Method Statement
Grouting of Post Tension tendons
1. Introduction
1.1 When post-tensioning stressing work is completed the tendons ducts will be
grouted with plain cement grout with added admixture.
2. Materials
4.2 The anchorage pockets should be capped with concrete or suitable capping
material prior to grouting operation
4.3 After the anchorage has been capped the tendon shall be air flushed through
the grout hole which projects from the top of the duct or anchorage
4.4 Grouting hoses of internal diameter for pumping shall be used with pressure
capacity excessive to the pump capacity.
Grout Method Bang Nam Priao
4.5 Grout quality tests shall be performed during trial mix as per Appendix-I ( BS
5400- Part7 specifications)
5. Grout mix shall have the mix proportion of water/cement ratio as specified by the
weight.
6.1 Water shall be added to the mixer first, followed by the Portland cement type
1 and then the admixture ( Vitacrete AG 3).
6.2 Mixing will be in such that the uniform blended grout is achieved.
6.5 Grout injection shall be continuous and shall be slow enough to avoid
segregation of grout during pumping.
6.6 Pumping continued until the no visible slugs or water or air is fully ejected.
6.7 The injection should ensure compete filling of the duct. A proper inspection at
6.8 A pressure of 0.5 N/sqmm shall be maintained during filling of tendon duct and
6.10 After completion of grouting the projected portion of grout vent shall be cut
flat to the top of segment level by means of abrasive disc.
Grout Method Bang Nam Priao
วิธีทดสอบและเกณฑ์การยอมรับตาม BS 5400
Fluidity test flow cone method spec Immediately after mixing Fluidity measurements
done immediately after
mixing are denominated in
cone method and after 30
minutes. The fluidity
expected results
immediately after mixing <
25 s
การเยิ้ม: Bleeding BS 5400 After 3 hours and after 24 hours When tested the bleeding
shall not exceed 2% of the
initial volume of the grout
after kept 3 hours at rest
and 4% max after 24 Hrs.
Water should be fully
absorbed after 24 hours
การเปลี่ยนแปลงปริมาตร Volume Change BS 5400 จนถึงเวลา 24 ชัว่ โมง Plastic shrinkage shall
not exceed 2%. A final
Volume change( expansion)
plastic expansion of 1 to
2 % is preferable.