Professional Documents
Culture Documents
Indian Standard
DESIGN AND CONSTRUCTION OF PILE
FOUNDATIONS - CODE OF PRACTICE
PART 4 LOAD TEST ON PILES
( Second Revision)
BIS
AUTHORISED COpy
@ DIS 2013
FOREWORD
This Indian Standard (Part 4) (Second Revision) was adopted by the Bureau of Indian Standards, after the draft
finalized by the Soil and Foundation Engineering Sectional Committee had been approved by the Civil Engineering
Division Council.
Pile load lest is the most direct method for determining the safe loads on piles including its structural capacity
with respect to soiUrock in which it is installed. It is considered more reliable on account of its being in-situ test
than the capacities computed by other methods, such as static formula, dynamic formulae and penetration test
data. There are widely varying practices followed for load tests on piles. Particularly, the difficulties regarding
the establishment of an acceptable criterion, for determining the ultimate and safe bearing capacity of piles, and
predicting the pile group behaviour from the test data obtained from individual load test on single piles cannot be
under estimated as the factors affecting are ma.ny. However, an attempt is made to bring out a unified approach to
the various aspects of load test on piles.
This standard (Part 4) was first published in 1979 to cover load test on piles. The other parts of this standard arc
as follows:
(Part I) Concrete piles
(Part 2) Timber piles
(Pari'3) Under-reamed piles
The standard was first revised in 1985 to give more details in regard to the rate of loading and unloading and the
details of the situations when the different types of tests are conducted. Later Amendment No. I to the standard
was issued in May 1989 modifying the test load for routine test of piles.
It has now been felt that the provisions regarding the load test of piles should be further revised to take into
account the recent developments in this field. This revision has been brought out to incorporate these developments.
In this revision following major modifications have been incorporated:
I
a) Definitions of various terms have been modified as per the p)evailing engineering practice;
b) The frequency for initial test has been modified;
c) The test load for initial test pile has been added; and
d) In case of both vertical load test and pull-out test, separate criteria for determining sufe load of piles
have been specified on the basis of diameter of piles.
For rock socketed piles and for piles through rock, assessment of safe load for different mode of loadings shall
conform to IS 14593: 1998 'Design and construction of bored cast in-situ piles founded on rocks _ Guidelines'.
The composition of the Committee responsible for the formulation of this standard is given in Annex C.
For the purpose of deciding whether a particular requirement of this standard is complied with, the final value,
observed or calculated, expressing the result of a test or analysis shall be rounded offin accordance with IS 2 : ] 960
'Rules for rounding off numerical values (rellised)'. The number of significant places retained in the rounded off
value should be the same as that of the specified value in this standard.
IS 2911 (Pari 4) : 2013
Indian Standard
DESIGN AND CONSTRUCTION OF PILE
FOUNDA TrONS - CODE OF PRACTICE
PART 4 LOAD TEST ON PILES
( Second Revision)
3.8 Initial Test Pile - One or more piles. which are f) Depth of water table and sub strata details with
not working piles, may be installed to assess the load applicable test results;
carrying capacity of a pile. g) Back up calculations for aniving the safe load
3.9 Kentledge - Dead.weight used for applying a and ultimate load capacity;
test load on piles. h) Availabilily and provision of type of piles or
anchors or kent ledge far"reaction;
3.10 Net Displacement - The net vertical movement
j) Nature of loading/loading plan Wilh a
of Ihe pile top after Ihe pile has been subjecled 10 a te,t
partiCUlarly mention of pile(s) which may be
load and subsequently released. .
free standipg when scour is expecled;
3.1l Routine Test - It Is carried oul on a working k) Permisslhle load considered in design: and
pile with a view to check whether pile is capable of m) Any other information concerning planning
taking .the working load assigned to il without and eonduqing tile tCsi,;including Ulerelevanl
exceeding permissible ,eulement. paSI experience cpocerlling simil~r testes),
3.l2 Safe Load -It is the load derived by applying a
factor of ,afely on Ihe ultimate 1mid capacily of the 5 TYPf;S OF Tf:STS
pile or 'as delermineQ from load le,t. . There are two types of IeSIS.namely. inilialand rou!lne
te'l for each type (mOQe) of loading (lhat Is. vertical.
3.13 Ultimate Load Capacity - The maximum load
laleral anll pull'out) ..
which a pile can carry before failure. that I, when the
founding slrata fails by shear as evident from the load 5.~ Initial Test
settlemenl CUrveor the pile fails as a struclur.1 member.
