Professional Documents
Culture Documents
Core Layer (10-500 Kg) 53.70 107.00 5745.90 0.70 4022.13 10658.64
Filter Layer (1-50 Kg)
(with shrinkage 10%) 19.30 107.00 2065.10 0.70 1445.57 4213.84
100 to 300 Kg 5.70 107.00 609.90 0.70 426.93 1131.36
40 mm stones 2.00 107.00 214.00 0.90 192.60 510.39
PCC 1:4:8 0.80 107.00 85.60 1.00 85.60 205.44
RCC M35 5.00 107.00 535.00 1.00 535.00 1337.50
Quantity
Materials (T/Cum)
EASTERN BREAKWATER
Sl.No
RATE (Rs)
QUANTITY UNIT AMOUNT (Rs)
1 Armour Layer PER unit
Providing concrete Tetrapod weighing ( 2T, 4T & 6T) in plain cement concrete M35
grade including, casting, finishing and curing, transporting placing in position as per
approved design and slope over a Armour layer of rubble mounded Break water.complete
as directed by the departmental officers and as per the drawings and specifications and as
per the condition laids in special conditions. The side slope should maintain as 1:1.5.
Porasity has assumed as 50 %.
TOTAL -
Formation of Core filling layer, with quarry stones (rough angular) weighing 50 kg to 500
kg with unit weight not less than 2.65 T/m3, loading at quarry, conveying in contractors
transporting by tippers / lorries including weighing in the electronic weigh bridge for the
purpose of measurment, Unloading/dumping placing in position to required level, profile
using crane and dumping into the sea with required width with necessary equipment and
45511.50T 1480 67,357,016.30
devices as per the drawings and specification etc., as directed by the Department Officers.
( The payment shall be made on weight basis (ie) laden weight minus unladden weight).
The contractor has to make his own arrangements for weigh bridge in the presence of
Department Officers. Porasity has assumed as 70 %.
Formation of Bedding Layer for rubble mound breakwater with quarry run hard blue
granite stone of weighing 1 kg to 50 kg having a specific gravity of not less than 2.65
T/m3 as per approved design and drawing including quarrying, loading transporting by
tippers/lorries weighing in the electronic weigh bridge for measurement, dumping, placing
in position to required level, profile with necessary equipment and devices as per the
drawings and specification etc complete as directed by the Departmental Officers. The 14872.59T 1480 22,011,436.68
rate is also inclusive of placing, sectioning and finishing with necessary equipment and
devices and hire and operational charges of tools and plants etc. (The payment shall be
made on weight basis (ie) laden weight minus unladden weight). The contractor has to
make his own arrangements for weigh bridge. Porasity has assumed as 70 %. The
additional volume of 10% should be added for shrinkage.
4 Subgrade (100 to 300 Kg) -
Formation of subgrade Layer of 0.5 m thickness for rubble mound breakwater with quarry
run hard blue granite stone of weighing 100 kg to 300 kg having a specific gravity of not
less than 2.65 T/m3 as per approved design and drawing including quarrying, loading
transporting by tippers/lorries weighing in the electronic weigh bridge for measurement,
dumping, placing in position to required level, profile with necessary equipment and
devices as per the drawings and specification etc complete as directed by the 2671.01 T 1480 3,953,101.46
Departmental Officers. The rate is also inclusive of placing, sectioning and finishing with
necessary equipment and devices and hire and operational charges of tools and plants etc.
(The payment shall be made on weight basis (ie) laden weight minus unladden weight).
The contractor has to make his own arrangements for weigh bridge. Porasity has assumed
as 70 %.
Base coarse (40 mm Stones)
-
Formation of base coarse Layer of 0.5 m thickness for rubble mound breakwater with
quarry run hard blue granite stone of 40 mm in size having a specific gravity of not less
than 2.65 T/m3 as per approved design and drawing including quarrying, loading
transporting by tippers/lorries weighing in the electronic weigh bridge for measurement,
dumping, placing in position to required level, profile with necessary equipment and
devices as per the drawings and specification etc complete as directed by the 1203.71 Cum 2407 2,897,328.77
Departmental Officers. The rate is also inclusive of placing, sectioning and finishing with
necessary equipment and devices and hire and operational charges of tools and plants etc.
(The payment shall be made on weight basis (ie) laden weight minus unladden weight).
The contractor has to make his own arrangements for weigh bridge. Porasity has assumed
as 90 %.
