TRENCH DRAIN WITH STEEL GRATING AT THE HOSPITAL DRIVEWAY EXIT

S/N SCOPE OF WORK UNITS QTY UNIT PRICE (Php) COST (Php)

1.0.0 CONCRETE WORKS (3000 PSI)

1.1.0 PORTLAND CEMENT 40-KG BAG 36.00 245.00 8,820.00


1.2.0 SAND CU. M. 2.40 800.00 1,920.00
1.3.0 CRUSHED GRAVEL CU. M. 4.80 900.00 4,320.00
1.4.0 FORMWORKS/STAGING
1.4.1 PLYWOOD (4'X8'X1/4") PC. 2.00 380.00 760.00
1.4.2 LUMBER (2"X3"X12') PC. 11.00 180.00 1,980.00

2.0.0 STEELWORKS

2.1.0 D12MM REBARS (GRADE 60) KG 182.04 38.00 6,917.52


2.2.0 D25MM REBARS (GRADE 60) KG 381.55 38.00 14,498.90
2.3.0 TIE WIRES (G.I. WIRE NO.16) KG 2.80 65.00 182.00
2.4.0 50X50X3MM ANGLE BAR (A36) KG 67.07 70.30 4,715.02
2.5.0 50X4MM FLAT BARS (A36) KG 30.81 70.30 2,165.94

TOTAL COST: 46,279.38