PERT ANALYSIS- Group Quiz Name:

The following PERT diagram is for "The evaluation of Informal business survey of surrounding Unklab area".
All data are counted based number of working days.

Based on the above network diagram complete the following table


Forward Pass Backward Pass
Acitivities Duration PredesessoSuccessor EST EFT LST LFT
A 6 0 C
B 10 0 D, E
C 4 A H
D 5 B H
E 5 B F, G
F 4 E I
G 7 E 0
H 12 C, D 0
I 7 F 0
The CPM is If the project started on August 30, 2021 It should be finished on

For the following questions you must link your answer from the table
1. Actitivies that can not be delayed are
2. Activities that can be delayed are
3. Maximum number of days delayed are
y of surrounding Unklab area".

Code Activities Days


A Clearing 6
B Construct base 10
C Floor setting after A 4
D Ring bulk setting after B 5
E Wall setting after B 5
F Plastering after E 4
G Framing after E 7
H Refining Floor after C & D 12
I Refining wall after F 7

Total