PCC 1:4:8 -
Formation of Plain Cement Concrete layer under the crest pavement which has a unit
weight of not less than 2.4 T/m3 as per approved design and drawing including mixing,
loading transporting by tippers/lorries weighing in the electronic weigh bridge for
measurement, dumping, placing in position to required level, profile with necessary
equipment and devices as per the drawings and specification etc complete as directed by
the Departmental Officers. The rate is also inclusive of placing, sectioning and finishing 484.51 Cum 3860 1,870,216.32
with necessary equipment and devices and hire and operational charges of tools and plants
etc. (The payment shall be made on weight basis (ie) laden weight minus unladden
weight). The contractor has to make his own arrangements for weigh bridge
Formation of Concrete road to faciliate vehicle movement having a unit weight of not less
than 2.4 T/m3 as per approved design and drawing including mixing, loading transporting
by tippers/lorries weighing in the electronic weigh bridge for measurement, dumping,
placing in position to required level, profile with necessary equipment and devices as per
the drawings and specification etc complete as directed by the Departmental Officers.
The rate is also inclusive of placing, sectioning and finishing with necessary equipment and 3176.50 Cum 7430 23,601,395.00
devices and hire and operational charges of tools and plants etc. (The payment shall be
made on weight basis (ie) laden weight minus unladden weight). The contractor has to
make his own arrangements for weigh bridge
Core Layer (10-500 Kg) 53.70 107.00 5745.90 0.70 4022.13 10658.64
Filter Layer (1-50 Kg)
(with shrinkage 10%) 19.30 107.00 2065.10 0.70 1445.57 4213.84
100 to 300 Kg 5.70 107.00 609.90 0.70 426.93 1131.36
40 mm stones 2.00 107.00 214.00 0.90 192.60 510.39
PCC 1:4:8 0.80 107.00 85.60 1.00 85.60 205.44
RCC M35 5.00 107.00 535.00 1.00 535.00 1337.50
WESTERN BREAKWATER
Sl.No
RATE (Rs)
QUANTITY UNIT AMOUNT (Rs)
1 Armour Layer PER unit
Providing concrete Tetrapod weighing ( 2T, 4T & 6T) in plain cement concrete M35
grade including, casting, finishing and curing, transporting placing in position as per
approved design and slope over a Armour layer of rubble mounded Break water.complete
as directed by the departmental officers and as per the drawings and specifications and as
per the condition laids in special conditions. The side slope should maintain as 1:1.5.
Porasity has assumed as 50 %.
TETRAPOD - 2 T (0.86 cum)
1277.40Cum 18,407,334.00
14410
TETRAPOD - 4 T (1.67 cum) 10304.95Cum 148,494,329.50
14410
TETRAPOD - 6 T (2.5 cum) 911.40Cum 14410 13,133,274.00
TOTAL -
-
GR-C (1-2 T)
107547.22T 1480 159,169,879.31
TOTAL -
Formation of Core filling layer, with quarry stones (rough angular) weighing 50 kg to 500
kg with unit weight not less than 2.65 T/m3, loading at quarry, conveying in contractors
transporting by tippers / lorries including weighing in the electronic weigh bridge for the
purpose of measurment, Unloading/dumping placing in position to required level, profile
using crane and dumping into the sea with required width with necessary equipment and 153018.67T 1480 226,467,634.19
devices as per the drawings and specification etc., as directed by the Department Officers.
( The payment shall be made on weight basis (ie) laden weight minus unladden weight).
The contractor has to make his own arrangements for weigh bridge in the presence of
Department Officers. Porasity has assumed as 70 %.
4 Bedding Layer (1 to 50 Kg) -
-
Formation of Bedding Layer for rubble mound breakwater with quarry run hard blue
granite stone of weighing 1 kg to 50 kg having a specific gravity of not less than 2.65
T/m3 as per approved design and drawing including quarrying, loading transporting by
tippers/lorries weighing in the electronic weigh bridge for measurement, dumping, placing
in position to required level, profile with necessary equipment and devices as per the
drawings and specification etc complete as directed by the Departmental Officers. The
39679.56T 1480 58,725,753.24
rate is also inclusive of placing, sectioning and finishing with necessary equipment and
devices and hire and operational charges of tools and plants etc. (The payment shall be
made on weight basis (ie) laden weight minus unladden weight). The contractor has to
make his own arrangements for weigh bridge. Porasity has assumed as 70 %. The
additional volume of 10% should be added for shrinkage.
