - -  EMSF/52 Approved
Ltd., Sri Lanka
Bathrooms)
Hanging Pipe Locally DJ Fabricators, Sri
Sri Lanka - -  -  EMSF/53 Approved
Brackets Fabricated Lanka
uPVC Pipes fitted
with Collars - Locally
made Puddle Collars S-LON Sri Lanka Shanko, Colombo - - - -  EMSF/063 Approved
for Balcony with
PVC welding

45
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

Electrical Material

Bare Copper (Cu) Richardson Project


FURSE UK - -  -  EMSF/010 Approved
Tape (Pvt) Ltd.
20 mm Diameter
Captain Steel (Pvt)
Plane MS Round Captain Steel Sri Lanka - -  -  EMSF/012 Approved
Ltd.
Bars (Rods)

Earthing Materials

Bare Cu Tape,
Copperbond Earth
Rod, Coupler, Diving
Stud, Non-Metalic DC  -    EMSF/027 Approved
Clip, Rod to Tape
Clamp, Squre Clamps,
Non-Metalic DC Clip KINGSMILL
(Circular Wrap Over KINGSMILL UK
Indestries (UK) Ltd.
Type)
Test clamp, 16mm
Gunmetal Air
Terminal Base, Earth
pit with cover,
 -    EMSF/058 Approved
16mm*10000mm
Copper elevation rod
& Copper air terminal
(Multi point)
S-LON Lanka (Pvt) Accepted with
PolyconPRO Sri Lanka  EMSF/028
Conduits & Ltd. comments.
Accessories Polycrome Electrical
Polycrome Sri Lanka    -  EMSF/032 Approved
Industries
The Supreme
Supreme, India India - -  - - EMSF/035 Approved
Industris, India
uPVC Pipe Fittings
China ERA Group,
ERA, China China - -  - - EMSF/036 Approved
Yonggao, China

Cable Solutions,
Fire Resistant Cables Cable Solutions Sri Lanka - -  -  EMSF/041 Approved
Kadawatha, Sri Lanka

46
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

Wilson Cables,
Wilson Singapore - - - - - EMSF/042 Approved
Singapore
Switch Boxes (Sunk Polycrome Electrical
Polycrome Sri Lanka - - - -  EMSF/067 Approved
Boxes) Industries

Cables - 1x1.5mm2
Cu/PVC/PVC, 1x2.5mm2 ACL Cables PLC, Sri
Cu/PVC/PVC, 1x2.5mm2 ACL Cable Sri Lanka - -    EMSF/068 Approved
Lanka
Cu/PVC/ (E.W)

Cables -
1.5mm27/.53mm
Cu/PVC/PVC Single
Core,
Sierra Cables PLC, Sri Accepted with
2.5mm27/.67mm Sierra Cables Sri Lanka -   -  EMSF/70
Lanka comments.
Cu/PVC/PVC Single
Core, 2.5mm2
7/0.67mm Cu/PVC/
(E.W)
Construction Materials

MIXGROUT
UAE N Chandraratne - -  - - EMSF/015 Approved
NS20
Decorators (Pvt) Ltd.
Conbextra GP2 India - -  - - EMSF/016 Approved
Construction Grouts FINEX
Finex Engineering
Construction Sri Lanka - -  - - EMSF/017 Approved
(Pvt) Ltd
Grout GP
Finex Engineering Accepted with
Mapefill GP Singapore -   - - EMSF/029
(Pvt) Ltd comments.
Concure WB India - -  - - EMSF/018 Resubmission
N Chandraratne
Decorators (Pvt) Ltd. Accepted with
Curing Agents MIXCURE AC UAE - -  - - EMSF/019
comments

MASTERKURE Finex Engineering


German -   - - EMSF/025 Approved
128 (Pvt) Ltd

47
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

MIXBOND N Chandraratne Accepted with


UAE - -  - - EMSF/020
SBR Decorators (Pvt) Ltd. comments
Bonding Agents

SPECbuild Solico International


UAE - -  - - EMSF/021 Approved
BA10 (Pvt) Ltd.
Anti-Termite
Biflex USA Lankem, Sri Lanka  -   - EMSF/024 Approved
Treatment
Fire Protection System Material
Surya, New Delhi,
Surya India - -  - - EMSF/040 Approved
India
Heavy Duty GI Pipes
Need
Mech Mech, China - -  - - EMSF/044
Resubmission
Accepted with
Iron Pipe Fittings Mech China Mech, China - - - - - EMSF/045
comments
Fire Hydrant
Equipment - Eversafe Malaysia Eversafe, Malaysia - - - - - EMSF/047 Approved
Standard Landing
Valve, Pressure Sri Malaysia Sri, Malaysia - - - - - EMSF/048 Approved
Reducing Valve,
Breecing Inlet, Fire
Fighting Hose, Kolling Engineering,
Jet/Spray Nozzle, Kolling Malaysia - - - - - EMSF/049 Approved
Malaysia
Manual Swing Type
Hose Reel
Alliance Valves &
Carbon Steel
RITIA China Fittings Company, Sri - - - -  EMSF/054 Approved
Weldable Flanges
Lanka
Finishing Material

Cement Blocks LU Fortune


Accepted with
(390*190*100 hollow Sri Lanka Construction (Pvt) - -  -  EMSF/064
comments
& 390*190*150 solid) Ltd.

Cement Blocks
ICC PRE CAST
(390*190*100 hollow Sri Lanka - -    EMSF/066 Resubmission
PRODUCTION
& 390*190*150 solid)

48
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

Nippon Paint Sri Lanka Nippon Paint Lanka    - EMSF/065


Material
Elevators (Pvt) Ltd., Approved with
Elevator OTIS, China USA  - -   EMSF/043
Sri Lanka Comments
Cast Iron Manhole
Locally DJ Fabricators, Sri
Covers - 450mm Sri Lanka - -  -  EMSF/055 Approved
Fabricated Lanka
*450mm
Finex Engineering
Chemical Anchoring Fastfix-it -     EMSF/014 Approved
(Pvt) Ltd
Stainless Steel Plane
Bar for Water Sump - India Lords Enterprise - -  -  EMSF/060 Approved
Runners
Native Way Private
200 KVA Generator Tekshan Turkey  -    EMSF/061 Resubmission
Limited
Cast Iron Manhole
Locally DJ Fabricators, Sri
Covers - 600mm Sri Lanka - -  -  EMSF/062 Resubmission
Fabricated Lanka
*600mm

49
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

2.3.1.3 Obesekarapura
Project: Design & Construction of 300 housing units
Consultant: State Engineering Corporation
at Obesekarapura
No of floors : G+15 Contractor: Subhasinghe Contractors
Warranty
Country Manufacture Material Submission
Sr Trade Name / Approved Date Remarks
Item Description of Origin / Local for Approval (Y-Yes/N-N0)
No (if relevant) Guaranty
Supplier
Specs Sample Date
Soil stabilizing
S
material
Pileman- AMRFEO
S1 Bentonite Y N 4/9/2020 22/10/2020
B.H. pvt.ltd
B Base Materials
B5 Reinforcement
Steel
B5.
Melwa Melwa Y N 4/9/2020 24/09/2020
1
B5. Lanwa (for
2 Lanwa Y N 4/9/2020 24/09/2020
piles)
B5. CN-Confab 20/10/202 Rejected
4 CN Y N
Ribbed steel steel(pvt ltd) 0 (22/10/2020)
B5. Lanwa (for 15/07/202
Lanwa Y N 19/07/2021
5 pile caps) 1
B5. GTB steel
6 29/11/202
GTB corporation Y N 23/12/2021
1
pvt ltd
Ready mix
B6
concrete
Acceess eng.
B6. Grade 40 (for
Access Readymix Y N 7/9/2020 9/9/2020
1 piling)
plant
Acceess eng.
B6. Grade 35 (for
Access Readymix Y N 10/9/2020 11/9/2020
2 piling)
plant

50
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

Acceess eng.
B6.
Grade 30 Access Readymix Y N 4/9/2020 9/9/2020
3
plant
INSEE
B6.
INSEE readymix Y N 4/12/2020 24/12/2020
4
plant
SAN
B6. SAN
readymix Y N 4/12/2020 24/12/2020
5 readymix
plant
Acceess eng.
B6.
Access Readymix Y N 7/12/2020 24/12/2020
6
plant
B6. Concrete batching Tokyo super Tokyo super 20/02/202
Y N 30/03/2021
8 plant mix mix 1

B6. Tudawe Tudawe 24/02/202


Y N 26/03/2021
9 brothers brothers 1

B6. Capital RMC


Capital RMC Y N 5/3/2021 30/03/2021 .
10 pvt. ltd

B7 Masonary

ultratech
B7. Ultratec 17/03/202
Cement cement lanka Y N 26/03/2021
1 OPC 1
pvt ltd
Ultratec
ultratech
B7. portland fly 17/03/202
Fly ash Cement cement lanka Y N 26/03/2021
2 ash cement 1
pvt ltd
(PFC)
B8 Cement Blocks
light weight
B8. Lanka AAC 14/10/202
blocks(600x150x20 AAC Y N 15/10/2020
1 pvt ltd 0
0)

51
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

CONBEXTR constructive
B12 Non Shrink Grout Y N 5/3/2021 10/3/2021
A solutions
Estogrout
20/04/202
B13 Shrink grout MP60&MP5 Estop group Y N 23/04/2021
1
0

M Finishing Material

F Fire system
P Plumbing System
D Drainage systems
S Sanitary ware
E Electrical System

52
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

2.3.1.4 Applewatta
Project: Design & Construction of 700
Consultant: State Engineering Corporation
Housing Units at Applewatta

No of floors: 16 Contractor: China Railway 25th Bureau Group Corporation Ltd.

Country
Material Submission
Sr Trade Name of Manufacture / Warranty/ Approved
Item Description for Approval (Y-Yes/N-N0) Remarks
No (if relevant) Origin Local Supplier Guaranty Date
Specs Sample Date

B Base Materials
B5 Reinforcment Steel
B5.1 Ceylon steel
Sri
Tor steel Lanwa cooporation Y Y 21.05.2021 09.07.2021
Lanka
Limited
Sri Melwire Rolling
Melwa Y Y 11.08.2021 27.08.2021
Lanka (pvt) Ltd
B5.2 Mild steel
B5.3 Ribbed steel
Sri Capital RMC (Pvt)
B6 Ready mix concrete Capital
Lnaka Ltd
Sri Detong Lanka
Detong
Lanka Concrete (Pvt) Ltd.
Sri Tudawe Brothers
Tudawe
Lnaka (Pvt) Ltd
Sri Tokyo Supermix
Tokyo
Lanka (Private) Limited
Sri Access
Access
Lnaka Engineering PLC
B7 Masonary
Sri Siam City Cement
B7.1 Cement INSEE 25.08.2021 06.10.2021
Lanka (Lanka) Limited
B7.2 River Sand
B7.3 Sea sand Y

53
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

B7.4 Metal
B8 Cement Blocks
B8.1 Ct.Sand Solid block 150x190x390mm Y Y
B9 Pre-Cast concrete items
GIM General
Sri Trading and
B10 Borrowed soil for filling RED Soil Y Y 08.08.2021 27.08.2021
Lanka Construction (Pvt)
Ltd
B11 DPC Tar
Mix Grout
B12 Construction Grout UAE HE Engineering Y 08.10.2021 27.10.2021
NS 20
B13 Water Proofing chemicals
B13.1 for lift
External Penetron USA HE Engineering Y 20.08.2021 13.10.2021
Internal
B13.2 Roof slab Rockal Plus Egypt HE Engineering Y 05.01.2022
B13.3 Toilet /Balcony Mixguard-AC UAE HE Engineering Y 20.08.2021 13.10.2021
N.Chandraratne
Brushbond
Toilet /Balcony Malaysia Decorators (Pvt) Y 15.09.2021 06.10.2021
FLX-III
Ltd
B13.4 Over Head water tank Mixguard-AC UAE HE Engineering Y 20.08.2021 13.10.2021
B13.5 Sump
Internal Penetron USA HE Engineering Y 20.08.2021 13.10.2021

