Professional Documents
Culture Documents
และวิเคราะห์ผลระบบเฝ้าตรวจแบบออนไลน์
Smart Digital Substation: Standards, Connection Code, Review
Design and Result Analysis for Online Monitoring System
Rathanak Seoun
Chanawee Jirapong
Rathanak Seoun
Chanawee Jirapong
Abstract
The project cooperative education report presents about smart digital
substation, standard, review design, connection code, and online monitoring according
to the IEC 61850 standard of high voltage digital substation. By comparing the
utilization of a merging unit to conventional substations. Calculating the digital
substation availability by the reliability blog diagram method and considering the
performance of the protection system by total fault clearance time. On the other hand,
collects data from electronic sensors and analysis for online monitoring, asset
performance management (APM), and dissolved gas analysis (DGA) on the power
transformer. Thousands of sensors are integrated into digital substations, increasing
reliability, availability, and safety will reduce costs and risks. The online monitoring
system increases the lifespan of transformers and improves maintenance efficiency.
Keywords: APM, Digital substation, IEC 61850 standards, Merging unit, Online
monitoring
II
Acknowledgment
This project would not have been successfully completed without the support
of Hitachi Energy (Thailand) Limited which offered the opportunity for us to
accomplish the project. We are grateful to the Sattahip Electricity Authority, The Royal
Thai Navy Welfare Concession for providing the case study information for this report
cooperative education. We are also deeply grateful to Dr.Praditpong Suksirithawornkul,
who assists in serving as a mentor and consultant throughout this project.
Rathanak Seoun
Chanawee Jirapong
III
Table of contents
Page
Abstracts I
Acknowledgment II
Table of contents III
List of tables VI
List of figures VII
CHAPTER I Objective and Scope of Study
1.1 Background and statement of problems 1
1.2 Objective 1
1.3 Scope of Study 2
1.4 Methodology 2
1.5 Contribution to knowledge 2
1.6 Procedure and research methodology 2
CHAPTER II Background Introduction
2.1 Substations 6
2.1.1 Definition of substation and its function 6
2.1.2 Types of switchgear 6
2.1.3 The conception of substation designing 8
2.1.4 Choosing the type to be applied 11
2.1.5 Conventional substation 12
2.1.6 The evolution from conventional substation to digital
substation 15
2.2 Digital Substation Based on IEC 61850 Standard 16
2.2.1 IEC 61850 standard 16
2.2.2 The three levels architecture of digital substation 16
2.2.3 Protocol used in digital substation 18
2.2.4 Reliability and availability 18
2.2.5 Network redundancy protocol 21
2.2.6 Fault clearance time of substation 22
2.2.7 Stand-alone merging unit (SAMU) 24
2.2.8 Intelligent electronic devices (IEDs) 25
2.2.9 Medium voltage switchgear (MV switchgear) 26
2.3 Transformer 27
2.3.1 Why need power transformers? 27
2.3.2 Power transformer working principles 27
2.3.3 Power transformer components 28
2.4 Surge arrester of power transformer 29
2.4.1 Definition of surge arrester 29
2.4.2 Why do we need the surge arrester? 29
2.4.3 Working and method of measurement of surge arresters 29
IV
REFERENCES 114
APPENDICES
Appendix A – Raw data 116
Appendix B – Technical data 119
Appendix C – Single line diagram and ANSI code 125
AUTHOR BIOGRAPHY 133
VI
List of tables
Table Page
2.1 Common standard of high-voltage equipment 10
2.2 The reasonable of choosing the type to be applied 11
2.3 MTBF of each equipment in the substation 19
2.4 Type of merging units 24
2.5 The regular monitoring of power transformers 31
2.6 The recommended temperature configuration 35
2.7 Condition classification of gas concentration limits by IEEE 37
2.8 Classification of gas concentration limits by key gas 37
2.9 Roger ratio 38
2.10 The signification ratio of each gas 38
2.11 Classification of gas concentration limits by IEC 39
2.12 Classification of gas concentration limits by doernenburge ratio 39
2.13 Classification of gas concentration limits by Duval’s triangle 40
4.1 Component of 115 kV switchgear 78
4.2 Per transmission line bay configuration 78
4.3 Per transformer bay configuration 79
4.4 Per bus tie bay configuration 79
4.5 Components of 22 kV switchgear 83
4.6 MTTF data of substation devices 84
4.7 Current measurement from RET670 (HV – TCPP1) 90
4.8 Current measurement from RET670 (MV - TCPP1) 90
4.9 Current measurement from REC670 (HV - TCPP1) 90
4.10 Current measurement from RET670 (HV – TCPP2) 90
4.11 Current measurement from RET670 (MV – TCPP2) 91
4.12 Current measurement from REC670 (HV – TCPP2) 91
4.13 Current measurement from RED6700 (LCPP2) 91
4.14 Voltage measurement from RED6700 (LCPP2) 91
4.15 Current measurement from REC6470 (LCPP2) 91
4.16 Voltage measurement from REC670 (LCPP2) 92
4.17 Trip time of digital substation 93
4.18 Trip time of conventional substation 93
VII
List of figures
Figure Page
2.1 Air-insulated switchgear (AIS) 7
2.2 Gas-insulated switchgear (GIS) 7
2.3 Mix-technology switchgear (MTS) 8
2.4 Land requirement of AIS GIS and MTS Substation 12
2.5 Conventional substation 12
2.6 Hardwired from primary to secondary equipment in
conventional substations 13
2.7 Communication of conventional substations 14
2.8 Copper wiring connection in conventional substations 14
2.9 The evolution from conventional substations to digital substations 15
2.10 IEC 61850 Communication bus 16
2.11The architecture of digital substations 17
2.12 Communication protocol use in digital substations 18
2.13 The structure of system 21
2.14 The PRP topology 21
2.15 The HSR topology 22
2.16 Secondary systems in conventional and digital substations system 22
2.17 Fault clearance time of conventional system 23
2.18 Fault clearance time of digital system 23
2.19 The connection from the instrument transformer to SMU 24
2.20 Merging unit architecture 24
2.21 Non-conventional instrument transformer 25
2.22 Relion 670 series IEDs 26
2.23 Medium voltage switchgear (ABB) 26
2.24 Location of transformer connection in electricity system 27
2.25 Working principle of power transformer 28
2.26 The component of a power transformer 29
2.27 The equivalent of surge arrester 30
2.28 The parameter that affects to transformer component 30
2.29 Types of any faults that fluence by gas generated 36
2.30 Duval’s triangle 40
3.1 Flow chart 42
3.2 Standalone merging unit in an SV Application 43
3.3 IEDs in GOOSE application 44
3.4 Method of communication in digital substations 44
3.5 SAM600 located at process bus 45
3.6 SAM600-I/O 45
3.7 Line feeder arrangement 46
3.8 Transformer feeder arrangement 46
3.9 Relion 670 Series 47
3.10 SSC600 49
3.11 Connection of SSC600 49
3.12 Structure of MV switchgear with SSC600 50
VIII
1.2 Objectives
1.2.1 To study the standard, connection code, and monitoring of digital
substations.
