LIFTING PLAN
Operation Director
Reviewed by: Alex Peh 13.09.2019
Good Year Contractor Pte Ltd
TABLE OF CONTENT
1 Scope of Work
2 Maintenance of Plant and equipment
3 Means of communication & resources
4 Identified Materials & Schedule
5 Application of Lifting Methods
6 Manpower & Personnel Details
7 Identification of Lifting Team
8 Training
9 Roles and Responsibilities of Lifting teams
10 Operation procedure
11 Permit to work system
12 Program Schedule of Work
13 Lifting Plan, Crane Position & Calculation
14 Crane Full Load Chart & Specification
15 Emergency Response & Contingency Plan
16 Regulations Reference
17 Appendix
GOODYEAR CONTRACTOR PTE LTD
Blk 1045 #01-122 Eunos Ave 4 Singapore 409795
Tel: 6744 2878 (3 lines) Fax: 6744 5338
Email: admin@goodyearcontractor.com GST Reg No:199904844M
1. Scope of Work
Proposed hoisting down of ACMV Equipment & demobilise from site premises.
Provision of competent lifting crew, lifting gears and appliances to execute the task.
.
GOODYEAR CONTRACTOR PTE LTD
Blk 1045 #01-122 Eunos Ave 4 Singapore 409795
Tel: 6744 2878 (3 lines) Fax: 6744 5338
Email: admin@goodyearcontractor.com GST Reg No:199904844M
A.Lifting Supervisor
Brown Helmet
Hi Reflective Green Vest with LIFTING SUPERVISOR Indication on the back.
B. Rigger Man
Red helmet
Hi Reflective Red / Orange Vest with RIGGERMAN indication on the back
C. Signalman
Red Helmet
Hi Reflective Red / Orange Vest with SIGNALMAN indication on the back.
Deployed lifting crews are to undergo training under MOM approved training center and
had successfully completed the course:
The lifting supervisor should be appointed in writing by the contractor. This position is defined as the
person who is charged with actively supervising the lifting operation on site. The person could be a
foreman, shift supervisor or other similar capacity.
In general, all lifting operation must be supervised by the appointed lifting supervisor as he is the
main person leading and coordinating the operation. A lifting supervisor may be allowed to supervise
more than one lifting operation at any point in time provided that he is able to discharge his duties
appropriately e.g., when the two operations are side by side in a close proximity. If so requested by the
contractor, the Lifting Supervisor should assist to develop the Lifting Plan and seek approval from the
contractor’s management.
The appointed rigger shall be attired in such a way that he/ she will be distinctively identified as the
rigger.
ensure all slings, webbings, shackles and other lifting gears used to rig the load are within the SWL
of the lift, in good condition an d duly certified;
ensure that the load is rigged up in a such a manner that it is stable, balanced (centre of gravity
beneath the hook) and secured (i.e., no loose items);
ensure that the lifting equipment operator has been informed of the weight of the load;
Report any defect in the lifting/ rigging and materials to the lifting supervisor.
The appointed signalmen shall be attired in such a way that he/ she will be distinctively identified as the
signalman.
There are different types of lifting equipment and the operator is one of the most important personnel of the
Lifting Team as he is in-charge of the lifting equipment. One of the key competencies of the crane
operator of mobile, crawler or tower cranes is the ability to read and understand the load capacity
chart, and to differentiate the Gross Capacity and Net Capacity of the lift. The operator needs to
know the SWL of the crane relative to the radius in order to prevent overloading of the crane.