External Penetron USA HE Engineering Y 20.08.2021 13.10.2021


B13.6 External Wall
B14 Expantion Joint Material
B14.1 Compressible material
B14.2 Sealant
B15 Termite Treatment Chemicals Bifenthrin
India Ultra Kill Pvt LTd N 27.12.2021 05.01.2022
100gL EC
M Finishing Material

54
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

M1 Door Shutters
Timber /Polynorm/ Aluminium Door
M2
Frame-size/slashes
Aluminum Window ( check
withstand to wind pressure
M4
certificate for frames & glass) -
frame sizes to be finalised

M5 Type of glass
M6 Aluminium Door Sealent Fittings
M7 Bath Room Fittings
M8 Paint Materials
M9 Hand rail bars
M11 Concrete Curb (for road)
M12 Tiles
F Fire system
P Items for Plumbing System
S Sanitary ware
E Electrical System
E40 Lightning Protection System

RR Copper Sri Empire Trading


E41 Copper tape Y Y 25.07.2021 40 x 6 mm
Tape Lanka Agency
E42 Copper plate
E43 Hot Dipped Galvanized Flat steel India Melwire Rolling Y 25.07.2021 17.08.2021
E44 Arrester rod
E45 Air Terminal
E46 Down Conductors/ clips
E47 Test clamp
Submission
E48 Earth Electrode (Earth rod) MS Rod 25.07.2021 17.08.2021
Incomplete
E49 Rod to tape/cable clamps
E50 Earth pits

55
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

E51 Main Earthing System


E52 Earth Cables
E53 Junction Panels
H Sump
H1 16 mm diameter Stainless Steel 25.07.2021
Mild
Steel( Waterbar width of the
Y 09.10.2021 3.11.2021
3mm water bar need
H2 Water Bar Thickness) to be specified.

56
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

2.3.1.5 Ferguson Road


Project: Design & Construction of 750 Housing Units at Ferguson Road,
Consultant: State Engineering Corporation
Colombo-14
No of floors: G+15 Contractor: C C E C C - C R 25 G JV PVT LTD
Country Material Submission
Sr Trade Name of Manufacture / Warranty/ Approved
Item Description Guaranty for Approval (Y-Yes/N-N0) Remarks
No (if relevant) Origin Local Supplier Date
Specs Sample Date
B Base Materials
B5 Reinforcement Steel
MELWIRE
MELWA ROLLING (PVT) Y 24.03.2021 31.03.2021
LTD
CEYLON STEEL
B5.1 Ribbed steel
LANWA CORPORATION Y 24.03.2021 31.03.2021
LIMITED
GTB Steel
GTB Y 24.03.2021 31.03.2021
Corporation Ltd
DETONG Detong Lanka
Y 02.06.2021 13.07.2021
LANKA Concrete (Pvt) Ltd
CAPITAL CAPITAL RMC
Y 24.06.2021 13.07.2021
RMC (PVT) LTD
B6 Ready mix concrete
Tudawe Brothers
TUDAWE (Pvt) Ltd
Y 22.12.2021 30.12.2021
BROTHERS Ready Mixed
Concrete
B7 Masonry
B8 Cement Blocks
B9 Pre-Cast concrete items
B10 Borrowed soil for filling
B11 DPC Tar
B12 Non-Shrink Grout
B13 Water Proofing chemicals

57
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

B14 Expansion Joint Material


B15 Termite Treatment Chemicals
M Finishing Material
F Fire system
P Plumbing System
D Drainage systems
S Sanitary ware
E Electrical System

58
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

2.3.1.6 Madampitiya
Project: Design & Construction of 700 housing units
Consultant: State Engineering Corporation
at No 320, Madampitiya Road, Colombo 14
No of floors : Fifteen (G+15) stories Contractor: Tudawe Brothers (Pvt.) Ltd
Warr
Material Submission
Country of anty / Approved
Sr Trade Name (if Manufacture / for Approval (Y-Yes/N- Remarks
Item Description Origin Guar Date
No relevant) Local Supplier N0)
anty
Sam
Specs Date
ple
B Base Materials
Reinforcment Steel
Tor steel Cylone Steel Cylone Steel
Corporation pvt Corporation pvt 20.03.2012
MADM/TBL/MAT/001 ltd ltd
MADM/TBL/MAT/002 Tor steel GTB GTB Steel 05.08.2021
MADM/TBL/MAT/003 Tor steel Melwa Melwa steel
MADM/TBL/MAT/004 Tor steel Melwa Captain steel
Thudawe brothers Thudawe brothers
Ready mix concrete 08.09.2021
MADM/TBL/DOC/39 Pvt Ltd Pvt Ltd
M Masonary
MADM/TBL/MAT/005 Cement INSEE cement
MADM/TBL/MAT/006 Cement Ultratech cement

C Cement Blocks
Pennsylvani
Bilex TC United
Bilex TC a
MADM/TBL/MAT/009 R1 Termiticide/Insecticide(A professionalAgen
Termiticide (Philadelphi
nti termite material) cies (pvt)ltd.
a) 09.12.2021
Mixbond SBR(Pychem)- Mixbond SBR N Chandrarathne
MADM/TBL/MAT/014 bonding agent NCD (pychem) UAE Decorators 01.11.2021
Mixcure AC (Pychem)- Mixcure AC N Chandrarathne
MADM/TBL/MAT/015 curing agent NCD (pychem) UAE Decorators 01.11.2021
Mixrelease WB(Pychem)- Mixrelease WB N Chandrarathne
MADM/TBL/MAT/016 mould oil NCD (pychem) UAE Decorators 01.11.2021
Conbextra GP2- N Chandrarathne
MADM/TBL/MAT/017 Construction grout NCD Conbextra India Decorators 01.11.2021

59
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

Finebond SBR- bonding


MADM/TBL/MAT/018 agent Finex Finexbond SBR Srilanka Finex 05.11.2021
MADM/TBL/MAT/019 Finex mould oil Finex mould oil Srilanka Finex 01.11.2021
Master emaco S 5400
Concrete repairing Master Emaco S
MADM/TBL/MAT/020 material- finex 5400 Singapore Finex 05.11.2021
Masterkure 181- curing
MADM/TBL/MAT/022 agent Masterkure 181 Singapore Finex 05.11.2021
Jigasu Hanbao
Plywood board for building material China
MADM/TBL/MAT/054 formwork co.ltd. 03.12.2021
Chemical anchoring WIT Wurth
Wurth lanka
MADM/TBL/MAT/055 PE 500 20.12.2021
Pending
MADM/TBL/MAT/056 Water bar MS plate Y Y 19.01.2022 From UDA
High rib mesh 0.2mm K U S Formwork
thickness for construction & Scafolding Pending
MADM/TBL/MAT/057 joints (pvt)ltd Y Y 19.01.2022 From UDA
Water Proofing
W
chemicals

Expansion Joint
E
Material

M1 Finishing Material

Timber /Polynorm/
M2 Aluminium Door
Frame-size

Aluminum Window (
check withstand to wind
M4 pressure certificate for
frames & glass) - frame
sizes to be finalised

M5 Aluminium Door
Sealent Fittings

M6 Bath Room

60
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

M7 Paint Materials
M8 Hand rail bars

Concrete Curb (for


M9
road)

M10 Tiles

F Fire system

P Plumbing System
S lon PVC multi trapped S-Lon
MADM/TBL/MAT/025R1
floor gully S-Lon Sri lanka lanka(pvt)ltd. 20.12.2021
ERA drinage pipe fittings Central industries
MADM/TBL/MAT/026 for waste water and storm PLC & S lon
water disposal system ERA Group China lanka (pvt)ltd 05.11.2021
National PVC pipes and
fittings for waste water
MADM/TBL/MAT/027
and storm water disposal National PVC Central industries
system pipe & fittings Srilanka PLC 01.11.2021
S lon solvent cement for S-Lon
MADM/TBL/MAT/029R1
PVC pipes and fittings S-Lon Sri lanka lanka(pvt)ltd. 28.12.2021
For all blocks and
buildings- Kitchen/Pantry Sealcore stainless
MADM/TBL/MAT/034
Sink- single bowl Kitchen sink- steel industries Pending
draining board sealcore Srilanka (pvt)ltd. Y From UDA
Close couple,floor
MADM/TBL/MAT/035 mounted water closet - Sona Field Krisho multi Pending
Sona Ceramic India trades (pvt)ltd. Y From UDA
For all blocks and
MADM/TBL/MAT/036 buildings-full pedestal Sona Field Krisho multi Pending
wash basin-Sona Field Ceramic India trades (pvt)ltd. Y From UDA
Close couple,floor
MADM/TBL/MAT/037 mounted water closet - ROCA Bathroom Krisho multi Pending
Parryware products (pvt)ltd India trades (pvt)ltd. Y From UDA
Full pedestal washing
basin for level 1
MADM/TBL/MAT/038
bathrooms in each tower- ROCA Bathroom Krisho multi Pending
Parryware products (pvt)ltd India trades (pvt)ltd. Y From UDA

61
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

Faucet Metal Krisho multi Pending


MADM/TBL/MAT039
Shower Head & Arm Master India trades (pvt)ltd. Y From UDA
Faucet Metal Krisho multi Pending
MADM/TBL/MAT/040
Shower concealed Valve Master India trades (pvt)ltd. Y From UDA
Faucet Metal Krisho multi Pending
MADM/TBL/MAT/041
Bib tap Master India trades (pvt)ltd. Y From UDA
Faucet Metal Krisho multi Pending
MADM/TBL/MAT/042
Basin Pillar tap Master India trades (pvt)ltd. Y From UDA
Faucet Metal Krisho multi Pending
MADM/TBL/MAT/044
Bidet spray Master India trades (pvt)ltd. Y From UDA
Floor gully grating - SS Faucet Metal Krisho multi Pending
MADM/TBL/MAT/045
304 Master India trades (pvt)ltd. Y From UDA
Faucet Metal Krisho multi Pending
MADM/TBL/MAT/046
Angle Valve Master India trades (pvt)ltd. Y From UDA
D Drainage systems

S Sanitary ware

E Electrical System
Electrical Juction Boxes
MADM/TBL/MAT/010-R1
For entire project PPI Srilanka Bandara Brothers Y 03.12.2021 10.01.2022
PVC conduits and
MADM/TBL/MAT/011 accessories for entire S-Lon lanka
project Polycon Srilanka (pvt)ltd Y 01.12.2021 13.12.2021
Polycrome
MADM/TBL/MAT/012 Electric industries
Switch mounting boxes Polycrome Srilanka (pvt)ltd. Y 01.12.2021 13.12.2021

62
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

2.3.2 DRAWING APPROVAL SUMMARY


2.3.2.1 Stadiumgama

SEC UDA
Submitted
Drawing Subject Submittal No Commented Comment Commented Comment
Date
Date Date

ARCHITECTURAL Accepted with


STDM/ACCESS/DRG/002R6 N/S N/S N/S 16/07/2021 comments as noted

STRUCTURAL
Accepted with comments as Accepted with
1. Pile
STDM/ACCESS/DRG/015R2 21/9/2020 24/09/2020 noted 1/2/2021 comments as noted
Accepted with comments as Accepted with
STDM/ACCESS/DRG/022R1 21/9/2020 24/09/2020 noted 1/2/2021 comments as noted
2. Pile cap
STDM/ACCESS/DRG/26R4 21/12/2020 31/12/2020 Accepted 25/02/2021 Accepted
3. GA Drawings
STDM/ACCESS/DRG/28R3 21/12/2020 31/12/2020 Accepted 29/01/2021 Accepted
Accepted with comments as Accepted with
STDM/ACCESS/DRG/31R4 25/02/2021 8/3/2021 noted 17/03/2021 comments as noted