1.2.2 To study and compare conventional substations and digital substations
according to IEC 61850 standard.
2
1.2.3 To study and understand the concept of design and analysis for the online
monitoring system.
1.2.4 To study and understand the operating of the appliances in the switchyard.
1.6.6 Review apparatus by using MV Digital SSC 600 according to IEC 61850
for the design and operation of Digital High Voltage Substations.
1.6.7 Analyze, compare, and evaluate the usage of the SAM 600 device.
1.6.8 Analyze, compare, and evaluate the usage of TXpertTM, CoresenseTM,
TM
CoreTec , EXCOUNT III.
1.6.9 Analyze, compare, and evaluate the usage of MV Digital SSC 600.
1.6.10 Summarize the result, prepare a handbook, and prepare to present the
project.
Background Introduction
Many types of research are related to the renovation of conventional substations
to digital substations, and try to find a solution for improving the substation in other to
increase more abilities and transmission stability power to consumers. Moreover, gain
more efficient and accurate data for protection. The topic is related to the project can
present as follows.
2.1 Substations
2.1.1 Definition of substation and its function [1][2]
Dave (2018) presented the electrical substation as a network of electrical
components that includes power transformers, busbars, auxiliaries, switchgear, and others.
The electrical substation is the part of the power system that could vary or transform the
voltage levels from high to low or versa to transmit the high voltage from the generation
source to the distribution consumers.
The components are interconnected in substations that are created with a control
and protection sequence of circuit cables to be switched OFF while in an emergency it can
be switched OFF automatically and provide a flexible system. Emergencies situations such
as earthquakes, floods, or short circuits can be managed.
The designer must be planed the primary equipment to be mounted on the steel
frame and the determined distance between each apparatus for electrical safety (Electrical
Clearance). Although the AIS substation mostly is installed Outdoor, therefore needed to
be considered environmental conditions such as pressure, temperature, humidity, fouling,
dust, and lighting protection must be considered.
The following are general conceptual and the consideration for designing
substations.
Service condition
• Location, Altitude
• High and low Mean temperatures
• Temperature extremes
• Wind load and ice loading
• Seismic qualifications
• Area classification
• Contamination
• System Frequency
• System grounding
• System impedance data
Utility requirements
• Application of utility specifications
• Application of utility standards
10
Communication/Monitoring requirements
• Manned or unmanned
• Power management/Trending
• Fault recording
• Local and remote annunciation
• Local and remote control
• Automation
• Communication protocol
Figure 2.4 Land requirement of AIS, GIS, and MTS substation [3]
Figure 2.4 compare that the AIS substation demands the largest area size of 100
%, followed by the MTS substation with 30 % of the AIS substation and the GIS substation
with 10 % of the AIS substation, which means that if the AIS substation covers an area of
200 meters, the GIS and MTS will cover an area of 20 meters and 60 meters, respectively.
In digital substations, the IEC61850 standard has been fully applied. The
copper cables connecting the primary side are eliminated by the IEC 61850 process bus
compatible with the Merging Unit. IEDs can perform both protection and control functions.
A digital communication capable of transmitting critical time data at high speeds capable
of transmitting data in milliseconds. Remote control of SCADA automation systems in
real-time via fiber optic cable with ethernet connection comes with redundancy to ensure
system reliability and availability.
Figure 2.9 The evolution from conventional substations to digital substations [6]
16
• Process level
Process level functions in a switchyard is including switchgear and merging
units. The merging units located at this level digitize voltage and current measurements
and send these digital values to IEDs.
• Bay level
Bay level consists of protection and control devices or IEDs. The IEDs
receive information and the status of the primary equipment from the process level and
process these data to perform protection and control functions through protective devices
in switchyards, including circuit breakers and disconnecting switches.
• Station level
Station level functions in a control room are used for control and monitoring
the substation. It consists of devices such as HMI and SCADA. it can monitor, control, and
record events in the substation. Operation in the station can be controlled with remote
control.
• Process bus:
The process bus is contained in the IEC61850-9-2 standard and allows
digital signals and messages to be sent and received between the process and bay levels.
This provides communication between the control IED and the protection IED, enabling
the circuit breaker to trip. process bus allows for a significant reduction of copper
hardwires.
• Station bus:
The station bus is for remotely controlling and monitoring all of the
substation's status and information. The station bus enables digital communication between
the station and bay levels. This allows control centers (HMI, SCADA) to monitor bay level
and process level operations. Generally, SCADA control, monitoring, and alarm services
are available via the station bus.
• SMV Protocol
SMV (Sampled measured Value) is used to transmit electrical data obtained
from measurements of instrument transformers in real-time digital data. The SMV is
converted from analog data by the Merging Unit (MU) with a sampling rate of 80 or 256
samples per system power cycle. Time reference and time synchronization are necessary
to separate samples from various sources.
• GOOSE Protocol
GOOSE (Generic Object-Oriented Substation Event) is the protocol for
control communication at the bay level. The GOOSE works at high speed (<3ms) and used
with systems where the time of operation is critical. The GOOSE message is used to
exchange and publish the data between IEDs for interlocking and logic and to control high
voltage equipment such as “trip” the circuit breaker.
• MMS Protocol
MMS (Manufacturing Message Specification) is a protocol that transmits
system information in the vertical direction from IEDs into the station level, to report
information on the HMI in the control room. The MMS protocol or client-server has no
critical times requirement.
Reliability is the reliability of the whole system. The system can work
according to the function in the specified conditions and time without fail and the system
can run with high confidence and high reliability.
