Prerequisite:
1. Create Work center of 0006 Capacity category (Project Management) with Capacity category
should be 002 1234567
2. Link HR personnel’s (HR master data) in the Work center
3. Maintain KP26 rate for Activity type & Cost center (which was assigned in the Work center in the
costing tab)
4. Capacity requirement checkbox should be active at Network header level
Whenever we assign work & work center, Person assignment tab will get activated
Enter actual time against desired date to book time for this activity (lets us assume that he worked on
26th Oct 5 hours)
Actual cost gets posted for 5 hours’ time booking form CATS