JOB HAZARD ANALYSIS (JHA) WORKSHEET

JOB HAZARD ANALYSIS [JHA] WORKSHEET


DATE
PTW
NO
JHA NO
WORK SPECIFIC
FACILITY /
PERMIT COLD BEKOK C WORKST CELLAR DECK
LOCATION
TYPE ATION
EQUIPME WORK
V-840 & V-890
NT NO. DESCRIPTION TO PERFORM RIG UP LIFTING GEAR ACTIVITY NEAR WORKING AREA
NOTE
1. JHA shall be applicable for all work activities which requires PTW.
2. The pre-prepared JHA and JHA prompters will be used as a reference/guide during the development of JHA.
3. Personnel carrying out the work shall be fully familiar with the written Work/Operating Procedures developed for the job. The Work/Operating
Procedures shall describe, in step-by-step instructions, the correct method of executing the specified work.
4. Prior to commencement of work (after PTW has been approved), the task-specific JHA shall be discussed amongst all personnel involved in the
execution; and requirements contained therein shall be fully understood and agreed by all involved personnel.

JO CONTROL ACTION PARTY MONITORING RECOVERY ACTION MONITORING


B DESCRIPTION OF POTENTIAL POTENTIAL BARRIERS REQUIREMEN BARRIERS PARTY REQUIREMEN
ST JOB STEP HAZARD Consequences T (Y/N) T (Y/N)
EP
1 Re-check and 25.01-Slip, - Personal - Use proper - Rigger Foreman - N - Medical Medic N
confirm work trip and fall injury PPE Treatment onboard
area suitable - Use - First aid
with lifting gears
handrail
when going
up/down
stairway
- Use body
hardness

2 Preparation work 25.01-Slip, - Personal - Beware of - Rigger - N - Medical Medic N


– transfer trip and fall injury tripping Foreman Treatment onboard
rigging/lifting - Equipment hazard - All team - First aid

Open
JOB HAZARD ANALYSIS (JHA) WORKSHEET

gear and related 25.10-Drop damage - Use leather - Equipment re-


tools to work object - Can cause glove check
area death / body - Use safety
injury pin and
whip check
3 Pre-install rigging 25.01-Slip - Personal - Secure - Rigger - N - Medical Medic N
gears and trip injury equipment Foreman Treatment onboard
- Asset and during - All team - First aid
25.10-Drop equipment rigging - Equipment re-
object damage installation check
- Use safety
body
hardness
4 Install beam 25.10-Pinch - Finger injury - Wear rigger - Rigger - N - Medical Medic N
clamp point - Asset and hand gloves Foreman Treatment onboard
equipment - Use safety - All team - First aid
6.03-Fall damage body - Equipment re-
from height hardness check
drop object - Secure
equipment
during
rigging gear
installation
5 Hook the 25.01-Trip -Personal injury - Watch out - Rigger - N - Medical Medic N
webbing sling and fall -Finger injury of any Foreman Treatment onboard
and shackle at tripping - All team
chain block 25.01-Pinch hazard
point - Use safety
body
6.03-Fall hardness
from height - Use proper
rigger glove
6 Hook chain block 6.03-Falling - Personal injury - Hook the - Rigger - N - Medical Medic N
to beam clamp object equipment Foreman Treatment onboard
properly
- Fall from - Use safety

Open
JOB HAZARD ANALYSIS (JHA) WORKSHEET

height body
hardness
7 Use tag line for 25.01-Crush - Finger injury - Keep load - Rigger - N - Medical Medic N
rigged up activity or pinch close Foreman Treatment onboard
injuries tended and
use strong
points to
secure
- Use proper
glove
8 Housekeeping 25.18-Slip, - Personal - Transfer - Rigger - N - Medical Medic N
trip and fall injury material Foreman Treatment onboard
from
obstructing
access way

Open
JOB HAZARD ANALYSIS (JHA) WORKSHEET

JHA APPROVAL DURING PTW APPLICATION

REVIEWED BY APPROVED BY
NAME NAME

DESIGNATION WORK LEADER DESIGNATION PRODUCTION SUPERVISOR /MAITENANCE SUPERVISOR /BASE


SUPERVISOR/FUNCTIONAL SUPERVISOR
SIGNATURE SIGNATURE

DATE DATE

AFTER PTW HAS BEEN APPROVED


WORK TEAM (CONFIRMATION THAT JHA HAS BEEN COMMUNICATED TO WORK TEAM AS PART OF PRE_JOB/TOOLBOX MEETING _ AFTER PTW HAS BEEN APPROVED)

Name (S) Designation Signature Signature Signature Signature Signature Signature Signature Name (S) Designation Signatur Signature Signature Signatur Signature Signatur Signature
e e e