Thi, lest is required for one or more of Iho follo\\'ing
3.14 Working Load/\leslgl\ Load - The load purroses:
assigoe~ 10 a pile a' per design.
a) Determinalion of ultimate load qpaelty anQ
3.15 Working Pile - A pHe forming parI of Ihe arrival at safe load by applicalion of factor of
foundation systein of a give~ 't~cture. safely. .
3.16 Constant Rnle of Pelletratlon (CRI') -In this b) To provide guidelines for selling up lhe limits
method. le,t pile Is made to penelrate the soil al a of acceptance for routlrie tesls, .
con slant speed while Ihe force applied al the top of the c) To gel an illea of sullal>lIity of piling 'yslem,
pile to maintain the rate of penelration Is continuously and
measured. As a rosult of the pile movemenl the soil is d) To have " check on calculated load by
progressively slressed unlil il fails In shear: when Ihat dynamic or static approaches"
occurs Ihe ultimate load of Ihe pile is reached.
5.1.1 The number of initial tests may be selected as
3.17 Cyclic Load Test - It is carried out on initial. given below depending upon the nature of sub-strata,
test piles to determine contribution from skin friction number of piles and "past experience at the site.
and point bearing load by loading and unloading in
cycle. a) For small size projects (for piles less than
I 000 numbers), a minimum of two tests.
4 NECESSARY INFORMATION b) For large size projects (for piles more than
The following information is necessary for pile(s) on 1 000 numbers), a minimum of two tests for
first I 000 piles and additional one test for
which test is proposed:
every additional 1 000 piles and part thereof.
a) Pile type including material and
reinforcement details, group of piles, if any; The frequency of testing stipulated above is applicable
for each diameter of pile and rated capacity of pile in
b) Method of driving/installation with record
each type (mod,,) of loading. The number of lests may
including date of casting, date of testing,
be increased/decreased depending upon whether the
formation level, cut off level as per relevant
strata is erratic/uniform, subjected to a minimum of
pile dala sheels given in IS 2911 (Part IISec
two tests.
1 to 4):
c) Pile deplh(s) and delails of cross-seclion(s); 5.1.2 The test load provision in the initial load test shall
not be less than the estimated safe load multiplied by
d) Type of lest desired;
the minimum factor of safety of 2.5.
e) Layoul of the pile(s) - Space available
around and position in the group for single 5.1.3 Inilialtest piles should be inslalled by the same
pile test; technique. same type of equipment as that proposed
:
IS 2911 (Part 4) : 2013
for working piles. Separate test piles shall be installed 6.2 Generally the load application and deflection
for different type (mode) of loadings (namely. vertical. measurement should be made at the pile top. Datum
lateral and pull-out). Initial pile load tests shall bars should rest on firm ground.
preferably be carried out prior to execution of piling
6.3 In particular cases where upper part of pile is likely
job. to be exposed later on due to scour, dredging.
liquefaction or otherwise then capacity contributed by
5.2 Routine Tesl
that portion of the pile during load test shall be duly
This test is required for one or more of the following accounted for or simulated by provision of larger
purposes: diameter casing around the pile up to scour depth.
a) Checking the safe load as determined from
dredge level or liquefiable depth. The pile groups in
these conditions shall be tested without their cap resting
static analysis [see IS 2911 (Part IISec I to
4), IS 2911 (Part 2) and IS 2911 (Part 3)]; on the ground.
b) Detection of any unusual performance 6.4 The test should be carried out at cut-off level
contrary to the findings of the initial test. if wherever practicable. otherwise suitable allowance
already done; and shall be made in the interpretation of the test results/
c) Workmanship. test load, if the test is not carried out at cut-off level.
The number of tests shall be 0.5 percent of the total 6.4.1 Alternatively. in case of vertical load test
number of piles, subject to a minimum of one (1) test. conducted at a level higher than cut-off level or in case
The number of tests may be increased up to 2 percent the soil parameters over the depth between the ground
in particular cases depending upon the nature, type of level and cut-off level is ambiguous. an annular space
structure and sub-strata condition. shall be created to remove the effect of skin friction
above cut-off level by providing an outer casing of
5.2.1 The piles to be tcsted for routine tests may suitable diameter larger than the pile diameter.
preferably be selected on the basis of the following; However, effect of over burden pressure may be taken
a) Abnormal variation in concrete consumption. into account for analysis of vertical pile load test.
b) Sudden drop in concrete level during 6.4.2 Whereas, in case of lateral load test_ test load
construction of piles. shall be applied at cut-off level: otherwise lateral
c) Problems encountered during boring and displacement at cut-off level shall be determined based
trernie operation. on measurements done at different level. However, the
d) Significant variation in depth of pile with acceptance criteria of deflection shall be at cut-off level
respect to other adjoining piles and boring or scour level or dredge level or liquefiable depth, as
record. the case may be.
e) Anomalies observed during the driving 6.5 Load cells may be used for measuring load.
operation in case of driven piles.
