You are on page 1of 67

(Annexure -I )

LUMP SUM TENDER MARKET RATE ANALYSIS AS PER TABLE 'H' OF CONTRACT MANUAL

NAME OF WORK : Provn of OTM Accn & Balance Work at Jaisalmer


Description of Sch 'A' : Sch 'A' Part-I, Item No. 14

Name of Building : Construction of Education Building

Estimated cost of building : Rs. 2268000/- (Annexure-B1)

Srl No Description of Item Estimated Cost as per Reasonable cost as per


SSR 2010 Market Rates

1 Material to be supplied by the 1477077.00 1526087.00


Contractor (As per Annexure-II)

2 Form work in corporated in the buildings 102673.92 98638.88


(As per Annexure-III)

3 Excavation & earthwork involved in the 34339.68 36926.23


buildings (As per Annexure-IV)

4 Cost of total labourer (for market cost 545909.39 889340.98


add @ 62.91 % on SSR cost for labourer)
i.e. Annexure V)

Total 2160000.00 2550993.09

5 Add @ 17.5% contractor's profit & over - 446423.79


head
2160000.00 2997416.88
Add 5% contigency for misc & unseen
6
items 108000.00 149870.84
Total Cost of the Block 2268000.00 3147287.73
7 Percentage above SSR 2010 38.77 %

Prepared by _____________ Checked by ______________

Approved by
Director (Contract)
MARKET ANALYSIS (As per report …………………………………..) Annexure -II

NAME OF WORK : Provn of OTM Accn & Balance Work at Jaisalmer


Name of Building : Construction of Education Building

Srl No Description of Item SSR No Unit Qty As per SSR 2010 As per Market
Rate Amount Rate Amount
1 2 3 4 5 6 7 8 9

1 Stone for hard core of gauge 03059 CUM 2.55 528.70 1350.23 600.00 1532.32
n. exc 63 mm
2 Chlorophyriphos (ATT 03063 LTR 138.05 305.50 42172.80 200.00 27609.03
Chemical)
3 Aggregate
(i) 40mm graded 04093 Cum 86.05 587.50 50552.74 700.00 60233.06
(ii) 20mm graded 04093 Cum 92.76 646.30 59952.41 700.00 64933.75
(iii) 12.50mm graded 04093 Cum 1.87 675.00 1258.98 700.00 1305.61
4 Sand for concrete/masonry/ 04095 Cum 117.54 646.30 75967.00 1100.00 129295.53
5 Sand for plastering 14079 Cum 21.06 705.00 14847.85 1100.00 23166.85
6 Cement 04098 Bag 1346.11 270.30 363852.36 210.00 282682.19
7 Bricks `06129 Nos 33894.82 2.30 77958.09 3.50 118631.87
8 TMT bars 10110 Kg 16091.01 41.10 661340.57 34.00 547094.39
9 Binding wire 10114 KG 207.82 56.40 11720.79 70.00 14547.08
10 Primer for roof treatment 11151 Ltr 68.27 47.00 3208.87 52.00 3550.24
15 Mineral colour 15015 Kg 0.25 52.9 13.33 70 17.64
16 Slaked Lime 04097 Kg 37.79 4.31 162.85 9 340.066692
17 Glue Assessed Kg 0.11 85 9.70 85 9.69535245
18 Blue Assessed Kg 0.11 90 9.72 90 9.7161912
23 Factory made Panelled door 08020 Sqm 9.33 1460.50 13622.81 3000.00 27982.50
shutter
25 Door stopper with hinge 09149, 51 Each 5.00 21.20 106.00 40.00 200.00
26 Pressed steel frames of size 10082,83 Rm 26.40 229.10 6048.24 270.00 7128.00
125x60mm
28 Aluminium barrel bolt ;09004, 9 Each 10 35.70 357.00 60.00 600.00
200mm long
30 MS Butt hinge 100 mm 09028. 56 Each 12 10.60 127.20 15.00 180.00
31 Aluminium handle 150mm 09083, 85 Each 10 25.80 258.00 30.00 300.00
32 CP Towel rail complete. 094147 Each 1.00 264.40 264.40 225.00 225.00
36 Vitrified tiles 13013 Sqm 37.71 316.10 11919.50 284.30 10720.38
38 Glazed ceramic coloured tiles 13152 Each 1473.203 7.05 10386.08 70.00 103124.18
7mm (200 x 200mm)
Total of page No 1 1407467.51 1425419.10
1 2 3 4 5 6 7 8 9
40 Oil bound distemper 15017 Kg 58.13 70.50 4098.13 70.00 4069.07
41 Primer for distemper Assessed Kg 34.88 50.00 1743.89 160.00 5580.43
42 Pink primer 17056 Litre 0.00 79.90 0.00 160.00 0.00
43 Zinc chrome primer 17056 Litre 0.00 103.40 0.00 160.00 0.00
44 Synthetic enamel paint 17060 Litre 0.00 150.40 0.00 185.00 0.00
49 PVC connection 15mm, 45cm 18152 Each 2 73.90 147.80 75.00 150.00
long
50 100mm bore CI pipe 18156 RM 6.50 680.20 4421.30 1500.00 9750.00
51 75mm bore CI pipe 18156 RM 10.00 584.50 5845.00 1100.00 11000.00
52 Bend 100 mm bore 18010 Kg 3.00 42.30 126.90 320.00 960.00
53 CI Junction 100 mm 18010 Kg 3.00 42.30 126.90 320.00 960.00
54 CI cowl 100mm 18168 Each 2 250.30 500.60 250.00 500.00
55 CI Nahani trap 75mm 18213 Each 4 367.20 1468.80 450.00 1800.00
56 Salt glazed GT 150 x 150mm Assesed Each 1 150.00 150.00 270.00 270.00

57 EWC 18302 Each 1 662.70 662.70 1300.00 1300.00


58 Flushing ciestern 10 Ltr 18314 Each 1 1496.90 1496.90 1250.00 1250.00
capacity PVC
59 Toilet Paper holder vitreous 18324 Each 1 205.60 205.60 500.00 500.00
china
60 W.H.B 18332 Each 1 740.10 740.10 1350.00 1350.00
61 Looking mirror for W.H.B Assessed Each 1 800.00 800.00 800.00 800.00
62 Looking mirror 300x450mm Assessed Sqm 1.00 300.00 300.00 800.00 800.00
63 Nipple etc for HDPE water Assessed Each 1 50.00 50.00 100.00 100.00
tank 500/300 litre capacity
64 PVC pipe 110mm dia 18349 RM 1 211.80 211.80 400.00 400.00
68 Information Plaque Assesed Each 1 750 750 1000 1000.00
69 Number Plaque Assesed Each 1 100 100 1000 1000.00
72 Material reqd for testing Assessed L/S 1.00 3500.00 3500.00 4000.00 4000.00
73 PVC Door Frame 8101 Rm. 3.15 2421.30 7627.10 250.00 787.50
74 PVC Door Shutter 8095 Sqm. 10.06 335.30 3373.12 1950.00 19617.00
79 HDPE Water Tank 500 Ltrs Nos 1.00 2200.00 2200.00 2800.00 2800.00
Total of page No 2 40646.63 70744.00
TOTAL OF PAGE NO 1 1407467.51 1425419.10
TOTAL OF PAGE NO 2 40646.63 70744.00
Total of page No 1-3 1448114.13 1496163.09
Add 2% for unseen items 28962.28 29923.26
1477076.42 1526086.36
Say 1477077.00 1526087.00
COST OF FORMWORK AT PAR SSR 2010 AND AS PER MARKET RATE Annexure-III

NAME OF WORK : Provn of OTM Accn & Balance Work at Jaisalmer


Name of Building : Construction of Education Building

Srl No Description of Item SSR No Unit Qty At par SSR 2010 As per Market
Rate Amount Rate Amount

1 Formwork to side of concrete 605'07004 Sqm 56.23 134.2 7546.33 200.00 11246.40
foundation, footing, base of
column, sides & sofits of plinth
beams

2 Formwork to slab 07006 Sqm 162.56 211.50 34380.76 200.00 32511.36

3 Formwork to bems/lintels 07010 Sqm 144.72 203.70 29478.57 200.00 28943.12

4 Formwork to Columns/posts 07014 Sqm 129.69 241.10 31268.26 200.00 25938.00


etc
102673.92 98638.88
EXCAVATION / EARTHWORK ITEMS Annexure-IV

NAME OF WORK : Provn of OTM Accn & Balance Work at Jaisalmer


Name of Building : Construction of Education Building

Srl Description of Item SSR No Unit Qty As per SSR 2010 As per Market
No
Rate Amount Labour Rate of Market Amount
factor Mazdoor Rate

1 Surface dressing in any 3426.85


type of soil 0'3011 Sqm 428.36 7.90 3384.02 0.04 200.00 8.00
2 Surface Excavation not 6853.71
exc 30 cm deep and
averaging 15cmp in 03004 Cum 428.36 15.90 6810.87 0.08 200.00 16.00
soft/ loose soil.