4 Subgrade (100 to 300 Kg) -
Formation of subgrade Layer of 0.5 m thickness for rubble mound breakwater with quarry
run hard blue granite stone of weighing 100 kg to 300 kg having a specific gravity of not
less than 2.65 T/m3 as per approved design and drawing including quarrying, loading
transporting by tippers/lorries weighing in the electronic weigh bridge for measurement,
dumping, placing in position to required level, profile with necessary equipment and
devices as per the drawings and specification etc complete as directed by the 7133.03 T 1480 10,556,886.62
Departmental Officers. The rate is also inclusive of placing, sectioning and finishing with
necessary equipment and devices and hire and operational charges of tools and plants etc.
(The payment shall be made on weight basis (ie) laden weight minus unladden weight).
The contractor has to make his own arrangements for weigh bridge. Porasity has assumed
as 70 %.
Formation of base coarse Layer of 0.5 m thickness for rubble mound breakwater with
quarry run hard blue granite stone of 40 mm in size having a specific gravity of not less
than 2.65 T/m3 as per approved design and drawing including quarrying, loading
transporting by tippers/lorries weighing in the electronic weigh bridge for measurement,
dumping, placing in position to required level, profile with necessary equipment and
devices as per the drawings and specification etc complete as directed by the 3216.65 Cum 2407 7,742,475.35
Departmental Officers. The rate is also inclusive of placing, sectioning and finishing with
necessary equipment and devices and hire and operational charges of tools and plants etc.
(The payment shall be made on weight basis (ie) laden weight minus unladden weight).
The contractor has to make his own arrangements for weigh bridge. Porasity has assumed
as 90 %.
PCC 1:4:8 -
Formation of Plain Cement Concrete layer under the crest pavement which has a unit
weight of not less than 2.4 T/m3 as per approved design and drawing including mixing,
loading transporting by tippers/lorries weighing in the electronic weigh bridge for
measurement, dumping, placing in position to required level, profile with necessary
equipment and devices as per the drawings and specification etc complete as directed by
1294.75 Cum 3860 4,997,742.72
the Departmental Officers. The rate is also inclusive of placing, sectioning and finishing
with necessary equipment and devices and hire and operational charges of tools and plants
etc. (The payment shall be made on weight basis (ie) laden weight minus unladden weight).
The contractor has to make his own arrangements for weigh bridge
Formation of Concrete road to faciliate vehicle movement having a unit weight of not less
than 2.4 T/m3 as per approved design and drawing including mixing, loading transporting
by tippers/lorries weighing in the electronic weigh bridge for measurement, dumping,
placing in position to required level, profile with necessary equipment and devices as per
the drawings and specification etc complete as directed by the Departmental Officers. 8451.50 Cum 7430 62,794,645.00
The rate is also inclusive of placing, sectioning and finishing with necessary equipment and
devices and hire and operational charges of tools and plants etc. (The payment shall be
made on weight basis (ie) laden weight minus unladden weight). The contractor has to
make his own arrangements for weigh bridge
Setting up the piling gantry for 1000mm dia piles and connected
equipment over each pile location, including cost of shifting, cost of all
1 materials for piling gantry, labour, setting up the rig to alignment and 257
correct dimensions as shown in the drawing and as directed by the EIC.
Total 257 Nos
Boring for the piles to the required depth through all types of soil
strata including cemented sand, if any upto the rock touch level and
stacking the bored soil at convenient place and transported to the low lying
area anywhere inside /outside the harbour area within a lead of 4 Km or as
directed by the Engineer’s representative and pile shaft cleaning and
3
keeping of all records etc. including bentonite solution (where ever
required), labour, tools, equipment, fuel etc..all as per drawing,
specification etc complete as directed.
NOTE
i) In case the soil stratum at the founding level is loose the Engineer or his
representative may direct the contractor to carryout additional length of
boring and payment shall be made accordingly.
ii) The sample of bored materials of regular interval shall be collected and
produced for the verification of the Engineer or his representative at no
extra cost . in case any test reqiured by engineer in-charge, bored the
samples so collected shall be referred to an authorized laboratory / agency
identified by the Engineer , cost for testing shall be included in the quoted
rate. engineer in-charge decision regarding founding level is final.`no
claims in this regards are entertained.
iii) Boring through all type of soil strata means soft soil, weathered rock,
cemented sand, boulders and hard rock etc.,
iv) The boring in all type of soil measurement will be made on the basis
of depth of boring from encountered soft soil level to founding/pile
termination level.
v) All the boring depths shall be jointly measured actually at site and
Engineer in-charge decision is final.
Dia of Pile -1000mm (Bed Level is (-) 4.0m CD) 257 - - 6.58 1691.06
Total 1691.06 Rm
Providing and laying reinforced cement concrete in concrete mix M40
for pile excluding cost of steel reinforcements in position as per approved
drawing and as directed by the Engineer-In-Charge including mixing,
4 laying, consolidating, curing, including all labours, slings, shackles, supply
of all labour, material, transportation cost, hire and running charges of all
machineries such as cranes, lorries etc., complete as directed by the
Engineer-In-Charge.