6.6 In case of off-shore and marine piles, simulated
o Piles under sensitive locations of structures.
load test may be conducted on-shore.
g) Any doubt arising from non destructive test
results. . 6.7 Plotting of load displacement curve shall be done
on rational basis by selecting suitable scale for load
NOTES and settlement axis.
1 Number of tests mentioned in 5.1.1 (a), 5.1.1 (b) and
5.2 are applicable separately for each type (mode) of
7 VERTICAL LOAD TEST (COMPRESSION)
loading (that is. vertical. lateral and pull-ouO, subject
10 design requirements.
7.1 General
2 Number of tests mentioned in 5.1.1 (a), 5.1.1 (b) and
5.2 are also applicable separately for each diameter of In this type of test, compression (vertical downward)
pile and rated capacity of pile.
load is applied to the pile top by means of a hydraulic
6 GENERAL REQUIREMENTS APPLICABLE jack against rolled steel joist or suitable load frame
TO ALL TYPES OF TESTS with adequate kentledge and the settlement is recorded
by suitably positioned dial gaugeslLVDTs. Maintained
6.1 Pile test may be carried out on a single pile or a load method as given in 7.2 should be used for
group of piles as required. In case of pile groups, caps determination of sare load. However. for specific
shall be provided such that the required conditions requirements cyclic and CRP methods, which are
of actual use are fulfilled. Pile cap can also be alternate methods. may be used as mentioned in 7.3
provided for single pile to accommodate load testing and 7.4. The general requirements applicable for these
jacks. etc.
3
IS 2911 (ParI 4) : 2013
7.1.1 Preparatian of Pile Head 7.1.4.1 Seltlement shall be recorded with minimum
4 dial gauges of 0.0 I mm sensitivity for bolh single
The pile head should be chipped off to natural pile and groups. The dial gauges shall be placed
horizontal plane tiIl sound concrete is met. The symmelrically and at equal dislances from the pile(s)
projecting reinforcement should be cut-off or bent and normally held by datum bars resting on immovable
suilably and the top finished smooth and level with supports at a distance of 3 D (subject to minimum of
cement plaster or similar synthetic material where 2.0 m) from the edge of the piles. where D is the pile
required. A bearing plate with a mark at Ihe centre stem diameter of circular piles or diameter of the
should be placed on the head of the pile for the jacks circumscribing circle in the case of square or non-
to rest. Finished pile head level may be measured prior circular piles.
and after the load tesl by suilable survey inslrument.
7.1.4.2 From safety point of view and to minimize the
7.1.2 Application of Load (not Applicable to CRP disturbance to datum bars, it is preferable to use
Method) remotely controlled linear variable differential
transducers (LVDT) wilh a digital read oul for
The lest should be carried out by applying a series of
recording the settlement. The LVDTs shall be
vertical downward incremental load each increment
calibrated.
being of about 20 percent of safe load on the pile. For
testing of raker piles it is essential that load is applied 7.1.4.3 Finished pile head level may be measured prior
along the axis of the pile. and after the load tesl by suitable survey inslrument.
7.1.3 Reaction 7.1.5 The safe vertical load on single pile for Ihe initial
test should be least of the following:
The reaction may be obtained from the following:
a) For piles up to and inc/uding 600 mm
a) Kentledge placed on a platform supported
diameter:
clear of the test pile. In case of 10ad test below
under-pinned structure, the existing structure, I) Two-thirds of the final load al which Ihe
if having adequate weighl and suilable total displacement attains a value of
construction may serve as kentledge. The 12 mm unless otherwise required in a
cenlre of gravity of Ihe kentledge should given case on the basis of nature and type
coincide with the axis of the pile and the load of structure in which case. the safe load
applied through the jack should also be should be corresponding to Ihe stated
coaxial wilh Ihis pile. If multiple jacks are to total displacement permissible; and
be used. these shall be arranged in parallel 2) Fifty percent of Ihe final load at which
arid connected to a single hydraulic pump and Ihe lotal displacement equal to 10 percent
pressure gauge. of the pile diameter in case uf uniform
b) Anchor piles with centre-la-centre distance diameter piles and 7.5 percent of bulb
from the test pile not less than 3 limes the lest diameter in case of under-reamed piles.