3 Excavation in trenches
n. exc 1.5 m wide &
n.exc 1.5 m deep and
getting out in any type 03006 Cum 181.00 115.20 20851.43 0.55 200.00 110.00 19910.22
of soil

4 Returning , filling in
trenches incl well 03009 Cum 35.70 41.70 1488.66 0.21 200.00 42.00 1499.37
ramming with moorum
5 Filling under floor 03017, 18 Cum 34.91 51.70 1804.70 0.35 200.00 150.00 5236.08
34339.68 36926.23
MARKET VARIATION ON LABOURS Annexure -V

NAME OF WORK : Provn of OTM Accn & Balance Work at Jaisalmer


Name of Building : Construction of Education Building

Srl No Description of Item Unit Qty As per SSR 2010 As per Market
Rate Amount Rate Amount

1 Mason/brick layer/paver Day 2.00 225.00 450.00 450.00 900.00

2 Painter Day 0.15 225.00 33.75 450.00 67.50

3 Welder / Fabricator Day 0.25 248.00 62.00 450.00 112.50

4 Black smith Day 0.45 192.00 86.40 450.00 202.50

5 Plasterer Day 0.25 225.00 56.25 450.00 112.50

6 Plumber Day 0.15 225 33.75 400.00 60.00

7 Mate Day 1 169.00 169.00 250.00 250.00

8 Mazdoor Day 9 169.00 1521.00 250.00 2250.00

9 Bhisti Day 1 169.00 169.00 250.00 250.00

Total 2581.15 4205.00

%age variation over SSR 2004 = 4205.00 2581.15 = 1623.85 62.91%


2581.15 2581.15

i.e. (+) 62.91% above


NAME OF WORK : Provn of OTM Accn & Balance Work at Jaisalmer

Name of building : Construction of Education Building

MARKET ANALYSIS (TAKING OUT OF QUANTITY OF MAJOR MATERIALS

1 Chemical for ATT


Item Qty. Mix ATT Qty
No.
6 Treating the back fill in contact 221.26 5.0 1106.28
with foundation at the rate of
7.5 liter of emulsion per square
meter of vertical surface (Area of
the sub structure in contact with
back fill to be measured).

52 Material and labour for treating 143.95 7.5 1079.60


the top surface of filled earth at
the rate of 5 liters of emulsion
per square meter of surface.

53 Material and labour for anti 140.26 2.25 315.59


termite treatment along the
external wall below concrete or
masonary apron using chemical
emulsion @ 2.25 liter per linear
meter including drilling and
plugging holes etc in apron.

68 Material and labour for treating 32.43 5.00 162.15


the soil under plinth protection
at the rate of 5 liter of emulsion
per square meter of surface
area.

69 Material and labour for anti 43.24 2.25 97.29


termite treatment along the
external wall below concrete or
masonary apron using chemical
emulsion @ 2.25 liter per linear
meter including drilling and
plugging holes etc in apron.

2760.90
Total Qty. 138.05
= 138.05 Litres
2 RCC M-25(design mix) other than pile

Item N Item Decription Qty.


8 RCC Columns Footting detail 49.07
9 Detail of RCC Columns upto 5.39
Plinth Level
10 RCC Plinth Beams 12.28
11 RCC Columns plinth level to 5.52
Lintel Level
16 RCC Columns Lintel level to First 2.10
Floor Slab Level
21 RCC Roof Beams 10.21
22 RCC Floor Slab 22.76
Total Qty. 107.34

(a) Cement @ 360.00 Kg/ Cum. = 38642.10 Kg


(b) Sand @ 0.43 Cum/ Cum = 46.16 Cum
(c) Agreegate 20mm @ 0.85 Cum/ Cum = 91.24 Cum

PCC (1:2:4) TYPE B-1


49 70.65 0.03 2.1195

Non skid ceramic tiles 7 to 8 mm


thick (square/ reactangular),
white in colour, area of each tile
exceeding 0.06 sqm. But not
exceeding 0.11 sqm. In floors
etc. set and jointed in neat
cement slurry and pointed in
white or colured cement to
match with joint free non skid
tiles.

Total Qty. 2.12

(a) Cement @ 308.53 Kg/ cum. = 653.93 Kg


(b) Sand @ 0.44 Cum/ cum = 0.93 Cum
(c) Agreegate 12.5mm @ 0.88 Cum/ cum. = 1.87 Cum

PCC (1:2:4) TYPE B-0

(a) Cement @ 308.53 Kg/ cum. = 0.00 Kg


(b) Sand @ 0.43 Cum/ cum. = 0.00 Cum
(c) Agreegate 12.5mm @ 0.86 Cum/ cum. = 0.00 Cum
4 PCC (1:3:6) TYPE C-1

Total Qty. 0.00

(a) Cement @ 213.20 Kg/ cum. = 0.00 Kg


(b) Sand @ 0.46 Cum/ cum. = 0.00 Cum
(c) Agreegate 20mm @ 0.92 Cum/ cum. = 0.00 Cum

4a PCC (1:3:6) TYPE C-2

67 50 mm thick PCC 1:3:6 as in sqm. 32.43


plinth protection over 75 mm
thick brocken stone aggregate
hard core over rammed earth.

Total Sqm. 32.43


Total Cum. 1.6215
(a) Cement @ 213.20 Kg/ cum. = 345.70 Kg
(b) Sand @ 0.47 Cum/ cum. = 0.76 Cum
(c) Agreegate 20mm @ 0.94 Cum/ cum. = 1.52 Cum

5 PCC (1:4:8) TYPE D-2


4 Material and labour for Cement Cum. 78.84
concrete in foundations, filling
and mass concrete type D2 1:4:8
using 40 mm graded stone
aggregate including compaction
of concrete, curing etc.
complete.

50 75 mm thick PCC 1:4:8 as in sub Cum. 10.80


base under floor over rammed
earth

Total Cum. 89.63


(a) Cement @ 161.95 Kg/ cum = 14515.99 Kg
(b) Sand @ 0.48 Cum/ cum. = 43.02 Cum
(c) Agreegate 40mm @ 0.96 Cum/ cum. = 86.05 Cum
7 Fly ash brick wall IN CM 1:6

11 Brick work with Fly Ash Bricks, cum. 15.42


straight or curved on plan
exceeding 6 meter mean radius
built in cement sand mortar 1:6
including curing, racking of joints
etc. complete in all respect.

12 Brick work with Fly Ash Bricks, Cum. 44.53


straight or curved on plan
exceeding 6 meter mean radius
built in cement sand mortar 1:6
including curing, racking of joints
etc. complete in all respect.

17 Brick work with Fly Ash Bricks, Cum. 23.13


straight or curved on plan
exceeding 6 meter mean radius
built in cement sand mortar 1:6
including curing, racking of joints
etc. complete in all respect.

Total Qty. 83.08

(a) Cement @ 75.00 Kg/ cum = 6230.67 Kg


(b) Sand @ 0.32 Cum/ cum = 26.67 Cum
(c) Bricks @ 408.00 Nos = 33895 Nos

9 5MM THICK PLASTER IN CM 1:3 ON CONCRETE SURFACE

39 5 mm thick cement sand mortar sqm. 134.95


1:3 plaster to exposed concrete
surfaces

Total Qty. 134.95

(a) Cement @ 5.03 Kg/ Sqm. = 678.78 Kg


(b) Sand @ 0.01 Cum/ Sqm. = 1.35 Cum
11 10MM THICK INTERNAL PLASTER IN CM 1:6 ON BRICK WALLS

37 10 mm thick rendering on fair sqm. 387.53


faces of brick work or concrete
surfaces in cement sand mortar
1:6 as in internal surfaces of
walls finished fair even and
smooth without using extra
cement.

387.53
Qty =
= 387.53 Sqm

(a) Cement @ 4.46 Kg/ Sqm. = 1728.38 Kg


(b) Sand @ 0.020 Cum/ Sqm. = 7.88 Cum

12 Keyed Pointing

38 15 mm thick rendering on rough sqm. 203.962


faces of brick work or concrete
surfaces I two layer of 10 mm
thick in cement sand mortar 1:6
and 5 mm thick in cement sand
mortar 1:4 mixed with water
proofing compound as in
external surfaces of walls
finished fair even and smooth.

203.962
(a) Cement @ 6.97 Kg/ Sqm. = 1421.62 Kg
(b) Sand @ 0.025 Cum/ Sqm. = 5.02 Cum

20MM SCREED IN CM 1:3


45 20 to 25 mm thick kota stone of Sqm. 34.28
size 550 x 500 as in flooring over
20 mm thick bedding layer in
cement sand mortar 1:3 over
base as specified including
cutting polishing etc complete.

49 Non skid ceramic tiles 7 to 8 mm Sqm. 70.65


thick (square/ reactangular),
white in colour, area of each tile
exceeding 0.06 sqm. But not
exceeding 0.11 sqm. In floors
etc. set and jointed in neat
cement slurry and pointed in
white or colured cement to
match with joint free non skid
tiles.

70 Aluminium paint @0.11 Kg/ sqm. sqm. 162.5568


Over a layer of 3 mm thick APP
membrane sheet over a coat of
bitumen primer @ 0.40 Ltr/ Sqm.
Over a coat of plaster in cement
sand mortar 1:4, 10 mm thick
over RCC slab.

