STANDARD OPERATING
PROCEDURE
DIESEL ENGINE GENERATOR MAINTENANCE PROCEDURE
1. Document Records
Version
Date Description Prepared By Approved By
No.
Page | 1
SOP NO: ACE-SOP-GEN-007
DIESEL ENGINE GENERATOR MAINTENANCE PROCEDURE
2. Table of Contents
1. Document Records 1
2. Table of Contents 2
3. Introduction 3
4. Objective 3
6. Quality Control 3
9. Supplementary Information 7
Page | 2
SOP NO: ACE-SOP-GEN-007
DIESEL ENGINE GENERATOR MAINTENANCE PROCEDURE
3. Introduction
Regular proper generator system maintenance is necessary to ensure that to standby and generate
electricity in case of commercial electricity fails to supply the data center. This maintenance shall be
conducted by the authorized personnel for all major equipment and system such as main engine,
alternator system, automatic controller unit, lubrication system, fuel system, filtering system, batteries
system, piping system, cooling and exhaust system and power quality for operation and infrastructure
reliability.
4. Objective
The objective of this standard operating procedure is to describe the measures & ways, role &
responsibility, precautions of the proper preventative maintenance of equipment and systems. It is also
aim for safe operation, improvement of the performance of the system, avoid unexpected failures. Load
and unload tests shall be carried out in conjunction with the drawings, specification, catalogs and its
settings.
6. Quality control
1) The test shall be carried out in accordance with the following standards & regulations:
a) Myanmar National Building Code-2020
b) Myanmar Electricity Rules and Regulations
c) SS 535: 2018 Code of practice for installation, operation, maintenance, performance and
construction requirements of mains failure standby generating systems
d) Workplace Safety & Health Guideline
2) All materials and equipment shall be checked in accordance with specifications where possible.
3) All instruments shall be calibrated and within required accuracies
4) Instruments shall be used in accordance with manufacturers’ recommendations (to be
calibrated if necessary)
5) Any professional/ authorized personnel? (if required)
6) Lockout/ Tag out procedure (if necessary)
7) Drawings (if have)
Page | 3
SOP NO: ACE-SOP-GEN-007
DIESEL ENGINE GENERATOR MAINTENANCE PROCEDURE
General
a. Necessary clearances for permit to work (POW) and use of testing instruments shall be
sought prior to commencement of works.
b. Check drawing, specifications and its settings.
c. Carry out visual inspection before the testing conducted.
d. Stand by spare parts if need to replace (engine oil, coolant, fuel filter, oil filter, air filter & etc.)
Page | 4
SOP NO: ACE-SOP-GEN-007
DIESEL ENGINE GENERATOR MAINTENANCE PROCEDURE
Rented Generator
• Check capacity
• Must have standard electricity output.
• Must have automatic start up system (if necessary).
• Check place and spacing for cables termination.
• Check engine oil, fuel, coolant, filters.
• Check & record overall status.
Existing Generator
• Check and record cranking, driving and running
hours.
• Check for leakage and condition (engine oil, fuel &
coolant) and advise top-up if necessary.
• Also check fuel supply and return piping for leakage.
• Check alarm on display
• Check control & charging panel
3 Check Environmental • Check condition of fan belt and charging alternator 30
belt. Advise to change when necessary and adjust
tension when necessary.
• Check charging alternator.
• Check battery electrolyte level or indicator point.
• Check general condition of conduit connectors,
switches and wiring insulation and terminations.
• Check air filters and clean if necessary.
• Verify operation of all lamp, meters and control.
• Check diesel fuel level in diesel tank. Advise to top-
up when necessary.
• Report fuel if less than 80% of tank capacity.
• Lighting System
• Corrosion & Painting
• Check tightness of bolts and nuts at the electrical
termination.
• Simulate failure/alarm signals on equipment.
Rental Generator
• Test run (About 5-10 minutes, with no load) before
electrical termination to load side panel.
• Remove existing genset output cables form load side
panel.
• Electrical terminate rented genset’s output cables to
Testing & Cable
4. load side panel. 30
Termination
• Check tightness of bolts and nuts at the electrical
termination of rented genset’s output panel & load
side panel.
• Test run (About 5-10 minutes, with load) after
electrical termination to load side panel.
• Check all power connections for signs of overheating
and function.
• Check & record rented genset output parameter
Check & Record
5. a) RPM
Parameters
b) Output voltage
c) Frequency
6. Maintenance State • Turn off breaker from existing generator. 240
• Replace new coolant with suitable grade.
Page | 5
SOP NO: ACE-SOP-GEN-007
DIESEL ENGINE GENERATOR MAINTENANCE PROCEDURE
Page | 6
SOP NO: ACE-SOP-GEN-007
DIESEL ENGINE GENERATOR MAINTENANCE PROCEDURE
11 Cleaning State 20
• Overall cleaning after maintenance process.
9. Supplementary Information
Summary Man Power
No. Role No. of Persons (min.)
1. Maintenance In-charge 2
2. Maintenance Engineer 2
3. Skilled Workers 3
4. General Workers 1
Page | 7