pile shaft diameter subject to minimum of b) For piles more than 600 mm diameter:
2 m. If the anchor piles are permanent I) 1\v~-thirds of the final load at which the
working piles, il should be ensured that their total displacement attains a value of
residual uplift is within limits. Care should 18 mm or maximum of 2 percent pile
be exercised to ensure that the datum bar diameter whichever is less unless
supports are not affecled by heaving up of the otherwise required in a given case on the
soil. basis of nature and type of structure in
c) Rock anchors with distance from the nearest which case. the safe load should be
edge of the piles at rock level being 2 times corresponding to the staled total
the test pile shaft diameter or 1.5 m, whichever displacement permissible; and
is greater. 2) 50 percent of Ihe final load al which the
tOlal displacement equal to 10 percent of
NOTE - In case wedge failure governs in Ihe pile :mehorsl
rock anchors. lhe pile dislance should be suilably maintained the pile diameter in case of uniform
10 avoid interference of the wedge with the test pile. diameler piles and 7.5 percent of bulb
diameter in case of under-reamed piles.
7.1.3.1 The reaclion to be made available for the lest
should be 25 percent more than the final test load 7.1.5.1 However. routine test shall be carried for a lest
proposed to be applied. load of at least 1.5 times the working load; the maximum
4
IS 2911 (Part 4) : 2013
seWement at the test load being not greater than 12 mm 2) Maximum settlement of pile exceeds a
for piles diameter up to and including 600 mm and value of 40 mm.
18 mm or 2 percent of pile diameter whichever is less b) In case a/routine load test;
for piles of diameter more than 600 mID. I) Applied load reaches the working load;
7.1.6 The safe vertical load on groups of piles for initial or
test shall be least of the following: 2) Maximum settlement of pile exceeds a
value of 25 mm.
a) Final load at which the total displacement
attains a value of 2S mm unless otherwise 7.3 Cyclic Method
required in a given case on the basis of nature
and type of structure; and
This method is used in case of initial test to find out
separately skin friction and point bearing load on single
b) Two-thirds of the final load at which the total
piles of uniform diameter. The procedure as given in
displacement attains a value of 40 mm.
Annex A or by suitable instrumentation may be used.
7.1.6.1 However. routine test on group of piles shall
be carried for a test load of at least equal to the working 7.4 CRP Method
l.q~.the maximum settlement of the test loading in This method which is used for initial test is generally
position being not exceeding 25 mm. considered to be morc suitable for determining ultimate
NarE -"FordifferentiaJ settlements. IS 1904shall be"referred. load capacity than by the maintained load test but the
load/deflection characteristics are quite different from
7.2 Maintained Load Method those of the maintained load test and cannot be used to
This is applicable for both initial and routine test. In predict settlement of the pile under working load
this method. each stage of loading shall be maintained conditions. This method should not be included in
-iiITthe rate of movement of the pile top is not more routine test. The procedure is given in Annex B.
than 0.2 mmlh or until 2 h have elapsed. whichever is
8 LATERAL LOAD TEST ON PILES
earlier subject to a minimum of 1 h. The maximum
test load shall be maintained for 24 h. 8.1 The test may be carried out by introducing a
hydraulic jack with gauge between two piles or pile
7.2.1 Duration of Vertical Loading groups under test or the reaction may be suitably
7.2.1.1 Vertical loading on single pile shall be obtained otherwise. If it is conducted by jack located
continued till one of the following takes place: between two piles or groups. the full load imposed by
the jack shall be taken as the lateral resistance of each
a) llJ. case of initial load test: pile or group. The loading should be applied in
I) Applied load reaches 2.5 times the safe increments of about 20 percent of the estimated safe
estimated load; or lateral load.
<f2) Maximum settlement of pile exceeds a
8.2 The next increment should be applied after the
value of 10 percent of pile diameter in
rate of displacement is less than or equal to 0.1 mm
case of uniform diameter piles and
per 30 min subject to minimum of 30 min.