267.4868

(Qty of mortar = 5.349736 Cum)


(a) Cement @ 493.03 Kg/ Cum = 2637.58 Kg
(b) Sand @ 1.07 Cum/ Cum = 5.72 Cum

10MM SCREED IN CM 1:4 floor


Qty = Sqm
(Qty of mortar = 0 Cum)
(a) Cement @ 382.33 Kg/ Cum. = 0.00 Kg
(b) Sand @ 1.07 Cum/ Cum. = 0.00 Cum

10MM SCREED IN CM 1:3 vertical surface


51 Glazed ceramic tiles in vertical Sqm. 53.571
surface 350 x 250 x 7 mm/ 450 x
350 x 7 mm thick, white in
colour, set and jointed in neat
cement slurry and pointed in
white or colour cement to
match.

53.571

(a) Cement @ 8.41 Kg/ Sqm. = 450.53 Kg


(b) Sand @ 0.020 Cum/ Sqm. = 1.09 Cum

14 TMT STEEL BARS FOR REINFORCEMENT 8#

10 RCC Plinth Beams kg. 403.30


15 8 mm dia bar in half brick wall Kg.
masonary 7.35

20 8 mm dia bar in half brick wall Kg.


masonary 5.15

21 RCC Roof Beams Kg. 468.63


22 RCC Floor Slab Kg. 1767.87
2652.29 1.025 2718.60 Kg

14 TMT STEEL BARS FOR REINFORCEMENT 10mm & Over#

8 RCC Columns Footting detail


10 mm dia bar kg. 186.58
12 mm dia bar kg. 2038.07
16 mm dia bar kg. 1044.38
20 mm dia bar kg. 497.95
9 Detail of RCC Columns upto
Plinth Level
10 mm dia bar in stirrups kg. 2146.81
16 mm dia bar kg. 156.74
20 mm dia bar kg. 1715.17
25 mm dia bar kg. 1336.72
10 RCC Plinth Beams
16 mm dia bar kg. 280.86
20 mm dia bar kg. 1125.68
25 mm dia bar kg. 335.80
21 RCC Roof Beams
12 mm dia bar Kg. 83.42
16 mm dia bar Kg. 302.48
20 mm dia bar Kg. 1068.77
25 mm dia bar Kg. 726.84
13046.26 1.025 13372.41 Kg

BINDING WIRE
Qty = 16091.01 x 0.012 x 1.05
202.75 Kg x 1.025 = 207.82
Kg.
16 THREE COATS OF WHITE WASH ON CEILING
134.95 13.49 Ten Sqm
= 2178.61 Sqm =

(a) Slaked Lime @ 2.80 Kg/ X Sqm. = 37.79 Kg


(b) Glue @ 0.007 Kg/ X Sqm. = 0.09 Kg
(c) Blue @ 0.008 Kg/ X Sqm. = 0.11 Kg
16 THREE COATS OF WHITE WASH ON wall
0.00 0.00 Ten Sqm
(a) Slaked Lime @ 2.80 Kg/ X Sqm. = 0.00 Kg
(b) Glue @ 0.007 Kg/ X Sqm. = 0.00 Kg
(c) Blue @ 0.008 Kg/ X Sqm. = 0.00 Kg
(b) Glue @ 0.007 Kg/ X Sqm. = 0.02 Kg
( c) Mineral colour @ 0.09 Kg/ X Sqm. 0.25 Kg

21 TWO COAT OF OIL BOUND DISTEMPER OVER A COAT OF ALKALI RESISTANT PRIMER
387.53 38.75 X Sqm
=

(a) Primer = 38.75 X Sqm x 0.90 Kg


(b) OBD = 38.75 X Sqm x 1.50 litre
(a) Primer = 34.88 Kg
(b) OBD = 58.13 litre

18A TWO COATS OF CEMENT BASE


PAINT
203.96 Sqm = 20.40 X Sqm
= 0.00

(a) cement base paint @ 4.00 Kg/ X Sqm. = 81.58 Kg

19 PRIMER FOR ROOF TREATMENT

Qty = 162.56 x 0.40 x 1.05


= 68.27 Ltr = 68.27 Ltr
TWO COATS OF SYNTHETIC ENAMEL PAINT OVER ZINC CHROME PRIMER ON STEEL SURFACE
Qty
0.00 Sqm = 0.00 X Sqm
(a) Zinc Chrome Primer @ 0.50 Ltr/ X Sqm. = 0.00 Ltr
(b) Paint @ 0.90 Ltr/ X Sqm. = 0.00 Ltr
Yard Stick
Schedule 'A' Part - I, Sl Item No. 14 (Education Building)
CA No. : ……………………………………..
Name of Work : Provn of OTM Accn & Balance Work at Jaisalmer
Name of Contractor : ……………………………………………

S. Stage of Works % age Yard Stick


No. Recommended

1 Stage - I upto Plinth Level


Surface dressing, excavation, RCC foottings including steel reinforcement, form work,
RCC M-25, PCC 1:4:8 as in foundation column reinfofrcement upto roof level, form
work & RCC M-25 upto Plinth level, return filling in foundation, & back filling under
floor complete upto plinth level including ATT.
2 Stage - II : Plinth level to Lintel Level
Column RCC M-25, Form work upto lintel level, stone masonary, Lintel Beams
complete upto lintel level.
3 Stage - III : Lintel Level to First Floor Slab Level
Column formwork & RCC M-25 lintel level to roof level, Stone masonary, Floor Slab
Beams, RCC slab including reinforcement, form work, RCC M-25 complete.
4 Stage - IV : Door Windows
Flat Iron at junction of wall and column, Door Shutters, Windows, etc complete
including Iron Morgi.
5 Stage - V : Plaster work
Plaster to internal surface of walls, ceilling and keyed pointing to external surfaces of
walls.
6 Stage - VI : Surface finishes
Painting work for internal, external, ceilling newly plastered surfaces, steel and
wooden surfaces
7 Stage - VII : Florring
PCC florring, sub base to floors, Non Skid Tiles, Kota Stone floor including skirting to
floor, filling under floor and ATT complete
8 Stage - VIII : Sainitary Fitting & Fixtures
Sainitary fitting & fixtures like WC, flushing cistern, WHB, soil & weast pipes, peg sets,
etc. complete.
9 Stage - IX : Plinth Protection to building
PCC 1:3:6 type C1, plinth protection including hard core, ATT etc. complete
10 Stage - X : Roof Treatment
Roof treatment complete
11 Stage - XI : Misc Items
Site clearance, misc and unseen items etc.

0.00

Contractor

GE Project Jaisalmer
Approved
% age Yard Stick
Approved
Yard Stick
Schedule 'A' Part - I, Sl Item No. 14 (Education Building)
CA No. : ……………………………………………
Name of Work : Provn of OTM Accn & Balance Work at Jaisalmer
Name of Contractor : ……………………………….

S. Stage Amount % age % age


No. Stage of Works as per Estimate Calculated Recommended

I Stage - I upto Plinth Level


Surface dressing, excavation, RCC foottings including
steel reinforcement, form work, RCC M-25, PCC 1:4:8
as in foundation column reinfofrcement upto roof
1170693.09 54.20 52.50
level, form work & RCC M-25 upto Plinth level, return
filling in foundation, & back filling under floor
complete upto plinth level including ATT.
II Stage - II : Plinth level to Lintel Level
Column RCC M-25, Form work upto lintel level, stone
113851.19 5.27 5.00
masonary, Lintel Beams complete upto lintel level.
III Stage - III : Lintel Level to First Floor Slab Level
Column formwork & RCC M-25 lintel level to roof
level, Stone masonary, Floor Slab Beams, RCC slab
431690.59 19.99 20.00
including reinforcement, form work, RCC M-25
complete.
VI Stage - IV : Door Windows
Flat Iron at junction of wall and column, Door
Shutters, Windows, etc complete including Iron 62842.38 2.91 2.00
Morgi.
VII Stage - V : Plaster work
Plaster to internal surface of walls, ceilling and keyed
74239.18 3.44 3.00
pointing to external surfaces of walls.
VIII Stage - VI : Surface finishes
Painting work for internal, external, ceilling newly
19999.09 0.93 0.75
plastered surfaces, steel and wooden surfaces
IX Stage - VII : Florring
PCC florring, sub base to floors, Non Skid Tiles, Kota
Stone floor including skirting to floor, filling under 137723.14 6.38 6.00
floor and ATT complete
X Stage - VIII : Sainitary Fitting & Fixtures
Sainitary fitting & fixtures like WC, flushing cistern,
19792.00 0.92 0.75
WHB, soil & weast pipes, peg sets, etc. complete.
XI Stage - IX : Plinth Protection to building
PCC 1:3:6 type C1, plinth protection including hard
11540.08 0.53 0.50
core, ATT etc. complete
XII Stage - X : Roof Treatment
Roof treatment complete 82232.07 3.81 3.50
XIII Stage - XI : Misc Items
Site clearance, misc and unseen items etc. 35397.20 1.64 6.00
Total Amount of the Building 2160000.00 100.00 100.00

Contractor

Approved
Abstract of Quantities for Block of Education Building Sch 'A' Part-I, Item No. 14
For Provn of OTM Accn & Balance Work at Jaisalmer
Cost as Per SSR 2010
COST AS PER SSR 2010 (Upto PL) 1170693.09
COST AS PER SSR 2010 (Above PL) 989306.91
Total Cost of the Block 2160000.00
Plinth Area of Block 162.56