4. Ground Beams STDM/ACCESS/DRG/28R3 21/12/2020 31/12/2020 Accepted 29/01/2021 Accepted


5. GF slab Accepted with comments as Accepted with
STDM/ACCESS/DRG/31R4 25/02/2021 8/3/2021 noted 17/03/2021 comments as noted
6. Column/Concrete
walls STDM/ACCESS/DRG/30R4 13/05/2021 25/05/2021 Accepted 19/08/2021 Accepted
7. Typical Floor Slab
STDM/ACCESS/DRG/54R2 19/03/2021 22/03/2021 Accepted 4/5/2021 Accepted
8. Typical Floor
Beams STDM/ACCESS/DRG/54R2 19/03/2021 22/03/2021 Accepted 4/5/2021 Accepted

63
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

Accepted with comments as Accepted with


9. StairCase
STDM/ACCESS/DRG/44R2 11/3/2021 25/03/2021 noted ... comments as noted
Accepted with comments as Accepted with
10. Roof Slab
STDM/ACCESS/DRG/097R1 22/9/2021 1/10/2021 noted 15/10/2021 comments as noted
Accepted with comments as Accepted with
11. Roof Beams
STDM/ACCESS/DRG/097R1 22/9/2021 1/10/2021 noted 15/10/2021 comments as noted
12. Machine room STDM/ACCESS/DRG/116 10/1/2022 20/01/2022 To be resubmitted 26/01/2022 To be resubmitted
13 Water Tank STDM/ACCESS/DRG/116 10/1/2022 20/01/2022 To be resubmitted 26/01/2022 To be resubmitted
STDM/ACCESS/DRG/49R3 21/06/2021 8/7/2021 Accepted 19/08/2021 Accepted
COLD WATER Accepted with
SUPPLY SYSTEM STDM/ACCESS/DRG/24R4 3/11/2021 24/11/2021 Accepted 16/12/2021 comments as noted

SEWAGE AND
WASTE WATER
DISPOSAL
SYSTEM Accepted with comments as
STDM/ACCESS/DRG/23R3 26/01/2022 27/01/2022 noted Pending

STORM WATER
DISPOSAL
SYSTEM
STDM/ACCESS/DRG/25R2 26/01/2021 Pending

ELECTRICAL

Drawing approval for


lightining protection
& earthing STDM/ACCESS/DRG/29R1 20/10/2020 13/11/2020 Accepted 13/11/2020 Accepted
Drawing approval for
Outdoor Lighting Accepted with comments as Accepted with
Layout STDM/ACCESS/DRG/35R2 20/12/2021 21/12/2021 noted 20/01/2022 comments as noted

64
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

Drawing approval for


Typical floor corridor Accepted with comments as Accepted with
light layouts STDM/ACCESS/DRG/36 25/11/2020 9/12/2020 noted 17/12/2020 comments as noted

Drawing Approval
for Lighting & Small
Power Arrangement
Utility Area - Ground
Floor Block A, B, C, Accepted with comments as Accepted with
D STDM/ACCESS/DRG/38R1 10/2/2021 15/02/2021 noted 11/3/2021 comments as noted

Drawing approval for Accepted with


CCTV layout STDM/ACCESS/DRG/42R2 27/12/2021 30/12/2021 Accepted 4/1/2022 comments as noted
Lighting & small
power conduit layout
for typical single
house unit STDM/ACCESS/DRG/62R2 19/07/2021 22/07/2021 Accepted 30/07/2021 Accepted
Drawing approval for
Rooftop lightning Accepted with comments as Accepted with
layout STDM/ACCESS/DRG/69 25/03/2021 31/03/2021 noted 7/4/2021 comments as noted
Cable tray & ladder
for Block A,B,C & D STDM/ACCESS/DRG/096R1 8/11/2021 19/11/2021 Accepted 25/11/2021 Accepted
Earthing system
achematic drawing - Accepted with comments as Accepted with
Block A,B,C,D STDM/ACCESS/DRG/102 6/9/2021 7/9/2021 noted ... comments as noted

MECHANICAL
Fire Protection
Drawings-
Construction Accepted with
drawings STDM/ACCESS/DRG/91R2 3/12/2021 8/12/2021 Accepted 5/1/2022 comments as noted
Accepted with comments as
To be resubmitted
Fire Detection STDM/ACCESS/DRG/68R1 3/11/2021 26/11/2021 noted 7/12/2021
Accepted with comments as
LP Gas system
STDM/ACCESS/DRG/107R1 7/1/2022 21/01/2022 noted Pending

65
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

2.3.2.2 Colombage Mawatha

DRAWING NO. DESCRIPTION Submittal No. Approved Date


ARCHITECTURAL
C0000 List of Drawings
C0100 Site Plan
C0200 Overall Ground Floor Plan
C1100 Ground Floor Plan - Main Building
C1101 Level 01 Floor Plan
C1102 Level 02 to 10 Typical Floor Plan
C1103 Level 11 Floor Plan
C1104 Roof Slab
C1105 Water Tank Level Plan
C1106 Water Tank Roof Slab
C1200 Typical Housing Unit Detail Plan
C1201 Fire Lobby 01 & 02 Detail
C1301 Facility Building 01 & 02
C1302 Generator, Transformer - Electrical Meter Room 1 & 2, Pump Room 1 & 2 Details DRSF/71 15/12/2021
C2101 Elevation A
C2102 Elevation B
C2103 Elevation C
C2104 Elevation D
C3101 Section A
C3102 Section B
C3103 Section C
C3104 Section D
C4101 Door Details
C4102 Window Details
C4103 Metal Work Details
C6101 Stair Case Details
C6102 Skylight Detail

66
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

STRUCTURAL
469M / WD / ST / 001 GENERAL NOTES DRSF/007 30/11/2020
469M / WD / ST / 002 PILE LAYOUT & DETAILS DRSF/011 11/2/2021
469M / WD / ST / 003 PILE CAP LAYOUT DRSF/006R2 12/3/2021
469M / WD / ST / 004 Pile Cut-Off Levels & Details DRSF/011R1 23/3/2021
469M / WD / ST / 005 DETAILS OF PILE CAPS DRSF/006R2 12/3/2021
469M / WD / ST / 006-1 DETAILS OF SUMP (SHEET-1) DRSF/104 9/12/2021
469M / WD / ST / 006-2 DETAILS OF SUMP (SHEET-2) DRSF/104 9/12/2021
469M / WD / ST / 007-1 COLUMN LAYOUT & DETAILS DRSF/022 6/3/2021
469M / WD / ST / 007-2 COLUMN LAYOUT & DETAILS DRSF/36R1 28/6/2021
469M / WD / ST / 008 GENERAL ARRANGEMENT OF GROUND FLOOR DRSF/98 23/11/2021
469M / WD / ST / 009 GENERAL ARRANGEMENT OF FIRST FLOOR DRSF/99 23/11/2021
GENERAL ARRANGEMENT OF SECOND FLOOR (2nd Floor to 5th Floor
469M / WD / ST / 010 DRSF/109 20/1/2022
Similar)
469M / WD / ST / 012 GENERAL ARRANGEMENT OF FIFTH TO 11TH FLOOR DRSF/36R1 28/6/2021
469M / WD / ST / 014 DETAILS OF GROUND FLOOR SLAB DRSF/016 4/3/2021
469M / WD / ST / 015 DETAILS OF FIRST FLOOR SLAB DRSF/107 21/12/2021
469M / WD / ST / 016 DETAILS OF SECOND TO ELEVENTH FLOOR SLAB DRSF/111 21/1/2022
469M / WD / ST / 017 DETAILS OF ROOF TERRACE SLAB DRSF/013 4/3/2021
469M / WD / ST / 019 DETAILS OF GROUND FLOOR BEAMS DRSF/98 23/11/2021
469M / WD / ST / 020-1 DETAILS OF FIRST FLOOR BEAMS DRSF/99 23/11/2021
469M / WD / ST / 020-2 DETAILS OF FIRST FLOOR BEAMS DRSF/100 23/11/2021
469M / WD / ST / 020-3 DETAILS OF FIRST FLOOR BEAMS DRSF/100 23/11/2021
469M / WD / ST / 020-4 DETAILS OF FIRST FLOOR BEAMS DRSF/100 23/11/2021
469M / WD / ST / 021-1 DETAILS OF SECOND FLOOR BEAMS DRSF/109 20/1/2022
469M / WD / ST / 021-2 DETAILS OF FIRST FLOOR BEAMS DRSF/109 20/1/2022
469M / WD / ST / 021-3 DETAILS OF FIRST FLOOR BEAMS DRSF/109 20/1/2022
469M / WD / ST / 022-1 DETAILS OF ROOF TERRACE BEAMS DRSF/012 4/3/2021
469M / WD / ST / 022-2 DETAILS OF ROOF TERRACE BEAMS DRSF/012 4/3/2021
469M / WD / ST / 022-3 DETAILS OF ROOF TERRACE BEAMS DRSF/012 4/3/2021
469M / WD / ST / 025 DETAILS OF STAIRCASES DRSF/060 6/5/2021

67
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

469M / WD / ST / 029 General Arrangement of 6th Floor DRSF/36R1 28/6/2021


469M / WD / ST / 030 Detail of Ground Floor (Lift Well) DRSF/044 28/6/2021

PLUMBING SYSTEM - Water Supply, Waste Water & Rain Water Layout

469M/PL/WS/GFL/01 Water Supply Layout - Ground Floor DRSF/83 22/10/2021


469M/PL/WS/L/01 Single Line Diagram Block - 01 (Typical Block 02) Water Supply DRSF/83 22/10/2021
469M/PL/WS/TFL/02 Water Supply layout - Typical Floor (From 1st Floor to 11th Floor) DRSF/83 22/10/2021
469M/PL/WS/WT/03 Water Supply Layout Water Tank DRSF/83 22/10/2021
469M/PL/WS/TD/01 Water Supply Layout Toilet Detail - Typical DRSF/83 22/10/2021

469M/PL/SW/L/01 Single Line Diagram Block - 01 (Typical Block 02) Sewer & Waste Water DRSF/83 22/10/2021

469M/PL/SW/GFL/02 Soil & Waste Water Layout - Ground Floor DRSF/83 22/10/2021

469M/PL/SW/TFL/03 Sewer & Waste Water Layout - Typical Floor (From 1st Floor to 11th Floor) DRSF/83 22/10/2021

