You are on page 1of 20

Appendix E: De-watering

Structural Design Report 2014-294, 19 Dawson Place. Page 15


Water levels:

Given the depths at which the water table appears and the proposed depth to which it is planned to
excavate the lower ground levels, it is likely that at worst case the construction will project 4m to 4.5m
into the water level over part of the site with much of the sub 2 floor being only 2m to 2.5m below the
current water table level.
Water table levels should continue to be monitored and measured to confirm the expected level at
which the water table will be encountered. Preliminary bore hole information and surrounding
boreholes have been used to establish the existing water table level but further monitoring will give a
more accurate view as the water movements around the site.

Dewatering Method Statement for The level of the water table can fluctuate seasonally and as such monitoring should be carried out at
different times over a number of months to ensure reliable information.

Lower Basement Construction Design:

The design principle is to remove water temporarily to allow for excavation of the soil below the water
table. The two proposed method vary slightly in how the achieve this.

Dewatering wells:
Here well points are bored in strategic points around the site using a cable percussion rig. The wells
Nature of Works: Dewatering method statement for the lower proposed basement level.
are the lined with a water permeable sleeve and submersible pumps are installed in each of the wells.

Introduction: The pumps are then adjusted and controlled specifically to suit the site soil conditions to locally lower
the water table levels to allow for excavation to progress. Adjustments can be made through the works
to allow for seasonal variations and movements in the water level. After completion of the excavation,
This report sets out the design philosophy for the proposed dewatering methods for construction below
the pumps are removed and the well heads capped to allow the water table to return to its previous
the water table. There are many tried and tested methods for allowing safe construction below the
level. The system is design, installed and monitored by an experience subcontractor and has been
water table, as consulting engineers we have successfully completed a number of jobs with below
successfully used on a project of similar size now nearing completion.
ground structures extending into the water table summaries of which are included in this report.
This report should be read in conjunction with the structural drawings which form part of the planning
Permeation grouting:
application. The aim of the method statement is to ensure safe and proper construction of the
This method requires the creation of a perimeter barrier around the site. The barrier consists of a grout
proposed works and ensure no adverse affects to existing or neighbouring structures.
which is pumped into the soil to infill the voids which allow water to travel through the soil. Again
strategic holes are bored around the perimeter of the site to allow for injection of the grout. The grout
While there are many different methods available, two are more commonly used for the proposed type
hardens to form a plug between the top of the water table and the underlying London clay and will
of construction, these will be discussed in detail and will both require party wall approval and input.
therefore minimise water ingress in to the construction of the permanent retaining works.
The two methods proposed are well dewatering or permeation grouting. Final decisions of which will
be employed will be based on cost and approvals but the principles by which both methods work are
Given the depths at which the water table appears and the proposed depth to which it is planned to
essentially the same.
excavate the sub levels, along with the temporary adjustment to the levels during construction it is safe
to conclude there will be no adverse affects by the development to the local hydrology of the area.
While detailed design of both these method require input from the sub-contractor performing the
installation, this method statement lays down the guide line of the proposed procedures.

Elite Designers Ltd, 12 Princeton Court, 55 Felsham Road, London SW15 1AZ Elite Designers Ltd, 12 Princeton Court, 55 Felsham Road, London SW15 1AZ
Tel 020 8785 4499 Fax 020 8785 4999 E info@elitedesigners.co.uk Tel 020 8785 4499 Fax 020 8785 4999 E info@elitedesigners.co.uk
Case Study 1: Case Study 2:

Project: 9 &10 Southwick Place Project: 70 Markham Sq

Dewatering Method: Deep wells. Dewatering Method: Permeation Grouting.

Summary: Summary:

Project consisted of a full basement storey below an existing lower ground floor. The water table was Project consisted of a sensitive basement install with difficult party wall requirements and construction

high with construction being carried out in a sandy gravel soil. Project dewatering ltd where into the water table. A scheme of permeation grouting was used to form a water impenetrable barrier

subcontracted to design and install a dewatering system to allow for excavation to be carried out around the site to allow for easy construction of the perimeter underpins. This job is currently under

safely. The job required deeper excavation than expected on this job and structure installation has construction with the permeation grouting appearing to have been successful. A design method

recently been completed successfully without issue. A design method statement for this job has been statement for this job has been included for information.

included for information.

Elite Designers Ltd, 12 Princeton Court, 55 Felsham Road, London SW15 1AZ Elite Designers Ltd, 12 Princeton Court, 55 Felsham Road, London SW15 1AZ
Tel 020 8785 4499 Fax 020 8785 4999 E info@elitedesigners.co.uk Tel 020 8785 4499 Fax 020 8785 4999 E info@elitedesigners.co.uk
Project Dewatering Limited
Groundwater Engineering



Method Statement Dewatering wells: 

RiskAssessment&MethodStatement
InstallationandCommissioning
DeepWellDewateringSystem

9&10SouthwickPlace
BasementExtension
StructuralLondonLimited
6thNovember2012


 Name Signature Date

PreparedBy MatthewRosson 06/11/2012

Approvedby DavidWright 06/11/2012

Elite Designers Ltd, 12 Princeton Court, 55 Felsham Road, London SW15 1AZ
Tel 020 8785 4499 Fax 020 8785 4999 E info@elitedesigners.co.uk

www.projectdewatering.co.uk  1 Tel:01473658807


Project Dewatering Limited Project Dewatering Limited
Groundwater Engineering Groundwater Engineering
Contents            

ITEM PAGE PROJECTOVERVIEW

1. ProjectOverview      3 Introduction            

i. Introduction      3
Wearepleasedtosubmitourmethodstatementfortheinstallation&commissioningof12nointernaldewatering
ii. SiteLocation&Contacts     3 wellsfortheaboveproject.Themainworksincludetheconstructionofabasementextensionattheabove
property.
iii. ScopeofWorks      4

iv. Programme      4 SiteLocation&Contacts          
v. GroundConditions     4 
SiteAddress: 9&10SouthwickPlace
vi. DewateringOutline     4    London
vii. Equipment&Materials     5      W22TN

viii. Personnel      5 Contact: PaulMcLaughlin–07538557329
ix. Health,Safety&Environment    5    ProjectManager
   
x. Health,Safety&Environment    6 
xi. RoutetoNearestHospital    7 LocationPlan:

xii. AttendancesfromMainContractor   8
2. Installation&CommissioningWorksProcedure   9
i. Introduction      9
ii. Access       9
iii. SetupofDrillingRig     9
iv. DrillingoftheWells     9
v. InstallationofWellMaterials    9
vi. DevelopmentofWells     10
vii. PumpandPipeworkInstallation    10
viii. Discharge      10
ix. ElectricalWorks      10
x. COSHHAssessments     10
xi. Decommissioning     10
3. SiteOperations       11
i. Maintenance      11
ii. Contact       11
4. Appendix       12
i. RiskAssessment   
ii. COSHHAssessmentSheets
   





www.projectdewatering.co.uk  2 Tel:01473658807 www.projectdewatering.co.uk  3 Tel:01473658807


Project Dewatering Limited Project Dewatering Limited
Groundwater Engineering Groundwater Engineering
ScopeofWorks            Equipment&Materials           

ThisMethodStatementcoversthefollowingworks: DrillingEquipment:  1No.Modularcablepercussiondrillingrig(maxitemweight550Kg)
      Temporarydrillingcasings&drillingtools
x Drillingbycablepercussiontechniques      1No.4WDvehicle
x Developmentbyairliftingtechniques 
x Commissioningthedeepwelldewateringsystem WellInstallationMaterials  140mmx125mmuPVCScreen,1.0mmslot
      140mmx125mmuPVCPlaincasing
RiskassessmentandrelevantCOSHHsheetsareincludedintheappendix.      FilterGravel
 
DevelopmentEquipment  125cfmcompressor
Programme            
     Airlineandairliftassembly

Weestimatethatthedeepwellswouldbedrilledandthesystemcommissionedwithin~2weekofmobilising,with
Personnel            
afurther~23daycontinuouspumpingtoachievemaximumdrawdown.
 DrillingPhase DrillRigOperator
GroundConditions                  DrillRigAssistant
 
Withlittlesiteinvestigationavailablewehaveassumedthestratumtobethatofaboreholelogfromourlibrary  CommissioningPhase  DewateringSupervisor
recordedinGloucesterSquare(~100maway)Ourassumptionsarebasedonthefollowsequenceofstratification:       DewateringLabourer
        
 TopLevel– Health,Safety&Environment          
 mBGL 
MADEGROUND 0.00 General
DensebrownverygravellySAND 3.00 x AllPersonneltoattendsiteinductionbeforecommencingworks.
x AllpersonnelwilladheretotherequirementsoftheCompanySafetyPolicydocumentandsitespecificrisk
DensebrownmediumtocourseSANDandfinetomediumGRAVEL 3.70 assessments.Suchriskassessmentswillbeundertakenandmadeknownpriortothecommencementof
StiffbrownfissuredsiltyCLAY 6.15 anywork,orrelatedwork,tothatdetailedinthisworksprocedure.
x Subsequentriskassessmentswillbeundertakenatintervalsdeterminedbyanychangeinworking
BoreholeComplete 10.00 practicesnecessaryforthecompletionofourcontract.
 x ProjectDewateringsupervisorwillberesponsibleforgivingamethodstatementbriefingtoallPDL
Groundwaterwasencounteredupto1.06mBGL operatives.Acopyofthisrecordwillberetainedandcanbesenttomaincontractorasrequested.
 x Ifapermittodigoperationisinplace,arelevant,uptodatepermittodigmustbeissuedbythemain
contractorandsignedbyallpersonnelinvolved.