7.5 percent of bulb diameter in case of
under-reamed piles. . 8.3 In case of unapproachable cut-off levels,
b) III case of routine load test: displacements shall be read by using at least two dial
1) Applied load reaches 1.5 times the gauges or LVDTs of 0.01 mm sensitivity (see Fig. I)
working lo"ad; or spaced at 30 cm and kept horizontally nne above the
other on the lest pile and the displacement shall be
2) Maximum settlement of pile exceeds a
interpolated at cut-off level from similar triangles.
value of 12 mm for piles diameter up to
However, for approachable cut-off levels. one dial
and including 600 mm and 18 mm or
gauge or LVDT placed diametrically opposite to the
maximum of 2 percent of pile diameter
jack shall directly measure the displacement. Where.
whichever is less for piles of diameter
it is not possible to locate one of the dial gauges in lhe
more than 600 mm.
line of the jack axes, there two dial gauges may be
7.2.1.2 Vertical loading on group of piles shall be kept at a distance of 30 cm at a suitable height and the
continued till one of the following takes place: displacement interpolated at load point from similar
triangles.
a) In case of initial load lest:
I) Applied load reaches 2.5 times the safe NOTES
lOne of the methods for keeping dial gauge on pile surface is
estimated load; or
5
IS 2911 (ParI 4) : 2013
10 chip off uneven concrete on the side of Ihe pile and to fix a 9 PULL-OUT TEST ON PILES
glass piece of 20 10 30 mm square. The dial gauges tips shall
reSI on the cenlral portion of the glass platc. 9.1 Uplift force may preferably be applied by means
2 In case the hydraulic jack is placed in between test pile and of hydraulic jack(s) with gauge using a suitable pull-
reaction pile. one dial gauge or LVDT shall be suitably placed
out set up. Pile top shall preferably be at cut-off level.
on reaclion pile to measure the displacemenl of reaction pile.
Displacement measurement shall be made at pile top
8.4 The safe lateral load on Ihe pile for initial test. for with at least two dial gauges placed at diametric
both free head and fixed head shall be taken as the opposite ends of pile.
least of the following:
NOTE - One of the methods for pull-out tests that may be
a) Fifty percent of the final load at which the used is where hydraulic jack is made to rest on rolled steel
joist(s) resting on two supports on the ground. The jack reacts
total displacement increases to 12 mm;
against a frame attached to the top of the test pile such that
b) Final load at which the total displacement when the jack is operated. the pile gets pulled up and the
corresponds to 5 mm; and reaction is transferred to the ground through the supports which
are at leasl 2.5 D away from the test pile periphery (where D is
c) Load corresponding to any other specified pile stem diameter of circular piles or diameter of the
displacement as per performance or design circumscribing circle in the case of square piles). The
requirements. framework can be attached to the pile top with the
reinforcement bars which may be threaded or to which threaded
8.4.1 Routine (ateralload test shall be carried out for a bolts may be welded. As an allernative it is sometimes
test load equal to the working load; the maximum preferable to use a central rod designed to take pile load and
embedded centrally in the pile to a length equal to the bond
deflection of test loading in position shall not exceed length load required. It will have threads at top for fixing it to
5mm. the framework. For larger loads the number of rods may have
to be more and depending on the set-up these may be put in a
NOTES
line or in any other symmetrical pattern. For routine tests, the
1 The above displacement is al the cut.off level of on-shore framework is nonnally auached to the reinforcing bars bul a
piles and at the scour line/mud line of off-shore piles. as the central rod may also be used in case the upper portion of the
case may be. pile is required to be built up.
2 In actual practice the piles are partially fixed or fixed.
Accordingly. to derive the advantage of increased lateealload 9.2 The test pile shall have adequate steel to withstand
due to partial fixitylfixity condition. it is desirable to carryout pulling. In some cases, in order to alI ow for neck
(a) Lateral load test on group of piles with pile cap; or (b) tension in a pull-out test, it may be necessary to provide
Single pile may be tested for lateral load under sustained
vertical load.
additional reinforcement in the piles to be tested.
3 Suitable analytical method may be considered to interpret 9.3 The pull-out load increments and consequent
load test results carried at free head condition to fixed head
displacement readings shall be read as in the case of
condition.
vertical load lest.
DATUM BAR
SUPPORT '
6
IS 2911 (Part 4) : 2013
9.4 The safe uplift load shall be taken as the least of working load or 12 mm total displacement for piles
the following: diameter up to and including 600 mm and 18 mm or
maximum of 2 percent of pile diameter. whichever is
a) For piles up 10 and including 600 mm
less for piles of diameter more than 600 mm, whichever
diameter:
is earlier.
I) 1\vo-thirds of the load at which the total
displacement is 12 mm or. the load 9.7 Pull-out test shall be carried out preferably on
corresponding to a specified permissible initial test piles. In case it is found necessary to conduct
uplift; and pull out test on working piles the following
considerations shall be made:
2) Half of the load at which the load
displacement curve shows a clear break a) To check that the pile shaft is designed to cater
(downward trend). for such uplift load; and
b) For piles more than 600 mm diameter: b) To limit the displacement within elastic
I) Two-thirds of the load at which the total deformation of pile beyond which the test
displacement is 18 mm or maximum of should be discontinued.