469M/PL/SW/RL/04 Sewer & Waste Water Layout - Roof Level DRSF/83 22/10/2021
469M/PL/SW/TD/01 Sewer & Waste Water Layout - Toilet Detail - Typical DRSF/83 22/10/2021
469M/PL/RW/EX/01 External Storm Water Layout DRSF/83 22/10/2021
469M/PL/SW/EX/01 External Soil & Waste Water Layout DRSF/83 22/10/2021
469M/PL/RW/L/01 Single Line Diagram Block - 01 (Typical Block 02) Rain Water DRSF/83 22/10/2021
469M/PL/RW/GFL/02 Rain Water Layout - Ground Floor DRSF/83 22/10/2021
469M/PL/RW/TFL/03 Rain Water Layout - Typical Floor (From 1st Floor to 11th Floor) DRSF/83 22/10/2021
469M/PL/RW/RL/04 Rain Water Layout - Roof Floor DRSF/83 22/10/2021
469M/PL/BW/GFL/01 Builders Work Layout & Detail, Ground Floor DRSF/83 22/10/2021
469M/PL/BW/GFL/02 Builders Work Layout & Detail, First Floor DRSF/102R1 24/12/2021
469M/PL/BW/2FL/03 Builders Work Layout & Detail, Second Floor DRSF/108 31/12/2021
469M/PL/WS/PR/01 Water Pump & Fire Pump Room Layout & Detail, Ground Floor DRSF/83 22/10/2021
ELECTRICAL SYSTEM - Lighting, Power & Conduit Layout and Lightning Protection
ELECTRICAL LIGHTING & POWER LAYOUT GROUND FLOOR (BLOCK
469M / EL/G/LP-001 DRSF/073 6/8/2021
01 & 02)
469M / SL/COM/SLD-001 SINGLE LINE DIAGRAM-1 DRSF/103 8/12/2021
469M / EL/FAC/PL-001 ELECTRICAL LIGHTING & POWER LAYOUT FACILITY BUILDING DRSF/090 2/11/2021

68
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

469M / SL/COM/SLD-002 SINGLE LINE DIAGRAM-2 DRSF/092 3/11/2021


469M / EL/LP-001 LIGHTNING PROTECTION SYSTEM AT PILECAP LEVEL DRSF/042 19/4/2021
469M / EL/LP-002 LIGHTNING PROTECTION SYSTEM AT ROOF TERRACE LEVEL DRSF/085 2/11/2021
469M / EL/LP-003 LIGHTNING PROTECTION SYSTEM ELEVATION (B1 & B2) DRSF/096 23/11/2021
LIGHTNING PROTECTION SYSTEM EQUIPOTENTIAL BONDING (B1 &
469M / EL/LP-004 DRSF/085 2/11/2021
B2)
469M / EL/TH/001 ELECTRICAL LIGHTING & POWER LAYOUT TYPICAL HOUSING UNIT DRSF/076 6/8/2021

469M / EL/1F/LP-002 ELECTRICAL LIGHTING LAYOUT FIRST FLOOR LEVAL (BLOCK 01 & 02) DRSF/079 6/8/2021

469M / EP/1F/LP-002 ELECTRICAL POWER LAYOUT FIRST FLOOR LEVEL (BLOCK 01 & 02) DRSF/079 6/8/2021
ELECTRICAL CABLE TRAY & TV CONDUIT LAYOUT FIRST FLOOR
469M / EC/1F/LP-002 DRSF/079 6/8/2021
(BLOCK 01& 02)
469M / SL/COM/SLD-003 SINGLE LINE DIAGRAM-3 DRSF/092 3/11/2021
ELECTRICAL LIGHTING LAYOUT 2nd TO 10th TYPICAL FLOOR LEVEL
469M / EL/2F/LP-003 DRSF/078 6/8/2021
(BLOCK 01& 02)
ELECTRICAL POWER LAYOUT 2nd TO 10th TYPICAL FLOOR LEVEL
469M / EP/2F/LP-003 DRSF/078 6/8/2021
(BLOCK 01 & 02)
ELECTRICAL CABLE TRAY & TV CONDUIT LAYOUT 2nd to 10th
469M / EC/2F/LP-003 DRSF/078 6/8/2021
TYPICAL FLOOR LEVEL (BLOCK01& 02)
469M / EL/11F/LP-004 ELECTRICAL LIGHTING LAYOUT 11th FLOOR LEVAL (BLOCK 01& 02) DRSF/075 6/8/2021
469M / EP/11F/LP-004 ELECTRICAL POWER LAYOUT 11th FLOOR LEVEL (BLOCK 01 & 02) DRSF/075 6/8/2021
ELECTRICAL CABLE TRAY & TV CONDUIT LAYOUT 11th FLOOR
469M / EC/11F/LP-004 DRSF/075 6/8/2021
(BLOCK 01& 02)
469M / EL/RF/LP-005 ELECTRICAL LIGHTING LAYOUT ROOF SLAB LEVEL BLOCK (01 & 02) DRSF/077 6/8/2021
469M/EP/RF/LP-005 ELECTRICAL POWER LAYOUT ROOF SLAB LEVEL (BLOCK (01 & 02) DRSF/077 6/8/2021
469M/ER/EX/001 EARTHING ARRANGEMENT DRSF/085 2/11/2021

469/EL/SCH/001 Block - 1 & 2 Common Area & Facility Building, Power Distribution Schematic DRSF/039 28/4/2021

469/EL/SCH/002 Shematic Diagram for Typical Housing Unit, Power Distribution System DRSF/039 28/4/2021

469/EL/SCH/003 Main Earthing Schematic (Block 01 & Block 02) DRSF/039 28/4/2021

69
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

469/SH/EL/TH/001 Electrical Lighting & Power layout, Typical Housing Unit (Block 01 & 02) DRSF/080 2/8/2021

469/BW/EL/01 Cable Trench & Sleeve Arrancgement Drawing DRSF/057 19/7/2021


469/SH/EL/GF/001 Ground Floor Slab Conduiting Layout for Lighting DRSF/088 2/11/2021
469/SH/EL/GF/002 Ground Floor Slab Conduiting Layout for Power DRSF/088 2/11/2021
469M/BW/FC/01 Builders Work Drawing for Fire & CCTV System DRSF/074 6/8/2021
FIRE SYSTEM - Fire Detection & Fire Protection
469M/FD/SCH/01 Fire Detection System – Schematic Layout DRSF/101 6/12/2021
469M/FD/RL/01 Fire Detection System – Roof Slab Level DRSF/106 9/12/2021
469M/FD/TF/01 Fire Detection System – Typical Floors DRSF/101 6/12/2021
469M/FD/GF/01 Fire Detection System – Ground Floor DRSF/101 6/12/2021
469M/FP/GF/02 Fire Sleeve Layout DRSF/106 9/12/2021
469M/FP/GF/01 Fire Protection System – Ground Floor DRSF/106 9/12/2021
469M/FP/TF/02 Fire Protection System – Typical Floor (From 1st Floor to 11th Floor) DRSF/106 9/12/2021
469M/FP/LMR/03 Fire Protection System – Lift Machine Room Level DRSF/106 9/12/2021
469M/FP/SCH/04 Fire Hydrant System - Schematic Layout DRSF/106 9/12/2021
469M/FP/SCH/05 Fire Sprinkler System - Schematic Layout DRSF/106 9/12/2021
469M/FP/TF/06 Typical Floor (1st to 11th Floor) Fire Sleeve Layout DRSF/106 9/12/2021
469M/PR/SCH/01 Pump Room Details DRSF/106 9/12/2021
469M/FDC/GF/02 Fire Detection System, Conduit Layout – Ground Floor DRSF/101 6/12/2021
469M/FDC/GF/AD/20 Fire Detection System, Additional Conduit Layout – Ground Floor DRSF/101 6/12/2021
469M/FDC/TF/AD/21 Fire Detection System, Conduit Layout – Typical Floor DRSF/101 6/12/2021
CCTV SYSTEM
469M/CTV/GF/01 CCTV System Ground Floor DRSF/072R2 2/11/2021

70
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

2.3.2.3 Obesekarapura
SEC UDA
Drawing Subject Submittal No Submitted Date Commented Commented Comment Type
Date Date
ARCHITECTURAL
1.Finalized Architectural Drawings
Architectural drawings -construction issue OBE300/DWG/02R1 5/5/2021 1/6/2021 accepted
accepted with comments as
Zone 1 plan (G.7) part section a-a , part b section b-b OBE300/DWG/64 17/12/2021 23/12/2021 30/12/2021
noted and need resubmission
Architectural Setting Out Plan OBE300/DWG/68R1
Architectural proposed level for filling and landscape
OBE300/DWG/69R1
layout
Architectural unit layout OBE300/DWG/70R1
Architectural gas supply system OBE300/DWG/71R1
Architectural wall sizes OBE300/DWG/72R1
18/01/2022 21/01/2022
Architectural floor plan OBE300/DWG/73R1
Architectural sections OBE300/DWG/74R1
Architectural elevations OBE300/DWG/75R1
Architectural door and windows details OBE300/DWG/76R1
Architectural toilets details OBE300/DWG/77R1
Architectural finishing schedule OBE300/DWG/78R1
Non structural
Accepted with comments as
tower crane pile layout OBE300/DWG/15 29/04/2021
noted.
shoring details (sump) OBE300/DWG/83 28/01/2021
STRUCTURAL
1. Pile
Submission incomplete and
Control points drawing- Revision 01 OBE300/DWG/06 12/11/2020 12/11/2020 need resubmission with
missing details.
Finite model analysis OBE300/DWG/07 R6 23/12/2020 4/1/2021 accepted
Structural piling Drawing-R5 and Structural Design accepted with comments as
OBE300/DWG/09 23/12/2020 4/1/2021
Report of the pile noted

71
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

accepted with comments as


Layout for additional piles and pile details OBE300/DWG/13-R1 15/07/2021 20/07/2021 noted (DWG 10,4R2
revised)
Design coordinates details of piles -Rev 03 OBE300/DWG/14 27/04/2021 30/04/2021 accepted
accepted with comments as
Pile As Built Drawing OBE300/DWG/65 23/12/2021 24/12/2021
noted
2. Pile Caps
typical pile cap details and revised detail to P1C5, Shear
wall detail, Wall and pile cap detail sheet 11, wall and
pile cap details-sheet 12,wall and pile cap detail sheet 13,
OBE300/DWG/17R2 2/11/2021 accepted
wall and pile cap details sheet14, wall and pile cap details
sheet 15, wall and pile cap details sheet 16, Wall and pile
cap details-sheet 17
Revised drawings typical pile cap details wall and pile
OBE300/DWG/18-R1 26/07/2021 accepted
cap details
accepted with comments as
Revised drawings details of pile caps PC1, PC2,PC3 OBE300/DWG/23 11/9/2021 15/09/2021
noted and need resubmission
Pile caps layout and details due to pile eccentricities OBE300/DWG/48 Resubmission 19/11/2021 24/11/2021 accepted
accepted with comments as
Pile cap and wall details OBE300/DWG/49/50/51/52 22/11/2021 26/11/2021
noted and need resubmission
accepted with comments as
Pile center deviation exceed 75 mm part 2 drawings OBE300/DWG/67 24/12/2021 29/12/2021
noted and need resubmission
3. GA Drawings
4. Ground Beams
Submission of Capping beam and Ground beam accepted with comments as
OBE300/DWG/21-R1 25/10/2021 29/10/2021
drawings. noted
5. GF slab
accepted with comments as
Ground floor slab reinforcement details OBE300/DWG/22- R2 17/12/2021 22/12/2021
noted and need resubmission
ground floor slab reinforcement key plan OBE300/DWG/85 28/01/2022
accepted with comments as
Ground floor plan and toilet details OBE300/DWG/46 17/11/2021 24/11/2021 25/11/2021
noted
submission incomplete and
Revised ground floor capping and ground beam layout OBE300/DWG/53-R1 17/12/2021 20/12/2021 need resubmission with
missing details
6. Column/Concrete walls
7. Typical Floor Slab

72
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

accepted with comments as


Typical floor slab (1-15 floor) R/F details drawings OBE300/DWG/41-R1 2/1/2022 4/1/2022
noted and need resubmission
Typical beam R/F details drawings OBE300/DWG/42-R1 2/1/2022 4/1/2022 accepted
8. Typical Floor Beams
9. Staircase
accepted with comments as
Staircase details OBE300/DWG/40 30/10/2021 9/11/2021
noted and need resubmission
10. Roof Slab
11. Roof Beams
12. Machine room
13 Water Tank
submission incomplete and
Submission of water tank level domestic use water supply
OBE300/DWG/29 13/10/2021 21/10/2021 need resubmission with
layout
missing details
14.Lift
OBE300/DWG/43
OBE300/DWG/44
Lift core details drawings 9/11/2021 9/11/2021 accepted
OBE300/DWG/45