DewateringOutline           
Training/Testing

x AlloperativesaretohaveaminimumCSCScertification.
    DeepWells     
x Alloperativestoundertakenmanualhandlingtraining.
No.ofBores:   12no.(vertical)  
x Supervisorstohavecompletedminimum2dayH&StrainingcoursesuchasCITBSiteSupervisorSafety
GroundLevel:   Front=99.65mAODRear=96.91mAOD   
TrainingScheme(SSSTS)orsimilar.
WellDepth:   maximum7.0m  
BoreSize:   Nominal250mm    x Allplantoperatorswillhaveappropriatetrainingandexperiencefortheplantbeingoperatedandhold
WelllinerSize:   Nominal125mmx140mmPVC   minimumredCPCScard.
Slottedwellscreen:  1.0mmslottedsection  x Allequipmentwillbecertifiedandtestedasappropriate.Acopyofcallcertificationwillbeissuedtosite
FilterPack:   1.7mmto4.2mmFilterSand  management
 
Deliveryofequipment

x Alldrillingequipmentwillbedeliveredbya4wheeldrivevehicleandtrailer

x Alldewateringequipmentwillbedeliveredinatransittypevehicle.

x Alldewateringmaterialswillbedeliveredby7.5Tcurtainsidedvehiclewithtaillift.

x Advancednoticetobegiventothemaincontractorpriortodeliveryarrivingatsite
 x Alldeliveriesshouldbemadetothemainsiteentrance
 
 
 

www.projectdewatering.co.uk  4 Tel:01473658807 www.projectdewatering.co.uk  5 Tel:01473658807


Project Dewatering Limited Project Dewatering Limited
Groundwater Engineering Groundwater Engineering
 RoutetoNearestHospital          
Health,Safety&Environment           
 Intheeventofanaccident,thenearestAccidentandEmergencyHospitalisasfollows:
FirstAid,EmergencePlanning,WelfareandPPE 
x Allpersonnelwillfollowthemaincontractorsemergencyprocedures LocalA&Eaddressandcontactdetails:
x Alloperativeswillbegivenaddressofworkinglocationincasetheyhavetocallemergencyservices. 
x Locationofmusterpointstobehighlightedduringsiteinduction.
x Locationofnearesthospitalcanbefoundbelow StMary'sHospital
x ThemaincontractorwillberesponsibleforprovidingsharedwelfarefacilitiestoallProjectdewatering PraedStreet
personnel. London
x All personnel will wear appropriate PPE at all times to comply with site safety requirements outlined GreaterLondon
withinthesiteinduction.Asaminimum,thiswillconsistofsafetygloves,safetyglasses,hardhat,high W21NY
visibilityjacket/vest&safetybootsasaminimum.
x SafetyGlovesaretobeappropriateforspecifictask. Tel:02033126666
x Ear defenders should be worn if working with plant and/or equipment with an operative dB rating of
80dB(A)orabove. 
 RoutetonearestA&EHospital:
Environment 
x Itisnotanticipatedthatcontaminatedgroundwillbeencounteredonthissite.However,ifweencounter
anymaterialshowingsignsofcontamination,includedabnormalcolouring,allpersonnelwillstopand
informsitemanagement.
x Usemostacousticallysilencedplantandequipmentavailable
x Controlwatergeneratedduringinstallationactivitiestoavoidcontaminatingwatercourses
x Useappropriatefiltersandfilterpacktobeinstalledtofacilitatethenonremovaloffines
x Ensuredischargewateriscleanandfreefromsuspendedsolids.
x Dirty/siltywatertobepassedthroughasettlementsystempriortodischarge
x Anysettlementsystemtobecheckedandmaintainedatregularintervals
x Ensureareasarounddischargelocationsarekeptclean




















 




www.projectdewatering.co.uk  6 Tel:01473658807 www.projectdewatering.co.uk  7 Tel:01473658807


Project Dewatering Limited Project Dewatering Limited
Groundwater Engineering Groundwater Engineering
 INSTALLATION&COMMISSIONINGWORKSPROCEDURE
AttendancesRequiredfrommainContractor         Introduction            

Wehavenotallowedforthefollowingitemswithinourproposals.WewouldrequiretheMainContractorto Wellswillbedrilledfromexistinggroundlevelsat12nolocationsaroundtheinternalperimeterofthe12mx25m
providethefollowingitemsfreeofchargetoProjectDewateringLtd,insuchmannerastonotdelayourworks.If basementareabycablepercussionmethodstoamaximumdepthof7.0m(or1.0mintoClay),terminatingwitha
requested,wewouldbewillingtoadjustourquotationshouldyoubeunabletoprovidesuchassistances. 250mmdiameterbore.

x Suitablecranageandassistance’sfortheinstallationandanysubsequentremovalofboreholepumpsand Access             
anyotherequipmentincludingthemobilisingofdrillingrigwithinthelowerbasementarearequired
duringtheworks–withaccessviafrontusingblock&tackle AccesswillbeoffSouthwickPlaceviaelectricgatedareaattherearofthepropert.Accessintothelower
 basementareasitetobepreparedbymaincontractor.Themodulardrillingrigwillbelowereddownintothe
x Adequatedisposalpointforwatergenerated basementareamanually.
 
x Removalofspoilandordrillingarisingsfromalldrillingpositions. TheMainContractoriscarryoutsitepreparationworks,andensureeachlocationisfreeofburiedservices,setout
 thelocationofeachwellandprovidesuitableclearandfirmunobstructed,accessforthedrillingrig,plusadequate
x Setoutthelocationofeachwell,breakoutandremoveanyhardstanding,hardlayersorunderground headroomforthedrillingrigandaflatstableareaateachlocation.TheMainContractorwillremove/breakoutall
servicesthatmayimpedeorendangertheoperationstoenableinstallationworktoproceed. tarmac,concreteandotherhardsuperficiallayersasnecessary.Ifapermittodigsystemisinoperation,apermit
 mustbeissuedbytheMainContractorpriortodrilling.Storageofdrillingandwellmaterialsistobeagreedwith
x Providesuitablefirmandunobstructeddriveaccessintothemewsforwheeledvehicleswithadequate sitemanagement.
headroomfordrillingplantinthebasementarea,plusadequatedrillingplatforms.Provideminimum0.8m
wideaccessand2.5mclearheightoverdrillinglocation. SetupofDrillRig           
 
x Obtainallpermissions,permits,sanctionsandconsentsnecessarytoallowtheabstractionrecharge Therighasa2.5mheightandhastheabilitytobedismantledandsetupoverthewelllocation.Componentsare
anddischargeofgroundwateratthesite,andpayforanychargeswhichmaybeincurred,to manuallyhandledandhaveamaximumwidthof0.8m.Thedrillrigwillbelocatedoverthemarkedwelllocation
enableworktoproceed. andwillbeerectedtoformthetripodarrangement.Thedrillerwillbeinstructedontherequireddepthofdrilling
 forthewellandgivenanindicationonthelevelsofthemainstratatobedrilledthrough,basedondetailsfromany
x Provisionofsharedwelfarefacilitiesandadequateandsecurespaceforstorageofthecompany’s siteinvestigationboreholelogavailable.Themaincontractorwillremove/setupallhoardingsandanyearth
plant,materials,equipmentandofficesetc,includingmainspowerandwaterservicestoanyonsite platforms,toallowrigtosetuponwellposition.Anextractorfanwillbesetuptoremoveexhaustfumesfrom
officesoraccommodation,inaccordancewithcurrentHealth&Safetylegislation withinthebasementareaduringdrilling.

x Provide240V/32AMPpowersupplytorunboreholepumps(1no32AMPisolatedsockets) DrillingoftheWells           
 
x Provide110cfmsingletoolcompressor~5days Thewellswillbedrilledbycablepercussionmethodsfromexistinggroundlevel.Theboreisadvancedbyusing
 drillingtoolssuspendedfromtherigwinchrope.Cleanwatermaybeaddedtotheboreduringdrillingasrequired
x Providewatersupplyfordrillingoperations toaidlubrication.Temporarycasingswillbeusedtosupportunstablestrata.Ifhardstrata,obstructionsorwhen
 withinthestratachisellingmayberequiredtoadvancethebore.
x Carryoutreinstatementworkuponcompletionincludingbackfillingorpluggingofboreholes 
 Shoulddrillingofawellusingeithertechniquebeatacriticalstageattheendofnormalworkinghours,itmaybe
 necessary,duetounstablegroundconditions,tocontinueworkuntilthewellscreenandgravelpackareinstalled.
Oncompletionboreholespoilandarisingswillbedepositedadjacenttothewelllocation.TheMainContractorwill
 removeanddisposeofthismaterialasrequired.Asignedboreholerecord/logwillbemadeanissuedtothe
 engineer.

