You are on page 1of 2

ISLAND PARK I & II

PLOT No. A-026 & A-027


DUBAI CREEK HARBOUR DEVELOPMENT, DUBAI, UAE

Volume 5, Part-E

28.0 TESTING OF EQUIPMENT

28.1 After installation, all equipment shall be tested for performance and proper functioning and for
demonstrating to the full satisfaction of the Engineer that the equipment meets the design requirements
as shown on the Drawings and as specified.

28.2 Should any equipment prove defective, unsatisfactory or does not comply with the Specification, the
Contractor shall correct, repair or replace such equipment or his own account as directed by the
Engineer. After the correction is made, subsequent tests shall be performed until the equipment is
proven to fulfil the requirements to the entire satisfaction of the Engineer.

29.0 REJECTION OF EQUIPMENT

Equipment shall be rejected if:

(a) It has a capacity less than required.


(b) Its electric motor is overloaded.
(c) It causes objectionable noise or vibration.

30.0 TESTING AND ADJUSTMENT OF CONTROLS

All controls and instruments shall be operated simultaneously with the equipment or system that they
control and tested for proper, accurate and dependable functioning and operation.

All controls and instruments shall be calibrated and adjusted to the satisfaction of the Engineer.

31.0 GOVERNMENT AND LOCAL AUTHORITIES

Perform at appropriate times during the currency of site work, all tests required by Government and
Local Authorities who may from time to time have jurisdiction over the work and obtain the necessary
certificates of approval. Local regulations shall be strictly followed.

32.0 DOMESTIC WATER PIPING STERILIZATION AFTER COMMISSIONING

On completion of the potable cold water supply services system, including any parts of the existing
service they shall be sterilized by the application of chlorine. The minimum requirements for
chlorination shall be to flush the pipework thoroughly to remove dirt. Chlorine shall then be added to
the storage tanks and water drawn from all draw-off points until chlorine is detected at each outlet
point with a concentration of 50 ppm. The mains are then to be allowed to stand for a period of 24
hours, after which the outlets are to be tested for chlorine. If chlorine is not found to be present or
detected with a concentration of less than 0.4 ppm, all the above shall be repeated until residual
chlorine is detected. After this, the system is to be completely flushed with clean water and
precautions taken to avoid subsequent contamination of the installation.

32.1 Follow the following procedure for sterilization of water piping and storage water tanks:

a. Prior to starting work, verify that system is complete, flushed and clean.

b. Ensure pH of water to be treated is between 7.4 and 7.6 by adding alkali (caustic soda or soda ash)
or acid (hydrochloric acid).

c. Add disinfectant, free chlorine in liquid, powder or tablet form to obtain 50 ppm residual.

Section 04 - PLUMBING WORKS Page 29 of 30 Rev. 00 – Dec.2022


Tender Addendum Submission
ISLAND PARK I & II
PLOT No. A-026 & A-027
DUBAI CREEK HARBOUR DEVELOPMENT, DUBAI, UAE

Volume 5, Part-E

d. Fill the system piping with chlorinated water and bleed water from outlets to ensure distribution
and test for disinfectant residual at minimum 15 percent of outlets.

e. Maintain disinfectant in system for 24 hours.


f. During the disinfections period install temporary warning signs in both Arabic and English at
conspicuous places throughout the Project against using the chlorinated water.

g. If final disinfectant residual tests less than 0.4 ppm, at any outlet, repeat treatment.

h. Flush disinfectant from system until residual equal to that of incoming water or 1.0 mg/L.

i. Take samples no sooner than 24 hours after flushing, from remote outlet of each riser and from
water entry and analyze in accordance with AWWA C651. Submit result of analysis to Engineer
for approval.

END OF SECTION

Section 04 - PLUMBING WORKS Page 30 of 30 Rev. 00 – Dec.2022


Tender Addendum Submission

You might also like