Project Name : VALE BAHODOPI MBB (2&3)

Project No. : 23-1255022


MINUTES OF MEETING MOM No. : VALE-MOM-RE-PP-002
Page : 1 of 8

Date / Time : August 9th, 2023 /13:30- End Written by : Junian

Place : Video Conference

Subject : Coordination Weekly Meeting

Agenda :
- MDR Target
- Comment Design 3D
- Standard Support

Attendance : Please refer to the attached sheet


Minutes : Please refer to the attached sheet

Distribution :

No Name Position Company / Ext. Telp.


1 P. Thomas A.M. Piping Representative PT.PP
2 P. Adit W. Senior Engineer Piping
3 P. Hariono Designer Piping
4 P. Aep Designer Piping
5 P. Andi G Designer Piping
6 P. Junian Engineer Piping
7 P. M. Rosyid Engineer Process

PT REKAYASA ENGINEERING PT PP (PERSERO)

Signature : Signature :

Name : Muhammad Junian Nurrahman Name :

Position : Lead Engineer Position :

Date : August 9th, 2023 Date : August 9th, 2023


Form No. PTRE_FM-452_C
Project Name : VALE BAHODOPI MBB (2&3)
Project No. : 23-1255022
MINUTES OF MEETING MOM No. : VALE-MOM-RE-PP-002
Page : 2 of 8

NO. ITEMS ACTION BY TARGET


Piping RE

2 Rencana 60% 3D review akan dilaksanakan 23 agustus Piping RE 23/08/23


2023
3 Standard Support akan didevelope dan dibikin tagging Piping RE 26/08/23
numbernya
4 Comment Design 3D akan diselesaikan untuk extract Piping RE 15/08/23
document pipingplan
5 Tagging support akan dimunculkan pada issue document Piping RE 30/08/23
IFC

Completed item 0
Total Action Item 5
Percentage of Completion 0%