Availability calculation:
The Availability is calculated from,
(2.1)
Where;
MTTR (Mean Time to Repair) is the amount of time it takes to repair a
system.
MTBF (Mean Time Between Failures) is the amount of time the system can
work normally
The reliability calculations in the model diagrams are done according to the
following formulas;
Availability:
A= A1*A2 if components 1 and 2 are in series
A= A1 + A2 – (A1*A2) if components 1 and 2 are in parallel
• MTBF
The following table contains reliability data for the used
components. This data is from supplier documents.
• MTTR
This time is expected to begin with the occurrence of a fault, involve
diagnosis and replacement of the failed part in the system, and finish when the failed part
is fully operational again.
In this system, we will determine MTTR as 3.5 hours.
• Calculation model
Gateway
MTTR = 3.5
RTU560CMR02 = 857,122/(857,122+3.5) = 0.9999959165
A (system)= A(1)*A(2)*A(34)*A(56)*(A78)
In reality, this value can be decreased which means the availability will be
increased. ABB has used the highest values (4 hours)
• PRP
PRP (Parallel redundancy protocol) uses two separated ethernet networks
(LANs) that are operated in parallel. If switch LAN A fails, an IED destination operates to
switch LAN B. The PRP can thereby accommodate more IEDs than HSR (high availability
seamless redundancy protocol).
• HSR
HSR (High availability seamless redundancy) is a network protocol that
employs in a single-ring topology. The HSR will allow sending data in both directions of
the single ring. If a link fails, an IED destination will operate to the other path that still
working. Due to ring topology, HSR is less expensive than PRP.
Figure 2.16 Secondary systems in conventional and digital substations system [13]
Figure 2.19 The connection from the instrument transformer to SMU [18]
No Scheme Observation
A SAMU is a device that is separated from
2 CT - DIG - SAMU
the instrument transformer and has digital inputs
alerted when there is an abnormality in IEDs. Common types of IEDs include protective
relay devices and circuit breaker controls.
Types of IEDs
The IEDs applied to IEC 61850 standard have the following categories:
• Protection IEDs
The protection IEDs include the bus, transmission line, and transformer
relays which perform protection functions such as overcurrent protection, differential
protection, directional protection, etc.
• Control IEDs
The control IEDs include bay control functions for switchgear equipment
and transformer tap changers with monitoring and metering functions.
• Breaker IEDs
The breaker IEDs are the circuit breaker monitors and controllers. These
IEDs send GOOSE messages throughout the whole system, mostly to the upper-level IEDs,
alerting them about state changes in the local substation network.
(2.1)
(2.2)
therefore (2.3)
28
Voltage times current in the primary = voltage times current in the secondary:
Vp*Ip = Vs*Is or kVA in = kVA out (less losses)
𝑉𝑝 𝑁𝑝
Voltages are proportional to the turn ratio: = (2.4)
𝑉𝑠 𝑁𝑠
Currents are inversely proportional to the turn ratio:
𝐼𝑝 𝑁𝑠
= therefore (2.5)
𝐼𝑠 𝑁𝑝
where
• Vp is the primary voltage
• Vs is the secondary voltage
• Ip is the primary current
• Is is the secondary current
• Np is the number of turns in the primary winding
• Ns is the number of turns in the secondary winding
2.3.3 Transformer components [23]
There are several components of a transformer including
1. Tank
2. Radiator & Fan
3. Local control cabinet
4. Breather (Silica-gel)
5. Conservator
6. HV bushing
7. LV bushing
8. MV cable box
9. Surge arrester
10. Buchholz relay
11. Air leakage detector
12. Tap changer (TC)
13. Core &Clamp, 14).
14. Winding
15. Insulator
29
• Visual inspects of
OLTC
• Check the oil level of
On Load Tap Changer OLTC Quarterly
• Test the dielectric
strength insulated of
transformer oil
3). The monitoring system of the transformer can roughly be separated into two-level, high-
level monitoring, and low-level monitoring.
• High level
Online monitoring: the online monitoring system is protection various
failures for better load capacity, minimal maintenance, and reliable operation. The online
monitoring system provided the data from just a few sensors such as temperature, gas in
oil, moisture, currents, voltage, and tap changer.
• Low level
- Periodic recording of a few parameters, visual inspection
- Oil condition monitoring
- Off-line monitoring
The parameters that were verified could be oil level, top oil temperature,
winding temperature, dehydrating breather, and load current. These parameters may be
checked daily and the visual inspection of the transformer for leakages and cracks in the
bushing should be performed weekly or monthly. Additionally, the oil and transformer’s
insulation condition is determined by taking oil samples from the transformer for dissolved
gas analysis (DGA). Off-line condition monitoring actually during transformer de-energize
to impossible to inspect components that are not visible when transformers still operating,
the internal checkup of the power transformer may be performed after draining the oil.
To measure and indicate the fault of transformers we need to implement
many of the accessories as listed below:
saturation value is reached at around 30% to 40% of its weight. And then may be indicated
by the changing color from blue to pink color of silica gel. The new type of silica gel will
show from orange to colorless.
Oil level indicators: the oil indicators are utilized to measure the oil level
in the conservator tank, and the dial instrument was placed directly on the conservator tank.
The indicator is equipped with switches for high and low oil levels with an alarm.
Pressure relief devices: pressure relief is used to limit the tank's exceeded
pressure on an internal fault and to reduce the harm of rupture of the tank and uncontrolled
spill of oil, that influence to make the fire associated with the fault.
Flow indicator: for controlling of oil flow out of pumps on the transformer
with forced oil cooling. The indicator is often based on a method of measuring the pressure
difference across an obstacle in the oil flow. The indicators are equipped with an alarm
switch and also include a dial.
All the connecting equipment must have a limited rate and functions
• Thermometer with contacts for alarm and tripping signal
• Oil level indicator with contacts for alarm signal
• Gas relay with contacts for alarm and trapping signals
• Pressure relief device with contacts for alarm Recommended thermometer
settings for ONAN transformers
35
Single gas
Hydrogen and moisture are defined as single gas, the exceeded quantity of
this mentioned gas very affects the power transformer since hydrogen gas is the main
component of any chemical gases that allowed the deterioration of the power transformer
oil and the exceeded moisture in of transformer oil, will raise the transformer temperature
in oil and impact to paper insulated.