 InstallationofWellMaterials         
 Uponcompletionofthebore,PDLwillbeadvisedofstrata'sandlevelsencountedbythedrillerswhowill
subsequentlybeadvisedofwellcompletiondetails.Completionwillconsistofatreadedplugatthebase,followed

byacombinationofslottedandcasedsectionstosuitobservationsextendingtosurfacelevel.A1.7mmto4.2mm
 silicasandfilterpackwillbeinstalledbygravityfeedaroundtheannulusoftheslottedsectiontosurface.Asthe
filterpackisaddedregulardipsoftheamountoffilterfedwillbetakentoensurebridgingofthegravelisnot

occurring.Asthefilterpackisaddedthetemporarydrillingcasingswillberemovedsectionbysection.The
 objectivesaretoprovidegroundstability,reducetheriskofremovingfinesuponpumpingandallowafreeflowing
conduit.


 

www.projectdewatering.co.uk  8 Tel:01473658807 www.projectdewatering.co.uk  9 Tel:01473658807


Project Dewatering Limited Project Dewatering Limited
Groundwater Engineering Groundwater Engineering
 
DevelopmentofWells           
 
Followingwelldrillingandinstallationofthewelllinerandgravelpack,welldevelopmentprocedureswill SITEOPERATIONS
commence.Theairliftwillbeattachedtotheairlineandplaceddownthewell,approximately1–2mfromthebase. 
Theairlinewillbecoupledtoa110cfmcompressor.Thewellswillthenbepumpedbyairliftforaminimumperiod Maintenance            
of1houroruntilthedischargewaterisfreeofdrillingmudand/orfines.Theairlinewillthenbeliftedin1.0m 
intervalsandpumpedonforatleast15minutesateachleveltothetopofthescreenedsectionofthewell.Initial APDLoperativewillbeonsitethroughoutthecommissionperiod.Wewillundertakeroutinethreeweekly
developmentwillonlyceasewhenfinesremovalisnegligible. maintenanceandoperationvisits.

Pump&PipeworkInstallation           Contact            

Individual(upto0.75kW)240Vsubmersibleboreholepumpsarecoupledto50mmMDPEriserpipe.Theriseris Atalltimesa24hourcontactservicewillbeinplace,intheeventofanyproblems.Wewillrespondimmediately
connectedtoawellheadandsecuredbyaclamp.Thewellheadconsistsofa90degreebendandcontrolvalve,this andcanbecontactedwiththefollowingtelephonenumbers:
inturniscoupledtoa2”flexiblehosethatwillextendfromeachwellheadlocationanteeintoa2”collectionmain 
whichwillbesuspendedabovegroundlevelandpositionedaroundthebasementperimeter. DavidWright:  Mobile  07747626407
     Office  01473658807
Discharge             
 MathewRosson  Mobile  07747806446
Thedischargelinewillterminateattheexistingmanholelocatedatthefrontofthepropertyandatgroundlevel. 
 
ElectricalWorks          
The12nopumpswillplugintoupto2no.6waypumpcontrolpanels.Regarding240V(singlephase)powerand
cabling;cablesfromeachpumpwillbe4coreSWAcontainedwithinathermoplasticcoatingtoBS6346.Pump
cableswillterminatewitha16Amp4pin+earthplug,whicharesubsequentlypluggedintosimilarlysizedsocket
outletsintoindividualisolatorswitchlocatedatexistinggroundlevel.Wehaveassumedpumpcableswillbetaped 
tothedischargehosefromthewelltothesurface.TheMDUpumpcontrolpanelswillgovernupto6noindividual
pumpsandanRCDandRCBprotecteachMDUchannel.Italsohasavisualandaudiblealarmsystem,whichis
triggeredbyanypumpingfailure.AllequipmentexposedtotheelementswillbeatleastIP67rated.Allsurface
cablingwillfollowtherouteofthecollectionmainandwillbeidentifiedbymeanofhivisibilitymarkingtape.

WewillrequireStructuralLondontoprovideuswith2no240V32AMP3pinisolatedsockets(IP67)topowerthe
dewateringsystem.

COSHHAssessments           

COSHHAssessmentareattachedforthefollowingmaterials:

x DieselOil
x EngineOil

Decommissioning          

Adequateaccessneedstobemadeforthesaferemovalofalldewateringpumpsandequipmentuponcompletion
ofthedewateringworks.Wewillrequirethemaincontractortoprovideadequatecranagefortheloadingofall
dewateringequipmentontoourtransportattheendofthecontract.









www.projectdewatering.co.uk  10 Tel:01473658807 www.projectdewatering.co.uk  11 Tel:01473658807


ProjectDewateringLimited
GroundwaterEngineering
RiskAssessment
Project
 9&10SouthwickPlace–BasementExtension JobNo: P00438 Date:6th November2012
Client StructuralLondonLimited DocumentRefNo: RAMS/P00438 Distribution:
Location 9&10SouthwickPlace,W22TN Assessor: MatthewRosson PDLStaff
Discipline DeepWells CheckedBy: DavidWright MainContractorStaff

Residual
Potentialfor Action
Whomay Potential
No. Hazards InitialRisk Harm Required ControlMeasures
beharmed forHarm
Yes/No
H M L H M L
General
1 ManualHandling Site Longtermhealthrisk  M  Yes Usemechanicalliftingwherepossible.Onlyitemsweighingupto25Kgtobelifted   L
Personnel manually,heavieritemsshouldbeliftedbymorethanoneoperativewitheach
operativeliftingupto25Kg.Correctliftingtechniquestobeadopted.Assessthe
loadpriortolift.Checkwalkingrouteisclear.Usecorrectgloves.
2 Workclasheswiththatofmain Site Vehicle/pedestrian H   Yes Attendsitespecificinduction.Ensurethatallworkactivitiesarefullycoordinated   L
contractor Personnel collision withsitemanagementandnotifymaincontractorimmediatelyofanyprogramme
change.
Slip,tripsandfalls
1 PoorHouseKeeping Site Slips,tripsandfalls. H   Yes HouseKeepingtobecontinuallymonitoredtoensuresafeandclear   L
Personnel Personalinjury access/egress.Safetyfootweartobeingoodworkingorder.Workplacetobe
keptingoodorder.Hosesandotherequipmenttobekeptinasinglestoragearea
untilrequired.
Excavations
1 Openexcavations Site Seriouspersonal  M  Yes Ensureexcavationhaveedgeprotection.Donotclimbontoedgeprotection.   L
Personnel injury Makeothersworkingbelowawareofyourpresenceandcommunicatewhen
workingoverthem.Useexclusionzonesifnecessary.
2 Buriedservices Site Deathorserious  M  Yes Ensurecorrectpermittodigisinplace.CommunicatewithMaincontractor,   L
Personnel personalinjury ensureCATscancarriedoutandexistingservicedrawingreviewed.Excavatetrial
pitifnecessary
UnloadingofEquipment
1 Plantmovement Site Overturningof  M  Yes InspectallliftingequipmentandensureSWLiscorrect.Onlyuseapproved   L
Personnel vehicles,Vehicle/ cranage.WearcorrectPPE.Useexclusionzoneifnecessary.Useapprovedblock
pedestriancollision andtackleforloweringrigintolowerbasement
2 Unstableloads/fallsof Site Seriouspersonal  M  Yes InspectallliftingequipmentandensureSWLiscorrect.Usecorrectlifting   L
materialsandequipment Personnel injury techniques.Unloadfromandontostableground.Useexclusionzoneduringoff
loadingifnecessary.Ensurematerialsarepackagedandslingcorrectlybeforelift
3 TrappedLimbsorextremities Site Crushinjury  M  Yes WearcorrectPPE.Onlytrainedpersonneltoslingandunload.Useexclusionzone   L
Personnel ifnecessary