Dia of Pile -1000mm (Cut-off level is 0.575m CD) 257 (π*1.0*1.0)/4 10.58 2134.54
3
Total 2134.54 m
3
Say 2135.00 m
Chiseling/Breaking using suitable tools and equipments the top of
1000mm Dia Pile concrete up to the receipt of dense concrete and dressing
the pile head suitably so as to receive the form work for deck work ,
including breaking to the required level exposing the pile reinforcement to
5 sufficient length as per approved drawing for embedding into the coping
beam etc. including removal of concrete debris from the site, supply of all
labour, material, transportation cost, hire and running charges of all
machineries complete as directed by the Engineer-In-Charge.
DECK STRUCTURE
Providing and laying reinforced cement concrete in concrete mix M40
for Pile muff excluding cost of steel reinforcements in position as per
approved drawing and as directed by the Engineer-In-Charge including
6 shuttering, mixing, laying, consolidating, curing, including all labours,
slings, shackles, supply of all labour, material, transportation cost, hire and
running charges of all machineries such as cranes, lorries etc., complete as
directed by the Engineer-In-Charge.
3
In-situ slab - Transition section at Approach jetty 658.50 0.15 98.78 m
3
Precast slab - Transition section at Approach jetty 658.50 0.15 98.78 m
3
Total 1496.31 m
3
Say 1497.00 m
Providing and laying reinforced cement concrete in concrete mix M40
for wearing coat as per approved drawing and as directed by the Engineer-
In-Charge including mixing, laying, consolidating, curing, including all
9 labours, slings, shackles, supply of all labour, material, transportation cost,
hire and running charges of all machineries such as cranes, lorries etc.,
complete as directed by the Engineer-In-Charge.
3
In-situ wearing coat - Main Jetty 1.0 310.0 10.0 0.075 232.50 m
3
In-situ wearing coat - Approach Jetty 1 87.8 14.0 0.075 92.19 m
3
In-situ wearing coat - Transition section at Approach Jetty 1 658.5 0.075 49.39 m
3
Total 324.69 m
3
Say 325.00 m
Carrying out Concrete mix test etc. complete as per specification &
direction of Engineer-in-charge.
18 80 Nos
ABSTRACT
Name of work : Development of Fishing Harbour at Manakudi
ITEM AMOUNT (in
Qty DESCRIPTION RATE (Rs) UNIT AMOUNT (Rs)
NO: lakhs)
Setting up the piling gantry and connected equipment over each pile location,
including cost of shifting, cost of all materials for piling gantry, labour, setting
1 257 up the rig to alignment and correct dimensions as shown in the drawing and as 16,983.00 Nos 4,364,631.00 43.65
directed by the EIC.
Note:-
1.The stiffener shall be measured under this item.
In case the soil strata found to be not good in the founding level of the liner,
extra depth may be provided as per site condition.
Boring through all types of soils, boulders, hard starta and rocks etc.. for
750mm and 600mm Dia vertical bored piles from the existing ground level (-
)4.00m CD to the founding level (-)10.00m CD of the piles, including bailing,
3 1691 flushing the bore bentonite with required density, chiselling, shifting of 32,044.00 Rm 54,188,326.64 541.88
materials etc.. complete as per directed by the Engineer-In-charge.
Providing and laying reinforced cement concrete in concrete mix M40 for
pile excluding cost of steel reinforcements in position as per approved drawing
and as directed by the Engineer-In-Charge including mixing, laying,
4 2135 consolidating, curing, including all labours, slings, shackles, supply of all 8,602.00 m3 18,365,270.00 183.65
labour, material, transportation cost, hire and running charges of all machineries
such as cranes, lorries etc., complete as directed by the Engineer-In-Charge.
Providing and laying reinforced cement concrete in concrete mix M40 for
Pile muff excluding cost of steel reinforcements in position as per approved
drawing and as directed by the Engineer-In-Charge including shuttering,
6 227 mixing, laying, consolidating, curing, including all labours, slings, shackles, 7,988.00 m3 1,813,276.00 18.13
supply of all labour, material, transportation cost, hire and running charges of
all machineries such as cranes, lorries etc., complete as directed by the Engineer
In-Charge.