2 percent of pile diameter whichever is
10 RECORDING OF DATA AND PRESENTATION
less or the load corresponding to a
specified permissible uplift; and 10.1 The pile test data essentially contains three
variables. namely. time, load and displacement. These
2) Half of the load at which the load
are to be recorded sequentially for the tests under
displacement curve shows a clear break
consideration and recorded in a suitable tabular form
(downward trend).
along with the information about the pile.
9.5 The initial test shall be carried out up to 2.5 times the
10.2 The data may be suitably presented by curves
estimated safe uplift load or until the load displacement
drawn between the variables and safe loads shown on
curve shows a clear break (downward trend).
the graphs. Load displacement curve shall be an
9.6 Routine test shall be carried out to 1.5 times the essential part of presentation.
ANNEXA
(Clause 7.3)
CYCLIC LOAD TEST METHOD
A.l METHOD A.2.l.3 Draw a straight line through the origin and
parallel to the straight portion of curve Ito divide the
Alternate loading and unloading shall be carried out at load. into two parts and thereby obtain approximate
each stage as in 7.1.2 and each loading stage shall be values of point resistance and skin friction.
maintained as in 7.2 and each unloading stage shaH be
maintained for at least 15 min and the subsequent A.2.l.4 From the approximate value of skin friction
elastic rebound in the pile should be measured and knowing the loads on top of pile, compute the
accurately by dial gauges or LVDTs as in 7.1.4. elastic compression of the pile corresponding to these
loads, by the following formula:
A.2 ANALYSIS OF RESULTS FOR FRICTIONAL
RESISTANCE
7
IS 2911 (Part 4) : 2013
\ ~ ,,
0-5 \
\
\
\\
\ \
E 1-0
\
\
\\
E \
\
Z \ ~
UJ
\
\
\
'\,
0 ,-5 \ ~,
«
0: \ SKIN FRICTION
(!) \
I \ ~\
en \
:J 2'0
(J)
LL \I
0 PARALLEL
\ Y
Z 2'5 \ \ II
0 \ \
(J)
(J) \ POINT \
UJ \ \ III AND. FINAL
RESISTANCE
0:: \ \
a:: 3-0
\ \
z: \ \
0
u \ \
U 3-5 . \-- PARALL EL ---\
I- \ ~
(/) \ \
«
...J
\ \
UJ \ \
4'0 \ \
\ \
\ \
\ \
4.5 \ \
\
\
\ ~
\ \
\
FIG. 2 ANALYSIS OF CYCLIC LOAD TEST DATA FOR SEPARATION OF SKIN FRICTION AND POINT RESISTANCE
8
IS 2911 (Part 4) : 2013
A = cross-sectional area of the pile. in cm2; and Sb = elastic settlement at any point 'b" on the
E = modulus of elasticity of the pile material, in straight line;
kgf/cm2• Sa = clastic settlement at any point 'a" on the
straight line;
(The value should normally be measured from an
exposed portion of pile stem by means of AT = change in applied load (T, -T,). in kgf;
compressorneter during the load test itself.) T, = applied load at the point 'b';
A.2.1.5 Obtain values of the elastic compression of the T, = applied load at the point 'a';
sub-grade by subtracting the elastic compression of the L = length of pile. in em;
pile from the total elastic recovery of pile and plot the A = cross-sectional area of pile, in cm2;
graph relating these new values to the corresponding E = elastic modulus of the material of the pile.
loads on pile top. \Vhen elastic compression of the
in kgf/cm2; and
subgrade works out negative. the negative value shall
be ignored un~il the value is positive. T = load on pile top. in kgf.
A.2.1.6 Repeat the procedures given in A.2.1.3 to A.2.2.2 Calculate the corrected settlement for different
obtain new values of skin friction. load increment by equation (2).
A -( AT
• AE
)L ... (I)
m=
AT S = mP+ ... (4)
where
where
m = constant:
A, = change in total elastic settlement of pile top P = point bearing. in kgf; and
(S, -S,l. in em; F = skin friction, in kgf.
