ANNEXURE - II

BILL OF QUANTITIES [ITEM RATE]


Development of Fishing Harbour at Manakudi
EASTERN BREAKWATER
CROSS SECTION OF TRUNK for LS 0 to 107 at (-) 2 m bed level
Materials Area (Sq.m) Length (m) Volume (Cu.m) Void ratio Deducted Volume (Cu.m) Quantity (Unit/T)

Armour Tetrapod (2 T) 18.30 107.00 1958.10 0.50 979.05 1165.54


Armour sea side, Toe and
secondary (1-2T) 48.70 107.00 5210.90 0.65 3387.09 8975.78

Core Layer (10-500 Kg) 53.70 107.00 5745.90 0.70 4022.13 10658.64
Filter Layer (1-50 Kg)
(with shrinkage 10%) 19.30 107.00 2065.10 0.70 1445.57 4213.84
100 to 300 Kg 5.70 107.00 609.90 0.70 426.93 1131.36
40 mm stones 2.00 107.00 214.00 0.90 192.60 510.39
PCC 1:4:8 0.80 107.00 85.60 1.00 85.60 205.44
RCC M35 5.00 107.00 535.00 1.00 535.00 1337.50

CROSS SECTION OF TRUNK for LS 107 to 134 at (-) 3 m bed level


Materials Area (Sq.m) Length (m) Volume (Cu.m) Void ratio Deducted Volume (Cu.m) Quantity (Unit/T)

Armour Tetrapod (2T) 22.10 27.00 596.70 0.50 298.35 355.18


Armour sea side, Toe and
secondary (1-2T) 56.10 27.00 1514.70 0.65 984.56 2609.07
Core Layer (10-500 Kg) 71.60 27.00 1933.20 0.70 1353.24 3586.09
Filter Layer (1-50 Kg)
(with shrinkage 10%) 20.80 27.00 561.60 0.70 393.12 1145.94
100 to 300 Kg 5.70 27.00 153.90 0.70 107.73 285.48
40 mm stones 2.00 27.00 54.00 0.90 48.60 128.79
PCC 1:4:8 0.80 27.00 21.60 1.00 21.60 51.84
RCC M35 5.00 27.00 135.00 1.00 135.00 337.50

CROSS SECTION OF TRUNK for LS 134 to 170 at (-) 4 m bed level


Materials Area (Sq.m) Length (m) Volume (Cu.m) Void ratio Deducted Volume (Cu.m) Quantity (Ton)

Armour Tetrapod (4 T) 31.80 36.00 1144.80 0.50 572.40 342.75


Toe and secondary (1-2T) 86.50 36.00 3114.00 0.65 2024.10 5363.87
Core Layer (10-500 Kg) 100.90 36.00 3632.40 0.70 2542.68 6738.10
Filter Layer (1-50 Kg)
(with shrinkage 10%) 24.90 36.00 896.40 0.70 627.48 1829.10
100 to 300 Kg 5.70 36.00 205.20 0.70 143.64 380.65
40 mm stones 2.00 36.00 72.00 0.90 64.80 171.72
PCC 1:4:8 0.80 36.00 28.80 1.00 28.80 69.12
RCC M35 5.00 36.00 180.00 1.00 180.00 450.00
CROSS SECTION OF TRUNK for LS 170 to 250 at (-) 5 m bed level
Materials Area (Sq.m) Length (m) Volume (Cu.m) Void ratio Deducted Volume (Cu.m) Quantity (Ton)

Armour Tetrapod (4 T) 36.40 80.00 2912.00 0.50 1456.00 871.86


Toe and secondary (1-2T) 94.90 80.00 7592.00 0.65 4934.80 13077.22
Core Layer (10-500 Kg) 129.70 80.00 10376.00 0.70 7263.20 19247.48
Filter Layer (1-50 Kg)
(with shrinkage 10%) 26.40 80.00 2112.00 0.70 1478.40 4309.54
100 to 300 Kg 5.70 80.00 456.00 0.70 319.20 845.88
40 mm stones 2.00 80.00 160.00 0.90 144.00 381.60
PCC 1:4:8 0.80 80.00 64.00 1.00 64.00 153.60
RCC M35 5.00 80.00 400.00 1.00 400.00 1000.00

HEAD SECTION for LS 250 to 290 at (-) 6 m bed level


Materials Area (Sq.m) Length (m) Volume (Cu.m) Void ratio Deducted Volume (Cu.m) Quantity (Ton)

Armour Tetrapod (6 T) 1822.80 0.50 911.40 364.56


Toe and secondary (1-2T) 1582.60 0.65 1028.69 2726.03
Core Layer (10-500 Kg) 2847.00 0.70 1992.90 5281.19
Filter Layer (1-50 Kg)
(with shrinkage 10%) 1653.60 0.70 1157.52 3374.17
100 to 300 Kg 14.90 0.70 10.43 27.64
40 mm stones 4.70 0.90 4.23 11.21
PCC 1:4:8 1.88 1.00 1.88 4.51
RCC M35 20.60 1.00 20.60 51.50

Quantity
Materials (T/Cum)

Armour Layer (Tetrapod)


2T (Cum) 1277.40
4T (Cum) 2028.40
6T (Cum) 911.40
Toe and secondary (1-2T) 32751.96
Core (1-500 Kg) 45511.50
Filter Layer (1-50 Kg)
(with shrinkage 10%) 14872.59
100 to 300 Kg 2671.01
40 mm stones (Cum) 1203.71
PCC 1:4:8 (Cum) 484.51
RCC M35 (Cum) 3176.50
Development of Fishing Harbour at Manakudi

EASTERN BREAKWATER
Sl.No
RATE (Rs)
QUANTITY UNIT AMOUNT (Rs)
1 Armour Layer PER unit

Providing concrete Tetrapod weighing ( 2T, 4T & 6T) in plain cement concrete M35
grade including, casting, finishing and curing, transporting placing in position as per
approved design and slope over a Armour layer of rubble mounded Break water.complete
as directed by the departmental officers and as per the drawings and specifications and as
per the condition laids in special conditions. The side slope should maintain as 1:1.5.
Porasity has assumed as 50 %.

TETRAPOD - 2 T (0.86 cum)


1277.40Cum 18,407,334.00
14410
TETRAPOD - 4 T (1.67 cum) 2028.40Cum 29,229,244.00
14410
TETRAPOD - 6 T (2.5 cum) 911.40Cum 14410 13,133,274.00
TOTAL -
-

2 Armour in the sea side, Secondary layer & Toe Mound -


Formation of Secondary layer and Toe mound filling layer, with quarry stones (rough
angular) weighing 1 T to 2 T with unit weight not less than 2.65 T/m3, loading at quarry,
conveying in contractors transporting by tippers / lorries including weighing in the
electronic weigh bridge for the purpose of measurment, Unloading/dumping placing in
position to required level, profile and finishing the side slopes of 1 : 1.5 using crane and
-
dumping into the sea with required width with necessary equipment and devices as per the
drawings and specification etc., as directed by the Department Officers. ( The payment
shall be made on weight basis (ie) laden weight minus unladden weight). The contractor
has to make his own arrangements for weigh bridge in the presence of Department
Officers. Porasity has assumed as 65 %.
GR-C (1-2 T)
32751.96T 1480 48,472,900.06

TOTAL -

3 Core Layer (50 to 500 Kg) -


-

Formation of Core filling layer, with quarry stones (rough angular) weighing 50 kg to 500
kg with unit weight not less than 2.65 T/m3, loading at quarry, conveying in contractors
transporting by tippers / lorries including weighing in the electronic weigh bridge for the
purpose of measurment, Unloading/dumping placing in position to required level, profile
using crane and dumping into the sea with required width with necessary equipment and
45511.50T 1480 67,357,016.30
devices as per the drawings and specification etc., as directed by the Department Officers.
( The payment shall be made on weight basis (ie) laden weight minus unladden weight).
The contractor has to make his own arrangements for weigh bridge in the presence of
Department Officers. Porasity has assumed as 70 %.

4 Bedding Layer (1 to 50 Kg) -


-

Formation of Bedding Layer for rubble mound breakwater with quarry run hard blue
granite stone of weighing 1 kg to 50 kg having a specific gravity of not less than 2.65
T/m3 as per approved design and drawing including quarrying, loading transporting by
tippers/lorries weighing in the electronic weigh bridge for measurement, dumping, placing
in position to required level, profile with necessary equipment and devices as per the
drawings and specification etc complete as directed by the Departmental Officers. The 14872.59T 1480 22,011,436.68
rate is also inclusive of placing, sectioning and finishing with necessary equipment and
devices and hire and operational charges of tools and plants etc. (The payment shall be
made on weight basis (ie) laden weight minus unladden weight). The contractor has to
make his own arrangements for weigh bridge. Porasity has assumed as 70 %. The
additional volume of 10% should be added for shrinkage.
4 Subgrade (100 to 300 Kg) -

Formation of subgrade Layer of 0.5 m thickness for rubble mound breakwater with quarry
run hard blue granite stone of weighing 100 kg to 300 kg having a specific gravity of not
less than 2.65 T/m3 as per approved design and drawing including quarrying, loading
transporting by tippers/lorries weighing in the electronic weigh bridge for measurement,
dumping, placing in position to required level, profile with necessary equipment and
devices as per the drawings and specification etc complete as directed by the 2671.01 T 1480 3,953,101.46
Departmental Officers. The rate is also inclusive of placing, sectioning and finishing with
necessary equipment and devices and hire and operational charges of tools and plants etc.
(The payment shall be made on weight basis (ie) laden weight minus unladden weight).
The contractor has to make his own arrangements for weigh bridge. Porasity has assumed
as 70 %.
Base coarse (40 mm Stones)
-

Formation of base coarse Layer of 0.5 m thickness for rubble mound breakwater with
quarry run hard blue granite stone of 40 mm in size having a specific gravity of not less
than 2.65 T/m3 as per approved design and drawing including quarrying, loading
transporting by tippers/lorries weighing in the electronic weigh bridge for measurement,
dumping, placing in position to required level, profile with necessary equipment and
devices as per the drawings and specification etc complete as directed by the 1203.71 Cum 2407 2,897,328.77
Departmental Officers. The rate is also inclusive of placing, sectioning and finishing with
necessary equipment and devices and hire and operational charges of tools and plants etc.
(The payment shall be made on weight basis (ie) laden weight minus unladden weight).
The contractor has to make his own arrangements for weigh bridge. Porasity has assumed
as 90 %.