Providing and laying reinforced cement concrete in concrete mix M40 for
Beams excluding cost of steel reinforcements in position as per approved
drawing and as directed by the Engineer-In-Charge including shuttering,
3
7 1003 mixing, laying, consolidating, curing, including all labours, slings, shackles, 7,988.00 m 8,011,964.00 80.12
supply of all labour, material, transportation cost, hire and running charges of
all machineries such as cranes, lorries etc., complete as directed by the Engineer
In-Charge.
Providing and laying reinforced cement concrete in concrete mix M40 for
Slabs excluding cost of steel reinforcements in position as per approved
drawing and as directed by the Engineer-In-Charge including shuttering,
mixing, laying, consolidating, curing, including all labours, slings, shackles,
8 1497 supply of all labour, material, transportation cost, hire and running charges of 7,988.00 m3 11,958,036.00 119.58
all machineries such as cranes, lorries etc., complete as directed by the Engineer
In-Charge.
Providing and laying reinforced cement concrete in concrete mix M40 for
wearing coat as per approved drawing and as directed by the Engineer-In-
Charge including mixing, laying, consolidating, curing, including all labours,
9 325 slings, shackles, supply of all labour, material, transportation cost, hire and 7,988.00 m3 2,596,100.00 25.96
running charges of all machineries such as cranes, lorries etc., complete as
directed by the Engineer-In-Charge.
Carrying out Concrete mix test etc. complete as per specification & direction
18 80 of Engineer-in-charge. 2,980.00 Nos 238,400.00 2.38
Setting up the piling gantry for 600mm dia piles and connected
equipment over each pile location, including cost of shifting, cost of all
1 materials for piling gantry, labour, setting up the rig to alignment and 36
correct dimensions as shown in the drawing and as directed by the EIC.
Total 36 Nos
Boring for the piles to the required depth through all types of soil
strata including cemented sand, if any upto the rock touch level and
stacking the bored soil at convenient place and transported to the low lying
area anywhere inside /outside the harbour area within a lead of 4 Km or as
directed by the Engineer’s representative and pile shaft cleaning and
3
keeping of all records etc. including bentonite solution (where ever
required), labour, tools, equipment, fuel etc..all as per drawing,
specification etc complete as directed.
NOTE
i) In case the soil stratum at the founding level is loose the Engineer or his
representative may direct the contractor to carryout additional length of
boring and payment shall be made accordingly.
ii) The sample of bored materials of regular interval shall be collected and
produced for the verification of the Engineer or his representative at no
extra cost . in case any test reqiured by engineer in-charge, bored the
samples so collected shall be referred to an authorized laboratory / agency
identified by the Engineer , cost for testing shall be included in the quoted
rate. engineer in-charge decision regarding founding level is final.`no
claims in this regards are entertained.
iii) Boring through all type of soil strata means soft soil, weathered rock,
cemented sand, boulders and hard rock etc.,
iv) The boring in all type of soil measurement will be made on the basis
of depth of boring from encountered soft soil level to founding/pile
termination level.
v) All the boring depths shall be jointly measured actually at site and
Engineer in-charge decision is final.
Dia of Pile -600mm (Bed Level is (-) 4.0m CD) 36 - - 6.58 236.70
Total 236.70 Rm
Providing and laying reinforced cement concrete in concrete mix M40
for pile excluding cost of steel reinforcements in position as per approved
drawing and as directed by the Engineer-In-Charge including mixing,
4 laying, consolidating, curing, including all labours, slings, shackles, supply
of all labour, material, transportation cost, hire and running charges of all
machineries such as cranes, lorries etc., complete as directed by the
Engineer-In-Charge.
Dia of Pile -600mm (Cut-off level is 0.575m CD) 36 (π*1.0*1.0)/4 10.58 299.00
3
Total 299.00 m
3
Say 300.00 m
Chiseling/Breaking using suitable tools and equipments the top of
600mm Dia Pile concrete up to the receipt of dense concrete and dressing
the pile head suitably so as to receive the form work for deck work ,
including breaking to the required level exposing the pile reinforcement to
5 sufficient length as per approved drawing for embedding into the coping
beam etc. including removal of concrete debris from the site, supply of all
labour, material, transportation cost, hire and running charges of all
machineries complete as directed by the Engineer-In-Charge.
36 36 Nos
Total 36 Nos
DECK STRUCTURE
Providing and laying reinforced cement concrete in concrete mix M40
for slabs excluding cost of steel reinforcements in position as per approved
drawing and as directed by the Engineer-In-Charge including shuttering,
6 mixing, laying, consolidating, curing, including all labours, slings,
shackles, supply of all labour, material, transportation cost, hire and
running charges of all machineries such as cranes, lorries etc., complete as
directed by the Engineer-In-Charge.
