Individual Assigment 4 NetworkDiagram
Individual Assigment 4 NetworkDiagram
Fig.1
Fig.2
The above-given images depict the project plan for the Loblaws. Fig. 1 is the work
breakdown structure which imparts the inputs for the network diagram displayed in Fig. 2
The project progressiveness will be understood by studying the fig.1 and Fig. 2
1. Loblaws project for tackling the new market competitors (i.e. Walmart and Amazon) and
providing something more to the new and existing consumers by enhancing the supply
2. All five components comprise 16 work packages, and the project lifecycle is estimated at
144 days. The first component, of the project, is the Project Initiation which is estimated
at 41 days starting from July 10th, 2023 and expected to be completed by Monday,
September 4th, 2023. This phase consists of four working work packages which are as
follows:
2.1. Defining Project Objectives and Scope- It is estimated to be completed within five
days, starting July 10th and ending July 14th. This activity will be conducted by the
project manager Mr. Shivankit Sharma who will also be responsible for the whole
project. He will define the project objective and scope. Also, it will be ensured that it
2.2. Identifying Key Stakeholders- The duration for this activity is estimated at around
ten days starting after the completion of the previous work package. It is expected
to be started by July 17th and completed by July 28th. This activity will have the
joint efforts of PM Mr. Shivankit and Business Analyst Mr. Danish Ahmed Pathan.
These two vital resources will take care of Stakeholder requirements and
satisfaction.
2.3. Establishing Communication Channels- This activity is expected to be completed
within six days after completing the previous work package. It will be conducted
from July 31st to August 7th. It will be governed by Chief Marketing Officer &
Facilitator Mr. Mimoh Singh Chouhan, and Team Lead & Co-ordinator Mr. Yash Naik
will do hands-on. Mr. Yash will co-ordinate every communication to the developing
and operating team, and if senior management help is required, Mr. Yash will
approach Mr. Mimoh. Then, he will discuss and facilitate communication within
senior management.
2.4. Assembling Project Team- Mr. Yash will oversee this activity, and the time allotted
for this activity is 20 days starting from August 8th and is expected to be completed
conducted. This activity is also dependent on the previous work package. With the
completion of this work package, phase-1 of the project will also be concluded.
3. Second component (Phase-2): This work component is the Analysis and Design,
estimated completion time is 18 days starting on September 13th and ending on October
6th. This component comprises three work packages which are as follows:
3.1. Gather Market Data- This work package will be completed in 3 days from
September 13th to September 15th. Mr. Mimoh will be the hands-on resource for
this activity.
3.2. Analyze Market Trends and Consumer Preferences- The time allotted for this work
package is five days from September 18th to September 22nd. This activity will have
joint efforts of Mr. Danish and Mr. Mimoh and will require the predecessor work
package to be completed. Mr. Mimoh will share information from the gathered
market data with Mr. Danish, and further brainstorming will be done in the direction
3.3. Developing Strategies- Mr. Danish will be the hands-on resource for this activity,
and it is expected to be completed within ten days from September 25th to October
6th. This activity will be started after the completion of the previous work package.
4. Third Component (Phase-3): After phase-2, phase-3 will be in play. It is expected to take
41 days for completion, starting from October 9th, 2023, to December 4th, 2023. This
component is the Research and Development(R & D), which consist of 3 work packages.
4.1. Researching the Emerging Technologies and Trends in the Retail Industry- Mr.
Danish and Mr. Yash are the resources allocated for this activity, and six days is
4.2. Identifying Potential Technological Solution- The time allocated for this activity is
15 days starting from October 17th to November 6th. It will be started after the
completion of the previous work package. Mr. Yash will be the hands-on resource for
this activity. Various technology will be reviewed, and multiple solution approaches
will be selected.
4.3. Pilot and Test New Technologies- This activity will have Mr. Mimoh and Mr. Yash
plan for the selected solution approach. It has an estimated 20 days, from
November 7th to December 4th. This activity has the previous work package as a
dependency.
5. Project Management Plan and Execution (Phase-4): This activity will be completed
within 38 days tentatively. It comprises four work packages. The estimated start date will
be December 5th, and the end date will be January 5th, 2024. Specification of included
5.1. Developing Project Management Plan- Estimated time is ten days, and the resource
allocated for this activity is Mr. Shivankit. This plan will be meticulous and have very
5.2. Defining Project Milestones, Deliverables, Timelines: Mr. Mimoh and Mr. Shivankit
will work together on this work package. Completing the previous work package will
be required to start this activity by December 19th and complete by December 25th,
5.3. Assigning Task and Responsibilities- Mr. Yash and Mr. Shivankit will work together in
this activity. It is expected to be completed within three days after completing the
previous work package. In this task, Mr. Yash will distribute work among the
project's developing and operational teams. Mr. Yash will also co-ordinate these
5.4. Track Issues and Manage Risks- Issues will be tracked, and Mr. Yash will manage
risk. This task will be started after completing the previous work package and is
expected to be completed within 20 days. Backlogs will be cleared, and risk handled
via Disaster Recovery or various Risk Management Systems. With this task, phase-4
6. Last Component: The last component of the project is sign-off. It has two short-duration
working together on this task. It is a formal task towards the project closure by
taking the client's approval on the agreement's quality, functionality and fulfilment.
6.2. Project Closure- If the client is satisfied with the project, the project can be officially
terminated as its life cycle is completed, and the project team will disband. The
estimated completion time is four days from January 4th to January 9th, 2024.
7. Critical Path: Project Management Plan and Execution (Phase-4) activities lies on the
critical path as shown in the network diagram (Fig.2). The critical path can be defined as
the longest sequences of tasks that must be completed to successfully complete the
The work packages included in Phase-4 which coincides with the critical path are:
The brief description of these activities is mentioned in point 5, which entails the specifics.