PCC 1:4:8 -

Formation of Plain Cement Concrete layer under the crest pavement which has a unit
weight of not less than 2.4 T/m3 as per approved design and drawing including mixing,
loading transporting by tippers/lorries weighing in the electronic weigh bridge for
measurement, dumping, placing in position to required level, profile with necessary
equipment and devices as per the drawings and specification etc complete as directed by
the Departmental Officers. The rate is also inclusive of placing, sectioning and finishing 484.51 Cum 3860 1,870,216.32
with necessary equipment and devices and hire and operational charges of tools and plants
etc. (The payment shall be made on weight basis (ie) laden weight minus unladden
weight). The contractor has to make his own arrangements for weigh bridge

Concrete pavement including crown wall -

Formation of Concrete road to faciliate vehicle movement having a unit weight of not less
than 2.4 T/m3 as per approved design and drawing including mixing, loading transporting
by tippers/lorries weighing in the electronic weigh bridge for measurement, dumping,
placing in position to required level, profile with necessary equipment and devices as per
the drawings and specification etc complete as directed by the Departmental Officers.
The rate is also inclusive of placing, sectioning and finishing with necessary equipment and 3176.50 Cum 7430 23,601,395.00
devices and hire and operational charges of tools and plants etc. (The payment shall be
made on weight basis (ie) laden weight minus unladden weight). The contractor has to
make his own arrangements for weigh bridge

Sub Total (Rs) 229,063,030.26

Unforseen quantities and Contigencies - 7% 16,034,412.12

GST @ 12% 27,487,563.63

Gross Total Amount (Rs) 272,585,006.01


Gross Total Amount in Crores (say) 27.26
Rupees Twenty Seven Crores and Twenty Six Lakhs only
Development of Fishing Harbour at Manakudi
WESTERN BREAKWATER
CROSS SECTION OF TRUNK for LS 0 to 107 at (-) 2 m bed level
Materials Area (Sq.m) Length (m) Volume (Cu.m) Void ratio Deducted Volume (Cu.m) Quantity (Unit/T)

Armour Tetrapod (2 T) 18.30 107.00 1958.10 0.50 979.05 1165.54


Armour sea side, Toe and
secondary (1-2T) 48.70 107.00 5210.90 0.65 3387.09 8975.78

Core Layer (10-500 Kg) 53.70 107.00 5745.90 0.70 4022.13 10658.64
Filter Layer (1-50 Kg)
(with shrinkage 10%) 19.30 107.00 2065.10 0.70 1445.57 4213.84
100 to 300 Kg 5.70 107.00 609.90 0.70 426.93 1131.36
40 mm stones 2.00 107.00 214.00 0.90 192.60 510.39
PCC 1:4:8 0.80 107.00 85.60 1.00 85.60 205.44
RCC M35 5.00 107.00 535.00 1.00 535.00 1337.50

CROSS SECTION OF TRUNK for LS 107 to 134 at (-) 3 m bed level


Materials Area (Sq.m) Length (m) Volume (Cu.m) Void ratio Deducted Volume (Cu.m) Quantity (Unit/T)

Armour Tetrapod (2T) 22.10 27.00 596.70 0.50 298.35 355.18


Armour sea side, Toe and
secondary (1-2T) 56.10 27.00 1514.70 0.65 984.56 2609.07
Core Layer (10-500 Kg) 71.60 27.00 1933.20 0.70 1353.24 3586.09
Filter Layer (1-50 Kg)
(with shrinkage 10%) 20.80 27.00 561.60 0.70 393.12 1145.94
100 to 300 Kg 5.70 27.00 153.90 0.70 107.73 285.48
40 mm stones 2.00 27.00 54.00 0.90 48.60 128.79
PCC 1:4:8 0.80 27.00 21.60 1.00 21.60 51.84
RCC M35 5.00 27.00 135.00 1.00 135.00 337.50

CROSS SECTION OF TRUNK for LS 134 to 170 at (-) 4 m bed level


Materials Area (Sq.m) Length (m) Volume (Cu.m) Void ratio Deducted Volume (Cu.m) Quantity (Ton)

Armour Tetrapod (4 T) 31.80 118.00 3752.40 0.50 1876.20 1123.47


Toe and secondary (1-2T) 86.50 118.00 10207.00 0.65 6634.55 17581.56
Core Layer (10-500 Kg) 100.90 118.00 11906.20 0.70 8334.34 22086.00
Filter Layer (1-50 Kg)
(with shrinkage 10%) 24.90 118.00 2938.20 0.70 2056.74 5995.40
100 to 300 Kg 5.70 118.00 672.60 0.70 470.82 1247.67
40 mm stones 2.00 118.00 236.00 0.90 212.40 562.86
PCC 1:4:8 0.80 118.00 94.40 1.00 94.40 226.56
RCC M35 5.00 118.00 590.00 1.00 590.00 1475.00

CROSS SECTION OF TRUNK for LS 170 to 250 at (-) 5 m bed level


Materials Area (Sq.m) Length (m) Volume (Cu.m) Void ratio Deducted Volume (Cu.m) Quantity (Ton)

Armour Tetrapod (4 T) 36.40 205.00 7462.00 0.50 3731.00 2234.13


Toe and secondary (1-2T) 94.90 205.00 19454.50 0.65 12645.43 33510.38
Core Layer (10-500 Kg) 129.70 205.00 26588.50 0.70 18611.95 49321.67
Filter Layer (1-50 Kg)
(with shrinkage 10%) 26.40 205.00 5412.00 0.70 3788.40 11043.19
100 to 300 Kg 5.70 205.00 1168.50 0.70 817.95 2167.57
40 mm stones 2.00 205.00 410.00 0.90 369.00 977.85
PCC 1:4:8 0.80 205.00 164.00 1.00 164.00 393.60
RCC M35 5.00 205.00 1025.00 1.00 1025.00 2562.50
CROSS SECTION OF TRUNK for LS 170 to 250 at (-) 6 m bed level
Materials Area (Sq.m) Length (m) Volume (Cu.m) Void ratio Deducted Volume (Cu.m) Quantity (Ton)

Armour Tetrapod (4 T) 43.70 215.00 9395.50 0.50 4697.75 2813.02


Toe and secondary (1-2T) 113.80 215.00 24467.00 0.65 15903.55 42144.41
Core Layer (10-500 Kg) 155.67 215.00 33469.05 0.70 23428.34 62085.09
Filter Layer (1-50 Kg)
(with shrinkage 10%) 31.70 215.00 6815.50 0.70 4770.85 13907.03
100 to 300 Kg 5.70 215.00 1225.50 0.70 857.85 2273.30
40 mm stones 2.00 215.00 430.00 0.90 387.00 1025.55
PCC 1:4:8 0.80 215.00 172.00 1.00 172.00 412.80
RCC M35 5.00 215.00 1075.00 1.00 1075.00 2687.50

HEAD SECTION for LS 250 to 290 at (-) 6 m bed level


Materials Area (Sq.m) Length (m) Volume (Cu.m) Void ratio Deducted Volume (Cu.m) Quantity (Ton)

Armour Tetrapod (6 T) 1822.80 0.50 911.40 364.56


Toe and secondary (1-2T) 1582.60 0.65 1028.69 2726.03
Core Layer (10-500 Kg) 2847.00 0.70 1992.90 5281.19
Filter Layer (1-50 Kg)
(with shrinkage 10%) 1653.60 0.70 1157.52 3374.17
100 to 300 Kg 14.90 0.70 10.43 27.64
40 mm stones 4.70 0.90 4.23 11.21
PCC 1:4:8 1.88 1.00 1.88 4.51
RCC M35 20.60 1.00 20.60 51.50

Materials Quantity (T/Cum)

Armour Layer (Tetrapod)


2T (Cum) 1277.40
4T (Cum) 10304.95
6T (Cum) 911.40
Toe and secondary (1-2T) 107547.22
Core (1-500 Kg) 153018.67
Filter Layer (1-50 Kg)
(with shrinkage 10%) 39679.56
100 to 300 Kg 7133.03
40 mm stones (Cum) 3216.65
PCC 1:4:8 (Cum) 1294.75
RCC M35 (Cum) 8451.50
Development of Fishing Harbour at Manakudi

WESTERN BREAKWATER
Sl.No
RATE (Rs)
QUANTITY UNIT AMOUNT (Rs)
1 Armour Layer PER unit

Providing concrete Tetrapod weighing ( 2T, 4T & 6T) in plain cement concrete M35
grade including, casting, finishing and curing, transporting placing in position as per
approved design and slope over a Armour layer of rubble mounded Break water.complete
as directed by the departmental officers and as per the drawings and specifications and as
per the condition laids in special conditions. The side slope should maintain as 1:1.5.
Porasity has assumed as 50 %.
TETRAPOD - 2 T (0.86 cum)
1277.40Cum 18,407,334.00
14410
TETRAPOD - 4 T (1.67 cum) 10304.95Cum 148,494,329.50
14410
TETRAPOD - 6 T (2.5 cum) 911.40Cum 14410 13,133,274.00
TOTAL -
-

2 Armour in the sea side, Secondary layer & Toe Mound -


Formation of Secondary layer and Toe mound filling layer, with quarry stones (rough
angular) weighing 1 T to 2 T with unit weight not less than 2.65 T/m3, loading at quarry,
conveying in contractors transporting by tippers / lorries including weighing in the
electronic weigh bridge for the purpose of measurment, Unloading/dumping placing in
position to required level, profile and finishing the side slopes of 1 : 1.5 using crane and
dumping into the sea with required width with necessary equipment and devices as per the -
drawings and specification etc., as directed by the Department Officers. ( The payment
shall be made on weight basis (ie) laden weight minus unladden weight). The contractor
has to make his own arrangements for weigh bridge in the presence of Department
Officers. Porasity has assumed as 65 %.