ANNEXB
(Clause 7.4)
CRPTEST
D.I PROCEDURE LVDTs will be selected for conducting the test. With
continuous application of pressure on the pile top by
D.1.1 The load shall be measured by a load cell having operating of the jack. a person watches the rate of
sensitivity of at least I percent of the desired test load. settlement of the dial gaugelL VDT against a stop watch
If a pressure gauge is used, the same should be used held in his hand and directs the pump operator to pump
with a loading ram to give the desired sensitivity. The faster or slower or at the same rate as needed to
penetration (deflection) should be measured by means maintain the prescribed rate of settlement say at every
of dial gaugeslLVDTs held by a datum bar resting on 0.25 mm settlement, he gives an indication to take
immovable supports at a distance of at least 3 D (subject readings. Immediately, other persons record the
to a minimum of 1.5 m) away from the test pile edge pressure gauge readings and other dial gaugelLVDT
where D is defined in 7.1.5. One of the dial gaugesl
9
IS 2911 (Pari 4) : 2013
B.l.2 The jack should be operated to cause the pile to B-2 ULTIMATE LOAD CAPACITY
penetrate at uniform rate which may be controJled by
checking the time taken for smaIl increments of B.2.1 The curve of load versus penetration in the case
penetration and adjusting the pumping rate accordingly. of a predominantly friction pile will represent either a
Readings of time, penetration and load should be taken peak and the subsequent downward trend. or a peak
at sufficiently close intervals to give adequate control and then almost a straight line, as shown in Fig. 3A.
of the rate of penetration. A rate of penetration of about The peak load marked A in Fig. 3A will represent the
ultimate load capacity of pile.
0.75 mm per minute is suitable for predominantly
friction piles. For pre-dominantly end~bearing piles in B-2.2 In the case of predominantly end-bearing pile
sand or gravel, rate of penetration of 1.5 mm/min may the curve will be similar to that shown in Fig. 3D and
be used. The rate of penetration. if steady. may be half the ultimate load capacity may be taken as the load
or twice these values without significantly affecting corresponding to the penetration equal to 10 percent
the results. The test should be carried out for the of the diameter of the pile base.
100
A
~
r- A
80 I ~
,
/'
t tiO I
.•..•
,
o
<! 40
I
o
...J
/
20
IV
o 5 10 15 20 25 30
-
35
3A PREDOMINANTLY FRICTION PILES
10
IS 2911 (Part 4) : 2013
200
160
/'
~ -
t 120 ./
o••
/
«
o 80 /
..J /.
40
11
IS 29/1 (Part 4) : 2013
ANNEXC
(Foreword)
COMMITTEE COMPOSITION
Soil and Foundation Engineering Sectional CommiUee. CED 43
Organil.otion
In personal capacity (/88190, Prince Anwar Shah Road. RepresenJalive(s)
KOlkata 700045)
DR N. SOM(01airman)
A.P. Engineering Research Laborarories, Hytlerabad
SHIU P. SIVAKA/'IoTHAM
AFCONS Infrastructure Limited, Mumbai SHIU P. JOHN VICTOR (A/lemme)
SHRI V. S. KULK ..••
RNI
AIMIL Limited, New Delhi SHRI DH •.••
N•.••
NJAY ACHYln' BHJDe (A/rernale)
REPR~lmTAnVE
Association of Consulting Civil Engineers (India), Bangalore
Association of Piling Specialists (India), Mumbai REPRE.~F.NTAnVE
Bhara! Heavy Elcclricals Ltd, New Delhi SIIRf MADHllKAR LoOHAIA (A/lernale)
SHRf C. PuSHPAKARAN
CCOlral BoanJ. of Irrigarion & Power, New Delhi SURJ HEMANT MAUii:rrRA (A/lernale)
DIRECTOR
Central Building Research Institute, Roorkee
SHIU A. GHOSH
Central Public Works Dep:lrtmenl. New Delhi DEPtJTy DIREcTOR (TeD) (A/lemare)
Centrdl Soil & Materials Research Station, New Delhi SHRI VASANT G. H.'W•.••
NGI (A/lemale)
DR R. CHrmA (CRO)
Consulling Engineering Services (India) Pvt Ltd. New Delhi S"RI M..••
HAVIR DIXlT (A/lunare)
Engineer.in.Chief's Branch (MES), New Delhi PROF ASHOK KUMAR GlIPT •.••
SURI A. K. JAIN
12
IS 2911 (Part 4) : 2013
Organization
Rep~senralivt'(s)
Indian Instilute of Technology Delhi. New Delhi
DR G. V, RAMANA
DR J. T. SHAHU (A/lunale)
Indian Institute of Technology Kanpur. Kanpur
DR SARVESH CHANDRA
DR NIH..••R RANJAN P ..••
T'RA (A/lema/e)
Indian Institute of Technology Mumbai. Mumbai
SHRI G. VENK..••
T..••
CH..••LAM
Indian Instilute of Technology Roorkee, Roorkce
PROF M. N. VILADKAR
DR MAllENORA SINOH (A/lfOrnatf')
Indian Road Congress. New Delhi
SECRET..••RY GENERAL
DIRECTOR (n
(A/Ie maid
Indian Society of Earthquake Technology. UUaranchal
REPRESENTATIVE
ITD Cementation India Ltd. Kolkata
SHRI P. S. SENGtIPTA
SHIH M ..••NISH KVMAR (A/ternate)
Jadhavpur University, Kolkata .