3
In-situ slab - Mobile boat hoist wheel approach 1 40.00 2.00 0.15 12.00 m
3
In-situ slab - Mobile boat hoist wheel approach 1 40.00 2.00 0.15 12.00 m
3
Precast slab - Mobile boat hoist wheel approach 1 40.00 2.00 0.15 12.00 m
3
Precast slab - Mobile boat hoist wheel approach 1 40.00 2.00 0.15 12.00 m
3
Total 48.00 m
3
Say 48.00 m
Providing and laying reinforced cement concrete in concrete mix M40
for wearing coat as per approved drawing and as directed by the Engineer-
In-Charge including mixing, laying, consolidating, curing, including all
7 labours, slings, shackles, supply of all labour, material, transportation cost,
hire and running charges of all machineries such as cranes, lorries etc.,
complete as directed by the Engineer-In-Charge.
3
In-situ wearing coat - Mobile boat hoist wheel approach 1.0 40.0 2.0 0.075 6.00 m
3
Total 6.00 m
3
Say 6.00 m
Note:-
1.The stiffener shall be measured under this item.
In case the soil strata found to be not good in the founding level of the
liner, extra depth may be provided as per site condition.
Boring through all types of soils, boulders, hard starta and rocks etc.. for
750mm and 600mm Dia vertical bored piles from the existing ground level
3 237 (-)4.00m CD to the founding level (-)10.00m CD of the piles, including 32,044.00 Rm 7,584,814.80 75.85
bailing, flushing the bore bentonite with required density, chiselling,
shifting of materials etc.. complete as per directed by the Engineer-In-
3 Filling the basement with excavated earth laid in layers if not more than
15 cm thick well watered and consolidated etc., complete as per 2521.00 Cum 90.00 226889.6598
standard specifications.
4 Supplying and filling in foundation and basement with filling river sand in
layers of not more than 15cm thick, well rammed, watered and
2227.00 Cum 1710.00 3808170.898
consolidated etc., complete complying with standard specification.
2 Cement Concrete 1:3:6 (One Cement, three sand and six hard broken
stone jelly) using 20 mm gauge hard broken granite stone jelly and laid
3.00 Cum 7750.00 23226.75
well rammed, consolidated and curing etc. complete complying with
standard specification
3 Cement concrete of mix 1:2:4 ( One cement four sand and eight
aggregate) using 20 mm gauge HBG Jelly for foundation and flooring
including cost and conveyance of all material and labour charges for 37.00 Cum 10450.00 386613.5295
laying land in layer of not more than 15 cm thick well ra
2 Reinforced Cement Concrete 1:1 1/2:3 (one cement, one and half sand &
three of HBG stone jally) using 20 m.m. gauge hard broken granite stone
jelly for all RCC items of works with minimum cement content of
430.80Kgs/ Cum of concrete, excluding costand
7 STEEL REINFORCEMENT 0
1 Supplying, fabrication and placing in position plain/ribbed Tor steel for all
RCC works and providing fusion bonded coating not less than 175
microns thickness and upto 300 microns to reinforcement of all 197.00 M.T 114420.00 22540600.42
diameters as per I.S code 13620-1993 for plain/ RT
3 Plastering with cm 1:3 (one cement and three sand) 12mm thick in all
floors including water proofing at 2%etc., complete complying with
0.00 Sqm 450.00
standard specification as directed by the departmental officers
4 Plastering with Cement Mortar 1:4 (One cement and four sand), 20 mm
thick including finishing neatly curing etc. complete complying with 5241.00 Sqm 470.00 2463271.429
standard specification
10 FLOORING
Providing granolithic floor finish of 25 mm thickness with plain cement
concrete 1:2:4 (one cement ,two sand and four aggregate using 10mm to
1 12mm size hard broken granite stone jelly etc) complete complying witth 174.00 Sqm 290.00 50460.841
standard specification and as directed by
Paving the floor with Colour design Ceramic tiles of size 300 x 300 x 6
mm
in all floors over a base layer of Cement Mortar 1:3 (One cement and
2 three sand) 20mm thick and pointed with white cement mixed with 135.00 Sqm 1190.00 160650
colouring pigments at the rate of 0.3 Kg/sq.m i
Flooring with Polished cuddapah slab of 20-30 mm thick laid in C.M 1:3
(One Cement and three sand) 20 mm thick and pointing with cement
3 mortar 1:3 (One cement and three sand) complying with standard 1432.00 Sqm 1080.00 1546556.112
specification. The size of slab should be 600 X 600 mm
Dadoing the walls with best approved first quality plain colour Glazed
tiles of size 150 mm X 150 mm X 6 mm set in Cement Mortar 1:2 (One
4 cement and two sand) 10mm thick and pointed with white cement 492.00 Sqm 1045.00 514136.3425
mixed with colouring pigments at the rate of 0.40 kg.