GR-C (1-2 T)
107547.22T 1480 159,169,879.31

TOTAL -

3 Core Layer (50 to 500 Kg) -


-

Formation of Core filling layer, with quarry stones (rough angular) weighing 50 kg to 500
kg with unit weight not less than 2.65 T/m3, loading at quarry, conveying in contractors
transporting by tippers / lorries including weighing in the electronic weigh bridge for the
purpose of measurment, Unloading/dumping placing in position to required level, profile
using crane and dumping into the sea with required width with necessary equipment and 153018.67T 1480 226,467,634.19
devices as per the drawings and specification etc., as directed by the Department Officers.
( The payment shall be made on weight basis (ie) laden weight minus unladden weight).
The contractor has to make his own arrangements for weigh bridge in the presence of
Department Officers. Porasity has assumed as 70 %.
4 Bedding Layer (1 to 50 Kg) -
-

Formation of Bedding Layer for rubble mound breakwater with quarry run hard blue
granite stone of weighing 1 kg to 50 kg having a specific gravity of not less than 2.65
T/m3 as per approved design and drawing including quarrying, loading transporting by
tippers/lorries weighing in the electronic weigh bridge for measurement, dumping, placing
in position to required level, profile with necessary equipment and devices as per the
drawings and specification etc complete as directed by the Departmental Officers. The
39679.56T 1480 58,725,753.24
rate is also inclusive of placing, sectioning and finishing with necessary equipment and
devices and hire and operational charges of tools and plants etc. (The payment shall be
made on weight basis (ie) laden weight minus unladden weight). The contractor has to
make his own arrangements for weigh bridge. Porasity has assumed as 70 %. The
additional volume of 10% should be added for shrinkage.
4 Subgrade (100 to 300 Kg) -

Formation of subgrade Layer of 0.5 m thickness for rubble mound breakwater with quarry
run hard blue granite stone of weighing 100 kg to 300 kg having a specific gravity of not
less than 2.65 T/m3 as per approved design and drawing including quarrying, loading
transporting by tippers/lorries weighing in the electronic weigh bridge for measurement,
dumping, placing in position to required level, profile with necessary equipment and
devices as per the drawings and specification etc complete as directed by the 7133.03 T 1480 10,556,886.62
Departmental Officers. The rate is also inclusive of placing, sectioning and finishing with
necessary equipment and devices and hire and operational charges of tools and plants etc.
(The payment shall be made on weight basis (ie) laden weight minus unladden weight).
The contractor has to make his own arrangements for weigh bridge. Porasity has assumed
as 70 %.

Base coarse (40 mm Stones)


-

Formation of base coarse Layer of 0.5 m thickness for rubble mound breakwater with
quarry run hard blue granite stone of 40 mm in size having a specific gravity of not less
than 2.65 T/m3 as per approved design and drawing including quarrying, loading
transporting by tippers/lorries weighing in the electronic weigh bridge for measurement,
dumping, placing in position to required level, profile with necessary equipment and
devices as per the drawings and specification etc complete as directed by the 3216.65 Cum 2407 7,742,475.35
Departmental Officers. The rate is also inclusive of placing, sectioning and finishing with
necessary equipment and devices and hire and operational charges of tools and plants etc.
(The payment shall be made on weight basis (ie) laden weight minus unladden weight).
The contractor has to make his own arrangements for weigh bridge. Porasity has assumed
as 90 %.

PCC 1:4:8 -

Formation of Plain Cement Concrete layer under the crest pavement which has a unit
weight of not less than 2.4 T/m3 as per approved design and drawing including mixing,
loading transporting by tippers/lorries weighing in the electronic weigh bridge for
measurement, dumping, placing in position to required level, profile with necessary
equipment and devices as per the drawings and specification etc complete as directed by
1294.75 Cum 3860 4,997,742.72
the Departmental Officers. The rate is also inclusive of placing, sectioning and finishing
with necessary equipment and devices and hire and operational charges of tools and plants
etc. (The payment shall be made on weight basis (ie) laden weight minus unladden weight).
The contractor has to make his own arrangements for weigh bridge

Concrete pavement including crown wall -

Formation of Concrete road to faciliate vehicle movement having a unit weight of not less
than 2.4 T/m3 as per approved design and drawing including mixing, loading transporting
by tippers/lorries weighing in the electronic weigh bridge for measurement, dumping,
placing in position to required level, profile with necessary equipment and devices as per
the drawings and specification etc complete as directed by the Departmental Officers. 8451.50 Cum 7430 62,794,645.00
The rate is also inclusive of placing, sectioning and finishing with necessary equipment and
devices and hire and operational charges of tools and plants etc. (The payment shall be
made on weight basis (ie) laden weight minus unladden weight). The contractor has to
make his own arrangements for weigh bridge

Sub Total (Rs) 705,492,211.21

Unforseen quantities and Contigencies - 7% 49,384,454.78


GST @ 12% 84,659,065.34

Gross Total Amount (Rs) 839,535,731.34

Gross Total Amount in Crores (say) 83.95


Rupees Eighty Three Crores and Ninety FiveLakhs only
Name of work : Development of Fishing Harbour at Manakudi
SUB STRUCTURE
SI.NO DESCRIPTION OF WORK Nos L(m) B(m) D(m) QTY UNIT

Setting up the piling gantry for 1000mm dia piles and connected
equipment over each pile location, including cost of shifting, cost of all
1 materials for piling gantry, labour, setting up the rig to alignment and 257
correct dimensions as shown in the drawing and as directed by the EIC.
Total 257 Nos

Providing and fabricating M.S.liners of specified thickness for required


length with M.S. shoes of 1.0m height using 12mm thick M.S. plates for
bored vertical pile measured from cut off level of pile to the terminating
level including supplying, cutting, rolling, bending, handling and welding
2 cost, labours, materials, accessories,all taxes, hire and running charges of
all machineries, royality, labour, material, T&P, conveyance charges, Port
entry fees etc. all complete complete as per drawings and specification as
directed by Engineer-In-charge

a) From cut-off level (+)0.575 (-)10m (1000 mm dia pile)


Liner 6mm thickness 257 3.14*(1.0+0.006)*0.006*9.575*7.85*263 657.60
Stiffner 12 mm thick 1000mm height 257 3.14*(1.006+0.012)*0.012*1*7.85*263 77.43
Total 735.02
Say 736.00 T

Boring for the piles to the required depth through all types of soil
strata including cemented sand, if any upto the rock touch level and
stacking the bored soil at convenient place and transported to the low lying
area anywhere inside /outside the harbour area within a lead of 4 Km or as
directed by the Engineer’s representative and pile shaft cleaning and
3
keeping of all records etc. including bentonite solution (where ever
required), labour, tools, equipment, fuel etc..all as per drawing,
specification etc complete as directed.

NOTE
i) In case the soil stratum at the founding level is loose the Engineer or his
representative may direct the contractor to carryout additional length of
boring and payment shall be made accordingly.

ii) The sample of bored materials of regular interval shall be collected and
produced for the verification of the Engineer or his representative at no
extra cost . in case any test reqiured by engineer in-charge, bored the
samples so collected shall be referred to an authorized laboratory / agency
identified by the Engineer , cost for testing shall be included in the quoted
rate. engineer in-charge decision regarding founding level is final.`no
claims in this regards are entertained.

iii) Boring through all type of soil strata means soft soil, weathered rock,
cemented sand, boulders and hard rock etc.,
iv) The boring in all type of soil measurement will be made on the basis
of depth of boring from encountered soft soil level to founding/pile
termination level.

v) All the boring depths shall be jointly measured actually at site and
Engineer in-charge decision is final.

Dia of Pile -1000mm (Bed Level is (-) 4.0m CD) 257 - - 6.58 1691.06
Total 1691.06 Rm
Providing and laying reinforced cement concrete in concrete mix M40
for pile excluding cost of steel reinforcements in position as per approved
drawing and as directed by the Engineer-In-Charge including mixing,
4 laying, consolidating, curing, including all labours, slings, shackles, supply
of all labour, material, transportation cost, hire and running charges of all
machineries such as cranes, lorries etc., complete as directed by the
Engineer-In-Charge.
Dia of Pile -1000mm (Cut-off level is 0.575m CD) 257 (π*1.0*1.0)/4 10.58 2134.54
3
Total 2134.54 m
3
Say 2135.00 m
Chiseling/Breaking using suitable tools and equipments the top of
1000mm Dia Pile concrete up to the receipt of dense concrete and dressing
the pile head suitably so as to receive the form work for deck work ,
including breaking to the required level exposing the pile reinforcement to
5 sufficient length as per approved drawing for embedding into the coping
beam etc. including removal of concrete debris from the site, supply of all
labour, material, transportation cost, hire and running charges of all
machineries complete as directed by the Engineer-In-Charge.