Multiple gases
The justification for using dissolved gas analysis is based on the discovery
that during a lifetime, oil or cellulose insulation can still operating condition. For many
years the method of analysis of gases dissolved in oil (DGA) has been used as a tool for
transformer diagnostics for purposes to detect incipient faults, to supervises, suspect
transformers, test a hypothesis or explanation cause of failures, to ensure that the new
transformer is healthy, so there are several gases need to know such as Hydrogen (H2),
Methane (CH4), Ethylene (C2H4), Ethane (C2H6), Acetylene (C2H2), Propene (C3H6),
36
Propane (C3H8), Carbon monoxide (CO), and Carbon dioxide (CO2). All gases are
combustible gases except oxygen and nitrogen, so the total dissolved combustible gasses
are TDCG = H2 + CH4 + C2H4 + C2H6 + C2H2 + CO.
The reason behind the dissolved gas analysis is based on the fault during a
lifetime, all oil and cellulose insulated systems generate decomposition gases under the
impact of stress, both normal and abnormal states that allowed many faults to the power
transformer, and the diagram below will describe why the gases are generated faults. These
gases concentrations are measured in Parts Per Million (ppm)
Moreover, if there are exceeded gases, means that need to take oil to a
laboratory for analysis and may be followed by the procedure.
The procedure for performing dissolved gas analysis consists of main four
steps:
• A sampling of oil from the transformer
• Extraction of oil from the transformer
• Analysis of the extracted gas mixture through gas chromatography
• Interpretation of the analysis according to an evaluation scheme.
The last step is the interpretation of gases is essential for defining the
condition and avoiding any faults of the power transformer for energized power
continuously. Interpretation is taken from DGA and followed by six popular methods such
as:
1. IEEE method
2. Key gas method
3. Roger’s ratio method
4. IEC method
5. Doemenburg ratio method
6. Duval triangle method
37
IEEE method
The interpretation of gases based on IEEE C57-104 and consideration of the Total
Dissolved Combustible Gases (TDCG) to determine whether a transformer is behaving
normally with the acceptable concentration of gases or over the limitation.
Principle
Case
fault CO H2 CH4 C2H6 C2H4 C2H2
gas
Arcing in
4
C2H2 - 60% 5% 2% 3% 30%
oil
Roger’s method
This method takes into account the criteria for each gas’s ratio, the ratio of gas is
significant and will be used for the analysis of the result. There are five ratios, but this
method will be taken only the ratio of R1, R2, and R5 (ppm).
R1
R2
R3
R4
R5
Case fault R2 R1 R5
IEC Method
The interpretation method according to IEC 60599 is similar to Roger’s ratio, by
focusing on three gas ratios R1, R2, and R5 (ppm) for indicates the abnormal and any faults
of the transformer as defined in the table below.
Thermal decomposition > 1.0 < 0.75 < 0.3 > 0.4
1
Corona (low-intensity partial < 0.1 - < 0.3 > 0.4
2 discharge)
Arcing (high-intensity partial 0.1 – 1.0 > 0.75 > 0.3 < 0.4
3 discharge)
(2.6)
(2.7)
(2.8)
Case
Fault diagnosis CH4 C2H2 C2H4
DT Combination of thermal
-
and electrical fault
This chapter covers the theory of digital and conventional substations, the IEC
61850 standards, reliability and availability, and fault clearance times of the substation.
The theory of the power transformers is also covered in this chapter and as well as the
impact of gas on transformers, several transformer protection devices are used. The next
chapter will focus on the online monitoring system of power transformers by applying a
variety of sensors and the communication of digital substations utilize by merging units
will be made possible in the next chapter.
CHAPTER III
Review Design
This chapter discusses the review design of the digital substation, the
communication, and the connection code, and how to transmit the data from the CT,
and VT to the control room for control. Moreover, will mention about SAM600 process
bus I/O enabling digital substations including IEDs for protection and control. In
another hand, to supplement substation reliability and efficiency, the power transformer
is the main component of the electrical system to thought about. So, the TXpertTM
enables the digitalization transformer. This section mainly talks about the digitalized
substation based on the products of Hitachi Energy.
Hitachi energy is the global technology leader and advancing a sustainable
energy future for all.
Figure 3.7 and Figure 3.8 Shows the installation and connection of SAM600
series devices, including the use of SAM600-CT connected to a current transformer to
digitize current, SAM600-VT connected to a voltage transformer to digitize voltage,
SAM600-TS connected to another SAM600 to synchronize time, and SAM600-I/O
connected to a circuit breaker to command the circuit breaker to operate.
3.1.3 Types of the relay in the digital substation (Relion 670 series) [19]
The protection relay in modern microprocessors is called IEDs. IEDs
can perform multifunction both control and protection functions, depending on the
system requirements by configurations the Relion 670 series. The Relion 670 series
include all applications as follow:
• Support pure digital as well as mixed applications with digital and
conventional IO
• Redundant communication on station and process bus
• Precise time synchronization over Ethernet (IEEE1588/IEC 61850-93)
Mainly used IEDs include covering all application areas with the
products REB670 (Busbar protection), REC670 (Bay control), RED670 (Transmission
line differential protection), REL670 (Transmission line distance protection), and
RET670 (Transformer protection).
Protection function:
• Bus Differential (87B)
• Internal phase-to-phase and phase-to-ground faults
• Internal multi-phase faults in isolated or high-impedance grounded
power systems
Protection function
• Line differential protection (87L)
• Distance protection phase/ground (21/21N)
• Synchronizing check relay (25)
• Auto reclose relay (79)
Protection function
• Line differential protection (87L)
• Distance protection phase/ground (21/21N)
• Synchronizing check relay (25)
• Auto reclose relay (79)
CoreTecTM. These data are taken for analysis through Asset Performance Management
(APM) or transmitted to User Interfaces or SCADA. More detail as Figure: 3.13.
conditions with temperature extremes from -50 to +50◦C, and corrosive conditions and
can operate under one meter of water.
OLTC Monitoring using CoreTec 4: to ensure that the oil, motor, and
tap position of OLTC protect from damage. There are some signals needed to monitor
3.3 The procedure for analysis and interpreting the measurable consequence from
sensors while displayed on CoreTecTM 4 interface [34]
Moreover, several parameters need to measure to ensure the limit values of the
power transformer. These parameters are shown in the Sub-screen clusters as shown in
Figure: 3.24.