Supplying and fixing of 17-18 mm thick black granite slab on brick pillar
as
5 101.00 Sqm 3965.00 400465
directed by the Departmental Officers
Supplying & fixing Eurocon of size 30 cm x 30 cm set in cement mortar
1:2, 10mm thick and pointed with white cement mixed with colouring
6 pigments at the rate of 0.40Kg/Sq.m, finishing neatly and curing etc 4026.00 Sqm 1065.00 4287690
complete as directed by the Departmental Engineer
Supply and fixing Paver block for Pavement 100 mm thick Paver block
7 M30 grade ,finishing neatly etc complete as directed by the Department 1388.00 Sqm 1710.00 2373488.208
Engineer
Sr.No Description Quantity Unit Basic Rate Total Amount
11 TERRACE FLOORING
Finishing the top of roof with one course of approved first quality
Machine Pressed Tiles of size 200mm x 200mm x 20mm thick laid in
1 Cement Mortar 1:3 (one cement and three sand) 12mm thick mixed with 2410.00 Sqm 1330.00 3205297.606
water proofing compound conforming to Indian standard
Weathering course concrete using best quality broken brick jelly of size
20mm uniform gauge in pure slaked lime in the proportion of brick jelly
2 to lime being 32:12-1/2 by volume and laid over the RCC roof slab in a 250.00 Cum 3600.00 900005.2992
single layer and consolidated to the re
13 SANITARY ARRANGMENTS
1 Supplying and fixing in position best approved quality and make white
glazed earthern ware oriya type Indian water closet of size 580 mm x 440
4.00 Each 2160.00 8640
mm with P or S trap embedding the closest and trap to shape in position
with brick jelly lime concrete 1:2:5 (on
2 Supplying and fixing of European water closet (White ) with 10 litres
capacity flusing tank (low level) of best quality and approved make with
100 mm size ‘p’ or ‘s’ tap with double flapped PVC rigid PVC cover with 2.00 Each 7270.00 14540
CP brass hinges etc, complete complyi
3 Supplying and fixing White Lipped mouth porcelin Flat Back Urinal with
all accessories such as 32 mm dia Bell mouth PVC connection , 15 mm dia
G.M Wheel vavle , 15 mm dia "B" class G.I Waster water pipes , 15 mm 6.00 Each 2883.00 17298
dia Nylon connection 15 mm dia Brass nipple
4 Supplying and fixing in position best quality and approved make of colour
wash hand basin of size 550 x 400 mm necessary cast iron bracket 15mm
dia chromium plated pillar tap 32mm dia 'B' class pvc Waste pipe 32mm 7.00 Each 4500.00 31500
chromium plated brass waste coupling with
5 Supplying and fixing of urinal partition with both side polished white
marble slabs of 20 mm thick with a size of 4' x 2' ( 1.22 x 0.61 M ) and
8.00 Each 3600.00 28800
fixin g with the wall by forming grooves grouting with cement mortar
making good the damaged portion includi
Supplying and fixing in position GULLY TRAP ( 150 mm x 100 mm)
6 fixed
with brick jelly lime concrete 1:2:5 ( one part of lime and 2 parts of sand
6.00 Each 450.00 2700
and 5 parts of 20mm brick jelly )over a bed cement concrete 1:3:6 using
20mm stone jelly complete.
7 Supplying and fixing best approved quality colour Porcelin Soap dish of
size 150 mm x 150 mm x 50 mm including cost of teak wood plugs , brass 10.00 Each 540.00 5400
screws complete with standard specification.
8 Supplying and fixing in position best quality anodoised aluminium plated
Towel rail of 600 mm length and with 20 mm dia CP brackets of same
8.00 Each 1080.00 8640
materias including cost of TW plugs chromium plated brass screw etc.