S. No. Description of Item Unit Qty. SI SSR Rate


Surface excavation not exceeding 30 cm deep and
1 average 15 cm deep and getting out in soft/loose sqm. 428.36 3001 61.60
soil.
1a Site Clearance sqm. 265.80 3012 5.30
Excavation in trenches, not exceeding 1.50 meter
wide and not exceeding 1.50 meter in depth, for
foundation, etc. or for shafts, wells, cesspits,
2 Cum. 181.00 3004 307.80
manholes, pier holes, etc. not exceeding 10
square meter on plan and not exceeding 1.50
meter in depth and getting out in soft/ loose soil.
Excavation in trenches, exceeding 1.50 meter
wide and not exceeding 3.00 meter in depth, for
foundation, etc. or for shafts, wells, cesspits,
3006,
3 manholes, pier holes, etc. not exceeding 10 Cum. 61.22 3007 520.30
square meter on plan and not exceeding 3.00
meter in depth and getting out in soft/
disintegrated rock soil.
Material and labour for Cement concrete in
foundations, filling and mass concrete type D2
4 1:4:8 using 40 mm graded stone aggregate Cum. 78.84 4025 2303.30
including compaction of concrete, curing etc.
complete.
Returning filling in, including spreading, levelling,
5 watering and well ramming in layers not exc. 25 Cum. 35.70 3009 41.70
cm in soft/ loose soil.
Treating the back fill in contact with foundation at
the rate of 7.5 liter of emulsion per square meter
6 Sqm. 221.26 3048 126.80
of vertical surface (Area of the sub structure in
contact with back fill to be measured).
Material and labour for sand filling under floors or
7 in foundation including watering and Cum. 34.91 3019 31.90
consolidation etc complete.
8 RCC Columns Footting detail
Form work to sides of concrete foundations,
foottings, bases of columns, raft and raft beams,
a sides and soffits of foundation and plinth beams sqm. 56.23 7004 134.20
and similar works; vertical or to batter for rough
finished surfaces.
RCC M-25 in foundation, including rafts, footings,
foundation beams, plinth beams, bases for
b cum. 49.07 4053 3482.20
columns etc; basement slabs, under reamed piles
and mass concrete.
c TMT bars
10 mm dia bar kg. 186.58 10034 48.60
12 mm dia bar kg. 2038.07 10034 48.60
16 mm dia bar kg. 1044.38 10034 48.60
20 mm dia bar kg. 497.95 10034 48.60
9 Detail of RCC Columns upto Plinth Level
Form work to sides of pillers, posts, struts, piers,
columns and stanchions for rough finished sqm. 53.71 7014 241.10
surfaces.
Reinforced cement concrete (design mix M-25) in
b cum. 5.39 4058 4159.00
columns, pillars, piers, posts and struts.
c TMT Bars
10 mm dia bar in stirrups kg. 2146.81 10036 49.70
16 mm dia bar kg. 156.74 10034 48.60
20 mm dia bar kg. 1715.17 10034 48.60
25 mm dia bar kg. 1336.72 10034 48.60
10 RCC Plinth Beams
Form work to sides of concrete foundations,
foottings, bases of columns, raft and raft beams,
a sides and soffits of foundation and plinth beams sqm. 81.88 7010 203.70
and similar works; vertical or to batter for rough
finished surfaces.
RCC M-25 in foundation, including rafts, footings,
foundation beams, plinth beams, bases for
b cum. 12.28 4057 4004.10
columns etc; basement slabs, under reamed piles
and mass concrete.
c TMT Bars
8 mm dia bar in stirrups kg. 403.30 10036 49.70
16 mm dia bar kg. 280.86 10034 48.60
20 mm dia bar kg. 1125.68 10034 48.60
25 mm dia bar kg. 335.80 10034 48.60
Brick work with Fly Ash Bricks, straight or curved
on plan exceeding 6 meter mean radius built in
11 cum. 5.78 5019 2250
cement sand mortar 1:6 including curing, racking
of joints etc. complete in all respect.
Total Stage - I
11 RCC Columns plinth level to Lintel Level
Form work to sides of pillers, posts, struts, piers,
columns and stanchions for rough finished Sqm. 55.02 7014 241.10
surfaces.
Reinforced cement concrete (design mix M-25) in
Cum. 5.52 4058 4159.00
columns, pillars, piers, posts and struts.
Brick work with Fly Ash Bricks, straight or curved
on plan exceeding 6 meter mean radius built in
12 Cum. 33.97 5019 2249.50
cement sand mortar 1:6 including curing, racking
of joints etc. complete in all respect.
Half brick wall masonaery in cement sand mortar
14 in CM 1:4 in sub class 'B' Bricks old size with fly Sqm. 2.94 5005 280.00
ash bricks in super structure
15 8 mm dia bar in half brick wall masonary Kg. 7.35 0 50.00
Total Stage - II
RCC Columns Lintel level to First Floor Slab Level
16
Form work to sides of pillers, posts, struts, piers,
columns and stanchions for rough finished Sqm. 20.96 7014 241.10
surfaces.
Reinforced cement concrete (design mix M-25) in
Cum. 2.10 4058 4159.00
columns, pillars, piers, posts and struts.
Brick work with Fly Ash Bricks, straight or curved
on plan exceeding 6 meter mean radius built in
17 Cum. 12.43 5019 2249.50
cement sand mortar 1:6 including curing, racking
of joints etc. complete in all respect.
Half brick wall masonaery in cement sand mortar
19 in CM 1:4 in sub class 'B' Bricks old size with fly Sqm. 2.06 5005 280.00
ash bricks in super structure
20 8 mm dia bar in half brick wall masonary Kg. 5.15 0 50.00
21 RCC Roof Beams
Formwork to sides and soffits of floor or roof
beams, beam haunchings, girders, bressummers,
a lintels cantilevers, shelves including supports, Sqm. 62.84 7010 203.70
overhungs etc. also splays between floors and
beams etc. as in rough finished surfaces.
Reinforced cement concrete (Design Mix, M-25)
b in beams, cantilevers, bressummers, lintels over Cum. 10.21 4057 4004.10
1.50 meter span
c TMT Bars
8 mm dia bar as in sttirrups Kg. 468.63 10036 49.70
12 mm dia bar Kg. 83.42 10034 48.60
16 mm dia bar Kg. 302.48 10034 48.60
20 mm dia bar Kg. 1068.77 10034 48.60
25 mm dia bar Kg. 726.84 10034 48.60
22 RCC Floor Slab
Formwork to soffits of suspended slabs such as
a roof slabs, floor slabs, landing and similar works Sqm. 162.56 7006 211.50
not exceeding 200 mm thick (Horizontal or
slopping)

Reinforced cement concrete (Design Mix M-25) in


slabs supported on walls, beams and columns in
b floors, roofs, landings, balconies, canopies, deck Cum. 22.76 4055 3770.00
slabs and in shelves and the like.

c TMT Bars 8 & 10 mm dia Kg. 1767.87 10034 48.60


Total Stage - III

Factory made pressed steel frames for doors with


23 one or more rebates including necessory fixing Rm. 26.40 10082 285.60
lugs, hinges, lock strike plate, etc. complete, as
specified supplied and fixed of size 125 x 60 mm

PCC 1:3:6 filling in Factory made pressed steel


24 sheet 1.25 mm thick single rebate door frames. Cum. 0.17 4025 2579.00

25 Tie bars in door frames Rm. 5.00 0 80.00


26 Taring to door frames in contact of wall/ columns Rm. 27.40 0 100.00
Plain framed, pannelled shutter (One Panal) with
lock rail and panel of 9 mm B.W.P. commercial ply
or 12 mm veveered on both faces. The size of rail
27 Sqm. 9.33 8021 1436.10
and stile as per IS 1003 (Part I), klin seasoned and
chemically pressure treated in second class hard
word rail and style of 35 mm thick.
28 200 mm long 10 mm dia tower bolt Nos. 10.00 9004 52.80
29 125 mm long D- type handle with 32 x 3 plate Nos. 10.00 965 31.03
30 Wooden door stopper with 50 mm butt hinge Nos. 5.00 LS 75.00
31 Factory Fixed Glazed Windows Sqm. 14.85 10070 1335.80
32 4 mm thick glass pan sheet for steel windows Sqm. 13.37 16006 470.50
Supply and fixing factory made solid PVC moulded
door shutter, 28 to 30 mm thick (stiles), with 2,4
or 6 raised panel design with 2 mm thick moulded
34 Sqm. 3.15 8101 2421.30
PVC sheet on the front face & 2 mm plain colour
PVC sheet on back face face, suppling and fixing in
frame at site as per specification and drawings.
Supply and fixing of solid PVC door frame of size
50 mm x 47 mm made ouit of 5 mm plain colour
35 PVC sheet reinforced with MS square tube, Rm. 10.06 8095 335.30
suppling and fixinx in opening as per specification
and drawing.
Total Stage - VI
10 mm thick rendering on fair faces of brick work
or concrete surfaces in cement sand mortar 1:6 as 14001,
37 sqm. 387.53 89.80
in internal surfaces of walls finished fair even and 14005

smooth without using extra cement.