1


ProjectDewateringLimited
GroundwaterEngineering
RiskAssessment
Project
 9&10SouthwickPlace–BasementExtension JobNo: P00438 Date:6th November2012
Client
 StructuralLondonLimited DocumentRefNo: RAMS/P00438 Distribution:
Location
 9&10SouthwickPlace,W22TN Assessor: MatthewRosson PDLStaff
Discipline DeepWells CheckedBy: DavidWright MainContractorStaff

SettingupforDrilling
1 Muscularskeletalinjuries Site PersonalInjury H   Yes Usemechanicalliftingwherepossible.Onlyitemsweighingupto25Kgtobelifted   L
Personnel manually,heavieritemsshouldbeliftedbymorethanoneoperativewitheach
operativeliftingupto25Kg.Correctliftingtechniquestobeadopted.Assess
workingenvironmentandroutepriortolift.Usecorrectgloves.
Drilling
1 Undergroundservices Site SeriousPersonal  M  Yes Maincontractortolocateandidentifyservices.Ensurecorrectpermittodigisin   L
Personnel injuryordeath placeandsignedbyrelevantpersons.CommunicatewithMaincontractor,ensure
CATscancarriedoutbymaincontractorandexistingservicedrawingreviewed.
Excavatetrialpitifnecessary.
2 Fallsofequipment Site SeriousPersonal  M  Yes Inspectallliftingequipmentatstartofeachshiftandensureallrelevant   L
Personnel Injury equipmentistestedandcertified.Standrigonstableground.Usecorrectlifting
techniques.Onlytrainedpersonstousedrillingequipment.Usesecondman.
WearcorrectPPE.
3 Openexcavation Site SeriousPersonal H   Yes Fenceoffworkingareaifnecessaryandensureonlydrillingpersonnelwithin   L
Personnel Injury workingarea.Ensureboreholesarebackfilledcorrectly.Donotleaveexcavation
openovernight.
Commissioningthesystem
1 Electricshock Site SeriousPersonal H   Yes Onlytrainedandcompetentpersontoinstallthepumps.Qualifiedelectricianto   L
Personnel Injury/Death checksystembeforeenergizing.Usewarningsignsonelectricalcontrolpanels
andlockoffsystemwhennotinuse.Allelectricalequipmenttobestored
undercoveruntilinstalled.
2 Highpressurehoses Site SeriousPersonal  M  Yes Checkairlinesfordefectsbeforeuse.Usewhipchecksatall   L
Personnel Injury couplings/connections.Appropriatecaretobetakenwhenusingcompressorand
airlinesfordevelopingthewells.Separatehosesfromothersiteactivitiesto
reduceriskofdamage.
3 Muscularskeletalinjuries Site PersonalInjury  M  Yes Usemechanicalliftingwherepossible.Onlyitemsweighingupto25Kgtobelifted   L
Personnel manually,heavieritemsshouldbeliftedbymorethanoneoperativewitheach
operativeliftingupto25Kg.Correctliftingtechniquestobeadopted.Assess
workingenvironmentandroutepriortolift.Usecorrectgloves.




2

ProjectDewateringLimited
GroundwaterEngineering
RiskAssessment
Project 9&10SouthwickPlace–BasementExtension JobNo: P00438 Date:6th November2012
Client StructuralLondonLimited DocumentRefNo: RAMS/P00438 Distribution:
Location 9&10SouthwickPlace,W22TN Assessor: MatthewRosson PDLStaff
Discipline DeepWells CheckedBy: DavidWright MainContractorStaff

RunningtheSystem
1 HighpressurePipelines Site PersonalInjury Yes Checkpipeworkfordefectsbeforeuse.Ensurecouplingsaresecurelyfastened.   L
 Personnel Separatepipelinefromothersiteactivities.
2 Weilsdisease Site Longtermhealth Yes WearPPE.Donotwashingroundwater.Cleanhandsandarms   L
Personnel impactordeath thoroughlyinhotwaterbeforeeating,drinkingorsmoking.ContactGPif
flusymptomsarise.
3 Hydrocarbons. Site Longtermhealth Yes WearPPE.Avoidskincontactwithfuelsandoils.Disposeofusedoil/fuel   L
Personnel impact filterscorrectly.
Maintenance
1 Fallsintoexcavations Site SeriousPersonal M Yes Onlyusedesignatedwalkways.Keepwalkwaysclear.Ensurefencedoff   L
Personnel injuryordeath areasaremaintained.
2 Tripsandfalls. Site SeriousPersonal M Yes Onlyusedesignatedwalkways.Keepwalkwaysclear.Maintainhouse   L
Personnel Injury keeping.
ENVIRONMENTAL
1 SiltPollution All Contaminationof H Yes Ensuredischargedgroundwaterisclearandfreefromsuspendedsolids.Ifin   L
localwatercourses doubt,useImoffconetomeasuresedimentcontent.Useappropriatesiltcontrol
systems.Cleanandmaintainsettlementsystems.
2 Noise All Hearingdamageto H Yes Operativestouseeardefendersduringdrillingoperations.Exclusionzonetobe   L
workers,nuisance setupifnecessary.Acousticfencingtobeerectedbymaincontractorif
noise necessary.
3 RefuellingofPlant Site Contaminationof M Yes Switchoffequipmentwhennotinuse.Useplantnappywhenrefuelling,and   L
Personnel groundandwater retainspillkitonsitetobeaccessibleatalltimes.Fuelstobestoredinappropriate
courses bundedcontainersandonlybroughtontositewhenrequired.
4 Contaminateddrilling Site Healthimpact M Yes Visualchecktoallmaterialbroughttosurface.Anyabnormaldiscolourationtobe   L
material personnel notifiedtositemanagement,
Decommissioning
1 Fallsintoexcavations Site Seriouspersonnel M Yes Onlyusedesignatedwalkways.Keepwalkwaysclear.Ensurefencedoff   L
Personnel injuryordeath areasaremaintained.
2 Muscularskeletalinjuries Site PersonalInjury M Yes Usemechanicalliftingwherepossible.Onlyitemsweighingupto25Kgtobelifted   L
Personnel manually.Correctliftingtechniquestobeadopted.Assessworkingenvironment
androutepriortolift.Usecorrectgloves.

3


Name

Issue No. 2
refuelling

Minor
+D]DUGV

6HYHULW\

Form Ref: HSF 22


Diesel fuel oil

&RQWUROVXVHG

Date of Issue April 2011


8VHRIFRQWUROV
Cannot eliminate use
 $GPLQLVWUDWLYH
'HSDUWPHQWVarious

N/A

working with this substance.


WELmg/m3

Occasional
3UREDELOLW\
Flammable (flash point > 560 C)
6XEVWDQFHVHQFRXQWHUHG

 (OLPLQDWLRQ6XEVWLWXWLRQ

:RUNSODFHDLUPRQLWRULQJN/a

sucking the liquid up a tube by mouth.


$FWLYLW\ Refuelling work equipment

smoking during refuelling etc operations.


care to avoid skin contact with the product.

,QIRUPDWLRQLQVWUXFWLRQDQGWUDLQLQJ
N/A

dermatitis, erythema, oil acne and oil folliculitis.

The appropriate PPE is to be worn at all times when

washed after use; Diesel must never be siphoned by

Diesel not to be used as a solvent or cleaning agent.


No eating, drinking or smoking whilst hands are dirty.

No eating during refuelling etc operations; Hands etc to be


No special handling precautions are necessary other than

1/2
SOP - Proper fuel containers and funnels to be used when

Medium
Respirable (mg/m3) 

Information on hazards to be provided to all diesel users; No


Provision of adequate hygiene facilities (water, soap, towels)
1$

)UHTXHQF\RI([SRVXUH
Can readily explode in the presence of electrostatic charges generated.

)LUVW$LG
Classified as a Category 3 carcinogen and harmful, owing to the aspiration hazard.
5HICA01 – Gas Oil

$FWLRQUHTXLUHG
 (QJLQHHULQJ
([SRVXUHV Normally low; may be higher if poor refilling practices are used.

Managers / Supervisors)
$FWLRQUHTXLUHGNone

Low
0DLQWHQDQFHRIFRQWUROV
to mists may cause a chronic inflammatory reaction of the lungs and a form of pulmonary fibrosis.

before reuse. Soap to be provided

([SRVXUH/HYHOV
inflammation and damage which in severe cases may be fatal – GRQRW induce vomiting if swallowed.

suitable eye protection should be used.