Alarm state 0 – Sensor/Data point value below or equal to the low Critical
threshold definition (RED)
Alarm state 1 – Sensor/Data point value below or equal to the low warning
threshold definition (ORANGE)
Alarm state 3 – Sensor/Data point value above or equal to the high warning
threshold definition (ORANGE)
Alarm state 4 – Sensor/Data point value above or equal to the high critical
threshold definition (ORANGE)
The overload screen is divided into two sections, overload capacity and
calculation tools (What-if analysis and forecast).
62
Colling – status: the status tab is used to show more detailed status
information about the cooler groups attached to the system. For each colling group
following information is provided:
• Total time: show how many hours the cooler group has been in
operation.
• Since last maintenance: shows many hours the cooler group has been in
operation since the last service.
• Date of last maintenance: this box allows for tracking of the last
completed service on the cooling system.
63
Colling – Control: inputs for the cooling control configuration are not
driven by selections made in the Category Mapping configuration screen. This screen
provides four mechanisms related to the transformer cooling control and fan
disposition: configuration of cooling groups, time for rotation of cooling groups, start
or stop of cooling groups, auto-configuration, and configuration of cooling groups. The
number of cooler groups to be automatically and/or manually controlled by the system.
DGA – levels: this screen displays the levels and/or rate-of-changes for
the concentration of the measured gases that are sampled by the configured DGA
devices.
64
DGA – IEC gas ratios: the content is dictated by the devices and
algorithms selected/configured for the specific subsystem. In the IEC 60599-3 (2015)
standard, the same ratio used by Rogers is used to diagnose 6 potential fault conditions.
66
OLTC – Status: the tap-changer basic information for which the system
is preconfigured is presented in the panel heading – information displayed on the screen
can be defined in the Nameplate parameter section. The tap-changer oil temperature is
displayed, sensor/data point can be assigned by the user in the category mapping section
of the configuration page. If a sensor fails, no value will be displayed, and an asterisk
will be shown. In normal service conditions, the temperature of the tap-changer should
not be more than 10 – 15 0C higher than the transformer top oil temperature. For tap-
67
Current position: current tap changer position and the number of days
since the last movement, based on the information provided by the external sensor.
Adjacent position: position and the number of days since the last
movement will be displayed here. The adjacent to the one in service is pre-selected load
free by the tap selector.
Diverter contact: position and the number of days since the last
movement will be displayed here. Switching between two different positions of the tap
selector. The selector position will operate under load. The other contact of the tap
selector determines the next tap position of the tap changer. The diverter switch moves
its contact from the operating to the selected tap.
Change over contact: position and the number of days since the last
movement will be displayed here. contacts of the change-over selector. In case of larger
tapping ranges the reversing arrangement can be used. The change-over selector allows
the taps to be added or subtracted from the main winding, giving a larger tapping range
from a smaller tap winding.
OLTC – contact wear: the contact wear tap is used to show a panel that
displays the number of tap-changer operations, the time to service, the time to contact
exchange, and the wear on each of the moving tap-changer contacts.
Insights: the contact wear function keeps track of the wear on each
contact during operation and calculates how much material has been worn off. From
this information, it calculates operating time and time to the next service/contact
replacement. This is especially important for transformers with frequent tap-changer
use, where more regular service is required. Instead of performing service based on
operations (1/5 of the contact life), TXpert Hup CoreTec 4 estimates when 1/5 of the
contacts are worn.
users can search for the appropriate device data tag to be displayed on the screen, select
and then update. The safety device consists of the eDevices, etc.
functionality of the digital transformer, it permits asset owners to leverage their online
and offline data to drive more intelligent, risk-based approaches to asset management.
Mandatory data
o Nameplate data
o Outline drawing data
o Factory test report data
Inspection data
o DGA lab results
o Insulation test results
o LTC DGA lab results
o Standard oil test results
o Visual inspection results
o Bushing test results
II. EXCOUNT-IIIA
• Real-time remote monitoring
• Count surges (with amplitude, steepness, and time stamp)
• Leakage current
• Resistive leakage current
• Surge current impulse analysis (enable overvoltage analysis).
Figure 3.46 Surge impulse waveform [9] Figure 3.47 Measured values [9]
This chapter examines the operation of the technologies that enable digital
communication in the digital substations according to the IEC 61850 standard.
Moreover, this section is focused on the effect of online monitoring transformers from
various sensors and the method of result analysis of online monitoring systems of a
power transformer. The next chapter will be discussing a case study at the Sattahip 2
substation, by assessing the reliability of the digital communication method, assessing
the performance of the digital protection system, then compared with the conventional
system. Including the study of collecting data from the power transformer monitoring
system to analyze the results and assess the availability status of the power transformer
at the Sattahip 2 substation.
CHAPTER IV
Case Study
4.1 Sattahip Electricity Authority, The Royal Thai Navy Welfare Concession [35]
Sattahip Electricity Authority, The Royal Thai Navy Welfare Concession has
a mission to distribute electricity in the concession area of Sattahip District, Chonburi
Province for people, private sectors, and government agencies in the aforementioned
area. Sattahip Electricity Authority, The Royal Thai Navy Welfare Concession has
continuously developed the power distribution system to be more steady, stable, and
efficient to meet the increasing demand for electrical consumption and to be able to
support the expansion of the community and the trend of industrial and economic
growth in line with government policies that promote the economy in the region.
Sattahip Electricity Authority, The Royal Thai Navy Welfare Concession also needs to
develop and improve the power distribution system to support the Eastern Economic
Corridor (EEC) following the government’s policy. Therefore, Sattahip Electricity
Authority, The Royal Thai Navy Welfare Concession has a renovation project for high-
voltage substation 2 to be able to receive 115 kV voltage from the Electricity
Generating Authority of Thailand (EGAT) in place of the old 22 kV system. The
construction project was held on 18 February 2019 and handed over on 30 July 2022.
This project finished according to the dates in the contract on 11 August 2022. The
renovation project for high-voltage substation 2 will provide the power distribution
system with more stability in this business concession area and also reduce the problem
of voltage sag and outages in this area.
The Sattahip 2 substation was designed for the scheme as the main and
transfer bus arrangement. Main and transfer bus arrangements have two buses namely
the main busbar and the transfer busbar. This kind of busbar arrangement is suitable for
the system where the power system with many connections and flexibility. The two
double isolating switches (disconnecting switch) and one circuit breaker are arranged
for each circuit as shown in the single diagram continuously supply and allowed
maintenance for some time without blackout. The main and transfer bus has been
utilities where loads and continuity supply are required.