15 mm thick rendering on rough faces of brick
work or concrete surfaces I two layer of 10 mm 14001,
38 thick in cement sand mortar 1:6 and 5 mm thick in sqm. 203.96 14005, 127.40
cement sand mortar 1:4 mixed with water 14004
proofing compound as in external surfaces of
walls finished fair even and smooth.
5 mm thick cement sand mortar 1:3 plaster to 14001,
14004,
39 sqm. 134.95 14005, 99.70
exposed concrete surfaces 14003
Total Stage - VII
Material and labour for preperation of surfaces
15002,
40 sqm 134.95 15007 12.70
and applying three coats of white wash to ceilling
Preperation of surfaces and applying two coats of
42 Sqm. 387.53
15001, 15003, 1500930.50
Oil Bound Distemper to internal surfaces of walls
Material and labour for preperation of surfaces
43 and applying two coats of cement base paint to sqm. 203.96 15001, 31.70
15010
walls (External)
Total Stage - VIII
20 to 25 mm thick kota stone of size 550 x 500 as
in flooring over 20 mm thick bedding layer in
45 Sqm. 34.28
13013, 14009, 14010673.10
cement sand mortar 1:3 over base as specified
including cutting polishing etc complete.
40 mm thick PCC 1:2:4 type B1 using 20 mm
graded stone aggregate over sub base (100 mm
thick PCC 1:4:8 type D2 using 40 mm graded stone 13033,
47 Sqm. 39.02 13040 130.30
aggregate) over rammed earth finished fair even
and smoothusing extra cement with groove of
size 30 x 10 mm.
Non skid ceramic tiles 7 to 8 mm thick (square/
reactangular), white in colour, area of each tile
exceeding 0.06 sqm. But not exceeding 0.11 sqm. 13082,
49 Sqm. 70.65 531.60
In floors etc. set and jointed in neat cement slurry 13085
and pointed in white or colured cement to match
with joint free non skid tiles.
75 mm thick PCC 1:4:8 as in sub base under floor
50 sqm. 143.95 13035 176.40
over rammed earth
Glazed ceramic tiles in vertical surface 350 x 250 x
7 mm/ 450 x 350 x 7 mm thick, white in colour,
51 Sqm. 53.57 13081 514.30
set and jointed in neat cement slurry and pointed
in white or colour cement to match.
Material and labour for treating the top surface of
52 filled earth at the rate of 5 liters of emulsion per sqm. 143.95 3049 80.60
square meter of surface.
Material and labour for anti termite treatment
along the external wall below concrete or
53 masonary apron using chemical emulsion @ 2.25 sqm. 140.26 3053 53.20
liter per linear meter including drilling and
plugging holes etc in apron.
Total Stage - IX
Supply and fixing of Vitreous china padestal pan
and trap, white in colour, including connection to
54 drain (or outgoing pipe) and to flushing pipem Nos 1 18251, 1,018.40
18302
antisyphonage pipe etc., complete, excluding
fixing bolts, flushing cistern and flush piep.
Pressed steel, enamelled white valveless syphonic
action type, flushing cistern, low level, white with 18315,
55 Nos 1 18264 1574.90
inlet, ball valve, float and handle including
brackets with capacity 10 liters.
Vitreous china wash basin, while, flat back and
size 580 x 450 iroun (for Hospital use) excluding
56 taps, waste, chain and plug and porcelain stopper Nos 1 18330, 957.30
18269
but including brackets, including cutting for and
pinning in ends of brackets or erecting stand.
57 Looking mirror Nos 1 300.00
58 Soap nitch Nos 1 300.00
59 Floor trap Nos 4 18,212 481.70
60 Gully Trap Nos 1 18231 318.50
Soil/ Vent pipe 100 mm dia CI as per IS 3989 spun
61 Rm. 6.50 18156 691.20
pipe
75 mm dia CI spun pipe as per IS 3989 as Waste
62 Rm. 10.00 18156 595.00
pipe
63 75 mm dia bend Nos 3 18158 337.10
64 100 mm dia bend Nos 3 18158 414.00
65 Peg set of two Nos 1 0 100.00
66 600 mm long Stainless Steel Towel Rail Nos 1 0 600.00
Total Stage - X
50 mm thick PCC 1:3:6 as in plinth protection over
67 75 mm thick brocken stone aggregate hard core sqm. 32.43 36 137.18
over rammed earth.
Brocken stone aggregate hard core in plinth
cum. 2.43 3050 895.10
protection
Material and labour for treating the soil under
68 plinth protection at the rate of 5 liter of emulsion sqm. 32.43 3050 80.60
per square meter of surface area.
Material and labour for anti termite treatment
along the external wall below concrete or
69 masonary apron using chemical emulsion @ 2.25 Rm. 43.24 3053 53.20
liter per linear meter including drilling and
plugging holes etc in apron.
Total Stage - XI
Aluminium paint @0.11 Kg/ sqm. Over a layer of 3
mm thick APP membrane sheet over a coat of
70 bitumen primer @ 0.40 Ltr/ Sqm. Over a coat of
plaster in cement sand mortar 1:4, 10 mm thick
over RCC slab.
PCC Padding sqm. 162.56 13037 135.97
Al Paint sqm. 162.56 0 60.00
Bitumen Primer sqm. 162.56 11051 47.00
APP Membrane sqm. 162.56 11068 171.80
Plaster sqm. 162.56 14001 91.10
Total Stage - XII
71 Fan Hooks Nos 5 75.00
72 HDPE Water storage tank 500 ltrs capacity Nos 1 18082 2203.49
73 Base slab for HDPE Water storage tank Nos 2.00 5000.00
Misc & unseen items like cub board shutters,
74
shelves, window cill, ramps, Parapet etc.
Total Stage - XI
No. 14

Amount

26386.78

1408.72

55712.42

31853.60

181584.09

1488.66

28055.13

1113.54
7546.33

170872.95

9067.83
99050.03
50756.87
24200.47

12949.48

22423.25

106696.68
7617.37
83357.16
64964.59

16678.55

49177.15

20043.76
13649.83
54707.94
16319.73

13010.16

1170693.09
13265.32

22970.16

76425.01

823.20

367.50
113851.19

5053.46

8750.54

27960.00

576.24

257.25

12800.02

40884.34

23290.81
4054.15
14700.29
51942.17
35324.50

34380.76

85797.48

85918.57
431690.59

7539.84

428.94

400.00
2740.00

13395.22

528.00
310.30
375.00
19836.63
6288.23

7627.10
3373.12

62842.38

34800.19

25984.76

13454.23

74239.18

1713.83

11819.67

6465.60

19999.09

23073.87

5083.93
37557.54

25392.27

27551.57

11602.14

7461.83

137723.14

1018.40

1574.90

957.30

300.00
300.00
1926.80
318.50
4492.80
5950.00
1011.30
1242.00
100.00
600.00
19792.00

4448.75

2177.11

2613.86

2300.37

11540.08

22102.31
9753.41
7640.17
27927.26
14808.92
82232.07
375.00
2203.49
10000.00
22818.71
35397.20
Estimate of Quantities for Block of Education Building Sch 'A' Part-I, Item No. 14
For Provn of OTM Accn & Balance Work at Jaisalmer

COST AS PER SSR 2010 2160000.00


Plinth Area of Block (GF) 162.56
Plinth Area Rate as per SSR 2010 13287.40

Item No. 1

Surface dressing not exceeding 30 cm deep and average 15 cm deep and getting out in soft/disintegrated
rock soil.
1 27.180 15.76 sqm. 428.36 L= 19.68 + 3.00 x 2 + 0.75 x 2 = 27.18 m.
W = 8.26 + 3.00 x 2 + 0.75 x 2 = 15.76 m.
1 428.36 162.56 sqm. 265.80 Site Clearance Item
S.I. Rate Amount
Total 428.36 3001 61.60 26386.78
Total 265.80 3012 5.30 1408.72

Item No.2

Excavation in trenches, not exceeding 1.50 meter wide and not exceeding 1.50 meter in depth, for
foundation, etc. or for shafts, wells, cesspits, manholes, pier holes, etc. not exceeding 10 square meter on
plan and not exceeding 1.50 meter in depth and getting out in soft/ disintegrated rock soil.

8 2.500 2.800 1.500 cum. 84.00 Footing F1


2 2.800 4.200 1.500 cum. 35.28 Footing CF1
2 2.600 4.330 1.500 cum. 33.77 Footing CF2
1 174.68 0.40 0.400 cum. 27.95 Plinth Beam Foundation
cum. 181.00 3004 307.80 55712.42

Item No.3

Excavation in trenches, exceeding 1.50 meter wide and not exceeding 3.00 meter in depth, for foundation,
etc. or for shafts, wells, cesspits, manholes, pier holes, etc. not exceeding 10 square meter on plan and not
exceeding 3.00 meter in depth and getting out in soft/ disintegrated rock soil.
8 2.500 2.800 0.600 cum. 33.60 Footing F1
2 2.800 4.200 0.600 cum. 14.11 Footing CF1
2 2.600 4.330 0.600 cum. 13.51 Footing CF2
cum. 61.22 3006, 3007 520.30 31853.60

Item No. 4

Material and labour for Cement concrete in foundations, filling and mass concrete type D2 1:4:8 using 40
mm graded stone aggregate including compaction of concrete, curing etc. complete.
8 2.500 2.800 0.600 cum. 33.60 Footing F1
2 2.800 4.200 0.800 cum. 18.82 Footing CF1
2 2.600 4.330 0.800 cum. 18.01 Footing CF2
1 221.26 0.38 0.100 cum. 8.41 Plinth Beam Foundation
cum. 78.84 4025 2303.30 181584.09

Item No. 5

Returning filling in, including spreading, levelling, watering and well ramming in layers not exc. 25 cm in soft/
loose soil.