 3HUVRQDO3URWHFWLYHHTXLSPHQW

Wash skin thoroughly with soap and water


when refuelling / filling up storage containers.
Prolonged or repeated liquid, mist, and vapour contact with skin can lead to defatting of the skin, drying, cracking,

ASPIRATION HAZARD! This material can enter the lungs during swallowing or vomiting and may cause acute lung
5HIHUHQFH
352-(&7'(:$7(5,1*/7'&26++$66(660(17

MSDS- Gas Oil

If there is a risk of splashing whilst handling the liquid,


'LHVHOIXHORLO

Wash eyes thoroughly with copious quantities of water

/2:5,6.
$VVHVVPHQW
Contaminated clothing should be removed and laundered
Exposure to high vapour concentrations can lead to nausea, headache and dizziness. Excessive and prolonged exposure

Since skin contact must be avoided, vinyl gloves to be worn

Information on hazards to be provided to all users (action by


352-(&7'(:$7(5,1*/7'&26++$66(660(17 352-(&7'(:$7(5,1*/7'&26++$66(660(17

'HSDUWPHQWVarious 5HICA05 – Engine Oil (QJLQH2LOV


)LUVW$LG $FFLGHQWDO5HOHDVH0HDVXUHV $FWLYLW\ Replacing oils during maintenance
 
(\HV Contain and recover spilled material using sand or other ([SRVXUHV Low if funnels and correct containers are used.
Wash eye thoroughly with copious quantities of water, suitable inert absorbent material. It is advised that stocks of
6XEVWDQFHVHQFRXQWHUHG 5HI
ensuring eyelids are held open. Obtain medical advice if any suitable absorbent material should be held in quantities
Name WELmg/m3 STWEL(mg/m3) Respirable (mg/m3) 
pain or redness develops or persists. sufficient to deal with any spillage which may be reasonably
6NLQ anticipated.
Various Engine oils None None None MSDS-Engine Oil
Wash skin thoroughly with soap and water as soon as Spilled material may make surfaces slippery. +D]DUGV
reasonably practicable. Remove heavily contaminated Protect drains from potential spills to minimize Health effects
clothing and wash underlying skin. contamination. Do not wash product into drainage system. i. Eye Contact: May cause eye irritation.
,QJHVWLRQ In the case of large spills contact the appropriate authorities. ii. Skin Contact: May cause skin irritation.
If contamination of the mouth occurs, wash out thoroughly If spillage occurs call the Environment Agency Hotline on iii. Inhalation: May cause irritation of the respiratory tract.
with water. Except as a deliberate act, the ingestion of large 0800 807060 (24 hours a day, 7 days a week).
amounts of product is unlikely. If it should occur, do not In the case of spillage on water, prevent the spread of iv. Ingestion: Harmful if swallowed. May cause nausea, vomiting, diarrhoea, or abdominal pain.
induce vomiting; obtain medical advice. product by the use of suitable barrier equipment. Recover
IQKDODWLRQ product from the surface. Protect environmentally sensitive
If inhalation of mists, fumes or vapour causes irritation to the areas and water supplies.
nose or throat, or coughing, remove to fresh air. If symptoms  
persist obtain medical advice. &RQWUROVXVHG
  (OLPLQDWLRQ6XEVWLWXWLRQ  (QJLQHHULQJ
Assessor Ian Turnbull Date: 04.04.2011 Cannot eliminate its use N/A
Signature:
Review: April 2012  $GPLQLVWUDWLYH  3HUVRQDO3URWHFWLYH(TXLSPHQW
Funnels to be used when filling; Eye: Wear approved safety glasses or goggles with
Provision of adequate hygiene facilities; unperforated sideshields.
No eating, drinking or smoking whilst hands are dirty Skin: Wear chemically impervious gloves. Wear long
sleeves and long pants.
Other: An emergency eyewash station should be
available in case of accidental eye contact.
8VHRIFRQWUROV 0DLQWHQDQFHRIFRQWUROV
The appropriate PPE is to be worn at all times when working with PPE is to be checked to ensure it is fit for purpose by
this substance. operatives before use.
 PPE is to be checked during site audits by HSEQ
Manager
:RUNSODFHDLUPRQLWRULQ $FWLRQUHTXLUHG

,QIRUPDWLRQLQVWUXFWLRQDQGWUDLQLQJ $FWLRQUHTXLUHG
All users to be made aware what to do if exposed to Engine oil Managers to inform all users

6HYHULW\ 3UREDELOLW\ )UHTXHQF\RI([SRVXUH ([SRVXUH/HYHOV $VVHVVPHQW

Negligible Possible Low Low 9HU\/RZ5LVN

&RPPHQWV


Form Ref: HSF 22 Form Ref: HSF 22


Issue No. 2 Issue No. 2
Date of Issue April 2011 2/2 Date of Issue April 2011 1/2
352-(&7'(:$7(5,1*/7'&26++$66(660(17 352-(&7'(:$7(5,1*/7'&26++$66(660(17

)LUVW$LG $FFLGHQWDO5HOHDVH0HDVXUHV 'HSDUWPHQWVarious 5HICA05 - %HQWRQLWH (clay) 


  $FWLYLW\ On all drilling sites, various applications but generally used as a borehole sealant.
(\HV Contain and recover spilled material using sand or other
Wash eye thoroughly with copious quantities of water, suitable inert absorbent material. It is advised that stocks of ([SRVXUHV Low if used correctly
ensuring eyelids are held open. Obtain medical advice if any suitable absorbent material should be held in quantities 6XEVWDQFHVHQFRXQWHUHG 5HI
pain or redness develops or persists. sufficient to deal with any spillage which may be reasonably Name WELmg/m3 STWEL(mg/m3) Respirable (mg/m3) 
6NLQ anticipated. %HQWRQLWH None None None MSDS- %HQWRQLWH
Wash skin thoroughly with soap and water as soon as Spilled material may make surfaces slippery.
+D]DUGV
reasonably practicable. Remove heavily contaminated Protect drains from potential spills to minimize
clothing and wash underlying skin. contamination. Do not wash product into drainage system. Health effects
,QJHVWLRQ In the case of large spills contact the appropriate authorities. 1. (\H&RQWDFW: May cause eye irritation.
If contamination of the mouth occurs, wash out thoroughly If spillage occurs call the Environment Agency Hotline on 2. 6NLQ&RQWDFW: May cause skin irritation.
with water. Except as a deliberate act, the ingestion of large 0800 807060 (24 hours a day, 7 days a week). 3. ,QKDODWLRQ The product, as shipped, does not pose any inhalation health hazard because it contains essentially
amounts of product is unlikely. If it should occur, do not In the case of spillage on water, prevent the spread of no particles in the respirable size range
induce vomiting; obtain medical advice. product by the use of suitable barrier equipment. Recover
,QKDODWLRQ product from the surface. Protect environmentally sensitive  ,QJHVWLRQ No adverse health effects are expected from swallowing.
If inhalation of mists, fumes or vapour causes irritation to the areas and water supplies.
nose or throat, or coughing, remove to fresh air. If symptoms
persist obtain medical advice.  
 &RQWUROVXVHG
  (OLPLQDWLRQ6XEVWLWXWLRQ  (QJLQHHULQJ
Assessor Ian Turnbull Date: 04.04.2011 Always look to use the best option N/a
Signature:  $GPLQLVWUDWLYH  3HUVRQDO3URWHFWLYH(TXLSPHQW
Review: April 2012
Provision of adequate hygiene facilities (water, soap, towels) Nitrile disposable / PVC gloves
No eating, drinking or smoking whilst hands are dirty
Use overalls at all times

8VHRIFRQWUROV 0DLQWHQDQFHRIFRQWUROV
The appropriate PPE is to be worn at all times when working with PPE is to be checked to ensure it is fit for purpose by
this substance. operatives before use.

PPE is to be checked during site audits by HSEQ


Manager
:RUNSODFHDLUPRQLWRULQJ $FWLRQUHTXLUHG
N/A N/A

,QIRUPDWLRQLQVWUXFWLRQDQGWUDLQLQJ $FWLRQUHTXLUHG
All users to be made aware what to do if exposed to %HQWRQLWH Managers to inform all users

6HYHULW\ 3UREDELOLW\ )UHTXHQF\RI([SRVXUH ([SRVXUH/HYHOV $VVHVVPHQW

Negligible Possible Low Low 9HU\/RZ5LVN

&RPPHQWV


Form Ref: HSF 22 Form Ref: HSF 22


Issue No. 2 Issue No. 2
Date of Issue April 2011 2/2 Date of Issue April 2011 1/2
352-(&7'(:$7(5,1*/7'&26++$66(660(17
Project Dewatering Limited
GroundwaterEngineering
)LUVW$LG $FFLGHQWDO5HOHDVH0HDVXUHV 
 Environmental care
6NLQ Avoid dusting
Wash with water and soap Personnel care 
(\HV ----
Flush with water for at least five minutes Cleaning methods
,QJHVWLRQ Scoop up spilled product, flush rest with water.
Flush mouth with water BECOMES SLIPPERY WHEN WET MethodStatementBriefingRecord
,QKDODWLRQ 
Rest. Fresh air. If symptoms develop seek medical advice
 9&10SouthwickPlace,W22TN
Assessor Ian Turnbull Date: 04.04.2011
Signature:
Review: April 2012