257 257 Nos


Total 257 Nos

DECK STRUCTURE
Providing and laying reinforced cement concrete in concrete mix M40
for Pile muff excluding cost of steel reinforcements in position as per
approved drawing and as directed by the Engineer-In-Charge including
6 shuttering, mixing, laying, consolidating, curing, including all labours,
slings, shackles, supply of all labour, material, transportation cost, hire and
running charges of all machineries such as cranes, lorries etc., complete as
directed by the Engineer-In-Charge.

Pile muff (1400x1400x450mm) 257 1.40 1.40 0.45 226.67 m3


3
Total 226.67 m
3
Say 227.00 m

Providing and laying reinforced cement concrete in concrete mix M40


for Beams excluding cost of steel reinforcements in position as per
approved drawing and as directed by the Engineer-In-Charge including
7 shuttering, mixing, laying, consolidating, curing, including all labours,
slings, shackles, supply of all labour, material, transportation cost, hire and
running charges of all machineries such as cranes, lorries etc., complete as
directed by the Engineer-In-Charge.
Main Jetty
3
Cross Beam 62 10 0.50 0.60 186.00 m
3
Longitudinal Beam 3 310 0.50 1.05 488.25 m
Approach Jetty
3
Cross Beam 15 14 0.50 0.60 63.00 m
3
Longitudinal Beam 3 87.8 0.50 1.05 138.29 m
Transition section at Approach Jetty
3
Cross Beam 4 114 0.50 0.60 34.20 m
3
Longitudinal Beam 10 177.2 0.50 1.05 93.03 m
3
Total 1002.77 m
3
say 1003.00 m

Providing and laying reinforced cement concrete in concrete mix M40


for slabs excluding cost of steel reinforcements in position as per approved
drawing and as directed by the Engineer-In-Charge including shuttering,
8 mixing, laying, consolidating, curing, including all labours, slings,
shackles, supply of all labour, material, transportation cost, hire and
running charges of all machineries such as cranes, lorries etc., complete as
directed by the Engineer-In-Charge.
3
In-situ slab - Main Jetty 1 310.00 10.00 0.15 465.00 m
In-situ slab - Approach Jetty 1 87.80 14.00 0.15 184.38 m3
3
Precast slab - Main Jetty 1 310.00 10.00 0.15 465.00 m
3
Precast slab - Approach Jetty 1 87.80 14.00 0.15 184.38 m

3
In-situ slab - Transition section at Approach jetty 658.50 0.15 98.78 m
3
Precast slab - Transition section at Approach jetty 658.50 0.15 98.78 m
3
Total 1496.31 m
3
Say 1497.00 m
Providing and laying reinforced cement concrete in concrete mix M40
for wearing coat as per approved drawing and as directed by the Engineer-
In-Charge including mixing, laying, consolidating, curing, including all
9 labours, slings, shackles, supply of all labour, material, transportation cost,
hire and running charges of all machineries such as cranes, lorries etc.,
complete as directed by the Engineer-In-Charge.
3
In-situ wearing coat - Main Jetty 1.0 310.0 10.0 0.075 232.50 m
3
In-situ wearing coat - Approach Jetty 1 87.8 14.0 0.075 92.19 m
3
In-situ wearing coat - Transition section at Approach Jetty 1 658.5 0.075 49.39 m
3
Total 324.69 m
3
Say 325.00 m

Fabricating and placing in position of steel reinforcement TMT bars(Fe


500D) as per IS 1786 for all reinforced cement concrete pile including
lifting hook, cutting, bending, tying with 16 gauge G.I. binding wire and
welding to proper specifications wherever required including cost of steel
10 and binding wire, cover blocks of 100mm dia in CC M40 mix, supply of
with supply of all materials, labour, transportation, T&P, all taxes, tollage,
safety measures, port entry fees, VAT, etc. all complete as directed by the
Engineer-In-Charge.

Pile 1 2135.00 250kg/m3 533.75 T


Total 533.75 T
Say 534.00 T

Supply of Fe500D steel confirming to IS specification of SAIL/ RINL/


TISCON/ Electro steel brands for pile muff including cutting,
straightening, bending , binding & plaving the grills in position for RCC
11 works including cost of binding wire of 16 to 18 gauge with supply of all
materials, labour, transportation, T&P, all taxes, tollage, safety measures,
port entry fees, VAT, etc. all complete as directed by the Engineer-In-
Charge.

Pile muff 1 227.00 250kg/m3 56.75 T


Total 56.75 T
Say 57.00 T

Supply of Fe500D steel confirming to IS specification of SAIL/ RINL/


TISCON/ Electro steel brands for Beams including cutting, straightening,
bending , binding & plaving the grills in position for RCC works including
12 cost of binding wire of 16 to 18 gauge with supply of all materials, labour,
transportation, T&P, all taxes, tollage, safety measures, port entry fees,
VAT, etc. all complete as directed by the Engineer-In-Charge.

Beams 1 1003.00 250kg/m3 250.75 T


Total 250.75 T
Say 251.00 T
Supply of Fe500D steel confirming to IS specification of SAIL/ RINL/
TISCON/ Electro steel brands for Slabs including cutting, straightening,
bending , binding & plaving the grills in position for RCC works including
13 cost of binding wire of 16 to 18 gauge with supply of all materials, labour,
transportation, T&P, all taxes, tollage, safety measures, port entry fees,
VAT, etc. all complete as directed by the Engineer-In-Charge.

Slabs 1 1497.00 200kg/m3 299.40 T


Total 299.40 T
Say 300.00 T

Supplying, handling, transporting and fixing in position of Cast iron


Bollard (10T capacity)with necessary cutting, concrete chipping, drilling,
grouting, welding with deck reinforcement steel and necessary coal tar
14 painting(wherever required) including all materials, labour , consumable 59 59.00 Nos
items etc. complete as per drawing and specifications as directed by the
EIC.

Supplying, handling, transporting and fixing in position of V- fender with


anchor bolts, U hooks, Chains,shall be hot dip G.I coating with 80micron
including cutting, concrete chipping, drilling, grouting, necessary welding
15 with deck reinforcement steel and necessary coal tar painting(wherever 59 59.00 Nos
required) including all materials, labour, consumable items, machineries,
tools, tackles,transportation etc... and complete as per Engineer Incharge.

Conducting High Strain Dynamic Test as per standard practices(ASTMD


4945 of 1989) The rate is inclusive of testing, hire charges for all
equipments like transducers, strain gauge, oscilloscope hammer crane and
16 cost of development of pile concrete with line and dismantling the 2 Nos
developed length of concrete, transportation of equipment, labour and
furnishing the test result etc., complete and as directed by the EIC.
2
Providing temporary platform to convey the material to the working spot
with required angles, channels including welding etc., complete adjacent to
17 Berthing structure (Jetty). 1680 Sq.m

Carrying out Concrete mix test etc. complete as per specification &
direction of Engineer-in-charge.
18 80 Nos
ABSTRACT
Name of work : Development of Fishing Harbour at Manakudi
ITEM AMOUNT (in
Qty DESCRIPTION RATE (Rs) UNIT AMOUNT (Rs)
NO: lakhs)
Setting up the piling gantry and connected equipment over each pile location,
including cost of shifting, cost of all materials for piling gantry, labour, setting
1 257 up the rig to alignment and correct dimensions as shown in the drawing and as 16,983.00 Nos 4,364,631.00 43.65
directed by the EIC.

Providing and fabricating M.S.liners of specified thickness for required length


with M.S. Shoes of 1.0m height using 12mm thick M.S. plates for 1000mm
mm dia bored vertical pile measured from cut off level of pile to the
terminating level including supplying, cutting, rolling, bending, handling and
welding cost, labours, materials, accessories,all taxes, hire and running charges
of all machineries, royality,labour, material, T&P, conveyance charges, Port
2 736 entry fees etc. all complete complete as per drawings and specification as 82,242.00 MT 60,530,112.00 605.30
directed by Engineer-In-charge

Note:-
1.The stiffener shall be measured under this item.
In case the soil strata found to be not good in the founding level of the liner,
extra depth may be provided as per site condition.

Boring through all types of soils, boulders, hard starta and rocks etc.. for
750mm and 600mm Dia vertical bored piles from the existing ground level (-
)4.00m CD to the founding level (-)10.00m CD of the piles, including bailing,
3 1691 flushing the bore bentonite with required density, chiselling, shifting of 32,044.00 Rm 54,188,326.64 541.88
materials etc.. complete as per directed by the Engineer-In-charge.

Providing and laying reinforced cement concrete in concrete mix M40 for
pile excluding cost of steel reinforcements in position as per approved drawing
and as directed by the Engineer-In-Charge including mixing, laying,
4 2135 consolidating, curing, including all labours, slings, shackles, supply of all 8,602.00 m3 18,365,270.00 183.65
labour, material, transportation cost, hire and running charges of all machineries
such as cranes, lorries etc., complete as directed by the Engineer-In-Charge.