76
Each feeder is connected to either the busbar with the bus coupler. For
normal working conditions, the main busbar is operated but when the main busbar is
needed maintenance, the transfer busbar is in operation. In this main and transfer busbar
arrangement, a bus coupler is always used to change the connection from one busbar to
another busbar. The advantages & disadvantages of the system with main and transfer
busbar are given below:
Figure 4.5 SAM600-VT and SAM600-CT [35] Figure 4.6 SAM600-I/O [35]
80
IEDs which are Relion 670 series located at the bay level will receive
SMV from the process bus and process the measurement data for control and protection
functions. RED670 will use to protect the transmission line bay. RET670 will use to
protect the transformer bay and REB670 will use to protect the bus tie bay. The IEDs
will transmit and publish the message by using the GOOSE protocol to broadcast events
to peer IEDs in a substation with horizontal communication and when the system is
abnormal, whether it is an abnormal current or voltage, the REC670 will send the
GOOSE message to SAM600-I/O to command the switchgear to operate, for example:
commanding the circuit breaker to “trip” or command the disconnector switch to be on-
off.
All data from IEDs and the process bus will gather in the Ethernet switch
network to send up to the station level by MMS protocol (Client-Server) to report the
status of a substation and the event that happened. The station level consists of HMI,
station computer, and SCADA, allowing the operator to monitor and remote control the
whole system of the substation in the operator workstation and control center room.
Figure 4.8 The working principal of SAM600 process bus I/O [7]
81
Relion670 is described in chapter 3. The IEDs in Sattahip 2 were installed in two units
on a single panel to offer redundancy by providing REC670 as backup protection. The
top IED performs the main protection function, while the lower IED performs the
control function while also providing backup protection.
control and protection within each bay and REU615 in the bus tie bay for voltage
protection and control relay for voltage and frequency of the distribution system. The
MV side also has a multifunction meter to measure electrical parameters and sends data
to the station level via RTU for monitoring on the SCADA system.
In this calculation, the control function of the local bay level and report
center are ignored. These control accesses could be viewed as a redundant control
facility for the SA system. In this case, the resulting availability would be even higher.
The general system structure relevant to this analysis is as follows:
(4.1)
Where,
MTTR (Mean Time to Repair) is the amount of time it takes to repair a
system.
MTBF (Mean Time Between Failures) is the amount of time the system
can work normally
Availability:
A = A1*A2 if components 1 and 2 are in series
A = A1 + A2 – (A1*A2) if components 1 and 2 are in parallel
MTTR = 4
GPS 1 (A1) = 142,636 / (142,636 + 4) = 0.99997195738
GPS 2 (A2) = 142,636 / (142,636 + 4) = 0.99997195738
A1 // A2;
⸫ A12 = A1 + A2 – (A1 * A2) = 0.99999999921
MTTR = 4.0
A3 = 1,320,000 / 1,320,000 + 4 = 0.99999696971
MTTR = 4
Prot. IED 1 = 893,000 / 893,000 + 4 = 0.99999552074
Prot. IED 2 = 893,000 / 893,000 + 4 = 0.99999552074
Protection IED 1 // Protection IED 2;
A’ = (IED1 + IED2) - (IED1 * IED2) = 0.99999999997
There are three line bays that connect in parallel to each other. As a
result, the line bay's availability value is equal to
A4 = A4’ // A4’ //A4’
= A4’ + A4’ – (A4’ * A4’) // A4’
= (0.99999999997) // A4’
=1
MTTR = 4
Prot. IED 1 = 893,000 / 893,000 + 4 = 0.99999552074
Prot. IED 2 0= 893,000 / 893,000 + 4 = 0.99999552074
There are two transformer bays that connect parallel to each other. As a
result, the transformer bay's availability value is equal to
A5 = A5’ // A5’
= (0.99999999991 * 0.99999999991) // (0.99999999991 *
0.99999999991)
=1
MTTR = 4
Prot. IED 1 = 893,000 / 893,000 + 4 = 0.99999552074
Prot. IED 2 = 893,000 / 893,000 + 4 = 0.99999552074
Protection IED 1 // Protection IED 2;
A’ = (IED1 + IED2) - (IED1 * IED2) = 0.99999999997
MU-VT = 893,000 / 893,000 + 4 = 0.99999552074
ETH 3 = 1,320,000 / 1,320,000 + 4 = 0.99999696971
MU-VT // ETH 3;
A’’ = (MU-VT + ETH3) – (MU-VT*ETH3)
= 0.99999999998
A6 = A’ * A’’
A6 = 0.99999999995
• Result
The availability of the Sattahip 2 Substation is 99.9996%. It shows that
the availability of equipment in the station is highly reliable. Calculated by the worst
case of MTTT; 4 hours. In reality, this value can be decreased which means the
availability will be increased.
• Meter and MU are synchronized in time using a GPS for the accuracy
of observation. The overall view of the system is shown in Figure 1.
Considering all errors from observing the measurement data such as time
synchronization, and analog to digital conversion of SAM600 compared to the
multifunction meter, these results are good which means the functionality and accuracy
of measuring using a merging unit are acceptable.
The average operating time was about 32.77 ms, considered adequate
for the current pre-fault zero condition.
The average operating time was about 21.30 ms, considered adequate
for the current pre-fault zero conditions.
The result of the fault clearance time test of the digital protection system
included ded tripping time of the circuit breaker contact was 72.77ms, which is slower
than the conventional protection system but still within the time limits set by IEC
60834-1 std, which specifies the total fault clearance time for the high voltage
substation at 75ms.
94
4.3 TXpertTM – Sattahip 2 substation, The Royal Thai Navy Welfare Concession
[35]
The TXpertTM monitoring system that has been implemented in Sattahip 2
substation is an open digital platform that helps enterprises make better and faster
decisions through enhanced asset performance visibility. A new generation of sensor
and diagnostics technology is opening up the potential for digital and analog monitoring
of the critical components of the power transformer. The Royal Thai Navy Welfare
Concession has been utilized by e-Device sensors like eOLI, eOTL, eSDB, eBR, ePRD,
eWTI, and CoreSenseTM. Moreover, the CoreTecTM 4, is a complete transformer
monitoring system that integrates the data from sensors and displays operational
parameters through a web interface to ensure the confidence to schedule maintenance.
