Professional Documents
Culture Documents
Beverly R. Batula
June 4, 2023
2
Test Completion
1. What is the Contractor’s Obligation under sub-clause 9.1 in FIDIC Red Book?
b. Tests on Completion
e. Employer’s Suspension
2. How many days should the Contractor submit a Notice for commencing a Test on
Completion?
a. 8 days
b. 12 days
c. 42 days
d. 14 days
e. 22 days
3. What’s the importance of giving ample time before the Tests to the Engineer?
a. To review the proposed test program and have it revised if it shows that it
a. The Contractor
b. The Engineer
c. The Personnel
3
d. The Employer
5. How many days does the Contractor have to wait to consider that the Engineer has
a. 21 days
b. 42 days
c. 14 days
d. 7 days
e. 18 days
6. Upon receiving the copy of the results from the Tests, Engineer is responsible to
a. If the Engineer finds out that there is a conflict with the contract, the Engineer
report.
7. Are there any provisions stating what the Employer must do if the cause of
c. Sub-Clause 9.1
e. Sub-Clause 11.4
4
8. How long may the Contractor be allowed to perform the tests if his team is the
a. 42 days
b. 14 days
c. 21 days
d. 8 days
e. 7 days
e. No.
10. What does Sub-Clause 20.2 imply to the Employer and the Contractor?
a. The provision states that the Employer is entitled to claim the costs incurred
c. Under Sub-Clause 20.2 states who is in charge of the plants and materials on-
site.
d. It clearly states that the Contractor cannot be asked to claim any additional
a. None, in retesting it is to consider the same terms and conditions for The Tests
on Completion.
c. Yes
12. In the absence of the Contractor for the tests, who can be the in-charge to proceed
a. Contractor
b. Employer’s Personnel
c. The Engineer
13. Can the contractor object to the result came in after conducting the test, without
the contractor?
a. Yes, because it is their team who works for the test program.
14. On what grounds, that the Engineer can reject the Work and or Sections done by
the Contractor?
a. The Engineer can reject the Work or Section if the effect of the failure is to
c. The Engineer is the one responsible if it fails to meet the standard of the
design.
6
fails to pass what Sub-clause 9.3 asks for, and if the Employer asks the
Engineer to issue the Certificate, Yes he can issue the Taking-Over Certificate.
b. No.
c. No, the Engineer is in the project to only supervise the work done.
References