Chiseling/Breaking using suitable tools and equipments the top of 1000mm


dia pile concrete up to the receipt of dense concrete and dressing the pile head
suitably so as to receive the form work for deck work , including breaking to
the required level exposing the pile reinforcement to sufficient length as per
5 257 approved drawing for embedding into the coping beam etc. including removal 6,052.00 Nos 1,555,364.00 15.55
of concrete debris from the site, supply of all labour, material, transportation
cost, hire and running charges of all machineries complete as directed by the
Engineer-In-Charge.

Providing and laying reinforced cement concrete in concrete mix M40 for
Pile muff excluding cost of steel reinforcements in position as per approved
drawing and as directed by the Engineer-In-Charge including shuttering,
6 227 mixing, laying, consolidating, curing, including all labours, slings, shackles, 7,988.00 m3 1,813,276.00 18.13
supply of all labour, material, transportation cost, hire and running charges of
all machineries such as cranes, lorries etc., complete as directed by the Engineer
In-Charge.

Providing and laying reinforced cement concrete in concrete mix M40 for
Beams excluding cost of steel reinforcements in position as per approved
drawing and as directed by the Engineer-In-Charge including shuttering,
3
7 1003 mixing, laying, consolidating, curing, including all labours, slings, shackles, 7,988.00 m 8,011,964.00 80.12
supply of all labour, material, transportation cost, hire and running charges of
all machineries such as cranes, lorries etc., complete as directed by the Engineer
In-Charge.

Providing and laying reinforced cement concrete in concrete mix M40 for
Slabs excluding cost of steel reinforcements in position as per approved
drawing and as directed by the Engineer-In-Charge including shuttering,
mixing, laying, consolidating, curing, including all labours, slings, shackles,
8 1497 supply of all labour, material, transportation cost, hire and running charges of 7,988.00 m3 11,958,036.00 119.58
all machineries such as cranes, lorries etc., complete as directed by the Engineer
In-Charge.
Providing and laying reinforced cement concrete in concrete mix M40 for
wearing coat as per approved drawing and as directed by the Engineer-In-
Charge including mixing, laying, consolidating, curing, including all labours,
9 325 slings, shackles, supply of all labour, material, transportation cost, hire and 7,988.00 m3 2,596,100.00 25.96
running charges of all machineries such as cranes, lorries etc., complete as
directed by the Engineer-In-Charge.

Fabricating and placing in position of steel reinforcement TMT bars(Fe 500D)


as per IS 1786 for all reinforced cement concrete pile including lifting hook,
cutting, bending, tying with 16 gauge G.I. binding wire and welding to proper
specifications wherever required including cost of steel and binding wire, cover
10 534 blocks of 100mm dia in CC M40 mix, supply of with supply of all materials, 68,510.00 MT 36,584,340.00 365.84
labour, transportation, T&P, all taxes, tollage, safety measures, port entry fees,
VAT, etc. all complete as directed by the Engineer-In-Charge.

Supply of Fe500D steel confirming to IS specification of SAIL/ RINL/


TISCON/ Electro steel brands for pile muff including cutting, straightening,
bending , binding & plaving the grills in position for RCC works including cost
11 57 of binding wire of 16 to 18 gauge with supply of all materials, labour, 68,510.00 MT 3,905,070.00 39.05
transportation, T&P, all taxes, tollage, safety measures, port entry fees, VAT,
etc. all complete as directed by the Engineer-In-Charge.

Supply of Fe500D steel confirming to IS specification of SAIL/ RINL/


TISCON/ Electro steel brands for Beams including cutting, straightening,
bending , binding & plaving the grills in position for RCC works including cost
12 251 of binding wire of 16 to 18 gauge with supply of all materials, labour, 68,510.00 MT 17,196,010.00 171.96
transportation, T&P, all taxes, tollage, safety measures, port entry fees, VAT,
etc. all complete as directed by the Engineer-In-Charge.

Supply of Fe500D steel confirming to IS specification of SAIL/ RINL/


TISCON/ Electro steel brands for Slabs including cutting, straightening,
bending , binding & plaving the grills in position for RCC works including cost
13 300 of binding wire of 16 to 18 gauge with supply of all materials, labour, 68,510.00 MT 20,553,000.00 205.53
transportation, T&P, all taxes, tollage, safety measures, port entry fees, VAT,
etc. all complete as directed by the Engineer-In-Charge.

Supplying, handling, transporting and fixing in position of Cast iron Bollard


(10T ton capacity)with necessary cutting, concrete chipping, drilling, grouting,
welding with deck reinforcement steel and necessary coal tar painting(wherever
14 59 required) including all materials, labour , consumable items etc. complete as 70,499.00 Nos 4,159,441.00 41.59
per drawing and specifications as directed by the EIC.

Supplying, handling, transporting and fixing in position of V- fender with


anchor bolts, U hooks, Chains,shall be hot dip G.I coating with 80micron
including cutting, concrete chipping, drilling, grouting, necessary welding with
15 59 deck reinforcement steel and necessary coal tar painting(wherever required) 104,330.00 Nos 6,155,470.00 61.55
including all materials, labour, consumable items, machineries, tools,
tackles,transportation etc... and complete as per Engineer Incharge.

Conducting High Strain Dynamic Test as per standard practices(ASTMD 4945


of 1989) The rate is inclusive of testing, hire charges for all equipments like
transducers, strain gauge, oscilloscope hammer crane and cost of development
16 5 of pile concrete with line and dismantling the developed length of concrete, 298,090.00 Nos 1,490,450.00 14.90
transportation of equipment, labour and furnishing the test result etc., complete
and as directed by the EIC.
Providing temporary platform to convey the material to the working spot with
required angles, channels including welding etc., complete adjacent to Berthing
17 1680 structure (Jetty). 11,178.00 Sq.m 18,779,040.00 187.79

Carrying out Concrete mix test etc. complete as per specification & direction
18 80 of Engineer-in-charge. 2,980.00 Nos 238,400.00 2.38

Sub- Total I 272,444,300.64 2724.44


Unforeseen quantity and contigencies (7% of total cost) 19,071,101.04 190.71
utility services @ 12% 32,693,316.08 326.93
GST @ 12% 32,693,316.08 326.93
Total Amount Rs. (in crores) 35.70
Rupees Thirty five crores and seventy lakhs only
Name of work : Development of Fishing Harbour at Manakudi
MOBILE BOAT HOIST WHEEL APPROACH
SI.NO DESCRIPTION OF WORK Nos L(m) B(m) D(m) QTY UNIT

Setting up the piling gantry for 600mm dia piles and connected
equipment over each pile location, including cost of shifting, cost of all
1 materials for piling gantry, labour, setting up the rig to alignment and 36
correct dimensions as shown in the drawing and as directed by the EIC.
Total 36 Nos

Providing and fabricating M.S.liners of specified thickness for required


length with M.S. shoes of 1.0m height using 12mm thick M.S. plates for
bored vertical pile measured from cut off level of pile to the terminating
level including supplying, cutting, rolling, bending, handling and welding
2 cost, labours, materials, accessories,all taxes, hire and running charges of
all machineries, royality, labour, material, T&P, conveyance charges, Port
entry fees etc. all complete complete as per drawings and specification as
directed by Engineer-In-charge

a) From cut-off level (+)0.575 (-)10m (600 mm dia pile)


Liner 6mm thickness 36 3.14*(1.0+0.006)*0.006*9.575*7.85*36 92.11
Stiffner 12 mm thick 1000mm height 36 3.14*(1.006+0.012)*0.012*1*7.85*36 10.85
Total 102.96
Say 103.00 T

Boring for the piles to the required depth through all types of soil
strata including cemented sand, if any upto the rock touch level and
stacking the bored soil at convenient place and transported to the low lying
area anywhere inside /outside the harbour area within a lead of 4 Km or as
directed by the Engineer’s representative and pile shaft cleaning and
3
keeping of all records etc. including bentonite solution (where ever
required), labour, tools, equipment, fuel etc..all as per drawing,
specification etc complete as directed.

NOTE
i) In case the soil stratum at the founding level is loose the Engineer or his
representative may direct the contractor to carryout additional length of
boring and payment shall be made accordingly.

ii) The sample of bored materials of regular interval shall be collected and
produced for the verification of the Engineer or his representative at no
extra cost . in case any test reqiured by engineer in-charge, bored the
samples so collected shall be referred to an authorized laboratory / agency
identified by the Engineer , cost for testing shall be included in the quoted
rate. engineer in-charge decision regarding founding level is final.`no
claims in this regards are entertained.

iii) Boring through all type of soil strata means soft soil, weathered rock,
cemented sand, boulders and hard rock etc.,
iv) The boring in all type of soil measurement will be made on the basis
of depth of boring from encountered soft soil level to founding/pile
termination level.
v) All the boring depths shall be jointly measured actually at site and
Engineer in-charge decision is final.

Dia of Pile -600mm (Bed Level is (-) 4.0m CD) 36 - - 6.58 236.70
Total 236.70 Rm
Providing and laying reinforced cement concrete in concrete mix M40
for pile excluding cost of steel reinforcements in position as per approved
drawing and as directed by the Engineer-In-Charge including mixing,
4 laying, consolidating, curing, including all labours, slings, shackles, supply
of all labour, material, transportation cost, hire and running charges of all
machineries such as cranes, lorries etc., complete as directed by the
Engineer-In-Charge.
Dia of Pile -600mm (Cut-off level is 0.575m CD) 36 (π*1.0*1.0)/4 10.58 299.00
3
Total 299.00 m
3
Say 300.00 m
Chiseling/Breaking using suitable tools and equipments the top of
600mm Dia Pile concrete up to the receipt of dense concrete and dressing
the pile head suitably so as to receive the form work for deck work ,
including breaking to the required level exposing the pile reinforcement to
5 sufficient length as per approved drawing for embedding into the coping
beam etc. including removal of concrete debris from the site, supply of all
labour, material, transportation cost, hire and running charges of all
machineries complete as directed by the Engineer-In-Charge.

