TIME FRAME PROJECT PEKERJAAN PERLUASAN

STOK SOIL

PT KALTIM DIAMOND COAL

PT BERAU COAL
BINUNGAN MINE OPERATION AREA-1 BLOK
PARAPATAN
2022
Time Frame Project Pekerjaan Perluasan Stok Soil
Bobot Week 42 Week 43 Week 44 Week 45
No Uraian Pekerjaan
% 19-Oct 20-Oct 21-Oct 22-Oct 23-Oct 24-Oct 25-Oct 26-Oct 27-Oct 28-Oct 29-Oct 30-Oct 31-Oct 01-Nov 02-Nov 03-Nov 04-Nov 05-Nov 06-Nov 07-Nov 08-Nov 09-Nov 10-Nov 11-Nov 12-Nov 13-Nov 26-Nov 27-Nov
67.83
1 Pemindahan Change Shift 54.00
- Pembuatan Layout Changeshift 2.50 0.63 0.63 0.63 0.63 62.50
- Stake out Layout Changeshift 2.50 1.25 1.25
57.17
- Dumping dan spreading OB untuk meratakan base 10.00 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25
- Dumping dan Spreading Scorea untuk base pad 15.00 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 51.83
- Pembuatan tanggul parkiran dan budnwall 5.00 0.63 0.63 0.63 0.63 0.63 0.63 0.63 0.63
- Pemasangan rambu 3.00 1.50 1.50
44.17
- Assesment area parkiran dan changeshift 1.00 1.00
- Pemindahan Parkiran unit OHT 5.00 2.5038.50 2.50
- Pengajuan MPRP 10.00 0.67 0.67 0.6735.71 0.67 0.67 0.67 0.67 0.67
34.42
2 Pemindahan Jalan ROM P3 43.50 33.13
32.50
31.25
30.63
- Stake out desain jalan 2.50 29.38 2.50
27.50
- Dumping base jalan dengan material OB 10.00 25.63 2.00 2.00 2.00 2.00
- Pembentukan badan jalan dan tanggul 10.00 22.50 2.00 2.00 2.00
- Install gorong - gorong di Jl. Baru masuk ROM P3 2.50 20.00
17.50
- Pembentukan drainase di sisi jalan 5.00 15.00
- Pemenuhan rambu jalan 2.50 12.50
10.00
- Assesment Jalan 1.00
7.50
- Pengajuan MPRP 10.00 5.00
0.67 0.67 0.67
3.75
3 Perluasan area Stok Soil 2.50 1.88 2.50
0.63 1.25
- Perbaikan jalan akses masuk Stok Soil 2.50
Total (%) 100.00 0.63 0.63 0.63 0.63 1.25 1.25 2.50 2.50 2.50 2.50 2.50 2.50 2.50 3.13 1.88 1.88 1.88 1.88 1.29 1.29 2.79 5.67 7.67 5.33 5.33 5.33
Bobot Rencana Kumulatif (%) 29.38 0.63 1.25 1.88 2.50 3.75 5.00 7.50 10.00 12.50 15.00 17.50 20.00 22.50 25.63 27.50 29.38 31.25 33.13 34.42 35.71 38.50 44.17 51.83 57.17 62.50 67.83
Bobot Realisasi Kumulatif (%) 29.38 0.63 1.25 1.88 2.50 3.75 5.00 7.50 10.00 12.50 15.00 17.50 20.00 22.50 25.63 27.50 29.38 30.63 32.50 32.50
Deviasi (%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 -0.63 -0.63 -1.92
Layout Cange Shift & Traffic Management
A : View Point & Mining Eyes
B : Parkiran Unit OHT 773 & 777
C : Parkiran Unit OHT 773 & ADT A60H
D : Pos Change Shift
: Arah Masuk
: Arah Keluar
: Parkir Unit
: Median

: Rambu Parkir
: Rambu Penunjuk Arah
: Rambu Forbidden
Analisis Geotek Change Shift
Layout Rencana Pemindahan Jalan ROM P3 dan Perluasan Area Stok Soil
: Boundary badan jalan

: Batas Kaki Timbunan Jalan

: Section line Analisis Geotek

: Rencana lokasi pemasangan


gorong-gorong
Analisis Geotek Pemindahan Jalan ROM P3
Analisis Geotek Pemindahan Jalan ROM P3
8