Supplying and fixing in posotion cast iron NAHINI TRAP of size 100 x
9 75
mm with best stainless steel gratings of approved brand and quality fixed
30.00 Each 360.00 10800
over a bed of brick jelly lime concrete 1:2:5 ( 1 part of lime, 2part of sand
nad 5 part of 20mm brick jelly
10 Supplying and fixing 4" ( 150 mm ) dia stone ware pipes including laying
earthwork excavation, jointing with cement mortar with spun yarn etc., 126.00 Rm 650.00 81900
complete
Supplying laying and jointing P.V.C pipe 4" (150 mm) dia (6 Kg / SqCm )
11 of
approved quality and best variety conforming to I.S.S & with I.S.I mark, of
51.00 Rm 755.00 38505
the following sizes including cutting , fixing to PVC specials using
adhesive but excluding cost of such
12 Supplying and fixing in position best quality Bevelled Edge Mirror of size
600 x 450 mm shelf type with necessary plywood backing rubber buttons
7.00 Each 1080.00 7560
brass chromium plated screws, plug etc. complete complying with
standard specification.
Sr.No Description Quantity Unit Basic Rate Total Amount
Supplying and fixing of HDPE pipe 140mm dia as per specification and
4 as
15.00 Rm 1260.00 18900
directed by the departmental officers
5 Supplying and fixing in position best approved of ISI quality of Syntex
6.00 Each 10810.00 64860
tank of 1000 litres capacity
15 ROAD
Providing and laying of Tack coat 4kg per 10 sq.m over the unprimed
WBM surface using 4 kg of 60/70 grade bitumen including labopur for
4 preparing the surface and applying the required quantity of bitumen as 3376.00 Sqm 35.00 118160
tack coat by bitumen sprayer etc., complete as p
Providing and laying and compacting open graded premix carpet 20mm
thick using graded HBG 13.2mm-6.70mm IRC metal and 60/70 bitumen
5 with a liquid seal coat which shall consist of open graded carpet of 20mm 3376.00 Sqm 575.00 1941200
thickness in single course composed of suitable s
Providing and laying Bituminous macadam using graded HBG metal and
bitumen 60/70 grade as per approved job mix formula including cost and
6 conveyance of all materials to the site including bitumen,heating the 170.00 Cum 8650.00 1470500
bitumen and aggregate to required temperature a
16 MISCELLANEOUS ITEMS
1 Fabricating, supplying and fixing in position of aluminium anodised
natural colour matt finished Door of double leaved with shutters
panelled top 2/3rd portion with plain glass of 5.5 mm thick and 19.00 Sqm 6850.00 130150
aluminium grill of 10 mm thick standard pattern (diamond
Supplying and fixing of factory made PVC rigid panel door made from
2 MS
tubes of 19 Gauge size of 19 mm X 19 mm and covered with head
moulded PVC channel of 5 mm thick and width of 50 mm to form styles 19.00 Sqm 3600.00 68382
and rails. The inner panel should be inserted betwee
8 Supplying and fixing of MS grill for steel gate, Hand rail, Steel ladder and
Chequered plate of required size and design with one coat of primer as 9.00 MT 104508.00 940673.1499
specified by the departmental officers
9 Providing and laying of sand gravel mix of 1:1 ratio including cost of
materials, conveyance charges to site, mixing , spreading to proper
1566.00 Cum 2162.00 3385689.038
camber, watering consolidation and compacting etc., complete.
Providing and fixing in position CI man hole cover (heavy duty) of size
10 450
mm X 450 mm of best approved quality and as per standard
9.00 Each 2162.00 19458
specification including fixing the frame in concrete all complete and as
directed by the departmental officers
Providing and fixing in position M.S rungs of approved quality of size
11 400
X 250 mm and required shape, including fixing in brick work using
38.00 Each 450.00 17100
cement concrete 1 : 1 ½ : 3 (one of cement, and onc and half sand and
three aggregate) and RCC structures all co
Supplying and fixing of Pre cast slab R.C.C 1:2:4 125 mm Thick
12 including
cost of mould, finishing etc., complete including of reinforcement 547.00 Sqm 1800.00 984595.68
13 Supplying and fixing of 110mm dia air vent pipe of PVC material with
necessary cowl and masonry structure etc complete as specified by the 2.00 Each 900.00 1800
departmental officers
14 Supplying and filling the percolation pit with 53 mm to 40 mm grade HBG
stone jelly including stacking for pre measurement as directed by the 11.00 Cum 1620.00 17820
departmental officers
15 Supplying and fixing in position wooden log in country wooden Cover
frame of cross section of 400 X 200 mm as directed by the departmental 11.00 Cum 162168.00 1783848
officers.
16 Supplying and fixing in position wooden log in country wood Beam of
cross section of 300 X 300 mm to concrete floor of slip way as directed by 8.00 Cum 162168.00 1297344
the departmental officers.
17 Supplying and fixing in posting of the Rubber fenders at 2 m centre to
centre using 200 x 100 mm and fixed with galvanized fixtures and
137.00 Each 48650.00 6665050
accessories etc. complete as directed by department officers.