36 36 Nos
Total 36 Nos

DECK STRUCTURE
Providing and laying reinforced cement concrete in concrete mix M40
for slabs excluding cost of steel reinforcements in position as per approved
drawing and as directed by the Engineer-In-Charge including shuttering,
6 mixing, laying, consolidating, curing, including all labours, slings,
shackles, supply of all labour, material, transportation cost, hire and
running charges of all machineries such as cranes, lorries etc., complete as
directed by the Engineer-In-Charge.
3
In-situ slab - Mobile boat hoist wheel approach 1 40.00 2.00 0.15 12.00 m
3
In-situ slab - Mobile boat hoist wheel approach 1 40.00 2.00 0.15 12.00 m

3
Precast slab - Mobile boat hoist wheel approach 1 40.00 2.00 0.15 12.00 m
3
Precast slab - Mobile boat hoist wheel approach 1 40.00 2.00 0.15 12.00 m

3
Total 48.00 m
3
Say 48.00 m
Providing and laying reinforced cement concrete in concrete mix M40
for wearing coat as per approved drawing and as directed by the Engineer-
In-Charge including mixing, laying, consolidating, curing, including all
7 labours, slings, shackles, supply of all labour, material, transportation cost,
hire and running charges of all machineries such as cranes, lorries etc.,
complete as directed by the Engineer-In-Charge.
3
In-situ wearing coat - Mobile boat hoist wheel approach 1.0 40.0 2.0 0.075 6.00 m
3
Total 6.00 m
3
Say 6.00 m

Fabricating and placing in position of steel reinforcement TMT bars(Fe


500D) as per IS 1786 for all reinforced cement concrete pile including
lifting hook, cutting, bending, tying with 16 gauge G.I. binding wire and
welding to proper specifications wherever required including cost of steel
8 and binding wire, cover blocks of 100mm dia in CC M40 mix, supply of
with supply of all materials, labour, transportation, T&P, all taxes, tollage,
safety measures, port entry fees, VAT, etc. all complete as directed by the
Engineer-In-Charge.

Pile 1 300.00 250kg/m3 75.00 T


Total 75.00 T
Say 75.00 T

Supply of Fe500D steel confirming to IS specification of SAIL/ RINL/


TISCON/ Electro steel brands for Slabs including cutting, straightening,
bending , binding & plaving the grills in position for RCC works including
9 cost of binding wire of 16 to 18 gauge with supply of all materials, labour,
transportation, T&P, all taxes, tollage, safety measures, port entry fees,
VAT, etc. all complete as directed by the Engineer-In-Charge.

Slabs 1 48.00 200kg/m3 9.60 T


Total 9.60 T
Say 10.00 T
ABSTRACT
Name of work : Development of Fishing Harbour at Manakudi
ITEM AMOUNT (in
Qty DESCRIPTION RATE (Rs) UNIT AMOUNT (Rs)
NO: lakhs)
Setting up the piling gantry and connected equipment over each pile
location, including cost of shifting, cost of all materials for piling gantry,
1 36 labour, setting up the rig to alignment and correct dimensions as shown in 16,983.00 Nos 611,388.00 6.11
the drawing and as directed by the EIC.

Providing and fabricating M.S.liners of specified thickness for required


length with M.S. Shoes of 1.0m height using 12mm thick M.S. plates for
1000mm mm dia bored vertical pile measured from cut off level of pile to
the terminating level including supplying, cutting, rolling, bending,
handling and welding cost, labours, materials, accessories,all taxes, hire and
running charges of all machineries, royality,labour, material, T&P,
2 103 conveyance charges, Port entry fees etc. all complete complete as per 82,242.00 MT 8,470,926.00 84.71
drawings and specification as directed by Engineer-In-charge

Note:-
1.The stiffener shall be measured under this item.
In case the soil strata found to be not good in the founding level of the
liner, extra depth may be provided as per site condition.

Boring through all types of soils, boulders, hard starta and rocks etc.. for
750mm and 600mm Dia vertical bored piles from the existing ground level
3 237 (-)4.00m CD to the founding level (-)10.00m CD of the piles, including 32,044.00 Rm 7,584,814.80 75.85
bailing, flushing the bore bentonite with required density, chiselling,
shifting of materials etc.. complete as per directed by the Engineer-In-

Providing and laying reinforced cement concrete in concrete mix M40


for pile excluding cost of steel reinforcements in position as per approved
drawing and as directed by the Engineer-In-Charge including mixing,
4 300 laying, consolidating, curing, including all labours, slings, shackles, supply 8,602.00 m3 2,580,600.00 25.81
of all labour, material, transportation cost, hire and running charges of all
machineries such as cranes, lorries etc., complete as directed by the
Engineer-In-Charge.

Chiseling/Breaking using suitable tools and equipments the top of


600mm dia pile concrete up to the receipt of dense concrete and dressing
the pile head suitably so as to receive the form work for deck work ,
including breaking to the required level exposing the pile reinforcement to
5 36 sufficient length as per approved drawing for embedding into the coping 6,052.00 Nos 217,872.00 2.18
beam etc. including removal of concrete debris from the site, supply of all
labour, material, transportation cost, hire and running charges of all
machineries complete as directed by the Engineer-In-Charge.
Providing and laying reinforced cement concrete in concrete mix M40
for Slabs excluding cost of steel reinforcements in position as per approved
drawing and as directed by the Engineer-In-Charge including shuttering,
3
6 48 mixing, laying, consolidating, curing, including all labours, slings, shackles, 7,988.00 m 383,424.00 3.83
supply of all labour, material, transportation cost, hire and running charges
of all machineries such as cranes, lorries etc., complete as directed by the
Engineer-In-Charge.

Providing and laying reinforced cement concrete in concrete mix M40


for wearing coat as per approved drawing and as directed by the Engineer-
In-Charge including mixing, laying, consolidating, curing, including all
7 6 labours, slings, shackles, supply of all labour, material, transportation cost, 7,988.00 m3 47,928.00 0.48
hire and running charges of all machineries such as cranes, lorries etc.,
complete as directed by the Engineer-In-Charge.

Fabricating and placing in position of steel reinforcement TMT bars(Fe


500D) as per IS 1786 for all reinforced cement concrete pile including
lifting hook, cutting, bending, tying with 16 gauge G.I. binding wire and
welding to proper specifications wherever required including cost of steel
8 75 and binding wire, cover blocks of 100mm dia in CC M40 mix, supply of 68,510.00 MT 5,138,250.00 51.38
with supply of all materials, labour, transportation, T&P, all taxes, tollage,
safety measures, port entry fees, VAT, etc. all complete as directed by the
Engineer-In-Charge.

Supply of Fe500D steel confirming to IS specification of SAIL/ RINL/


TISCON/ Electro steel brands for Slabs including cutting, straightening,
bending , binding & plaving the grills in position for RCC works including
9 10 68,510.00 MT 685,100.00 6.85
cost of binding wire of 16 to 18 gauge with supply of all materials, labour,
transportation, T&P, all taxes, tollage, safety measures, port entry fees,
VAT, etc. all complete as directed by the Engineer-In-Charge.

Sub- Total I 25,720,302.80 257.20


Unforeseen quantity and Contigencies (7% of total cost) 1,800,421.20 18.00
Utility services @ 12% 3,086,436.34 30.86
GST @ 12% 3,086,436.34 30.86
Total Amount Rs. (in crores) 3.37
Rupees Three Crores and thirty seven lakhs only
Name of Work : Construction of Fishing Harbour at Manakudi in Kanyakumari District

Bill Of Quantities for Mobilization and Onshore Facilities

Sr.No Description Quantity Unit Basic Rate Total Amount

1 Mobilisation of all equipments , accessories, Model Study, Design of


LS 10,000,000.00
structures, etc.,
3 EXCAVATION
1 Earth work excavation for foundation in all soils and sub soils and to full
depth as may be directed except hard rock requiring blasting but
9369.00 Cum 235.00 2201714.857
inclusive of shoring, strutting and baling out water wherever necessary
and refilling the sides of foundation with
2 Earth work open excavation in all soils and sub soils and to full depth as
may be directed except in rock requiring blasting but inclusive of shoring,
strutting and boiling water wherever necessary and depositing the 3269.00 Cum 235.00 768216.0931
surplus earth within the compound in p

3 Filling the basement with excavated earth laid in layers if not more than
15 cm thick well watered and consolidated etc., complete as per 2521.00 Cum 90.00 226889.6598
standard specifications.
4 Supplying and filling in foundation and basement with filling river sand in
layers of not more than 15cm thick, well rammed, watered and
2227.00 Cum 1710.00 3808170.898
consolidated etc., complete complying with standard specification.

