mproperly treated and untreated runoff of conservation practices, and temporary
from exposed soils of a construction site and permanent cover, erosion and
can cause soil erosion and sedimentation problems can be managed.
sedimentation problems resulting in the
pollution of lakes, and other water bodies. What is required by the
This factsheet provides guidance on NPDES/SDS construction
stabilizing a construction site to protect the stormwater permit?
quality of our water resources.
The NPDES/SDS construction stormwater
The Erosion Process permit identifies slope and site stabilization
requirements that, if followed properly, can
Erosion is the natural process in which soil control erosion and sediment problems on a
and rock material is weathered and carried construction site.
away by wind, water or ice. On a • Prior to construction, areas not to be
construction site there are factors such as disturbed should be clearly flagged,
rainfall, climate, location, and soil type that staked or identified with signs and noted
influence erosion and may not be on the plan sets.
controllable. • All exposed areas must be stabilized no
later than 14 days after the construction
activity in that area is temporarily or
permanently completed.
• The normal wetted perimeter of any
temporary or permanent drainage ditch
must be stabilized within 200 feet from
the property edge.
• Drainage ditches and conveyance
systems must be inspected for evidence
of erosion and sediment deposition. All
deltas and sediment deposited must be
removed and the areas must be
restablized where sediment removal
Sediment entering a storm sewer inlet as a result of results in exposed soil.
construction related erosion.
• In order to maintain sheet flow and
Construction activities can increase erosion minimize rills and gullies, there shall be
by removing vegetation, disturbing soil and no unbroken slope lengths of greater
exposing sediment to the elements. Eroded than 75 feet for slopes with a grade of
soil quickly becomes a sedimentation 3:1 or steeper.
problem when wind and rain carry the soil
off the construction site and sediment is
deposited in our surface waters. Through
proper slope and site stabilization, the use
Minnesota Pollution Control Agency • 520 Lafayette Rd. N., St. Paul, MN 55155-4194 • www.pca.state.mn.us
651-296-6300 • 800-657-3864 • TTY 651-282-5332 or 800-657-3864 • Available in alternative formats
If the construction site is within 1 mile of a special or Any and all tools that you plan to implement on the site
impaired water, the following revised and additional should be included in the site’s SWPPP. When writing
requirements are listed in Appendix A of the permit: the SWPPP, include a description of the practices and
• All exposed areas must be stabilized no later than 7 integrate them into the time line of all construction
days after the construction activity in that area has activities. In addition, label the locations of the practices
temporarily or permanently ceased. on site plans and include detailed specifications for each
• An undisturbed buffer zone of not less than 100 feet practice. Including these elements into the SWPPP
from special waters shall be maintained at all times. before construction activity begins will aid in proper
For full details of the permit requirements, a copy of the planning for the site and ensure that the sediment and
NPDES/SDS construction stormwater permit is available erosion control techniques are implemented effectively
online: www.pca.state.mn.us/water/stormwater/stormwat and efficiently.
er-c.html.
What are conservation practices?
What can I do to keep my site stabilized and Conservation practices are treatments and management
prevent sediment and erosion problems? strategies used in construction planning to reduce soil
There are several ways to keep a site stabilized and limit erosion, shelter critical areas, create wildlife habitat, and
and control sediment and erosion: protect soil and water quality. Successful conservation
• Develop and implement a sound stormwater practices are integrated into the early stages of planning
pollution prevention plan (SWPPP) prior to the start for construction and implemented throughout the life of
of construction. a project. The following are a few examples of
• Utilize conservation practices. conservation practices that could be utilized to ensure
proper site and slope stabilization.
• Leave as much vegetation on site as possible and
reduce the overall disturbed area.
Construction site phasing is the development of a
• Prevent runoff from flowing across disturbed areas
construction work schedule that strategically coordinates
by diverting the flow to vegetated areas.
the timing of land disturbing activities to minimize soil
• Break up slope lengths and steepness.
exposure and plans for the timely installation of all
• Use sufficient sized temporary basins. erosion and sediment control practices. The goal of
• Protect stock piles. construction site phasing is to disturb a smaller portion
• Minimize the total area of a site exposed at once. of an overall site, substantially finish grading and other
• Minimize the length of time that soil is exposed. construction activities and achieve temporary or
• Temporarily or permanently stabilize disturbed soils permanent stabilization in the area before disturbing the
as quickly as possible after construction activity has next portion of the overall site. Soil exposure time is
stopped. decreased, soil and erosion control practices are more
manageable, and permit violations can be easily avoided.
The permanent stormwater treatment system must be in Mn/DOT Standard Specifications for
place and functioning. Drainage ditches and other Construction http://www.dot.state.mn.us/pre-
conveyance systems must have all collected sediment letting/spec/index.html
cleaned out and be stabilized with permanent cover. MPCA Protecting Water Quality in Urban Areas –
Temporary erosion and sediment control BMPs must be Manual – Chapter 6: Erosion Prevention and Sediment
removed. Control http://www.pca.state.mn.us/water/pubs/sw-
bmpmanual.html
MPCA Stormwater Construction Inspection Guide
http://www.pca.state.mn.us/publications/wq-strm2-
10.pdf