MethodStatementreferencenumber:RAMS/P00438

Briefingdeliveredby:

Position:

Date:

Ihavebeenbriefedandfullyunderstoodtheworksprocedureandwillcomplywiththe
specifiedrequirementsandcontrolmeasuresfortheaboveproject:

Name Signature Date


  
  
  
  
  
  
  
  
  


Form Ref: HSF 22


Issue No. 2
Date of Issue April 2011 2/2
&RQWHQWV

,QWURGXFWLRQ

0HWKRG
Method Statement Permeation Grouting
%RUHKROH 'ULOOLQJ

*URXW ,QMHFWLRQ

*URXWHG %ORFN

6RGLXP 6LOLFDWH *URXW

6HFWLRQ 'UDZLQJ

3HUPHDWLRQ *URXWLQJ %URFKXUH

 .HQVLQJWRQ 3DODFH *DUGHQV &DVH +LVWRU\

 *LOVWRQ 5RDG &DVH +LVWRU\

&26++ $VVHVVPHQW

Elite Designers Ltd, 12 Princeton Court, 55 Felsham Road, London SW15 1AZ For ALBYNS LONDON
Tel 020 8785 4499 Fax 020 8785 4999 E info@elitedesigners.co.uk
 0DUNKDP 6TXDUH ² 3(50($7,21 *5287,1* %RUHKROH 'ULOOLQJ

,W LV XQGHUVWRRG WKDW D VFKHPH LV UHTXLUHG IRU WKH GHVLJQ DQG H[HFXWLRQ RI JURXQG $ VPDOO WUDFNHG ULJ XWLOLVLQJ FDVH DQG DXJHU GULOOLQJ ZLOO EH XVHG 7KH ULJ ZLOO GULOO
WUHDWPHQW WR PLWLJDWH JURXQGZDWHU LQJUHVV DQG WKHUHE\ UHGXFH WKH ULVN RI VRLO WKH FDVLQJV WKURXJK WKH JUDYHO DQG LQWR WKH /RQGRQ &OD\ WKH VRLOV ZLWKLQ WKH ERUH
LQVWDELOLW\ GXULQJ WKH H[FDYDWLRQ IRU WKH ORZHU OHYHO XQGHUSLQV ZLOO EH UHPRYHG XVLQJ WKH DXJHUV

2XU SURSRVDO LV EDVHG RQ LQMHFWLQJ D 6RGLXP 6LOLFDWH JURXW YLD WXEHDPDQFKHWWH 2QFH WKH GULOO FDVLQJ LV LQVWDOOHG WR WKH UHTXLUHG GHSWK D FHPHQW  EHQWRQLWH
SLSHV WR IRUP D JURXQGZDWHU FXWRII ZDOO IURP WKH *UDYHO  &OD\ LQWHUIDFH WR DERYH VOHHYH JURXW ZLOO EH SXPSHG WKURXJK D WUHPLH SLSH LQWR WKH FDVLQJ WR GLVSODFH DQ\
WKH JURXQGZDWHU WDEOH DORQJ WKH OLQH RI WKH SURSRVHG XQGHUSLQ ZDWHU DQG WRWDOO\ ILOO WKH ERUHKROH 7KH 7$0 SLSH ZLOO EH VFUHZHG WRJHWKHU DQG
LQVHUWHG LQWR WKH JURXW ILOOHG ERUHKROH FRPSOHWH ZLWK DQ HQG FDS WR SUHYHQW JURXW
HQWHULQJ WKH WXEH 7KH 7$0 SLSH ZLOO EH VXSSOLHG LQ P OHQJWKV ZLWK WKUHDGHG
0HWKRG HQGV IRU FRXSOLQJ $ERYH WKH JURXQG WUHDWPHQW ]RQH SODLQ SLSH LV XVHG WR H[WHQG
WKH WXEH EDFN WR WKH JURXQG VXUIDFH 7KH 7$0 ZLOO EH WHUPLQDWHG DSSUR[LPDWHO\
7KH 7XEH k 0DQFKHWWH 7$0 FRQVLVWV RI D SODVWLF RU VWHHO SLSH ZLWK KROHV GULOOHG  P DERYH JURXQG OHYHO
WKURXJK LW DW UHJXODU FHQWUHV HYHU\ ѿ PHWUH  7KH KROHV DUH FRYHUHG E\ UXEEHU
VOHHYH ZKLFK DFWV DV D VLPSOH QRQ UHWXUQ YDOYH 7KH 7$0 LV LQVWDOOHG LQ D ERUHKROH 7KH VOHHYH JURXW ZLOO EH PL[HG LQ D FROORLGDO RU SDGGOH PL[HU DQG GLVFKDUJHG LQWR
DQG VXUURXQGHG E\ D ZHDN FHPHQWEHQWLRQLWH JURXW WR VHDO LW LQWR SRVLWLRQ WKH ERUHKROH XVLQJ D WUHPLH

$ GRXEOH SDFNHU LV XVHG WR LVRODWH D SDUWLFXODU VOHHYH DOORZLQJ JURXW LQMHFWLRQ DW 7KH ULJ ZLOO WKHQ EH FRXSOHG WR WKH FDVLQJ DQG WKH FDVLQJ ZLWKGUDZQ RYHU WKH 7$0
WKH UHTXLUHG ORFDWLRQ 7KH LQMHFWLRQ YROXPHV DQG SUHVVXUHV PD\ EH YDULHG RQ HDFK SLSH $V WKLV RSHUDWLRQ LV EHLQJ FDUULHG RXW VOHHYH JURXW ZLOO EH WRSSHG XS XVLQJ D
VOHHYH DOORZLQJ D KLJK GHJUHH RI FRQWURO 7KH V\VWHP DOVR DOORZV PXOWLSOH WUHPLH
LQMHFWLRQV RQ WKH VDPH VOHHYH LQFOXGLQJ WKH XVH RI GLIIHUHQW JURXW W\SHV ZKHUH
DSSURSULDWH
*URXW ,QMHFWLRQ

7KH SHUPHDWLRQ JURXW ZLOO EH PL[HG LQ D SDGGOH JURXW PL[HU DQG GLVFKDUJHG WR WKH
DJLWDWLRQ KROGLQJ WDQNV

$ GRXEOH LQIODWDEOH SDFNHU ZLOO EH ORZHUHG LQWR WKH 7$0 SLSH RQ D IOH[LEOH KRVH 7KH
SDFNHU ZLOO EH SRVLWLRQHG RQ WKH VHOHFWHG VOHHYH DQG LQIODWHG 7KLV HQVXUHV WKDW
JURXW LV LQMHFWHG DW WKH VHOHFWHG SRVLWLRQ RQO\

*URXW ZLOO EH LQMHFWHG XVLQJ D YDULDEOH VSHHG SXPS FDSDEOH RI VXIILFLHQW SUHVVXUH
WR IUDFWXUH WKH VOHHYH JURXW 2QFH WKH VOHHYH LV RSHQ WKH SUHVVXUH ZLOO EH UHGXFHG
WR IDFLOLWDWH SHUPHDWLRQ JURXWLQJ 7KH IORZ UDWH ZLOO EH DGMXVWHG WR FRQWURO WKH
LQMHFWLRQ SUHVVXUH
   &  

 
&    
*URXWHG %ORFN     
 >  
    
   
;    
    <
  
7KH SLFWXUH
$ >   
VKRZV D KDQG
  > > 
GXJ IDFH RI  <
JURXWHG VRLOV RQ
&RQWUDFW  RI
/* $ $ , 
WKH -XELOHH OLQH 9::

([WHQVLRQ &  ' --  1,.   1        0
,   " " 1               
6:
    /*        1* 1* /

   &    


:
:<::8 :
 <:5 8<: 5:       
/ = 2
, @?       >
'&/;$%/<         
    <%=  
/ ;0  <
/        
 < / ;$<    <

&=  > > / ;&-1;,$0-$<  


    < )/ < /     
7KH JURXQG WUHDWPHQWW LV LQWHQGHG WR DOORZ WKH H[FDYDWLRQ WR SURFFHHG LQ D UHODWLYHO\ -     / 2
; <  
VWDEOH GU\ HQYLURQPHQQW 7KH SUHVHQFH RI VLOW SDUWLFOHV ZLWKLQ WKH
H VRLO PD\ OLPLW WKH    >       <
$ $  <
IORZ RI WKH JURXW DQG PD\ OHDG WR D SDUWLDOO\ WUHDWHG VRLO $Q DOOORZDQFH VKRXOG EH  <    
PDGH IRU SXPSLQJ RXWW WKH WUDSSHG ZDWHU . < &   <
$   <
%  <
$   "   >  <
KLV VL]H WKH ZDWHU LQJUHVV FDQ XVXDOO\ EH PDQDJHG E\ QU 
)RU DQ XQGHUSLQ RI WK    <  
LQFK SXPSV -    < <
(=  < %
"   <
*    < ==   > 
H WDEOH EHORZ
2XU PL[ SURSRUWLRQV DQG UHFHQW VWUHQJWK UHVXOWV DUH VKRZQ LQ WKH      &      
 == @#1)?      <
   #1) 
  ,    <
 = 
       > +   
    <  <
  !!  #    $&#>/&#  <
 " !!# "#  ! $ %*
- #<>?@!# "#  @ZX [
 X !   \ \

- #<>?@!# "#  @ZX [
]^ X  
  _*< *<


PDF created with pdfFactory trial version www.pdffactory.com


3URMHFW &RPSOHWLRQ 5HSRUW
   &  

)!