4 PLAIN CEMENT CONCRETE


1 Cement concrete of mix 1:4:8 ( One cement four sand and eight
aggregate) using 40 mm gauge HBG Jelly for foundation and flooring
including cost and conveyance of all material and labour charges for 1598.00 Cum 7565.00 12088844.37
laying land in layer of not more than 15 cm thick well ra

2 Cement Concrete 1:3:6 (One Cement, three sand and six hard broken
stone jelly) using 20 mm gauge hard broken granite stone jelly and laid
3.00 Cum 7750.00 23226.75
well rammed, consolidated and curing etc. complete complying with
standard specification
3 Cement concrete of mix 1:2:4 ( One cement four sand and eight
aggregate) using 20 mm gauge HBG Jelly for foundation and flooring
including cost and conveyance of all material and labour charges for 37.00 Cum 10450.00 386613.5295
laying land in layer of not more than 15 cm thick well ra

5 REINFORCED CEMENT CONCRETE


1 Providing and placing in situ design mix reinforcement cement concrete
of M30 (M.Thirty only) by weight basis using ordinary port land cement
(OPC) 43 grade confirming to IS 8112 and as per table 5 of BIS-456-2000 2262.00 Cum 12610.00 28523771.42
with minimum cement concrete of 440 (Four

2 Reinforced Cement Concrete 1:1 1/2:3 (one cement, one and half sand &
three of HBG stone jally) using 20 m.m. gauge hard broken granite stone
jelly for all RCC items of works with minimum cement content of
430.80Kgs/ Cum of concrete, excluding costand

RCC FOR BELOW BASEMENT 912.00 Cum 11710.00 10679555.55


RCC FOR ABOVE BASEMENT 643.80 Cum 12610.00 8118310.926
3 Reinforced cement concrete 1:2:4, using 20 mm gauge HBG stone jelly
including cost and conveyance of all materials to site excluding centering
401.00 Cum 9370.00 3757370
strutting and cost of reinforcement grill in position but including laying
curing etc., complete.
6 BRICK WALL
1 Brick work in cement mortar 1:5, using country bricks of size 8 3/4"x 4
1/4"x 2 1/4"for foundation and basement and superstructure etc.,
complete.
BRICK WALL FOR BELOW BASEMENT 1148.00 Cum 9370.00 10756726.31
BRICK WALL FOR ABOVE BASEMENT 636.00 Cum 10090.00 6417240.651
2 Brick partition wall in 11.5 cm thickness in cement mortar 1:3 using
country bricks of size 8 3/4"x 4 1/4"x 2 1/4" cost and conveyance and 878.00 Sqm 1300.00 1141400.26
labour charges etc., complete.
3 Randon rubble masonry in cement mortar 1:5 (One cement and five
sand) for foundation and basement using new R.R stones/ bond stones
including simultaneous flush pointing of the exposed surface and all 320.00 cum 5405.00 1729604.865
incidental charges such as baling out water, scaffold
Sr.No Description Quantity Unit Basic Rate Total Amount

7 STEEL REINFORCEMENT 0
1 Supplying, fabrication and placing in position plain/ribbed Tor steel for all
RCC works and providing fusion bonded coating not less than 175
microns thickness and upto 300 microns to reinforcement of all 197.00 M.T 114420.00 22540600.42
diameters as per I.S code 13620-1993 for plain/ RT

8 SHUTTERING AND CENTERING


1 Supplying and erecting steel centring including necessary supports for
plane surfaces in foundation and basement for reinforced cement
concrete works such as column footings, plinth beam, grade beam, raft 7522.00 Sqm 675.00 5077349.042
beam, raft slabs, bed blocks etc. using M.S. sheet

2 Supplying and erecting steel centring including necessary supports for


plane surfaces in foundation and basement for reinforced cement
4827.00 Sqm 720.00 3475443.211
concrete works such as,roof beam, roof slabs,lintel beam. using M.S.
sheet.
3 Supplying and erecting steel centring for sides and soffits including
supports and strutting up to a height of 3.65 meters for plain surfaces
3925.00 Sqm 750.00 2943753.3
such as RCC square and rectangular columns and sunshade. Top and
bottom slabs of sunshade boozing still slabs
9 PLASTERING
1 Plastering with Cement Mortar 1:5 (One cement and Five sand), 12mm
thick including finishing neatly curing etc. complete complying with 12345.00 Sqm 405.00 4999725.15
standard specification
2 Special ceiling plastering and finishing the exposed surface of RCC items
of work such as slab, beam, sunshade, facia, canopy slab, staircase waist
slab, landing slab etc. with Cement Mortar 1:3 (One Cement and Three 6216.00 Sqm 450.00 2797199.055
Sand) 10 mm thick including hacking th

3 Plastering with cm 1:3 (one cement and three sand) 12mm thick in all
floors including water proofing at 2%etc., complete complying with
0.00 Sqm 450.00
standard specification as directed by the departmental officers

4 Plastering with Cement Mortar 1:4 (One cement and four sand), 20 mm
thick including finishing neatly curing etc. complete complying with 5241.00 Sqm 470.00 2463271.429
standard specification
10 FLOORING
Providing granolithic floor finish of 25 mm thickness with plain cement
concrete 1:2:4 (one cement ,two sand and four aggregate using 10mm to
1 12mm size hard broken granite stone jelly etc) complete complying witth 174.00 Sqm 290.00 50460.841
standard specification and as directed by

Paving the floor with Colour design Ceramic tiles of size 300 x 300 x 6
mm
in all floors over a base layer of Cement Mortar 1:3 (One cement and
2 three sand) 20mm thick and pointed with white cement mixed with 135.00 Sqm 1190.00 160650
colouring pigments at the rate of 0.3 Kg/sq.m i

Flooring with Polished cuddapah slab of 20-30 mm thick laid in C.M 1:3
(One Cement and three sand) 20 mm thick and pointing with cement
3 mortar 1:3 (One cement and three sand) complying with standard 1432.00 Sqm 1080.00 1546556.112
specification. The size of slab should be 600 X 600 mm

Dadoing the walls with best approved first quality plain colour Glazed
tiles of size 150 mm X 150 mm X 6 mm set in Cement Mortar 1:2 (One
4 cement and two sand) 10mm thick and pointed with white cement 492.00 Sqm 1045.00 514136.3425
mixed with colouring pigments at the rate of 0.40 kg.

Supplying and fixing of 17-18 mm thick black granite slab on brick pillar
as
5 101.00 Sqm 3965.00 400465
directed by the Departmental Officers
Supplying & fixing Eurocon of size 30 cm x 30 cm set in cement mortar
1:2, 10mm thick and pointed with white cement mixed with colouring
6 pigments at the rate of 0.40Kg/Sq.m, finishing neatly and curing etc 4026.00 Sqm 1065.00 4287690
complete as directed by the Departmental Engineer

Supply and fixing Paver block for Pavement 100 mm thick Paver block
7 M30 grade ,finishing neatly etc complete as directed by the Department 1388.00 Sqm 1710.00 2373488.208
Engineer
Sr.No Description Quantity Unit Basic Rate Total Amount

11 TERRACE FLOORING
Finishing the top of roof with one course of approved first quality
Machine Pressed Tiles of size 200mm x 200mm x 20mm thick laid in
1 Cement Mortar 1:3 (one cement and three sand) 12mm thick mixed with 2410.00 Sqm 1330.00 3205297.606
water proofing compound conforming to Indian standard

Weathering course concrete using best quality broken brick jelly of size
20mm uniform gauge in pure slaked lime in the proportion of brick jelly
2 to lime being 32:12-1/2 by volume and laid over the RCC roof slab in a 250.00 Cum 3600.00 900005.2992
single layer and consolidated to the re

12 PAINTING AND COLOUR WASHING


Painting the wall with two coats of Plastic emlusion paint of approved
quality colour and make over plastered surfaces and ceiling with a
1 13224.00 Sqm 320.00 4231680.768
priming coat including clearing, preparation of wall surfaces and cruing
etc., complete complying with standard speci
Painting new iron works such as steel doors, windows,ventilators
window barsbalustrades etc. with two coats to best approved first
2 quality and colour of synthetic enamel paint over the existing red-oxide 283.00 Sqm 290.00 82070
priming coat in all floors excluding cost of primi

13 SANITARY ARRANGMENTS
1 Supplying and fixing in position best approved quality and make white
glazed earthern ware oriya type Indian water closet of size 580 mm x 440
4.00 Each 2160.00 8640
mm with P or S trap embedding the closest and trap to shape in position
with brick jelly lime concrete 1:2:5 (on
2 Supplying and fixing of European water closet (White ) with 10 litres
capacity flusing tank (low level) of best quality and approved make with
100 mm size ‘p’ or ‘s’ tap with double flapped PVC rigid PVC cover with 2.00 Each 7270.00 14540
CP brass hinges etc, complete complyi

3 Supplying and fixing White Lipped mouth porcelin Flat Back Urinal with
all accessories such as 32 mm dia Bell mouth PVC connection , 15 mm dia
G.M Wheel vavle , 15 mm dia "B" class G.I Waster water pipes , 15 mm 6.00 Each 2883.00 17298
dia Nylon connection 15 mm dia Brass nipple

4 Supplying and fixing in position best quality and approved make of colour
wash hand basin of size 550 x 400 mm necessary cast iron bracket 15mm
dia chromium plated pillar tap 32mm dia 'B' class pvc Waste pipe 32mm 7.00 Each 4500.00 31500
chromium plated brass waste coupling with

5 Supplying and fixing of urinal partition with both side polished white
marble slabs of 20 mm thick with a size of 4' x 2' ( 1.22 x 0.61 M ) and
8.00 Each 3600.00 28800
fixin g with the wall by forming grooves grouting with cement mortar
making good the damaged portion includi
Supplying and fixing in position GULLY TRAP ( 150 mm x 100 mm)
6 fixed
with brick jelly lime concrete 1:2:5 ( one part of lime and 2 parts of sand
6.00 Each 450.00 2700
and 5 parts of 20mm brick jelly )over a bed cement concrete 1:3:6 using
20mm stone jelly complete.
7 Supplying and fixing best approved quality colour Porcelin Soap dish of
size 150 mm x 150 mm x 50 mm including cost of teak wood plugs , brass 10.00 Each 540.00 5400
screws complete with standard specification.
8 Supplying and fixing in position best quality anodoised aluminium plated
Towel rail of 600 mm length and with 20 mm dia CP brackets of same
8.00 Each 1080.00 8640
materias including cost of TW plugs chromium plated brass screw etc.