PCC 78.84 cum.


Footing 49.07 cum. Total Earth work 181.00
Columns 1.15 cum. Total filling (Less) -141.34
Plinth Beam 12.28 Total 39.67
Less 10% due to
Total 141.34 cum. Bulkage (-) 3.97
Net Qty. of filling 35.70
Qty. S.I. Rate Amount
35.70 3009 41.70 1488.66

Item No. 6

Treating the back fill in contact with foundation at the rate of 7.5 liter of emulsion per square meter of
vertical surface (Area of the sub structure in contact with back fill to be measured).

2 221.26 0.50 221.255

Qty. S.I. Rate Amount


221.26 3048 126.80 28055.13

Item No. 7

Material and labour for sand filling under floors or in foundation including watering and
consolidation etc complete.

1 71.97 0.485 34.91 3019 31.90 1113.54

Total 327602.94
B/f 327602.94
Item No. 8

RCC Columns Footings


Footing F1 (Size 2300 x 2600)
No. No. No. Length Qty. Dia
8 1 18 2.65 381.60 12 Nos = 2.15/ 0.125 + 1 = 18
8 1 21 2.35 394.80 12 Nos = 2.45/ 0.125 + 1 = 21
8 1 12 2.75 264.00 12 Nos = 2.15/ 0.20 + 1 = 12
8 1 13 2.45 254.80 12 Nos = 2.45/ 0.20 + 1 = 13
8 1 4 2.65 84.80 10 Nos = 0.55/ 0.15 + 1 = 4
8 1 6 2.45 117.60 10 Nos = 0.70/ 0.15 + 1 = 6
8 1 5 2.50 100.00 10 Nos = 0.70/ 0.20 + 1 = 5

8 1 9.80 0.300 23.52 Sqm. Form Work


8 1 2.90 0.150 3.48 Sqm. Form Work

8 2.30 2.60 0.300 14.35 Cum. RCC M-25


8 0.65 0.80 0.150 0.62 Cum. RCC M-25
RCC M-25
8 1.10 8.80 Cum. A1 2.30 x 2.600 = 5.98
A2 0.65 x 0.80 = 0.52
V = 0.40/ 6 x (5.98 + 0.52 + 2.95 x 3.40) =
= 1.10

Footing CF1 (Size 2600 x 4000)


2 1 12 4.05 97.20 12 Nos = 2.45/ 0.22 + 1 = 12
2 1 19 2.65 100.70 12 Nos = 3.85/ 0.22 + 1 = 19
2 1 21 4.05 170.10 16 Nos = 2.45/ 0.125 + 1 = 21
2 1 32 2.65 169.60 16 Nos = 3.85/ 0.125 + 1 = 32
2 1 12 4.20 100.80 20 12
2 2 27 2.82 304.56 12 Nos = 3.85/ 0.15 + 1 = 27

2 1 13.20 0.300 7.92 Sqm. Form Work


2 1 9.40 0.300 5.64 Sqm. Form Work

2 2.60 4.00 0.300 6.24 Cum. RCC M-25


2 4.00 0.70 0.300 1.68 Cum. RCC M-25
RCC M-25
2 1.40 2.80 Cum. A1 2.60 x 4.000 = 10.4
A2 0.90 x 0.80 = 0.72
V = 0.30/ 6 x (10.40 + 0.72 + 3.50 x 4.80) =
= 1.40
Footing CF2 (Size 2400 x 4130)
2 1 12 4.20 100.80 12 Nos = 2.25/ 0.20 + 1 = 12
2 1 21 2.45 102.90 12 Nos = 4.00/ 0.20 + 1 = 21
2 1 19 4.20 159.60 16 Nos = 2.25/ 0.125 + 1 = 19
2 1 33 2.45 161.70 16 Nos = 4.00/ 0.125 + 1 = 33
2 1 12 4.20 100.80 20 12
2 2 27 2.72 293.76 12 Nos = 3.85/ 0.15 + 1 = 27

2 1 13.06 0.300 7.84 Sqm. Form Work


2 1 13.06 0.300 7.84 Sqm. Form Work

2 2.40 4.13 0.300 5.95 Cum. RCC M-25


2 2.40 4.13 0.300 5.95 Cum. RCC M-25
RCC M-25
2 1.34 2.68 Cum. A1 2.40 x 4.130 = 9.912
A2 0.90 x 0.80 = 0.72
V = 0.30/ 6 x (9.912 + 0.72 + 3.30 x 4.93) =
= 1.34

Summary of Columns Foottings


Item Wt. Qty. Rm. Qty. in Kg. S.I. Rate Amount
10 mm dia 0.617 302.40 186.58 10034 48.60 9067.83
12 mm dia 0.888 2295.12 2038.07 10034 48.60 99050.03
16 mm dia 1.58 661.00 1044.38 10034 48.60 50756.87
20 mm dia 2.47 201.60 497.95 10034 48.60 24200.47
Form work sqm 56.23 7004 134.20 7546.33
RCC M-25 cum 49.07 4053 3482.20 170872.95
Total 689097.42
B/f 689097.42
Item No. 9

RCC Columns upto plinth level and errection of steel upto first floor slab level

Qty Dia of bar Column C1 (Size 350 x 500)


14 1 8 6.20 694.40 20 Length = 0.30 + 1.95 + 0.45 + 3.20 + 0.30 = 6.20
14 1 4 6.20 347.20 25 Length = 0.30 + 1.95 + 0.45 + 3.20 + 0.30 = 6.20
14 1 61 1.60 1366.40 10 Nos = 3.42/ 0.075 + 2.13/ 0.15 + 1 = 61 Nos
14 1 61 1.00 854.00 10 Length = (0.30 + 0.45) x 2 + 0.10 = 1.60
14 1 61 1.20 1024.80 10 Length = (0.15 + 0.30) x 2 + 0.10 = 1.00
Length = (0.10 + 0.45) x 2 + 0.10 = 1.20

14 1.70 2.05 48.79 Sqm. Form work

14 0.35 0.50 2.05 5.02 Cum. RCC M-25

Column C2 (Size 300 x 300)


2 1 8 6.20 99.20 16 Length = 0.30 + 1.95 + 0.45 + 3.20 + 0.30 = 6.20
2 1 61 1.10 134.20 10 Nos = 3.42/ 0.075 + 2.13/ 0.15 + 1 = 61 Nos
2 1 61 0.82 100.04 10 Length = (0.25 + 0.25) x 2 + 0.10 = 1.10
Length = (0.18 + 0.18) x 2 + 0.10 = 0.82

2 1.20 2.05 4.92 Sqm. Form work

2 0.30 0.30 2.05 0.37 Cum. RCC M-25

B/f 689097.42

Summary of RCC Columns


Item S.I. Rate Amount
10 mm dia stripps Kg 2146.81 10036 49.70 106696.68
16 mm dia Kg 156.74 10034 48.60 7617.37
20 mm dia Kg 1715.17 10034 48.60 83357.16
25 mm dia Kg 1336.72 10034 48.60 64964.59
Form work sqm. 53.71 7014 241.10 12949.48
RCC M-25 cum. 5.39 4058 4159.00 22423.25
Total 298008.54

Total C/o 987105.95


Item No. 10
B/f 987105.95
RCC Plinth Beams
No. No. No. Length Qty. Dia
Size 300 x 500 PB1 - No's 7 6.23 c/c
7 1 4 6.71 187.88 20 Length = 6.23 + 0.18 + 2 x 0.15 = 6.71
7 1 2 6.71 93.94 20 Length = 6.23 + 0.18 + 2 x 0.15 = 6.71
7 1 4 3.12 87.22 25 Length = 6.23 x 0.50 = 3.12
7 1 49 1.48 507.64 8 Nos = 2.00/ 0.10 + 4.23/ 0.15 + 1 = 49
Length = (0.25 + 0.45) x 2 + 0.08 = 1.48

7 2 6.23 0.500 43.61 sqm. Form work

7 6.23 0.30 0.500 6.54 cum RCC M-25

Size 300 x 450 PB2 - No's 2 1.80 c/c


2 1 4 2.28 18.24 16 Length = 1.80 + 0.18 + 2 x 0.15 = 2.28
2 1 2 2.28 9.12 20 Length = 1.80 + 0.18 + 2 x 0.15 = 2.28
2 1 4 0.90 7.20 20 Length = 1.80 x 0.50 = 0.90
2 1 19 1.38 52.44 8 Nos = 1.80/ 0.10 + 1 = 19
Length = (0.25 + 0.40) x 2 + 0.08 = 1.38

2 2 1.80 0.450 3.24 sqm. Form work

2 1.80 0.30 0.450 0.49 cum RCC M-25

Size 300 x 450 PB2 - No's 2 19.46 c/c


2 1 4 19.94 159.52 16 Length = 19.46 + 0.18 + 2 x 0.15 = 19.94
2 1 2 19.94 79.76 20 Length = 19.46 + 0.18 + 2 x 0.15 = 19.94
2 1 4 9.73 77.84 20 Length = 19.46 x 0.50 = 9.73
2 1 167 1.38 460.92 8 Nos = 10.80/ 0.10 + 8.66/ 0.15 + 1 = 167
Length = (0.25 + 0.40) x 2 + 0.08 = 1.38

2 2 19.46 0.450 35.03 sqm. Form work

2 19.46 0.30 0.450 5.25 cum RCC M-25

Summary Plinth Beams

Item Qty. S.I. Rate Amount


8 mm dia st. 403.30 10036 49.70 20043.76
16 mm dia 280.86 10034 48.60 13649.83
20 mm dia 1125.68 10034 48.60 54707.94
25 mm dia 335.80 10034 48.60 16319.73
Form work 81.88 7010 203.70 16678.55
RCC M-25 12.28 4057 4004.10 49177.15
Total C/o 1157682.93
Item No. 10
0 B/f 1157682.93
Brick work with Fly Ash Bricks, straight or curved on plan exceeding 6 meter mean radius built in cement sand
mortar 1:6 including curing, racking of joints etc. complete in all respect.