15. Sump
accepted with comments as
Submission of layout of water sump. OBE300/DWG/24 4/10/2021 7/10/2021
noted and need resubmission
Water sump structural drawing OBE300/DWG/47R1 28/01/2022
COLD WATER SUPPLY SYSTEM
submission incomplete and
Water supply and drainage drawings- construction issue
OBE300/DWG/19 26/07/2021 28/07/2021 18/08/2021 need resubmission with
(Ground floor commercial use water supply layout.)
missing details
submission incomplete and
Water supply and Drainage drawings- Construction issue OBE300/DWG/16 6/5/2021 21/05/2021 need resubmission with
missing details
submission incomplete and
Ground floor domestic use water supply layout OBE300/DWG/26 13/10/2021 21/10/2021 need resubmission with
missing details
submission incomplete and
1st floor to 15th floor domestic use water supply layout OBE/DWG/27 13/10/2021 21/10/2021 need resubmission with
missing details

73
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

submission incomplete and


Roof terrace domestic use water supply layout OBE300/DWG/28 13/10/2021 21/10/2021 need resubmission with
missing details
submission incomplete and
Typical Unit Water supply layout and other details OBE300/DWG/30 13/10/2021 21/10/2021 9/11/2021 need resubmission with
missing details
accepted with comments as
Water supply drawings OBE300/DWG/55 15/12/2021 19/12/2021
noted and need resubmission
accepted with comments as
Standard drawings OBE300/DWG/58 15/12/2021 21/12/2021
noted and need resubmission
SEWAGE AND WASTEWATER DISPOSAL
SYSTEM
submission incomplete and
Sewer and waste water disposal drawing. OBE300/DWG/56 15/12/2021 21/12/2021 need resubmission with
missing details
STORM WATER DISPOSAL SYSTEM
accepted with comments as
Storm Water Disposal Drawings OBE300/DWG/57 15/12/2021 21/12/2021
noted and need resubmission
catch pit details OBE300/DWG/84 28/01/2022
ELECTRICAL
Electrical drawings
Lighting drawings OBE300/DWG/59R1 29/12/2021 3/1/2022 19/01/2022 accepted
accepted with comments as
Power drawings OBE300/DWG/60R1 29/12/2021 3/1/2022 19/01/2022
noted and need resubmission
accepted with comments as
Lighting protection drawings OBE300/DWG/61R1 29/12/2021 3/1/2022 19/01/2022
noted
accepted with comments as
Schematics drawings OBE300/DWG/62R1 29/12/2021 3/1/2022 19/01/2022
noted and need resubmission
submission incomplete and
CCTV drawings OBE300/DWG/63R1 29/12/2021 3/1/2022 need resubmission with
missing details
Proposed Earthing details for lighting protection system OBE300/DWG/66 24/12/2021 24/12/2021 4/1/2022 Rejected
power conduits and lighting OBE300/DWG/86 28/01/2022
MECHANICAL
Fire Drawings OBE300/DWG/82 18/01/2022

74
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

2.3.2.4 Applewatta

SEC UDA
Submitted
Drawing Subject Submittal No Commente Comment Commented Comment
Date
d Date Date
ARCHITECTURAL

STRUCTURAL
Select the test pile closer to
a borehole so as to verify
1.Submission of the drawing of test piling CR25G/APPLEWATTA/DRA
17.01.2021 19.01.2021 the pile design 19.01.2021 Accepted
location /006
parameters.borehole layout
is not submitted
CR25G/APPLEWATTA/DRA
2.Submission of design cordinates of piles 15.03.2021 15.03.2021 noted,forwarded to UDA 15.03.2021 Accepted
/014
CR25G/APPLEWATTA/DRA
3. General arrangement of pile caps - R2 19.05.2021 21.05.2021 Drawings can be accepted 21.05.2021
/026R2
4.Submission of the general arrangement of
ground floor(Block A,B,C) - Construction CR25G/APPLEWATTA/DRA 12.07.2021 14.07.2021 Drawings can be accepted 05.08.2021 Accepted
Issue /023R4
5. Submission of the lift pile cap -design CR25G/APPLEWATTA/DRA Construction
13.07.2021 21.07.2021 Drawings can be accepted 05.08.2021
drawings-Construction issue /034R1 Issue
6. The Revised General Arrangement &
Construction
Beam Details of Ground Floor(Block - CR25G/APPLEWATTA/DRA 03.10.2021 08.10.2021 Drawings can be accepted 15.10.2021
Issue
A)-Construction Issue /041R1
7.The Revised General Arrangement &
Construction
Beam Details of Ground Floor(Block -B)- CR25G/APPLEWATTA/DRA 05.12.2021 07.12.2021 Drawings can be accepted 21.12.2021
Issue
Construction Issue /043R1

75
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

Please verify the concrete


grade of columns.Includ
e the cover for water
8. Submission of General Notes(Block CR25G/APPLEWATTA/DRA Need
09.12.2021 09.12.2021 retaining structures.Typical 16.12.2021
A,B,C) /048 Resubmission
balcany drop detail shall be
as per the given slab r/f
details
9. Submission of the Beam Details of Ground CR25G/APPLEWATTA/DRA Construction
28.07.2021 28.07.2021 Drawing s can be accepted 06.08.2021
Floor - Construction issue /028R4 Issue
10. Submission of the General arrangement
CR25G/APPLEWATTA/DRA Construction
of 1st,2nd and typical Floors - Construction 13.07.2021 21.07.2021 Drawing s can be accepted 05.08.2021
/019R2 Issue
issue
Drawings can be
11. Submission of Slab details(Block - CR25G/APPLEWATTA/DRA accepted,refer comments Construction
30.06.2021 02.07.2021 08.07.2021
A,B,C)-R2 /024R2 attach send via email on Issue
22nd june 2021.
Refer comments attached
CR25G/APPLEWATTA/DRA Need
12.Submission of beam details(1-15 floors) 15.04.2021 08.06.2021 send via email on 8th june
/027 Resubmission
2021 10.06.2021
Drawings can be accepted.
Aspecial precaution to be
taken while construction
13. Submission of the column details - CR25G/APPLEWATTA/DRA and curing of concrete of Construction
12.07.2021 20.07.2021 22.07.2021
Construction Issue /020R3 concrete walls to avoid any Issue
thermal shrinkage cracks as
cover to reinforment is
fairly high.
14.Columns Layout of second to Roof Floor CR25G/APPLEWATTA/DRA
22.07.2021 27.07.2021 Drawings can be accepted Accepted
( Block A,B,C) /038 05.08.2021
15. Submission of the redesigned design CR25G/APPLEWATTA/DRA Construction
05.12.2021 08.12.2021 Drawings can be accepted 21.12.2021
drawing of sump details-Construction Issue /035R5 Issue
16. Submission of the lift wall details - CR25G/APPLEWATTA/DRA Construction
12.07.2021 14.07.2021 Drawing s can be accepted
Construction Issue /021R3 Issue

76
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

Please Clarify adequacy of


loading thickness (125mm)
& Reinforcement
arrangement according to
CR25G/APPLEWATTA/DRA the idealization used in the Need
17. Fire Staircase Details-Block A,B,C 21.10.2021 26.10.2021 12.11.2021
/045 design calculation.Refer Resubmission
drawing for the other
comments .Include refernce
for notes & other details in
the drawings
COLD WATER SUPPLY SYSTEM

Drawings can be
accepted.Drawing need to
CR25G/APPLEWATTA/DRA be checked,sump drwaing Need
1. The water supply system - R3 12.11.2021 22.11.2021 03.12.2021
/016R3 no.has been given Resubmission
to ......drwaings ( Block A
& Block B)
SEWAGE AND WASTE WATER
DISPOSAL SYSTEM

Drawings can be
accepted,MH support detail
to prevent settlement need
to be submitted
separately.Under ground
pipe laying detail,Hume
1. Submission of the drawing of the plumbing CR25G/APPLEWATTA/DRA pipe connection
06.12.2021 09.12.2021 22.12.2021 Accepted
system(A,B,C) /010S3R5 detail,Hume pipe
connection to canal details
need to be submitted
separatelyu.Strom water
Mhs need to bw
incorporated with latest
architectural drawings

77
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

STORM WATER DISPOSAL SYSTEM


1. Submission of the rain water disposal CR25G/APPLEWATTA/DRA Submit with the revised Need
25.11.2021 30.11.2021 13.12.2021
system /018R1 architectural drawing Resubmission
ELECTRICAL
2.Submission of the Electrical Drawings CR25G/APPLEWATTA/DRA
08.09.2021 14.09.2021 Accepted
(Block - A,B,C) /022R4
Previous comments has not
been addressed.(according
3.Submission of the the Drawings of to my comments on
CR25G/APPLEWATTA/DRA
Lightning Protection System (Block A- 07.12.2021 08.12.2021 CR25G/APPLEWATTA/D 17.12.2021 Accepted
/029R6
Typical for Block B & C) RA/029R5 the contractor
shall address them and no
need of resubmission
MECHANICAL
1.Submission of Fire Protection Systems -
Fire Hydrant system & Sprinkler system CR25G/APPLEWATTA/DRA Need
05.12.2021 09.12.2021 Accepted 17.12.2021
/025R4 Resubmission

3.Submission of gas districbution and CR25G/APPLEWATTA/DRA See the comments in the Need
03.05.2021 05.05.2021 27.09.2021
detection system Block A,B,C /10S1-R2 drawings Resubmission

4.Submission of LP Gas distribution system CR25G/APPLEWATTA/DRA See the comments in the Need
03.05.2021 05.05.2021 27.09.2021
for typical Arrangement (Block A,B,C) /030 drawings Resubmission

2.Fire detection and communication system CR25G/APPLEWATTA/DRA


27.12.2021
(block A,B,C) /049
No issues
observed.However the
design & build contractor is
5.Design of External MEP Coordination CR25G/APPLEWATTA/DRA
05.01.2022 10.01.2022 responsible for coordinating
Drawing(block A) /042
services and any case
contractor shall rectify the
matter by there own cost
6.Design of Internal MEP Coordination CR25G/APPLEWATTA/DRA
13.01.2022
Drawing(block A) /051

78
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

2.3.2.5 Ferguson Road


Submittal No
(FRGSN750/ SEC UDA
Submitted
Drawing Subject CCECC- Commented Comment Commented Comment
Date
CR25GJV/ Date Date
DRA/…)
ARCHITECTURAL
Submission of architectural drawing - C - Submission incomplete. Need B - Accepted with comments.
2R1 19/11/2021 25/11/2021 7/12/2021
schematic drawing R1 resubmission with missing details. Need resubmission.
Submission of architectural drawing -
2R2 20/01/2022 21/01/2022
schematic drawing R3
STRUCTURAL

1. Pile

Submission of the location of test pile 1R1 8/4/2021 9/4/2021 A - Accepted 6/5/2021 A - Accepted

C - Submission incomplete and C - Submission incomplete and


Submission of general arrangement of
4 19/5/2021 21/5/2021 need resubmission with missing 14/7/2021 need resubmission with missing
piles
details. details.
Submission of Final Pile Coordinates
drawings R3 with NiM Surveyors 5R6 4/8/2021 9/8/2021 A - Accepted
signature and seal
Submission of revised general B - Accepted with comments. B - Accepted with comments.
6 31/5/2021 1/6/2021 14/7/2021
arrangement of block C piles Need resubmission. Need resubmission.
Submission of revised general C - Submission incomplete. Need C - Submission incomplete. Need
6R1 17/9/2021 23/9/2021 26/10/2021
arrangement of block C piles R4 resubmission with missing details. resubmission with missing details.
Submission of revised general B - Accepted with comments. B - Accepted with comments.
6R2 16/11/2021 25/11/2021 30/11/2021
arrangement of block C piles R5 Need resubmission. Need resubmission.
Submission of updated key plan and
7R1 9/7/2021 13/7/2021 A - Accepted 19/7/2021 A - Accepted
pile details (Block A B C)
Submission of general arrangement of
8 11/6/2021 14/6/2021 B - Accepted with comments.
block B piles

79
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

Submission of general arrangement of B - accepted with comments. B - accepted with comments.