PROF SI8APRIV..••MUKHElUEE
PROF RAMENOll BIKAS S ..••HlI (AlJertUlfe)
Kirloskar Pneumatic Company Limited, Pune
REPRF.SF.NTATIVE
Larsen and Toubro Limited, Chennai
DR K. S. R ..••MAKRISHN..••
SHRI JESlrOOSS ASIRV..•• TH..••M (A/tl"malt')
M.N. Dastur & Company (P) Limited, Kolkata
DR ASHurr O ..••SGUPT..••
Smu SUVENOU DEY (Alternale)
MIs Cengrs Geotechnica Pvt Ltd. New Delhi
SHRI S ..••NJ..••y GUPT..••
SHRI R ..•• vI SUNDARAM (A/tertUlte)
MECON Limited. Ranchi
SURI SH..••NKAR RAY
Ministry of Shipping, Road Transport and Highways, New Delhi
SHRI A. K. B ..••NERJEE
SHRI S ..••
nsH KUM..••R (Alternate)
Mumbai Port Trust. Mumbai
'. StiRIMATI R. S. HARDJK..••R
SHRI A. J. LOKHANDE (A/ternau)
Nagndi Consultants Pvt Limited. New Delhi
DR V. V. S. RAo
SHRI N. S ..••NTOSH R ..••
o (AltfOmale)
National Institute of Disaster Management. New Delhi
REPRESENT..••
TIVE
National Thennal Power Corporation Limited. Noida
DR D. N. NARESH
SHRI R. R. M ..••
URy..••(A/terM/e)
Pile Foundation Constructions Co (I) Pvt Ltd. Kolkata
SHRI B. P. GUH..••NIYOGI
t SHRI S. BHowMIK (AftuMte)
Research Designs and Standards Organization (RDSO). Ministry
of Railways, Lucknow REPR~r""TIVE
13
Bureau of Indian Standards
DIS is a statutory institution established under the Bureau of Indian Standards Acr, J 986 to promote
harmonious development of the activities of standardization, marking and quality certification of goods
and attending to connected matters in the country.
Copyright
BIS has the copyright of all its publications. No part of these publications may be reproduced in any form
without the prior permission in writing of DIS. This does not preclude the frce use, in the course of
implementing the standard, of necessary details, such as symbols and sizes, type or grade designations.
Enqoiries relating to copyright be addressed to the Director (Publications), BIS.
Amendments are issued to standards as the need arises on the basis of comments. Standards are also reviewed
periodically; a standard along with amendments is reaffirmed when such review indicates that no changes are
needed; if the review indicates that changes are needed, it is taken up for revision. Users of Indian Standards
should ascertain that they are in possession of the latest amendments or edition by referring to the latest issue of
'BIS Catalogue' and 'Standards: Monthly Additions'.
This Indian Standard has been developed from Doc No.: CED 43 (7678).
Teleplumes
Central Manak Bhavan, 9 Bahadur Shah Zafar Marg 2323 7617
NEW DEUIl 110002 { 23233841
Eastern 1114C.LT. Scheme VII M, V. L P. Road, Kankurgachi 23378499,23378561
KOLKATA 700054 { 23378626,23379120
Northern SCO 335-336, Sector 34-A, CHANDIGARH J 60022 2603843
{ 2609285
Southern C.IT. Campus, IV Cross Road, CHENNAI 600113 2254 1216.22541442
{ 22542519,22542315
\Vcstcrn Manakalaya, E9 MIDC, Marol, Andheri (East) { 28329295, 2832 7858
MUMBAl400093 28327891,28327892
Branches: AHMEDABAD. BANGALORE. BHOPAL. BHUBANESHWAR. COIMBATORE. DEHRADUN.
FARIDABAD. GHAZIABAD. GUWAHATI. HYDERABAD. JAIPUR. KANPUR. KOCH I.
LUCKNOW. NAGPUR. PARWANOO. PATNA. PUNE. RAJKOT. VISAKHAPATNAM.