, ! * 

$, 

#1), & 

& 
   
)!

0 /;
- %
& 
, 
!" 0+   !" 0)   
           
 00           
!" 1 0)                 1
                 
     /       /    /

#1), & 

1 
$ 

% 
/
#  
.  

& 
1 
, ! * 
3HUPHDWLRQ *URXWLQJ
 .HQVLQJWRQ 3DODFH *DUGHQV
7 6
  , 

$ &!            1* 


 # 0  
     1#  0    
) #        
) # (   1& 1#   0         $   352-(&7
                        
           / /       *URXQG WUHDWPHQW WR SURYLGH WHPSRUDU\ VXSSRUW
    WR DQ H[LVWLQJ SURSHUW\ GXULQJ EDVHPHQW
   /
&    $*  FRQVWUXFWLRQ DW  .HQVLQJWRQ 3DODFH *DUGHQV
/RQGRQ
.   

62/87,21
   

6: ! - 

6RGLXP VLOLFDWH EDVHG JURXW ZDV XVHG WR


SHUPHDWH WKH 7HUUDFH *UDYHOV 7KH JURXQG
4:=3:

, /  

WUHDWPHQW SURYLGHG VXSSRUW GXULQJ WKH


%#(   1 H[FDYDWLRQ RI FRQYHQWLRQDO XQGHUSLQV EHORZ
#  0(    JURXQG ZDWHU OHYHO
#  +    
&  0&  *           
            /    3+272*5$3+6
       7RS /HIW  7KH SURSHUW\ GXULQJ H[FDYDWLRQ
#  * /
7RS 5LJKW ² 7HUUDFH JUDYHOV ERXQG E\ 6RGLXP
6LOLFDWH *URXW
%RWWRP /HIW ² $ YHUWLFDO IDFH H[FDYDWHG LQ WKH
JURXWHG VRLOV 7KH EOXH SLSH LV WKH VOHHYHG 7XEH k
0DQFKHWWH SLSH LQVWDOOHG WR JLYH DFFHVV IRU DQ
LQIODWDEOH SDFNHU WR DOORZ DFFXUDWH SODFHPHQW LI
WKH JURXW

PDF created with pdfFactory trial version www.pdffactory.com


.(< '(7$,/6 3URMHFW &RPSOHWLRQ 5HSRUW
6(&725  'RPHVWLF 3URSHUW\
352-(&7 0$1$*(5  +ROORZD\ :KLWH $OORP
(1*,1((5  3ULFH 0\HUV
&2175$&725  - %URZQH &RQVWUXFWLRQ &RPSDQ\ /WG -%&
7(0325$5< :25.6 (1*,1((5  0DODFK\ :DOVK 3DUWQHUV 7HPSRUDU\ :RUNV IRU
-%&
62/87,21  3HUPHDWLRQ *URXWLQJ

&216758&7,21
7KH ZRUNV UHTXLUHG SHUPHDWLRQ JURXWLQJ FKHPLFDO $ ]RQH RI  OLQHDU PHWUHV ZDV WUHDWHG IURP
WR VWDELOLVH WKH JURXQG SULRU WR FRQVWUXFWLRQ RI P $2' WR P $2' WKH UHPDLQLQJ  OHQJWK ZDV
WUDGLWLRQDO FRQFUHWH XQGHUSLQQLQJ WR WKH SDUW\ ZDOO WR JURXWHG IURP P $2' WR P $2' ,Q WRWDO
DOORZ FRQVWUXFWLRQ RI D EDVHPHQW VZLPPLQJ SRRO DSSUR[LPDWHO\  P RI VRLO IDFH ZDV JURXWHG

7KH JURXQG FRQGLWLRQV FRQVLVWHG RI PDGH JURXQG 7KH SURGXFWLRQ ZRUNV ZHUH FDUULHG RXW RYHU D  ZHHN
GRZQ WR P $2' RYHUO\LQJ VDQGV DQG JUDYHOV SHULRG FRPPHQFLQJ  -DQXDU\ 
UDQJLQJ IURP ORRVH WR PHGLXP GHQVH DQG YHU\ GHQVH
DW RQH ORFDWLRQ  7KH ERUHKROHV ZHUH GULOOHG ZLWK D PP URWDU\
3HUPHDWLRQ *URXWLQJ 0LQLSLOLQJ
GULOO FDVLQJ DQG LQWHUQDO DXJHUV $ SODVWLF WXEH k
7KH VLWH ZDV FRQJHVWHG ZLWK UHVWULFWHG DFFHVV IRU PDQFKHWWH 7$0 SLSH ZDV LQVWDOOHG DQG VHDOHG LQWR
GHOLYHULHV DQG VWRUDJH $ PLQL GULOO ULJ DQG VPDOO VFDOH WKH JURXQG ZLWK D ZHDN VOHHYH JURXW 7KH 7$0 KDG
 *LOVWRQ 5RDG
JURXWLQJ SODQW ZDV XVHG ZLWK PDWHULDOV VXSSOLHG LQ VLPSOH QRQ UHWXUQ VOHHYHV DW PP FHQWUHV 'XULQJ
EDUUHOV DQG ,%&·V 7KH ZRUNLQJ DUHD ZDV VKDUHG ZLWK JURXWLQJ HDFK LQGLYLGXDO VOHHYH FRXOG EH VHOHFWHG ZLWK 352-(&7
RWKHU WUDGHV ZDV DOVR UHVWULFWHG ZLWK ORZ KHDGURRP D SQHXPDWLF GRXEOH SDFNHU $ VHW TXDQWLW\ RI JURXW
*URXQG WUHDWPHQW WR PLWLJDWH JURXQG ZDWHU
DQG XQGHUSLQ SLOHV VXSSRUWLQJ WKH XSSHU VWRUH\V FRXOG WKHQ EH LQMHFWHG DW ORZ SUHVVXUH WR WDUJHW D
RI WKH EXLOGLQJ 7KH ZRUNLQJ SODWIRUP ZDV FRQVWUXFWHG VSHFLILF DUHD RI VRLO 5HSHDWHG LQMHFWLRQV RQ DGMDFHQW LQJUHVV UHGXFH WKH ULVN RI VRLO LQVWDELOLW\
DV WKH ZRUNV GHVFHQGHG VOHHYHV DOORZHG WKH ZKROH ]RQH WR EH WUHDWHG ZLWK D GXULQJ EDVHPHQW FRQVWUXFWLRQ DW  *LOVWRQ
KLJK OHYHO RI FRQWURO 5RDG &KHOVHD /RQGRQ