8R1 16/11/2021 25/11/2021 30/11/2021
block B piles Need resubmission. Need resubmission.
Submission of general arrangement of B - accepted with comments.
12 9/7/2021 13/7/2021 A - Accepted 19/7/2021
piles (Block A B C) Need resubmission.
Submission of General arrangement of B - accepted with comments. B - accepted with comments.
20 26/11/2021 2/12/2021 7/12/2021
piles (Block A) Need resubmission. Need resubmission.
2. Pile cap
Submission of General Arrangement of
13 17/9/2021 27/9/2021 B - Accepted with comments. 26/10/2021 B - Accepted with comments.
Pile caps Block C
Submission of General Arrangement of C - Submission incomplete. Need C - Submission incomplete. Need
17 18/11/2021 3/12/2021 7/12/2021
Pile Caps (Block ABC) resubmission with missing details. resubmission with missing details.

3. GA Drawings

Submission of General Arrangement of


C - Submission incomplete. Need C - Submission incomplete. Need
Ground Floor, First Floor, Typical 14 17/9/2021 1/10/2021 8/10/2021
resubmission with missing details. resubmission with missing details.
Floor, Roof Floor (Block C)

Submission of General Arrangement of


C - Submission incomplete. Need C - Submission incomplete. Need
Ground Floor, First Floor, Typical 14R1 16/11/2021 3/12/2021 7/12/2021
resubmission with missing details. resubmission with missing details.
Floor, Roof Floor (Block C) R1

Submission of General Arrangement of


15 17/9/2021 27/9/2021 B - Accepted with comments. 26/10/2021 B - Accepted with comments.
Columns Layout Block C

Submission of General Arrangement of


B - Accepted with comments.
Ground Floor, First Floor, Typical 16 21/10/2021 25/10/2021
Need resubmission.
Floor, Roof Floor (Block A)

Submission of General Arrangement of


C - Submission incomplete. Need C - Submission incomplete. Need
Ground Floor, First Floor, Typical 16R1 16/11/2021 3/12/2021 7/12/2021
resubmission with missing details. resubmission with missing details.
Floor, Roof Floor (Block A) R1

Submission of General Arrangement of


B - Accepted with comments. B - Accepted with comments.
Column Layout of Ground Floor to 18 16/11/2021 29/11/2021 2/12/2021
Need resubmission. Need resubmission.
Roof (Block ABC)
19 16/11/2021 29/11/2021 2/12/2021

80
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

Submission of General Arrangement of


C - Submission incomplete. Need C - Submission incomplete. Need
Ground Floor, First Floor, Typical
resubmission with missing details. resubmission with missing details.
Floor, Roof Floor (Block B)
4. Ground Beams
5. GF slab
6. Column/Concrete walls
7. Typical Floor Slab
8. Typical Floor Beams
9. Staircase
10. Roof Slab
11. Roof Beams
12. Machine room
13 Water Tank
14. Sump

Submission of water sump and pump B - Accepted with comments. B - Accepted with comments.
11 6/7/2021 8/7/2021 21/07/2021
room arrangement for all three blocks Need resubmission. Need resubmission.

WATER SUPPLY SYSTEM

Submission of water supply system for


B - Accepted with comments. B - Accepted with comments.
roof terrace and single line diagram 24 14/12/2021 16/12/2021 22/12/2021
Need resubmission. Need resubmission.
(Block ABC)

Submission of Water Supply System B - Accepted with comments. B - Accepted with comments.
26 20/12/2021 22/12/2021 28/12/2021
(Block A) Need resubmission. Need resubmission.

COLD WATER SUPPLY SYSTEM

SEWAGE AND WASTE WATER DISPOSAL SYSTEM

81
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

Submission of sewer and waste water B - Accepted with comments. B - Accepted with comments.
27 20/12/2021 22/12/2021 31/12/2021
disposal system (Block A) Need resubmission. Need resubmission.
STORM WATER DISPOSAL SYSTEM
Submission of rain water disposal C - Submission incomplete. Need C - Submission incomplete. Need
25 20/12/2021 22/12/2021 30/12/2021
system (Block A) resubmission with missing details. resubmission with missing details.
ELECTRICAL
Submission of lightning protection
21 14/12/2021 16/12/2021 B - Accepted with comments. 22/12/2021 B - Accepted with comments.
system drawings (Block A)
Submission of lightning protection
22 14/12/2021 16/12/2021 B - Accepted with comments. 22/12/2021 B - Accepted with comments.
system drawings (Block B)
Submission of lightning protection
23 14/12/2021 16/12/2021 B - Accepted with comments. 22/12/2021 B - Accepted with comments.
system drawings (Block C)

Submission of Electrical distribution


28 28/12/2021 29/12/2021 B - Accepted with comments.
system drawing (Block ABC)

MECHANICAL

ROAD DETAIL
Submission of site layout internal B - Accepted with comments. B - Accepted with comments.
10R1 19/11/2021 25/11/2021 7/12/2021
roadways R1 (Master plan with DPC) Need resubmission. Need resubmission.
SETTING OUT
Submission of Setting Out Drawing R2 9R3 30/6/2021 2/7/2021 B - Accepted with comments.

82
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

2.3.2.6 Madampitiya

SEC UDA
Drawing Subject Submittal No Submitted Date Commented Comment Commented Comment
Date Date
ARCHITECTURAL
Architectural drawings for B-Accepted with comments as noted
construction issue MADA/TBL/DRG/002-R2 07.12.2021 15.12.2021 and need resubmission Pending

STRUCTURAL

initial test pile locations and


details MADM/TBL/DRG/001 Through mail
Architectural drawings for B-Accepted with comments as noted
construction issue MADA/TBL/DRG/002-R2 07.12.2021 15.12.2021 and need resubmission
Submission of revised
structural Drawings-layout of MADM/TBL/DRG/003-
piles(Block A,B & C) R3 14.12.2021 15.12.2021 A-Accepted 20.12.2021 A- Acceptance
Acceptance with
comments as noted
Setting out drawing of pile and need
points of tower B MADM/TBL/DRG/004 16.07.2021 20.07.2021 Accepted 05.08.2021 resubmission
Submission of Building Setting Accepted with
out drawing A,B & C MADM/TBL/DRG/005 19.07.2021 20.07.2021 Accepted with comments as noted 05.08.2021 comments as noted
Setting out drawing of pile
points of tower A MADM/TBL/DRG/006 27.07.2021 29.07.2021 Accepted 05.08.2021 Accepted
Contractor's reply as per
comments- layout and details of
piles tower D MADM/TBL/DRG/007 R1 04.10.2021 08.10.2021 A-Accepted 15.11.2021 A-Accepted
Reinforcement details of Shear MADM/TBL/DRG/008- B- Acceptance with comments as
walls - Tower A R2.12 21.01.2022 24.01.2022 noted and need resubmission
Reinforcement Details of Pile MADM/TBL/DRG/008-
caps (PC1,PC2 & PC3) R3.6 21.01.2022 25.01.2022 A- Acceptance
Reinforcement details of
ground floor level beam - MADM/TBL/DRG/008-
Tower A R3.7 21.01.2022 24.01.2022 A- Acceptance

83
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

Reinforcement details of Shear MADM/TBL/DRG/008- B- Acceptance with comments as


21.01.2022 24.01.2022
walls - Tower A R3.8 noted and need re submission
Ground floor slab R/F Details - MADM/TBL/DRG/008- 21.01.2022 24.01.2022 A- Acceptance
Tower A R3.9
Reinforcement details of Shear MADM/TBL/DRG/008- 21.01.2022 24.01.2022 A- Acceptance
walls - Tower A R3.10
Ground floor level beam r/f MADM/TBL/DRG/008- 21.01.2022 25.01.2022 A -Acceptance
detail - Tower A R3.11
General arrangement of lift pit MADM/TBL/DRG/008- 21.01.2022 24.01.2022 A- Acceptance
level (At -1.5) Tower A R4.1
General arrangement of ground
floor pile caps & capping MADM/TBL/DRG/008- 21.01.2022 24.01.2022 A- Acceptance
beams at +0.300 level tower A R4.2
RF details of pile capping MADM/TBL/DRG/008- 21.01.2022 25.01.2022 A- Acceptance
beams at lift pit level tower A R4.3
R/F details of lift pit level slab MADM/TBL/DRG/008- 24.01.2022 25.01.2022 A- Acceptance
Tower A R4.4
General arrangement of ground
floor level at +3.500 level- MADM/TBL/DRG/008- 24.01.2022 25.01.2022 A- Acceptance
Tower A R4.5
General arrangement of Lift pit B- Accepted with
level at -1.500, lift pit B- Accepted with comments as noted comments as noted
11.01.2022 18.01.2022
levelbeam r/f details,r/f details and need resubmission and need
of lift pit level slab- Tower B MADM/TBL/DRG/009R2 21.01.2022 resubmission
General Arrangement of
ground floor (Pile caps and
24.01.2022 25.01.2022 A- Acceptance
capping beams at +3.25 level)
Tower B MADM/TBL/DRG/010R2
Ground floor level beam R/F C-Submission incomplete and need
18.01.2022 24.01.2022
details MADM/TBL/DRG/011 R1 resubmission with missing details
General arrangement of ground 20.01.2022 26.01.2022 A- Acceptance
floor-Tower B MADM/TBL/DRG/012R2
Ground floor slab R/F details B-Accepted with comments as noted
18.01.2022 24.01.2022
Tower B MADM/TBL/DRG/013 R1 and need resubmission

84
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

General arrangement of lift pit


level (at -1.500) Tower C,
General arrangement of ground
floor (pile caps & capping
MADM/TBL/DRG/014 R2 20.01.2022 27.01.2022 A- Acceptance
beams at +.300 level) tower C
and General arrangement of
ground floor (at +0.300 level)
tower C
Setting out drawing of pile
MADM/TBL/DRG/015 15.09.2021 17.09.2021 A-Acceptance
points of tower C
Setting out drawing of pile
MADM/TBL/DRG/016 22.09.2021 23.09.2021 A-Acceptance 01.11.2021 A-Acceptance
points of tower D
C-Submission
Fire stair case drawing Tower C-Submission incomplete and need incomplete and need
MADM/TBL/DRG/017 22.09.2021 27.09.2021 14.10.2021
A,B and C resubmission with missing details resubmission with
missing details
B-Accepted with
General arrangement of GF, B-Accepted with comments as noted comments as noted
MADM/TBL/DRG/018 28.09.2021 08.10.2021 01.11.2021
Pile caps and Capping beams D and need resubmission and need
resubmission
B-Accepted with
B-Accepted with comments as noted comments as noted
Fire stair case details D MADM/TBL/DRG/019 28.09.2021 08.10.2021 15.11.2021
and need resubmission and need
resubmission
C-Submission
Ground floor at +0.3 level C-Submission incomplete and need incomplete and need
MADM/TBL/DRG/020 28.09.2021 08.10.2021 01.11.2021
beam R/f details D resubmission with missing details resubmission with
missing details
R/f details-Pile cap,lift C-Submission incomplete and need
MADM/TBL/DRG/021 28.09.2021 08.10.2021
pits,beam,slab D resubmission with missing details
C-Submission
R/F details-Ground floor slab C-Submission incomplete and need incomplete and need
MADM/TBL/DRG/022 28.09.2021 12.10.2021 01.11.2021
and shear walls D resubmission with missing details resubmission with
missing details
layout & pile details of Piles in MADM/TBL/DRG/023 R
14.12.2021 15.12.2021 A-Acceptance 20.12.2021 A-Acceptance
Tower D 2