Supplying and fixing in posotion cast iron NAHINI TRAP of size 100 x
9 75
mm with best stainless steel gratings of approved brand and quality fixed
30.00 Each 360.00 10800
over a bed of brick jelly lime concrete 1:2:5 ( 1 part of lime, 2part of sand
nad 5 part of 20mm brick jelly
10 Supplying and fixing 4" ( 150 mm ) dia stone ware pipes including laying
earthwork excavation, jointing with cement mortar with spun yarn etc., 126.00 Rm 650.00 81900
complete
Supplying laying and jointing P.V.C pipe 4" (150 mm) dia (6 Kg / SqCm )
11 of
approved quality and best variety conforming to I.S.S & with I.S.I mark, of
51.00 Rm 755.00 38505
the following sizes including cutting , fixing to PVC specials using
adhesive but excluding cost of such
12 Supplying and fixing in position best quality Bevelled Edge Mirror of size
600 x 450 mm shelf type with necessary plywood backing rubber buttons
7.00 Each 1080.00 7560
brass chromium plated screws, plug etc. complete complying with
standard specification.
Sr.No Description Quantity Unit Basic Rate Total Amount

14 WATER SUPPLY ARRANGMENT


Supplying and fixing in position first quality Gun metal PUSH COCK -
1 1/2"(
15mm ) dia with ISI mark including cost of shellac, thread etc including
73.00 Each 1080.00 78840
labour for cutting threading of G.I pipe etc complete both internal and
external water supply arrangements.
2 Supplying and fixing in position first quality and approved variety of Gun
Metal Wheel Valve heavy type with ISI mark of the following sizes
including cost of shellac, thread, including labour charges for cutting and 15.00 Each 1080.00 16200
threading of PVC pipes as directed by

Supplying and fixing in position best approved of ISI quality of 110mm


3 dia
PVC rain water down fall pipes having a working pressure of 4Kg./sq.cm
including cost of necessry PVC shoe, PVC bend, C.I. gratings of required 219.00 Rm 450.00 98550
diameter and special clamps, brass

Supplying and fixing of HDPE pipe 140mm dia as per specification and
4 as
15.00 Rm 1260.00 18900
directed by the departmental officers
5 Supplying and fixing in position best approved of ISI quality of Syntex
6.00 Each 10810.00 64860
tank of 1000 litres capacity
15 ROAD

Providing and laying Granular Sub base grade I designed to give


minimum soaked CBR value of 30 including conveyance of gravel crushed
1 1014.00 Cum 2522.00 2557308
stone or quarry fines or any other granular materials or combination of
those to the work site and mixing the required qu

Providing and laying WBM 75 mm compacted thickness with grade-II


metal using 1.00 cum of 63-45mm IRC size HBG metal with 0.24 cum of
2 gravel for blindage per 10 sqm including cost and conveyance of all 255.00 Cum 3243.00 826948.785
materials ,labour charges for spreading metal and grav

Providing and laying WBM 75 mm compacted thickness Grade-I,metal


using 1.00cum of 53-26.5mm IRC size HBG metal with 0.24 cum gravel
3 for blindage per 10 s.qm including cost and conveyance of all 255.00 Cum 3423.00 872847.885
materials,labour charges for spreading metals and gravel ,han

Providing and laying of Tack coat 4kg per 10 sq.m over the unprimed
WBM surface using 4 kg of 60/70 grade bitumen including labopur for
4 preparing the surface and applying the required quantity of bitumen as 3376.00 Sqm 35.00 118160
tack coat by bitumen sprayer etc., complete as p

Providing and laying and compacting open graded premix carpet 20mm
thick using graded HBG 13.2mm-6.70mm IRC metal and 60/70 bitumen
5 with a liquid seal coat which shall consist of open graded carpet of 20mm 3376.00 Sqm 575.00 1941200
thickness in single course composed of suitable s

Providing and laying Bituminous macadam using graded HBG metal and
bitumen 60/70 grade as per approved job mix formula including cost and
6 conveyance of all materials to the site including bitumen,heating the 170.00 Cum 8650.00 1470500
bitumen and aggregate to required temperature a

16 MISCELLANEOUS ITEMS
1 Fabricating, supplying and fixing in position of aluminium anodised
natural colour matt finished Door of double leaved with shutters
panelled top 2/3rd portion with plain glass of 5.5 mm thick and 19.00 Sqm 6850.00 130150
aluminium grill of 10 mm thick standard pattern (diamond

Supplying and fixing of factory made PVC rigid panel door made from
2 MS
tubes of 19 Gauge size of 19 mm X 19 mm and covered with head
moulded PVC channel of 5 mm thick and width of 50 mm to form styles 19.00 Sqm 3600.00 68382
and rails. The inner panel should be inserted betwee

3 Fabricating, supplying and fixing in position of Aluminium anodised


natural colour matt finish sliding windows in all floors with sliding
arrangements and gutter arrangements so as to drain the water 37.00 Sqm 5405.00 199985
entering, for TWO TRACk WINDOWS the outer frames being

4 Fabricating, supplying and fixing in position of Aluminium natural colour


matt finish louvered Ventilator in all floors made with extruded
aluminium section of following size with necessary accessories such as 51.00 Sqm 6305.00 321555
rubber beading best quality of handle, lock i

5 Manufacturing and fixing of pull and push type Rolling shutters of


required sizes confirming to IS 8248/1971 with ISI mark made out of 18
gauge 75 mm wide CRCA lath section with rolling centres of 76 mm and 46.00 Sqm 4500.00 207000
effective bridge depth of 12 mm with out any wel
Sr.No Description Quantity Unit Basic Rate Total Amount

6 Construction of Inspection Chamber of inner clear size of 0.60 M X 0.60


M meters and average depth of 0.75 m with a base concrete of 100 mm
thick cement concrete 1 : 5 : 10 (One cement, five sand and 10 27.00 Each 8108.00 218916
aggregate) the chamber should be constructed in

7 Casting supplying and fixing of reinforced cement concrete Jally of 5 cm


thickness in Cement Concrete 1 : 2 : 4 (One cement , Two sand and Four
aggregate) with minimum cement content of 323.10Kgs/ Cum of 289.00 Sqm 1440.00 416160
concrete, excluding cost of reinforced grill in pos

8 Supplying and fixing of MS grill for steel gate, Hand rail, Steel ladder and
Chequered plate of required size and design with one coat of primer as 9.00 MT 104508.00 940673.1499
specified by the departmental officers
9 Providing and laying of sand gravel mix of 1:1 ratio including cost of
materials, conveyance charges to site, mixing , spreading to proper
1566.00 Cum 2162.00 3385689.038
camber, watering consolidation and compacting etc., complete.

Providing and fixing in position CI man hole cover (heavy duty) of size
10 450
mm X 450 mm of best approved quality and as per standard
9.00 Each 2162.00 19458
specification including fixing the frame in concrete all complete and as
directed by the departmental officers
Providing and fixing in position M.S rungs of approved quality of size
11 400
X 250 mm and required shape, including fixing in brick work using
38.00 Each 450.00 17100
cement concrete 1 : 1 ½ : 3 (one of cement, and onc and half sand and
three aggregate) and RCC structures all co
Supplying and fixing of Pre cast slab R.C.C 1:2:4 125 mm Thick
12 including
cost of mould, finishing etc., complete including of reinforcement 547.00 Sqm 1800.00 984595.68

13 Supplying and fixing of 110mm dia air vent pipe of PVC material with
necessary cowl and masonry structure etc complete as specified by the 2.00 Each 900.00 1800
departmental officers
14 Supplying and filling the percolation pit with 53 mm to 40 mm grade HBG
stone jelly including stacking for pre measurement as directed by the 11.00 Cum 1620.00 17820
departmental officers
15 Supplying and fixing in position wooden log in country wooden Cover
frame of cross section of 400 X 200 mm as directed by the departmental 11.00 Cum 162168.00 1783848
officers.
16 Supplying and fixing in position wooden log in country wood Beam of
cross section of 300 X 300 mm to concrete floor of slip way as directed by 8.00 Cum 162168.00 1297344
the departmental officers.
17 Supplying and fixing in posting of the Rubber fenders at 2 m centre to
centre using 200 x 100 mm and fixed with galvanized fixtures and
137.00 Each 48650.00 6665050
accessories etc. complete as directed by department officers.

18 Supplying and Fixing galvanized life chain 0.00 Each


Sub Total 187,673,621.46
% Unforseen quantities and Contigencies - (7% of total cost) 13,137,153.50
Utitlity Services @ 12% 22,520,834.58
GST @
12% 22,520,834.58
Gross Total Amount 245,852,444.12
Gross Total Amount in Crores (say) 24.59
Rupees Twenty four crores and fifty nine lakhs only
Filename: Document1
Directory:
Template:
C:\Users\User\AppData\Roaming\Microsoft\Templates\Normal.do
tm
Title:
Subject:
Author: HP
Keywords:
Comments:
Creation Date: 6/21/2018 10:22:00 AM
Change Number: 1
Last Saved On:
Last Saved By:
Total Editing Time: 0 Minutes
Last Printed On: 6/21/2018 10:22:00 AM
As of Last Complete Printing
Number of Pages: 24
Number of Words: 12,628 (approx.)
Number of Characters: 71,985 (approx.)