02 Pre-check travel route and lorry parking location for unloading works. Good Year
Workplace Safety and Health (Risk Management) Regulations 2006 then be approved by
an authorised person (typically the project manager) who shall have oversight on the entire
work process so as to avoid any situation of conflicting or incompatible work being carried
out at the same time. The work can commence only after the permit is approved
GOODYEAR CONTRACTOR PTE LTD
Blk 1045 #01-122 Eunos Ave 4 Singapore 409795
Tel: 6744 2878 (3 lines) Fax: 6744 5338
Email: admin@goodyearcontractor.com GST Reg No:199904844M
T.B.A
GOODYEAR CONTRACTOR PTE LTD
Blk 1045 #01-122 Eunos Ave 4 Singapore 409795
Tel: 6744 2878 (3 lines) Fax: 6744 5338
Email: admin@goodyearcontractor.com GST Reg No:199904844M
l. Safe working load at 9,400 KGS n. Total %loading on 80.0 % ( Business Critical Lift)
working radius Load Chart crane
GOODYEAR CONTRACTOR PTE LTD
Blk 1045 #01-122 Eunos Ave 4 Singapore 409795
Tel: 6744 2878 (3 lines) Fax: 6744 5338
Email: admin@goodyearcontractor.com GST Reg No:199904844M
a. SUMMARY/ OUTLINE
The purpose of an emergency response plan is to ensure that adequate arrangements are in place for the
protection of all employees and other persons that may be presenting the area or premises in the event of a
emergency occurring.
b. EMERGENCY SITUATION
In the event of Emergency situation, Person in Charge E.g.; Supervisors, Project Coordinators shall immediately
notify the end user (Main Con) / Client representatives, EHS Personnel onsite and/or the Fire Command
Centre(FCC).
Depending on the situation and nature of Emergency, Fire Command Centre(FCC) shall decide and call relevant
emergency services E.g. Singapore Police Force (SPF) / Singapore Civil Defence Forces (SCDF)/ Ministry of
Manpower (M.O.M) where necessary.
Call 995
If the fire is small, attempt to put it out with a fire extinguisher if you can do so safely.
Never allow the fire to come between you and an exit path
If the fire involves electrical equipment that is active, attempt to unplug the device.
If you are unable to put the fire out, evacuate by the nearest emergency exit.
Touch closed doors with the back of your hand prior to opening them. If it is hot or if smoke is
visible, do not open that door. Seek another exit path.
If there is fire, confine it as much as possible by closing doors and windows (do not lock the doors).
Do not wear high heel shoes or carry liquids, beverages, or water bottles into the stairwell (fall and
slip hazards)
Wait for the Fire Department to declare the building safe to re-entry.
GOODYEAR CONTRACTOR PTE LTD
Blk 1045 #01-122 Eunos Ave 4 Singapore 409795
Tel: 6744 2878 (3 lines) Fax: 6744 5338
Email: admin@goodyearcontractor.com GST Reg No:199904844M
Use extinguishers on small fires ONLY if safe to do so – use the P-A-S-S method
o Sweeping motion
If its not life threatening, the location of incident shall be cordon off.
If it involves public worksite, a control measures shall be taken in place to ease the situation.
Immediately notify the In-House EHS Dept & provide aid or assistance in case any life is at risk due to
the incident.
Supervisors / Person in Charge shall retreat manpower from the incident zone immediately.
Do not attempt to move the injured person from the zone if the situation is critical.
For minor injury (cuts/lacerations), try to move the person to a safe zone and well-ventilated point.
In case injury was too serious & life threatening, immediately seek further actions like calling an
Ambulance / SCDF – Hotline-995)
In case of fatality, operations to be ceased immediately, cordon off the work zone and call in the Main-
Con / Site P.I.C to notify SCDF and report the incident to the Ministry of Manpower.
GOODYEAR CONTRACTOR PTE LTD
Blk 1045 #01-122 Eunos Ave 4 Singapore 409795
Tel: 6744 2878 (3 lines) Fax: 6744 5338
Email: admin@goodyearcontractor.com GST Reg No:199904844M
- Damage to property
Inform Supervisor if any damage occurred to any parts of the building /premises during the work
process.
EMERGENCY /
INCIDENT
NOTIFICATION TO
SITE SUPERVISOR /
Inform/NotifyP.I.C
Activates
EMERGENCY WORK CREW SITE
CONTACT MEMBER CONTROL
(P.I.C / FCC)
EMERGENCY
SERVICES
Proceed To
(SCDF/SPF/MOM)
PROCEED TO
ASSEMBLY POINT
GOODYEAR CONTRACTOR PTE LTD
Blk 1045 #01-122 Eunos Ave 4 Singapore 409795
Tel: 6744 2878 (3 lines) Fax: 6744 5338
Email: admin@goodyearcontractor.com GST Reg No:199904844M
16. REFERENCE