85
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

B-Accepted with
Reinforcement details-Typical B-Accepted with comments as noted comments as noted
MADM/TBL/DRG/024 15.10.2021 02.11.2021 15.11.2021
floor slabs Tower A ,B ,C and need resubmission and need
resubmission
C-Submission
Reinforcement details-Typical C-Submission incomplete and need incomplete and need
MADM/TBL/DRG/025 15.10.2021 02.11.2021 15.11.2021
floor beam, Tower A resubmission with missing details resubmission with
missing details
C-Submission
General Arrangement of B- Acceptance with comments as incomplete and need
MADM/TBL/DRG/026 15.10.2021 02.11.2021 15.11.2021
Typical floor Tower A noted resubmission with
missing details
C-Submission
General Arrangement of B- Acceptance with comments as incomplete and need
MADM/TBL/DRG/027 15.10.2021 03.11.2021 15.11.2021
Typical floor Tower B noted resubmission with
missing details
C-Submission incomplete and need
Lightning protection system MADM/TBL/DRG/028 R1 18.12.2022 19.01.2022
resubmission with missing details
Architectural, Structural
MADM/TBL/DRG/029 14.12.2021 15.12.2021 A-Acceptance 21.12.2021 A-Acceptance
softcopy drawings
C-Submission
Building work details Tower A C-Submission incomplete and need incomplete and need
MADM/TBL/DRG/030 R1 10.01.2022 10.01.2022 19.01.2022
ground floor resubmission with missing details resubmission with
missing details
C-Submission
Building work details Tower B C-Submission incomplete and need incomplete and need
MADM/TBL/DRG/031 29.12.2021 31.12.2021 10.01.2022
ground floor resubmission with missing details resubmission with
missing details
B- Acceptance with comments as B- Acceptance with
Typical sump Rungs Detail MADM/TBL/DRG/032 05.01.2022 06.01.2022 19.01.2022
noted comment as noted
R/F Details of Lift Pit Level
MADM/TBL/DRG/033 20.01.2022 26.01.2022 A-Acceptance
Slab - Tower B
Builders work details Tower A
C-Submission incomplete and need
Sump and pump room area MADM/TBL/DRG/034 24.01.2022 25.01.2022
resubmission with missing details
below ground floor
Builders work details Tower C C-Submission incomplete and need
MADM/TBL/DRG/035 24.01.2022 25.01.2022
Ground floor resubmission with missing details

86
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

R/F details of new pile cap


MADM/TBL/DRG/037 27.01.2022
PCB 12a
Level 01 beam R/F details -
MADM/TBL/DRG/038 27.01.2022
Tower A,B,C
1st floor slab R/F Details -
MADM/TBL/DRG/039 27.01.2022
Tower A,B,C
General arrangement of level 1-
MADM/TBL/DRG/040 27.01.2022
Tower A
Layout of secondary concrete
MADM/TBL/DRG/041 27.01.2022
fill @ level 1- Tower A
Column Layout - Tower A,B,C MADM/TBL/DRG/042 27.01.2022
Layout of secondary concrete
MADM/TBL/DRG/043 27.01.2022
fill @ level 1- Tower B
General arrangement of level 1-
MADM/TBL/DRG/044 27.01.2022
Tower B

PLUMBING
C-Submission
Building work details Tower A C-Submission incomplete and need incomplete and need
MADM/TBL/DRG/030 R1 10.01.2022 10.01.2022 19.01.2022
ground floor resubmission with missing details resubmission with
missing details
C-Submission
Building work details Tower B C-Submission incomplete and need incomplete and need
MADM/TBL/DRG/031 30.12.2021 31.12.2021 10.01.2022
ground floor resubmission with missing details resubmission with
missing details

MEP
Lightning protection system MADM/TBL/DRG/028 R1 18.12.2022 Pending Pending

87
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

4 Financial Progress
2.4.1 Work done certification
2.4.1.1 Stadiumgama

IPA No SEC Received Issued Date Claimed amount Certified amount Remarks
Date (LKR-Mn) (LKR-Mn)
Not issued work
done certificate.
2 24/07/2020 24/07/2020 84.590
Approved only
percentage
3 10/9/2020 20/11/2020 153.11 134.66
4 7/10/2021 20/10/2021 132.99 158.19
5 5/11/2020 11/11/2021 365.86 210.38
6 17/12/2020 30/12/2020 186.34 113.41
7 8/1/2021 20/1/2021 61.72 55.24
8 11/2/2021 23/02/2021 133.84 63.79
9 11/3/2021 31/3/2021 150.48 103.37
10 10/4/2021 4/5/2021 53.84 63.76
11 7/5/2021 25/5/2021 65.02 59.03
12 8/6/2021 18/6/2021 118.11 74.37
13 5/7/2021 16/7/2021 128.11 120.17
14 5/8/2021 18/8/2021 169.42 115.17
15 7/9/2021 17/9/2021 158.13 114.35
16 6/10/2021 21/10/2021 262.81 200.87
17 6/11/2016 26/11/2021 171.24 106.87
18 01/12/202 03/12/2021 280.34 118.29
19 05/01/2021 13/01/2022 253.20 206.07
Total 2,929.15 2,017.99

88
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

2.4.1.2 Colombage Mawatha


IPA No SEC Received Issued Date Claimed amount Certified amount Remarks
Date (LKR-Mn) (LKR-Mn)
2 19/01/2021 3/2/2021 94.01 58.97
3 12/3/2021 26/03/2021 59.79 53.78
4 9/4/2021 29/4/2021 84.75 82.17
5 20/5/2021 28/05/2021 57.06 21.03
6 28/06/2021 8/7/2021 57.44 22.96
7 19/07/2021 27/07/2021 29.30 26.94
8 18/8/2021 1/9/2021 37.46 14.65
9 30/9/2021 13/10/2021 81.91 53.57
certified amount increased
10 12/11/2021 25/11/2021 54.41 57.96 due to correction of error
found in contractor’s price
fluctuation calculation

11 08/12/2021 14/12/2021 50.76 42.02


12 11/01/2022 21/01/2022 59.29 58.28
Total 666.18 492.33

89
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

2.4.1.3 Obesekarapura

IPA No SEC Received Issued Date Claimed amount Certified amount Remarks
Date (LKR-Mn) (LKR-Mn)
1 7/12/2020 16/12/2020 50.83 25.75
2 5/2/2021 11/2/2021 82.27 29.33
3 22/3/2021 5/4/2021 58.71 25.70
4 9/4/2021 29/4/2021 76.58 31.69
5 17/5/2021 7/6/2021 50.94 30.20
6 5/8/2021 10/8/2021 37.11 25.79
7 17/9/2021 14/10/2021 26.18 4.10
8 18/10/2021 3/11/2021 11.62 5.20
9 2/11/2021 8/11/2021 59.31 11.62
10 9/12/2021 10/12/2021 43.58 21.22
11 4/01/2022 12/01/222 33.99 6.59
Total 531.12 217.19

90
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

2.4.1.4 Applewatta
IPA No SEC Received Issued Date Claimed amount Certified amount Remarks
Date (LKR-Mn) (LKR-Mn)
1 9/4/2021 29/4/2021 135.37 69.00
2 6/5/2021 8/6/2021 148.40 43.50
3 6/6/2021 25/6/2021 161.50 87.50
4 4/7/2021 30/7/2021 179.80 58.00
5 6/8/2021 7/9/2021 142.30 42.00
6 5/9/2021 30/9/2021 116.60 11.60
7 7/10/2021 2/11/2021 133.80 22.10
8 6/11/2021 26/11/2021 83.3 4.4
9 6/12/2021 21/12/2021 65.4 3.8

10 6/1/2022 20/1/2022 65.1 10.4

Total 1231.57 352.3

Note- Please note that the Contractor prepared some IPAs based on the Contractors previous amount when they did not receive the copy of previous bill.

91
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

2.4.1.5 Furgusion
IPA No SEC Received Issued Date Claimed amount Certified amount Remarks
Date (LKR-Mn) (LKR-Mn)

1 2/12/2021 7/12/2021 187.30 118.0

Total 187.30 118.0

2.4.1.6 Madampitiya

IPA No SEC Received Issued Date Claimed amount Certified amount Remarks
Date (LKR-Mn) (LKR-Mn)
1 23/9/2021 25/10/2021 208.10 155.40

2 10/11/2021 30/11/2021 348.4 178.60


Material at site not
considered due to
non-availability of
3 06/12/2021 16/12/2021 359.4 69.7 proof document to
material stored in
off site
Material at site not
considered due to
non-availability of
4 10/01/2022 26/01/2022
234.8 29.8 proof document to
material stored in
off site
Total 1150.7 433.5

92
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

2.4.2 Variation Log

2.4.2.1 Stadiumgama
VO No Description SEC Status of the SEC Issued Claimed Recommended Remarks
Received submission Date Amount (Rs) Amount (Rs)
Date
DPC level Evaluation
VO1 18/11/2020 17/12/2020 18,860,477.88
Change completed 34,818,665.74

Demolition Evaluation
VO2 16/12/2020 18/12/2020 665,270.00
Work completed 1,603,800.00
Additional
VO3 Surveying
Work and plot 01/09/2021 Evaluation 02/09/2021
108,000.00 88,000.00
a new completed
surveying plan

2.4.2.2 Colombage Mawatha


VO No Description SEC Received Date Status of the SEC Issued Claimed Recommended Remarks
submission Date Amount (Rs) Amount (Rs)

Evaluation
09/12/2020
VO1 MLT Test 12/11/202021/01/2021 completed 134,233,215.44 36,527,089.01
01/02/2021

93
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

2.4.2.3 Madampitiya
VO No Description SEC Status of the SEC Issued Claimed Recommended Remarks
Received submission Date Amount (Rs) Amount (Rs)
Date
Cost of the Temporary fence
3m high 27/08/2021 Evaluation 29/10/2021 2,226,704.40 - is considered with the
V01 additional completed preliminary item no.36 until
fence the site possession is cleared
by the Employer. Once the
site possession will clear cost
is considered as lump sum
adjustment.

