PROCESS PROCEDURE WORK INSTRUCTION TOOLS/MATERIALS/ PERSONNEL PPE

EQUIPMENT INVOLVED

Replacement of I. Replacement of meter and/or - Multi-tester Special Equipment - Hard Hat


Metering Instrument Transformers - Screw drivers Line Crew - Working
- Ladder Gloves
Equipment
- Hot Stick - Raincoat
- Shot gun (if
Raining)
● Purpose - Safety
Shoes
- To minimize
- Climber/B
system loss
ody belt

i. Secure work permit, Trip Ticket See Driver’s SOP


and gate pass
ii. Verify the report Inspect the meter and wiring
● Scope connections. Check the
parameters.
- All defective
Metering
Instruments
including
iii. Disengage fuse cut-out Make sure that the primary line is
not energized by disengaging the
cut-out using hot stick and shot
gun

iv. Replace the meter and/or


Instrument Transformers
v. Energize the metering  Double check all the
equipment connections
 Do necessary safety
clearance before engaging
the cut-out for energization

vi. Record data  Gather necessary


data/information. Old and
new meter/ instrument
transformer data, Terminal
seal.
 Accomplish Service Memo
to be forwarded to Billing
Section.