%(1(),76 62/87,21
,QLWLDO DWWHPSWV WR FRQVWUXFW ZLWK XQGHUSLQV ZLWKRXW 7KH SHUPHDWLRQ JURXWLQJ SURFHVV XVLQJ WKH WXEH
k PDQFKHWWH V\VWHP ZDV VHOHFWHG 7KLV DOORZHG WKH
6RGLXP VLOLFDWH EDVHG JURXW ZDV XVHG WR
JURXWLQJ KDG SURYHG SUREOHPDWLF 7KH LQVWDELOLW\ RI WKH
RULJLQDO XQGHUSLQV GXULQJ H[FDYDWLRQ KDG UDLVHG LQMHFWLRQ SUHVVXUHV DQG YROXPHV WR EH FDUHIXOO\ SHUPHDWH WKH 7HUUDFH *UDYHOV 7KH JURXQG
FRQFHUQV UHJDUGLQJ WKH ULVN RI PRYHPHQW RI WKH FRQWUROOHG WR IDFLOLWDWH DFFXUDWH SODFHPHQW RI WKH WUHDWPHQW SURYLGHG ERWK JURXQG ZDWHU FRQWURO
RYHUO\LQJ VWUXFWXUH 7KH SHUPHDWLRQ JURXWLQJ ZDV JURXW 7KH SURFHVV FRXOG EH FRQGXFWHG XVLQJ VPDOO VRLO VWDELOLVDWLRQ GXULQJ WKH H[FDYDWLRQ RI
LQVWUXFWHG WR ELQG WRJHWKHU WKH VRLOV DOORZLQJ WKH VFDOH SODQW DQG HTXLSPHQW VXLWDEOH IRU WKH UHVWULFWHG FRQYHQWLRQDO XQGHUSLQV ERWK DERYH EHORZ
FRQYHQWLRQDO XQGHUSLQV WR EH FRQVWUXFWHG VDIHO\ DQG DFFHVV EHQHDWK WKH VWUXFWXUH 7KH VHOHFWLRQ RI WKH JURXQG ZDWHU OHYHO
ZLWKRXW GDPDJH WR WKH RYHUO\LQJ DQG DGMDFHQW ULJKW JURXW WR VXLW WKH VRLO SURILOH ZDV SURYHG GXULQJ
SURSHUWLHV 7KH JURXWHG JURXQG FRXOG WKHQ EH H[FDYDWLRQ 7KH EHQHILWV RI VRGLXP VLOLFDWH JURXW DUH
H[FDYDWHG YHUWLFDOO\ LQ ED\V ZLWKRXW DGGLWLRQDO ZHOO HVWDEOLVKHG LQ WKH 7HUUDFH *UDYHOV LQ WKH /RQGRQ 3+272*5$3+6
VXSSRUW 7KLV VLPSOLILHG WKH XQGHUSLQQLQJ ZRUNV DQG $UHD 7RS /HIW  7KH SURSHUW\ GXULQJ LQVWDOODWLRQ
SURWHFWHG WKH DGMDFHQW VWUXFWXUHV JURXWLQJ RI 7XEH k 0DQFKHWWH

7RS 5LJKW ² 7HUUDFH JUDYHOV ERXQG E\ 6RGLXP


6LOLFDWH *URXW FXW DW D ϶ DQJOH
&217$&7 '(7$,/6
)RU IXUWKHU LQIRUPDWLRQ FRQWDFW 3DXO 0DUVGHQ 0LGGOH /HIW ² 'ULOO ULJ LQVWDOO 0DQFKHWWH 3LSHV
7   LQ YHU\ WLJKW DFFHVV 7KH ULJ KDV EHHQ FKRFNHG
( SDXOPDUVGHQ#NHOOHUFRXN WR SURWHFW WKH GULOOHU
ZZZNHOOHUFRXN %RWWRP /HIW ² P ZLGH DFFHVV WR WKH SURSHUW\
.(< '(7$,/6
6(&725  'RPHVWLF 3URSHUW\
352-(&7 0$1$*(5  +ROORZD\ :KLWH $OORP
(1*,1((5  (FNHUVOH\ 2·&DOODJKDQ
62/87,21  3HUPHDWLRQ *URXWLQJ

&216758&7,21
7KH ZRUNV UHTXLUHG SHUPHDWLRQ JURXWLQJ FKHPLFDO $ ]RQH RI  OLQHDU PHWUHV ZDV WUHDWHG IURP
WR VWDELOLVH WKH JURXQG SULRU WR FRQVWUXFWLRQ RI P %*/ WR P %*/ D WRWDO RI DSSUR[LPDWHO\
WUDGLWLRQDO FRQFUHWH XQGHUSLQQLQJ WR WKH SDUW\ ZDOO WR Pò RI JURXQG ZDV JURXWHG Pñ RI IDFH DUHD 
DOORZ FRQVWUXFWLRQ RI D WZR VWRUH\ EDVHPHQW $ P OHQJWK ZDV JURXWHG WR VXUIDFH WR SURYLGH
JURXQG VWDELOLVDWLRQ WR DQ DGMRLQLQJ JDUGHQ ZDOO
7KH JURXQG FRQGLWLRQV FRQVLVWHG RI PDGH JURXQG
GRZQ WR P %*/ RYHUO\LQJ 5LYHU WHUUDFH *UDYHOV 7KH SURGXFWLRQ ZRUNV ZHUH FDUULHG RXW RYHU D 
WR P %*/ RYHUO\LQJ /RQGRQ &OD\ ZHHN SHULRG QRW FRQWLQXRXV FRPPHQFLQJ 
2FWREHU 
7KH VLWH ZDV FRQJHVWHG ZLWK UHVWULFWHG DFFHVV IRU
GHOLYHULHV DQG VWRUDJH $ PLQL GULOO ULJ DQG VPDOO VFDOH 7KH ERUHKROHV ZHUH GULOOHG ZLWK D PP URWDU\
JURXWLQJ SODQW ZDV XVHG ZLWK PDWHULDOV VXSSOLHG LQ GULOO FDVLQJ DQG LQWHUQDO DXJHUV $ SODVWLF WXEH k
EDUUHOV DQG ,%&·V 7KH ZRUNLQJ DUHD VKDUHG ZLWK RWKHU PDQFKHWWH 7$0 SLSH ZDV LQVWDOOHG DQG VHDOHG LQWR
WUDGHV ZDV UHVWULFWHG ZLWK ORZ KHDGURRP DQG WKH JURXQG ZLWK D ZHDN VOHHYH JURXW 7KH 7$0 KDG
XQGHUSLQ FRQWLJXRXV PLQLSLOHV LQVWDOOHG E\ .HOOHU VLPSOH QRQ UHWXUQ VOHHYHV DW PP FHQWUHV
VXSSRUWLQJ WKH XSSHU VWRUH\V DQG SURYLGLQJ WKH HQGV RI 'XULQJ JURXWLQJ HDFK LQGLYLGXDO VOHHYH FRXOG EH
WKH ER[ VHOHFWHG ZLWK D SQHXPDWLF GRXEOH SDFNHU $ VHW
TXDQWLW\ RI JURXW FRXOG WKHQ EH LQMHFWHG DW ORZ
SUHVVXUH WR WDUJHW D VSHFLILF DUHD RI VRLO 5HSHDWHG
LQMHFWLRQV RQ DGMDFHQW VOHHYHV DOORZHG WKH ZKROH
]RQH WR EH WUHDWHG ZLWK D KLJK OHYHO RI FRQWURO

%(1(),76
.HOOHU ZHUH LQYLWHG WR SURYLGH D VROXWLRQ WR DOORZ 7KH SHUPHDWLRQ JURXWLQJ SURFHVV XVLQJ WKH WXEH k
H[FDYDWLRQ IRU XQGHUSLQV EHORZ JURXQG ZDWHU OHYHO WR PDQFKHWWH V\VWHP ZDV VHOHFWHG 7KLV DOORZHG WKH
EH XQGHUWDNHQ ZLWKLQ GU\ ZDWHU LQJUHVV UHGXFHG WR LQMHFWLRQ SUHVVXUHV DQG YROXPHV WR EH FDUHIXOO\
SXPSDEOH OLPLWV VWDEOH FRQGLWLRQV 7KH SHUPHDWLRQ FRQWUROOHG WR IDFLOLWDWH DFFXUDWH SODFHPHQW RI WKH
JURXWLQJ ZDV LQVWUXFWHG WR ELQG WRJHWKHU WKH VRLOV JURXW 7KH SURFHVV FRXOG EH FRQGXFWHG XVLQJ VPDOO
DOORZLQJ WKH FRQYHQWLRQDO XQGHUSLQV WR EH FRQVWUXFWHG VFDOH SODQW DQG HTXLSPHQW VXLWDEOH IRU WKH
VDIHO\ DQG ZLWKRXW GDPDJH WR WKH RYHUO\LQJ DQG UHVWULFWHG DFFHVV EHQHDWK WKH VWUXFWXUH 7KH
DGMDFHQW SURSHUWLHV 7KH JURXWHG JURXQG FRXOG WKHQ VHOHFWLRQ RI WKH ULJKW JURXW WR VXLW WKH VRLO SURILOH
EH H[FDYDWHG YHUWLFDOO\ LQ ED\V XVLQJ FRQYHQWLRQDO ZDV SURYHG GXULQJ H[FDYDWLRQ 7KH EHQHILWV RI
VXSSRUW 7KLV VLPSOLILHG WKH XQGHUSLQQLQJ ZRUNV DQG VRGLXP VLOLFDWH JURXW DUH ZHOO HVWDEOLVKHG LQ WKH
SURWHFWHG WKH DGMDFHQW VWUXFWXUHV 7HUUDFH *UDYHOV LQ WKH /RQGRQ $UHD $W WKH WLPH RI
ZULWLQJ ZRUNV RQ VLWH KDYH FRQWLQXHG WR ILUVW OHYHO V
RI XQGHUSLQQLQJ

&217$&7 '(7$,/6
)RU IXUWKHU LQIRUPDWLRQ FRQWDFW 3DXO 0DUVGHQ
7  
( SDXOPDUVGHQ#NHOOHUFRXN

ZZZNHOOHUFRXN

You might also like