94
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

2.4.3 Claim Log-Cost

2.4.3.1 Stadiumgama
SEC Received Status of the Certified
Events Issued Date Remarks
Date submission amount
Covid 19 related
expenses 14/07/2021 Not evaluated - -

05/08/2021 25/10/2021 -
Not yet finalized and under
Evaluated
review, sent a letter to UDA on
27/09/2021 25/10/2021 -
25/10/2021

95
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

2.4.4 Claim Log-Extension of Time

2.4.4.1 Stadiumgama
EOT Events SEC Status of the SEC Requested Recommended
Nr Received submission issued Dates Dates Remarks
Date Date

EOT Delay incurred due to the obstacles 14/07/2021 Evaluation 10/8/2021 86 10


01 at the initial stage of the project completed
Delay incurred due to the change in
DPC level by 200mm
Delay in clearance of utility lines
Delay due to the re-emergence of
COVID 19 (2nd wave)
Delay due to the re-emergence of
COVID 19 (3rd wave)

96
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

2.4.4.2 Colombage Mawatha


EOT Nr Events SEC Status of SEC Requested Recommende Remarks
Received the issued Dates d Dates
Date submission Date
EOT 01 Delay in decision making on
MLT testing 19/02/2021 Evaluation 6/4/2021 176 71
COVID 19 lock down completed
Preparation of cost estimate &
procurement
Demolition work of additional
PB and pile cap
Eccentricity checking
PIT test
Core test
Pile build up for MLT
Ground preparation and MLT
testing
EOT 01R1 Delay in decision making on
MLT testing 20/05/2021 Evaluation 21/07/2021 Claimed Not more than
COVID 19 lock down completed previous the days in
Preparation of cost estimate & requested EOT 01
procurement days (as in evaluation
Demolition work of additional EOT 01) report
PB and pile cap
Eccentricity checking
PIT test
Core test
Pile build up for MLT
Ground preparation and MLT
testing

97
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

SEC Status of SEC


Requested Recommended
EOT Nr Events Received the issued Remarks
Dates Dates
Date submission Date

EOT 02 Inclement of weather 25/06/2021 Evaluation 20/07/2020 13 9


completed

EOT 03 Delay in the appointment of 27/10/2021 Evaluation 12/11/2021 178 29


Engineer’s Representative’s & completed (including
hence approval delay recommende
Variation Instruction for d days in
addition test on existing piles EOT 01)
Lockdown for COVID 19
Pandemic
Variation Work (MLT test,
core test, Ec. checking &
demolishing for MLT)

EOT 04 Inclement of weather - 11/11/2021 Evaluation 26/11/2021 21 -


September 2021 completed

98
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

2.4.4.3 Obesekarapura
EOT Nr Events SEC Status of SEC issued Requested Recommended Remarks
Received the Date Dates Dates
Date submission
COVID 19 lock down from 20th
EOT 01 March 2020 to 28th June 2020 22/3/2021 Evaluation 23/4/2021 118 36
COVID 19 post curfew effect completed
from 28th June 2020 to 12th July
2020
COVID 19 lock down from 25th
Oct to 29th Oct 2020
Curfew effect from 04th Oct 2020
to 25th Oct 2020
Extended curfew for Western
province from 30th Oct 2020 to
9th Nov 2020
Post curfew effect from 09th Nov
2020 to 29th Nov 2020

Covid 19 – 1st Wave


EOT 02 Island wide lockdown and 11/11/2021 Evaluation 23/11/2021 218 11
restriction due to spreading of completed
Covid 19 - from October 2020 to
July 2021
Island wide lockdown and
restriction due to spreading of
Covid 19 - from July 2021 to 11th
November 2021

EOT 2R1 Post Curfew effect of COVID 19 11/11/2021 Evaluation 144 81 Further
Post COVID 19 effect completed 23/11/2021 evaluation
of EOT 02

99
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

2.4.4.4 Applewatta
EOT Nr Events SEC Status of SEC issued Requested Recommended Remarks
Received the Date Dates Dates
Date submission
Due to non availability of
EOT 01 COVID- 19 20/07/2021 Rejected 22/7/2021 26 - documentary evidence
lock down evaluation is not done.
Requested to re-submit the
claim.
Due to non availability of
EOT 01 COVID- 19 29/12/2021 Need 31/12/2021 43 - documentary evidence
lock down resubmission evaluation is not done.
Requested to re-submit the
claim.

100
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

2.4.5 Executive Summary


Cumulative Cumulative Work done
Total Physical Progress Physical Progress Time Delay- Average
No. Time Value as at
Project Starting as at end of Dec as at end of Jan Elapsed Days Manpower
Project of End Date Elapsed End Jan
Cost (Rs Date 2021 2022 as at End (If for Jan
Units % 2022 (Rs.
Mn) Jan 2022 any) 2022
Target Actual Target Actual Mn.)
Stadiumgama 1000 5,951 4-May-20 16-Oct-23 33.8% 35.6% 36.7% 39.61% 637 50.56% 0 2408.07 410
Colombage Mawatha 624 3,127 1-Jun-20 16-May-23 23.82% 18.06% 26.82% 19.94% 609 56.38% ** 624.43 105
Obeysekarapura 300 1,723 4-May-20 21-Oct-22 55.3% 11.50% 59.20% 11.90% 638 70.80% 235 237.56 25
Applewatta 700 3,890 27-Oct-20 17-Oct-23 35.13% 13.77% 38.49% 14.48% 462 42.5% 140 402.57 53
Ferguson 750 3,923 20-Jan-21 4-Jan-24 19.10% 6.50% 19.54% 6.59% 377 34.90% 186 138.88 4
Madampitiya 700 3,937 20-May-21 3-May-24 10.80% 8.42% 12.16% 9.78% 256 23.70% 40 434.90 55
Overall Summary 4,074 22,550 04-May-20 3-May-24
** 100 additional days were granted after the EOT evaluation. However revised master program to be submitted by MAGA.

SCHEDULE PROGRESS VS ACHIVED PROGRESS


100.00%
90.00%
80.00%
70.00%
59.20%
60.00%
50.00%
39.60% 38.49%
40.00% 36.70%

30.00% 26.82%
19.94% 19.54%
20.00% 11.90% 14.48% 12.10% 9.78%
10.00% 6.59%

0.00%
Stadiumgama Colambage Mawatha Obesekarapura Applewatta Furgusion Road Madampitiya

SCHEDULE PROGRESS ACHIVED PROGRESS

101
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

2.4.6 Major Achievements in last month

1 Stadiumgama -

2 Colombage Mawatha First floor slab concreting was completed.


3 Obeysekarapura -
4 Applewatta Completion of ground beam concreting of Block B

5 Ferguson Road -

6 Madampitiya -

102
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

2.5 Progress of Health, safety provision and Implementation of Environmental


provisions
During the site visits, it was observed that all of the contractors have performed more than 50%
achievement in General Safety.

Summary of checklists observed on months of January 2022

Environme
Project Health & Safety Checklists ntal & Remarks
Social
General Work at Piling Hot Excavation
Safety Height Safety work

Construction
works were not
progressing during
the inspection day.
Periodic awareness
to the Muwadora
uyana dwellers to
be conducted for
safety. Proper
dewatering method
Ferguson Road 68% - - - - 46.5% to be executed.
Interim monitoring
has to be
conducted when
started work.
Housekeeping to
be improved. Fire
training to be
conducted and fire
extinguishers to be
kept at site.
Poor progress and
labours observed
Obeysekarapura 76.5% - - - - 67.5% during the visit.
Housekeeping,
waste water

103
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

discharge method
at canteen, safe
pathways within
the construction
site and store
rooms have to be
properly improved.
Public complaints
to be addressed.
Fire training to be
done.
Dewatering pond
to be properly
maintained.
Fuel/oil to be
stored without
leakage. Proper
shoring to be done
Apple Watta at sump excavation
79% - - - 86% 77%
area as per the
method statement.
Safe electrical
practices to be
implemented.
Adequate fire
extinguishers to be
provided.
Housekeeping to
be improved.
Safety notice
boards/ barricades
around open to sky
Colombage
91.5% 86% - - - 88% areas to be
Mawatha
practiced within
the buildings under
construction.
Contamination of
oil to the ground at

104
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

fuel storage area


has to be avoided.
Records to be kept
for checking
scaffolding safety.
Stadiumgama - - - Site visit yet to be
conducted.

Madampitiya 94.5% - Storeroom to be


84% properly labelled
and housekeeping
to be improved
further. Approved
waste dumping
yard to be
submitted.

105
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

2.6 Progress photos


2.6.1 – Stadiumgama

106
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

2.6.2 Colambage Mawatha

107
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

2.6.3 Obeysekarapura

108
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

2.6.4 Applewatta

109
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

2.6.5 Ferguson Road

110
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

2.6.6 Madampitiya

111
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

3.0 CLEARANCES AND BUILDING PERMITS


Project Name Clearance Type Approval Status
Aviation clearance Received
Fire clearance Received
Water board clearance Received
Drainage & Sewer clearance
(CMC) Received

Storm water (SLLDC) Received


Stadiumgama
CEB clearance Received
NBRO Received
ECC Received
CMA Processing
Building permit Processing
Street Line (CMC) Received
Aviation clearance Received
Fire clearance Received
Water board clearance Received
Drainage & Sewer clearance
Received
(CMC)
Storm water (SLLDC) Received
Colambage Mawatha CEB clearance Received
Conditional approval given.
NBRO
Applied for the final approval.
ECC Received
CMA Processing.
Building permit Received
Street Line (CMC) Received

Aviation Clearance Received


Fire Clearance Received
Water board clearance Received
STP clearance Processing
Obeysekarapura CEB Clearance Received
NBRO Received
ECC Processing.
CMA Processing
Building permit Processing
Street Line (CMC) Received
Aviation clearance Received
Applewatta Fire clearance Received
Water board clearance Received

112
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

Drainage & Sewer


Received
Clearance (CMC)
Storm water (SLLDC) Pending
CEB clearance Received
NBRO Received
ECC Pending
CMA Pending
Building permit Pending
Street Line (CMC) Received

Aviation clearance Received


Fire clearance Received
Water board clearance Received
Drainage & Sewer
Pending
Clearance (CMC)
Furgusion Road Solid waste clearance Received
Storm water (SLLDC) Pending
CEB clearance Received
NBRO Pending
ECC Pending
CMA Pending
Building permit Pending
Aviation clearance Received
Approval granted for
Fire clearance
Architectural drawings
Water board clearance Received
Drainage & Sewer
Received
Clearance (CMC)
Storm water (SLLDC) Processing
Madampitiya
CEB clearance Received
Conditional Approval granted
NBRO
for the project
ECC Processing
CMA Processing
Building permit Pending
Street Line (CMC) Received
CMC  Colombo Municipal Council
ECC  Environmental Consultative Committee
CMA  Condominium management Authority
SLLDC  Sri Lanka Land Development Corporation
CEB  Ceylon Electricity Board
NBRO  National Building Research Organization
STP  Sewerage Treatment Plant

113
Monthly Progress Report No. 07 (Month of January 2022)
Support To Colombo Urban Regeneration Project (SCURP – AIIB) Urban Development Authority, Sri Lanka

4.0 PREVAILING DRAWBACKS


Project Name Drawbacks
- Material shortage in the market. (Cement, Aggregates)
Stadiumgama - Obstacles (unauthorized dwellings) in the site access road
causing problems for material transportation.
- Night work concreting near the road area cannot be done due
Colombage Mawatha to the neighbors’ complaints.
- Cement shortage in the market.
- Delays in submission of design deliverables and method
statements.
- Delays in submission of testing results.
- Delay in fixing the broken-down tower crane
- Manpower shortage
Obeysekarapura
- Issues in staff retention
- Due to prevailing Economic crisis
 Material shortage in the market and high price
 Importation restrictions.

- Construction of pile caps of Block C cannot be started since two


PDA Test results of Block C are still pending.
- There was no continuous concreting process due to difficulties
in obtaining ready-mix concrete because of the prevailing
Applewatta
cement shortage of the country. (According to Contractor’s
information).
- Lack of labor force at site compared to the approved
construction programme.
- No pile boring & concreting work due to no concrete supply
from approved batching plants (Detong Lanka, Capital &
Tudawe Brothers) as per contractor’s information.
Furgusion Road
- Not proceeding the pile hacking & pile testing works
- Most of the structural & MEP drawings are not submitted yet
- Unavailability of key technical persons at site.
- Block E area is required to clear in order to proceed the soil
investigation and structural design. There are existing houses
to be removed.
- Approval for site entrance is required from Madampitiya
Madampitiya roadside. To have easy access for the main stores, material
storing area and bar bending yard, site entrance from
Madampitiya road is highly required.
- Actual labor strength is considerably behind the scheduled
manpower, and it will directly affect for the physical progress.