The TXpertTM structure of The Royal Thai Navy Welfare Concession is as the figure
below.
These e-Device sensors and CoreSenseTM will be allowed with the digital and
analog output providing continuous monitoring of the key transformer parameters such
as:
• Oil levels and oil temperature
• Winding temperature
• Air humidity
• Gas and moisture levels
• Internal pressure
• Gas accumulation
• Hydrogen and moisture detection.
95
Figure 4.28 CoreSense (Gas sensor) [35] Figure 4.29 eWTI [35]
Figure 4.30 Pressure relief (OLTC) [35] Figure 4.31 Pressure relief (Main tank) [35]
Figure 4.32 eBR [35] Figure 4.33 eOLI (Main tank) [35]
97
4.4 Collecting data from an online monitoring system of the power transformer
for analysis [35]
This section will be discussed the consequence of the online monitoring
system by collecting the data from the CoreTecTM 4 web interface to evaluate the
98
parameters of the transformer as mentioned in 4.3 points are in good condition or not.
The online monitoring data are shown as the results below:
A – oil temperature: the top oil temperature from the asset displayed here is
45 oC show that the data point value is within a normal operating range between low
and high warning thresholds (Blue – Positive Value). The threshold is between 0 – 120
o
C. The low critical point is under 0 oC and the high critical point is over 120 oC.
B – hot sports: the calculate hot spot temperature in the transformer winding
based on sensor/data inputs is displayed here. The calculated hot spot temperature is
related to ambient temperature, rated hot-spot temperature rise above top oil-rated
current and load current. This interface does not display because the signal of the load
current from CT of a power transformer cannot consign to CoreTecTM 4.
E – DGA: the dissolved gas analysis information collected by the gas sensor
(CoreSenseTM) shows that the transformer oil is in good condition. This display
interface shows the value of dissolved gas in oil of Hydrogen at 4 ppm and the moisture
value at 3 ppm, by this online monitoring result can consider that it is in good condition
for operation. The limitation of moisture is 25 ppm by IEC and the limitation of
Hydrogen is 100 ppm by IEEE C57-104.
99
G – oil level: the system can display oil level information as an input
sensor/data point acquired from external devices. The oil level would define the oil
level OLCT and the oil level of the main tank. The configured thresholds of oil levels
in the Sattahip 2 substation are defined:
• The low critical level at 10%
• The high critical level of 90%
• The low warning level is between 10 – 20%
• The high warning is between 80 – 90%
• The normal operating range between low and high warning thresholds is 20 –
80%
H – aging: there is no value display on this screen because it requires the hot
spot of the winding. The aging is calculated according to IEEE or IEC and the normal
aging which defined by different values of hot spot temperature, where 110 oC to IEEE
and 98 oC to IEC. If the hot spot temperature is over this standard temperature, it means
that power transformers lose a life.
Figure 4.40 there is no value data displayed because there are some problems
related to thermal sensors do not send the signals to CoreTecTM 4.
100
Figure 4.42 shows the top oil temperature measurement, HV Aging Factor, LV
Aging Factor and TV Aging Factor as listed below:
• Top Oil Temperature is 45.2 oC and which means that the data point is within
a normal operating range between low and high warning with a threshold
between 0 – 120 oC. the low warning point is under 0 oC and the high warning
point is over 120 oC
• Cumulative Aging is the measurement value of accumulated calculated aging
of the winding since the monitoring system began conducting the
measurements
• Aging Factor effects by the hot spot temperature which means that it is usually
taken in investigating the aging process with the hot spot temperature. The
aging factor value represents time in hours (smaller numbers are better).
Moreover, the aging factor is the ratio of current transformer aging compared
to the specified transformer aging accumulation at 100% load and rated
ambient temperature.
These values did not display because it required aging calculation that is
related to hot spot temperature, so the main problem is the 4 -20 mA signal of CT of
the transformer connected to CoreTecTM 4 for calculation.
102
Overload capacity: predictions of the highest allowed load without the top oil
and hot-spot temperature exceeding preset values in the order datasheet. The basic idea
is to know how much the transformer can be loaded for a certain amount of time without
exceeding the limit
What-if analysis: the forecast is calculated in two steps. Enter the forecast
value in all entry fields in the two calculation groups “start value” and “overload”, then
click the Update Graph bottom
Thermal forecast: using inputs provided by the user, the thermal forecast of
the unit temperature is calculated. The required inputs for the forecast are the ambient
temperature, top oil temperature, max hot spot and expected transformer load. The
reason of disable the value on this screen may be the same problem as mentioned above
point
Figure 4.44 shows the displays of the oil-immersed of transformer oil. The
hydrogen and moisture are within a normal operating range between low and high
warning thresholds.
• The normal operating point of hydrogen is under 50 ppm. The high warning
point of hydrogen is between 50 - 100 ppm and the critical point is over 100
ppm. If the hydrogen in oil concentration close to the critical point the operator
must take investigate and find the problems of power transformers
• The normal operating point of moisture is under 20 ppm. The high warning
point of moisture is between 20 – 30 ppm and the critical point is over 30 ppm.
If the moisture in oil concentration close to the critical point the operator must
take investigate and find the problems of power transformers
The TDGC stacking screen, Duval Triangles screen, Roger Ratios screen, and
IEC Gas Ratios screen of will not display because there is no sensor for multiple gas
analysis CoreTecTM 4.
105
Figure 4.49 shows that there is no value or data point display on this screen
because there is no TXpert BM sensor for transformer bushing monitoring.
Figure 4.50 and Figure 4.51 shows that there is no value or data point display
on this screen because there is no sensor for online monitoring of OLTC, no value will
be displayed, and an asterisk will be shown. monitoring.
Figure 4.52 shows that there are four types of e-Device display measurements
on the Safety Devices screen.
• eBR: the Buchholz Relay for checking gas accumulation in the Buchholz relay
that is mounted between the main tank and the conservator. It is within a
normal operating range between low and high warning thresholds of 0 – 220
cm3 (5 cm3). The high warning point of gas accumulation is between 220 - 240
cm3 and the critical point is over 240 cm3
107
• eOLI: the oil transformer levels of the main tank or OLTC, with this result (46
o
C) within a normal operating range between low and high warning thresholds.