No. Description No's Length Width Height Quantity

Length = (19.68 + 8.26) x 2 = 55.88 Rm. 1 55.88 0.23 0.45 5.78


Total 5.78
Qty. S.I. Rate Amount
5.78 5019 2249.50 13010.16

Total C/o 1170693.09


B/f 1170693.09
Item No. 11

RCC Columns upto plinth level and errection of steel upto first floor slab level

Qty Dia of bar Column C1 (Size 350 x 500)


14 1.70 2.10 49.98 Sqm. Form work

14 0.35 0.50 2.10 5.15 Cum. RCC M-25

Column C2 (Size 300 x 300)


2 1.20 2.10 5.04 Sqm. Form work

2 0.30 0.30 2.10 0.38 Cum. RCC M-25

B/f 1170693.09

Summary of RCC Columns

Item S.I. Rate Amount


Form work sqm. 55.02 7014 241.10 13265.32
RCC M-25 cum. 5.52 4058 4159.00 22970.16
Total 36235.48

Total C/o 1206928.57


Item No. 12
B/f 1206928.57
Brick work with Fly Ash Bricks, straight or curved on plan exceeding 6 meter mean radius built in cement sand
mortar 1:6 including curing, racking of joints etc. complete in all respect.

No. Description No's Length Width Height Quantity

Length = 19.68 x 2 - 14 x 0.30 + 6.46 x 3 - 6 x

0.45 + 8.26 x 2 - 4 x 0.45 - 2 x 0.30 + 3.96 x 2 1 83.14 0.23 2.10 40.16

- 4 x 0.30 + 3.23 + 3.00 + 4.23 = 83.14 Rm.


Deductions
PD10B 5 1.00 2.10 0.23 -2.42
PVC8 1 0.80 2.10 0.23 -0.39
BW15B 8 1.50 1.20 0.23 -3.31
SLV5 1 0.50 0.60 0.23 -0.07
Total 33.97
Qty. S.I. Rate Amount
33.97 5019 2249.50 76425.01

Item No. 14

Half brick wall masonaery in cement sand mortar in CM 1:4 in sub class 'B' Bricks old size with fly ash bricks in
super structure

No. Description No's Length Height Quantity

Length = 1.50 + 0.60 = 2.10


1 2.10 2.10 4.41
Deductions
PVCD7 1 0.70 2.10 -1.47
Total 2.94
Qty. S.I. Rate Amount
2.94 5005 280.00 823.20

Item No. 15

8 mm dia bar in half brick wall masonary


2.94 2.50 7.35
Qty. S.I. Rate Amount
7.35 50.00 367.50

Total C/o 1284544.28


B/f 1284544.28
Item No. 16

RCC Columns lintel level to first floor slab level

Qty Dia of bar Column C1 (Size 350 x 500)


14 1.70 0.80 19.04 Sqm. Form work

14 0.35 0.50 0.80 1.96 Cum. RCC M-25

Column C2 (Size 300 x 300)


2 1.20 0.80 1.92 Sqm. Form work

2 0.30 0.30 0.80 0.14 Cum. RCC M-25

B/f 1284544.28
Summary of RCC Columns
Item S.I. Rate Amount
Form work sqm. 20.96 7014 241.10 5053.46
RCC M-25 cum. 2.10 4058 4159.00 8750.54
Total 13803.99
C/o 1298348.27
Item No. 17
B/f 1298348.27
Brick work with Fly Ash Bricks, straight or curved on plan exceeding 6 meter mean radius built in cement sand
mortar 1:6 including curing, racking of joints etc. complete in all respect.

No. Description No's Length Width Height Quantity

Length = 19.68 x 2 - 14 x 0.30 + 6.46 x 3 - 6 x

0.45 + 8.26 x 2 - 4 x 0.45 - 2 x 0.30 + 3.96 x 2 1 83.14 0.23 0.65 12.43

- 4 x 0.30 + 3.23 + 3.00 + 4.23 = 83.14 Rm.


Total 12.43
Qty. S.I. Rate Amount
12.43 5019 2249.50 27960.00

Item No. 19

Half brick wall masonaery in cement sand mortar in CM 1:4 in sub class 'B' Bricks old size with fly ash bricks in
super structure

No. Description No's Length Height Quantity

Length = 1.50 + 0.60 = 2.10


1 2.10 0.98 2.06

Total 2.06
Qty. S.I. Rate Amount
2.06 5005 280.00 576.24

Item No. 20

8 mm dia bar in half brick wall masonary


2.06 2.50 5.15
Qty. S.I. Rate Amount
5.15 50.00 257.25

Total C/o 1327141.76


Item No. 21
B/f 1327141.76
RCC Roof Beams
No. No. No. Length Qty. Dia

Size 350 x 500 RB1 - No's 7 6.23 c/c


7 1 2 6.71 93.94 12 Length = 6.23 + 0.18 + 2 x 0.15 = 6.71
7 1 4 6.71 187.88 20 Length = 6.23 + 0.18 + 2 x 0.15 = 6.71
7 1 3 6.71 140.91 25 Length = 6.23 + 0.18 + 2 x 0.15 = 6.71
7 1 4 3.12 87.22 20 Length = 6.23 x 0.50 = 3.12
7 1 49 1.58 541.94 8 Nos = 2.00/ 0.10 + 4.23/ 0.15 + 1 = 49
Length = (0.30 + 0.45) x 2 + 0.08 = 1.58

7 2 6.23 0.360 31.40 sqm. Form work

7 6.23 0.35 0.360 5.49 cum RCC M-25

Size 300 x 450 RB2 - No's 2 19.46 c/c


2 1 4 19.94 159.52 16 Length = 19.46 + 0.18 + 2 x 0.15 = 19.94
2 1 2 19.94 79.76 20 Length = 19.46 + 0.18 + 2 x 0.15 = 19.94
2 1 4 9.73 77.84 20 Length = 19.46 x 0.50 = 9.73
2 1 167 1.38 460.92 8 Nos = 10.80/ 0.10 + 8.66/ 0.15 + 1 = 167
Length = (0.25 + 0.40) x 2 + 0.08 = 1.38

2 2 19.46 0.310 24.13 sqm. Form work

2 19.46 0.30 0.310 3.62 cum RCC M-25

Size 300 x 450 CRB - No's 7 1.80 c/c


7 1 2 2.28 31.92 16 Length = 1.80 + 0.18 + 2 x 0.15 = 2.28
7 1 3 2.28 47.88 25 Length = 1.80 + 0.18 + 2 x 0.15 = 2.28
7 1 19 1.38 183.54 8 Nos = 1.80/ 0.10 + 1 = 19
Length = (0.25 + 0.40) x 2 + 0.08 = 1.38

7 2 1.80 0.290 7.31 sqm. Form work

7 1.80 0.30 0.290 1.10 cum RCC M-25

Summary of Roof Beams

Item Qty. S.I. Rate Amount


8 mm dia st. 468.63 10036 49.70 23290.81
12 mm dia 83.42 10034 48.60 4054.15
16 mm dia 302.48 10034 48.60 14700.29
20 mm dia 1068.77 10034 48.60 51942.17
25 mm dia 726.84 10034 48.60 35324.50
Form work 62.84 7010 203.70 12800.02
RCC M-25 10.21 4057 4004.10 40884.34
Total C/o 1510138.05
Item No. 22
B/f 1510138.05
RCC First Floor Slab

(A) Form work

No. Length width Unit Qty. Description

1 19.68 8.26 sqm. 162.56


Total 162.56

Qty S.I. Rate Amount


162.56 7006 211.5 34380.76

(B) RCC first floor slab

No. Length width Height Qty. Description

1 19.68 8.26 0.14 22.76

S.I. Rate Amount


Total 22.76 cum. 4055 3770.00 85797.48

Total C/o 1630316.29


Cont……… Item No. 22

Description No's No's Length 8Φ Description and detail

Slab 1 RS1 3.50 x 6.00 m. span I/I 1 No's


Short span C/C 140 280 c/c
Long span C/C 140 280 c/c
No's = 6.00 / 0.140 = 44
Short span C/C 1 8Φ 22 5.16 113.52 L = 3.50 + 0.46 + 4.00 x 0.30 = 5.16
1 8Φ 22 4.56 100.32 L = 3.50 + 0.46 + 0.60 = 4.56
No's = 3.50 / 0.140 = 26.00
Long Span 1 8Φ 13 6.93 90.10 L = 6.00 + 0.46 + 1.57 x 0.30 = 6.93
1 8Φ 13 7.06 91.78 L = 6.00 + 0.46 + 0.60 = 7.06
No's = 6.00 / 0.28 = 46
Temp Bar SS 1 8Φ 46 2.75 126.50 L = 3.50 x 0.70 + 0.30 = 2.75
No's = 3.50 / 0.30 = 26
Temp Bar LS 1 8Φ 26 4.50 117.00 L = 6.00 x 0.70 + 0.30 = 4.50

