Professional Documents
Culture Documents
1.3 Layout Design - General Philosophy and Principles
1.3 Layout Design - General Philosophy and Principles
Plant Plant
Layout Layout
Process Structural
Operation Maintenance
Design Design
Land Cost
+
Piping Cost
+
Safety Cost (function of distance vs. cost)
+
Protection devices Cost
Definitions
• Plant – A general term used to describe anyone or all
of the units on a given site.
• Plot – An area of the site containing one or more
processing units, or tankage.
• Process Unit – A main production component of a
plant, consisting of groups of equipment arranged to
perform one or more process operations
• Non-Severe Service Equipment – Equipment
operating below 410°F and 500 psig.
• Severe Service Equipment – Equipment operating at
or above 410°F or 500 psig.
Site Layout
Flare
Siting Consideration
Siting of a proposed expansion or new plant should
consider the following factors:
– Buffer zones between the plant and the public;
– Worst credible scenarios for release of a toxic
chemical, explosion or fire, and effect(s) on exposed
groups;
– Exposure hazard to / from adjacent plants or facilities;
– Possible exposures due to natural events such as
earthquake, flood, tornado, etc.; and
– Effects of transportation of hazardous material
feedstocks or products through local communities.
1/3
Fire and Explosion Hazard
Reduction Measures for Piping
CONCEPTUAL Phase
Minimize inventory of combustible material
Process and compress gas onshore to reduce processing risks offshore
Avoid high energy systems
Select less hazardous materials
Hold materials in a form, or under conditions, to render them non/less
hazardous
Use less hazardous materials
Include systems for flaring
Provide a TR on an adjacent bridge linked structure
Promote permit to work culture
Build accommodation platform separate from production platform
Separate personnel from process hazards
Improved means of escape
2/3
Fire and Explosion Hazard
Reduction Measures for Piping
FEED Phase
Maximize ventilation including use of blow out panels
Ensure adequate supply of deluge systems
Divide the inventory to reduce the amount with a potential to ignite
Reduce the number of flanges
Design for maximum pressure
Ensure critical pipelines do not rupture when subjected to blast pressure
Increase flange rating for critical piping
Use welding rather than bolting
Adopt pipe routes that will avoid drag loads
Adopt pipe routes that avoid large Δ displacement between supports
Adopt pipe routes with shielding and running behind beams
Adopt pipe routes avoiding vent areas
Optimize location and level of piperacks
3/3
Fire and Explosion Hazard
Reduction Measures for Piping
DESIGN Phase
Improve layout of equipment and minimize congestion
Design blast walls for high over pressures
Minimize penetrations through blast walls, and provide seals where
required to avoid transferring blast loading to penetrating services
Deluge system feeders and their manual bypass lines should be protected
by providing PFP cladding or coating to piping and where necessary to
supports, or by extended deluge cover.
Main blowdown header to be protected from fire in high hazard areas.
Specifically relevant to header in vicinity of gas export metering
package
All Emergency shutdown valves which are recognized to be critical in
isolating major inventories will satisfy fail to safe condition
Optimize equipment fixings and piping supports
-Roads
-Access
-Storage
Process Plant
-Admin -Roads
-Utilities -Access
-Units
Process Unit
-Buildings -Access
-Equipment Process
Equipment
-Spacing
-Arrangement
Typical
Examples
of
Minimum
Plot
Separation
Distances
Typical
Separation
Distances
Between
Non-severe
Equipment
Within a
Plot
Typical
Separation
Distances
Between
Severe and
Non-severe
Equipment
Within a Plot
Typical
Separation
Distances
Between
Severe
Equipment
Within A Plot
Loading Racks
Service Buildings
Flares
Control Rooms
Requirements (feet)
Pipe Racks
Fired Heaters
Heat exchangers
Emergency Controls
Compressors 30
Pipe Racks 50 ---
Fired Heaters 50 50 25
Analyzer Rooms
Heat Exchangers 30 10 50 5
Recommended Inter-Unit
Equipment Separation Distances for
Traditional Chemical/Oil Plants
30
(Distances in ft.)
30 5
50 5 5 Ref: Guidelines for Engineering Design
50 10 25 25 for Process Safety, CCPS, 1993
50 10 15 25 15
50 10 15 25 15 15
50 10 15 50 25 25 15
100 100 100 100 100 100 100 100
50 50 50 50 50 50 50 100 25
30 15 15 25 15 15 15 100 50 1
30 10 15 25 15 10 10 100 50 15 5
30 10 15 25 15 10 10 100 50 1 50 1
50 50 50 100 50 50 50 100 50 50 50 50 1
50 50 50 100 50 50 50 100 50 50 50 50 1 1
50 50 50 50 50 50 50 100 50 50 50 50 1 1 1
PIP PNE00003
Minimum Requirements
Item Description Dimension
Roads Clearance over primary access roads where major 18'-0"
maintenance vehicles are expected to pass
Clearance over electrical transmission and distribution lines 22'-0"
Width of primary access roads 20'-0"
Clearance over secondary access roads and pump access roads 10'-0"
Width of secondary access roads and pump access roads 10'-0"
Railroads Clearance over through-railroads (from top of rail) 22'-0" (check local regulations)
Clearance over dead ends and sidings (from top of rail) 16'-0" (check local regulations)
Horizontal clearance from track centerline to obstructions 8'-6"
Clearance under electrical lines Check applicable regulations
Access Clearance height for projections over platforms, working 7'-6” (6’-8” for bottom of valve
Walkways areas, walkways handwheels)
Width of stairways (unobstructed width) 3'-0"
Width of landings (in direction of stairways) 3'-0"
Width of walkways 3'-0"
Maximum vertical rise of one flight of stairway 18'-0"
Maximum horizontal distance from any point on platform to 7 5'-0"
an emergency exit
Maximum length of dead-end platforms 20'-0"
PIP PNE00003
Minimum Requirements
Item Description Dimension
Ladders Maximum vertical rise of ladders in a single run 30'-0"
Maximum allowable slope of ladders from vertical 15 degrees
Minimum toe clearance from centerline of rung to obstruction 7"
Platforms Maximum variance in platform elevations without an 1'-0"
intermediate step
Minimum unobstructed width of platforms 2'-6"
Occasional obstructions ( level glass, transmitter, etc.) 1’-6”
Minimum width of manhole platforms on vertical vessels 3'-6"
Minimum platform extension beyond centerline of manhole 2'-6"
flange on vertical vessels
Minimum width of platform from three sides of manhole on 2'-6"
vessel top head platforms
Minimum width of platforms at ends of horizontal tube 3'-6"
furnaces
Operation Minimum clearance in front of channel end of horizontal Tube bundle length plus 5 ft.
and exchanger for tube removal or cleaning
Maintenance Minimum clearance around exchanger body flanges 1'-6"
Vertical exchangers Unobstructed vertical access
API RP 752
According to RP 752, there are several types of buildings commonly
used in process areas. These building types and the effects of
explosion overpressure on each are as follows:
EXAMPLE
API RP 753
Allowable Locations and Personnel for Portable Buildings
Intended for Occupancy
Portable Buildings
Light Wood Occupancy
other than Light
Trailers Restrictions
Wood Trailers
Detailed analysis House only
Zone 1 Not allowed
required essential personnel
Detailed analysis Detail analysis
Zone 2 No restrictions
required required
Zone 3 No restrictions No restrictions No restrictions