The normal operating point is between 20 – 80 oC. The high warning point of
oil levels is between 80 -90 oC. The low critical point is under 20 oC and the
high critical point is over 90 oC
• ePRD: is the pressure relief device of the main tank and the OLTC of
transformers, the result is within a normal operation
• eWTI: is the winding temperature of power transformers. It shows the 3 phases
of winding temperature within a normal operating range between low and high
warning as follows 47 oC, 46 oC and 47 oC. The normal operating range is
between 20 - 120 oC. The low warning point is between 0 - 20oC and the high
warning point is between 120 – 130 oC. The low critical point is under 0 oC
and the high critical point is over 130 oC
Figure 4.53 shows that there are two types of e-Device display measurements
on the Safety Devices screen such as eOLI and eSDB:
• eOLI: certainly, the oil levels of the main tank and OLTC (35% and 36%) are
within a normal operating range between low and warning thresholds of 20 –
80%. The low warning point is between 10 - 20% and the high warning point
is between 80 -90%. The low critical point is under 10% and the high critical
point is over 90%. The min and max levels today mean to show the highest
and the lowest oil levels
• eSDB: the self-dehydrating breather is an automatic silica gel with a
regeneration process, so there is no need to set the thresholds for this sensor.
The result of the percent of eSDB is display the capacity value that can absorb
moisture and the temperature tank shows the temperature through the eSDB
device
108
Figure 4.55 show the present leakage current value (mA) and can display the
history leakage current by chosen interval time for analysis of resistive leakage current
or surge arrester with the resistive current standard condition.
109
Figure 4.56 displays the total number of surge arresters, the date occurred
surge current/voltage, front time, maximum surge amplitude and minimum surge
amplitude by chosen date interval of register surges.
Figure 4.57 show the surge current impulse with this screen displayed and
allowed us with the current waveform, the date and time of the surge occurred, max
peak and rise time of the current surge:
• Date: 19 December 2020
• Time: 19:49:59s
• Max peak: 38.1 A
• Rise time: 0.03 μs
110
Figure 4.58 show the surge current impulse with this screen displayed and
allowed us with the current waveform, the date and time of the surge occurred, max
peak and rise time of the current surge:
• Date: 21 December 2020
• Time: 10:38:26s
• Max peak: 75.9 A
• Rise time: 0.58 μs
Figure 4.59 show the surge current impulse with this screen displayed and
allowed us with the current waveform, the date and time of the surge occurred, max
peak and rise time of the current surge:
111
Figure 4.60 displays a measured value that allows us the information related
to leakage current, harmonic leakage current, number of surge impulses, etc. Along
with this result will mainly focus on resistive leakage of the surge arrester to compare
with the maximum recommended resistive currents to ensure that the surge arrester has
good insulation for protecting power transformers. With the results of online
monitoring of surge arrester can read the value of a total leakage current is 0.001 mA
and a resistive leakage current is 0.5 μA.
The analysis of the availability value calculated from the Sattahip 2 substation
shows that there were benchmark values, and the comparison between the merging unit
and the multimeter showed low tolerance. Moreover, this chapter discussed the
comparison of the total fault clearance time between digital and conventional protection
found to pass the criteria. On the other hand, evaluate the results of the power
transformers from the online monitoring system. However, the values of hot spots and
aging factors did not display because of the signal of thermal sensors and the 4 -20 mA
signal of CT of the power transformer does not consign to CoreTecTM4.These results
will be summarized and recommended in the next chapter.
5.2 Recommendation
CoreTecTM 4:
• Need to check the CT signal of a power transformer to ensure the load
current signal consign to CoreTecTM 4 for calculation:
• Hot Spot Temperature
• Aging Factor
• Should have identifiable names of safety devices and accessories since
displayed on an online monitoring system (CoreTecTM 4)
113
[19] Energy, H. (n.d.). Relion 670 and 650 series substation solution, Hitachi Energy.
[20] Energy, H. (n.d.). Air Insulated Switchgear – Medium Voltage. [Online] state
<https://new.abb.com/medium-voltage/switchgear/air-insulated> (25 September
2022).
[21] Transformer handbook, (n.d.). www.iec.ch.
[22] Energy, H. (n.d.). Presentation on Transformer Structure.
[23] IEEE Seminar. “Maintenance of Power Transformer”.
[24] Vachiratarapadorn, Y., Wieck, H., Taylor, J., Zetterberg, O., M., & Generating, E.,
(n.d.). Measurement of Resistive Leakage Current of Metal Oxide Surge Arrester in
Service and Inspection of Surge Arrester Type PEXLIM after Field Trail: Case
Study of EGAT in Thailand.
[25] Service Handbook for Transformer. (n.d.).
[26] Irfan Akhtar, (2016). “Transformer Routine Inspection and Testing”.
[27] Vichakorn, H., & Members (2018). “Dissolved Gas Analysis in Transformer Oil for
Preventive Maintenance Planning”.
[28] Mohan, M. (2016). “Grid Automation Products SAM600 Process Bus I/O System
Product Guide 1MRK 511 428-BEN”.
[29] Hitachi Energy (2019). “Substation Merging Unit SMU615 Technical Manual”.
[30] Hitachi Energy (2021). “ABB AbilityTM Smart Substation Control and Protection
SSC600 Operation Manual”.
[31] Hitachi Energy (n.d.). “Smart Substation Control and Protection SSC600”.
[32] Hitachi Energy (n.d.). “Online Dissolved Gas Monitoring Introducing the
CoreSenseTM family”.
[33] Hitachi Energy (n.d.). “e-Device-Family”.
[34] Hitachi Energy (n.d.). “Digital Transformer Monitoring and Diagnostics Device
TXpert Hub CoreTec 4 Software Version 2”.
[35] Learning Center (2022). “Sattahip 2 Substation, The Royal Thai Navy Welfare
Concession”.
[36] Hitachi Energy (2012). “Relion 615 Series Feeder Protection and Control REF615
Application Manual”.
[37] ABB Limited (2018). “Test and Commissioning Inspection and Test Report 115/33
kV Substation Hanuman Wind Farm (HWF)”.
APPENDICES
117
Appendix A
Raw Data
Appendix B
Technical data
Appendix C
Single diagram and ANSI code
126
127
128
129
130
131
132
Author Biography
Author Biography