Slab 2 RS1 4.00 x 6.00 m. span I/I 1 No's


Short span C/C 140 280 c/c
Long span C/C 140 280 c/c
No's = 6.00 / 0.140 = 44
Short span C/C 1 8Φ 22 5.53 121.68 L = 4.00 + 0.46 + 3.57 x 0.30 = 5.53
1 8Φ 22 5.36 117.92 L = 4.00 + 0.46 + 3.00 x 0.30 = 5.36
No's = 4.00 / 0.140 = 30.00
Long Span 1 8Φ 15 6.93 103.97 L = 6.00 + 0.46 + 1.57 x 0.30 = 6.93
1 8Φ 15 7.06 105.90 L = 6.00 + 0.46 + 0.60 = 7.06
No's = 6.00 / 0.28 = 46
Temp Bar SS 1 8Φ 46 3.10 142.60 L = 4.00 x 0.70 + 0.30 = 3.10
No's = 4.00 / 0.30 = 30
Temp Bar LS 1 8Φ 30 4.50 135.00 L = 6.00 x 0.70 + 0.30 = 4.50
Slab 3 RS1 3.00 x 6.00 m. span I/I 1 No's
Short span C/C 140 280 c/c
Long span C/C 140 280 c/c
No's = 6.00 / 0.140 = 44
Short span C/C 1 8Φ 22 4.66 102.52 L = 3.00 + 0.46 + 4.00 x 0.30 = 4.66
1 8Φ 22 4.36 95.92 L = 3.00 + 0.46 + 3.00 x 0.30 = 4.36
No's = 3.00 / 0.140 = 23.00
Long Span 1 8Φ 11 6.93 76.24 L = 6.00 + 0.46 + 1.57 x 0.30 = 6.93
1 8Φ 12 7.06 84.72 L = 6.00 + 0.46 + 0.60 = 7.06
No's = 6.00 / 0.28 = 46
Temp Bar SS 1 8Φ 46 2.40 110.40 L = 3.00 x 0.70 + 0.30 = 2.40
No's = 3.00 / 0.30 = 22
Temp Bar LS 1 8Φ 22 4.50 99.00 L = 6.00 x 0.70 + 0.30 = 4.50
Slab 4 RS1 3.00 x 6.00 m. span I/I 1 No's
Short span C/C 140 280 c/c
Long span C/C 140 280 c/c
No's = 6.00 / 0.140 = 44
Short span C/C 1 8Φ 22 4.36 95.92 L = 3.00 + 0.46 + 3.00 x 0.30 = 4.36
1 8Φ 22 4.36 95.92 L = 3.00 + 0.46 + 3.00 x 0.30 = 4.36
No's = 3.00 / 0.140 = 23.00
Long Span 1 8Φ 11 6.93 76.24 L = 6.00 + 0.46 + 1.57 x 0.30 = 6.93
1 8Φ 12 7.06 84.72 L = 6.00 + 0.46 + 0.60 = 7.06
No's = 6.00 / 0.28 = 46
Temp Bar SS 1 8Φ 46 2.40 110.40 L = 3.00 x 0.70 + 0.30 = 2.40
No's = 3.00 / 0.30 = 22
Temp Bar LS 1 8Φ 22 4.50 99.00 L = 6.00 x 0.70 + 0.30 = 4.50

Slab 5 RS1 3.00 x 6.00 m. span I/I 1 No's


Short span C/C 140 280 c/c
Long span C/C 140 280 c/c
No's = 6.00 / 0.140 = 44
Short span C/C 1 8Φ 22 4.36 95.92 L = 3.00 + 0.46 + 3.00 x 0.30 = 4.36
1 8Φ 22 3.91 86.02 L = 3.00 + 0.46 + 1.50 x 0.30 = 3.91
No's = 3.00 / 0.140 = 23.00
Long Span 1 8Φ 11 6.93 76.24 L = 6.00 + 0.46 + 1.57 x 0.30 = 6.93
1 8Φ 12 7.06 84.72 L = 6.00 + 0.46 + 0.60 = 7.06
No's = 6.00 / 0.28 = 46
Temp Bar SS 1 8Φ 46 2.40 110.40 L = 3.00 x 0.70 + 0.30 = 2.40
No's = 3.00 / 0.30 = 22
Temp Bar LS 1 8Φ 22 4.50 99.00 L = 6.00 x 0.70 + 0.30 = 4.50

Slab 6 RS2 1.50 x 3.90 m. span I/I 1 No's


Short span C/C 140 280 c/c
Long span C/C 200 400 c/c
No's = 3.90 / 0.140 = 29
Short span C/C 1 8Φ 14 2.86 40.04 L = 1.50 + 0.46 + 3.00 x 0.30 = 2.86
1 8Φ 15 2.56 38.40 L = 1.50 + 0.46 + 0.60 = 2.56
No's = 1.50 / 0.200 = 9.00
Long Span 1 8Φ 4 4.99 19.96 L = 3.90 + 0.46 + 2.10 x 0.30 = 4.99
1 8Φ 5 4.96 24.80 L = 3.90 + 0.46 + 0.60 = 4.96
No's = 3.90 / 0.28 = 30
Temp Bar SS 1 8Φ 30 1.35 40.50 L = 1.50 x 0.70 + 0.30 = 1.35
No's = 1.50 / 0.30 = 12
Temp Bar LS 1 8Φ 12 3.03 36.36 L = 3.90 x 0.70 + 0.30 = 3.03
Slab 7 RS2 1.50 x 2.10 m. span I/I 1 No's
Short span C/C 140 280 c/c
Long span C/C 200 400 c/c
No's = 2.10 / 0.140 = 16
Short span C/C 1 8Φ 8 2.86 22.88 L = 1.50 + 0.46 + 3.00 x 0.30 = 2.86
1 8Φ 8 2.43 19.47 L = 1.50 + 0.46 + 1.58 x 0.30 = 2.43
No's = 1.50 / 0.200 = 9.00
Long Span 1 8Φ 4 3.46 13.84 L = 2.10 + 0.46 + 3.00 x 0.30 = 3.46
1 8Φ 5 3.16 15.80 L = 2.10 + 0.46 + 0.60 = 3.16
No's = 2.10 / 0.28 = 18
Temp Bar SS 1 8Φ 18 1.35 24.30 L = 1.50 x 0.70 + 0.30 = 1.35
No's = 1.50 / 0.30 = 12
Temp Bar LS 1 8Φ 12 1.77 21.24 L = 2.10 x 0.70 + 0.30 = 1.77

Slab 8 RS1 1.57 x 1.57 m. span I/I 1 No's


Short span C/C 140 280 c/c
Long span C/C 140 280 c/c
No's = 1.57 / 0.140 = 13
Short span C/C 1 8Φ 6 2.66 15.96 L = 1.57 + 0.46 + 2.10 x 0.30 = 2.66
1 8Φ 7 2.63 18.41 L = 1.57 + 0.46 + 0.60 = 2.63
No's = 1.57 / 0.140 = 13.00
Long Span 1 8Φ 6 2.93 17.58 L = 1.57 + 0.46 + 3.00 x 0.30 = 2.93
1 8Φ 7 2.63 18.41 L = 1.57 + 0.46 + 0.60 = 2.63
No's = 1.57 / 0.28 = 14
Temp Bar SS 1 8Φ 14 1.40 19.59 L = 1.57 x 0.70 + 0.30 = 1.40
No's = 1.57 / 0.30 = 14
Temp Bar LS 1 8Φ 14 1.40 19.59 L = 1.57 x 0.70 + 0.30 = 1.40

Slab 7 RS2 1.57 x 3.00 m. span I/I 3 No's


Short span C/C 140 280 c/c
Long span C/C 200 400 c/c
No's = 3.00 / 0.140 = 23
Short span C/C 3 8Φ 11 3.83 126.39 L = 1.57 + 0.46 + 6.00 x 0.30 = 3.83
3 8Φ 12 2.63 94.68 L = 1.57 + 0.46 + 0.60 = 2.63
No's = 1.57 / 0.200 = 9.00
Long Span 3 8Φ 4 4.36 52.32 L = 3.00 + 0.46 + 3.00 x 0.30 = 4.36
3 8Φ 5 4.36 65.40 L = 3.00 + 0.46 + 3.00 x 0.30 = 4.36
No's = 3.00 / 0.28 = 24
Temp Bar SS 3 8Φ 24 1.40 100.73 L = 1.57 x 0.70 + 0.30 = 1.40
No's = 1.57 / 0.30 = 14
Temp Bar LS 3 8Φ 14 2.40 100.80 L = 3.00 x 0.70 + 0.30 = 2.40
Slab 8 RS2 1.57 x 4.00 m. span I/I 1 No's
Short span C/C 140 280 c/c
Long span C/C 200 400 c/c
No's = 4.00 / 0.140 = 30
Short span C/C 1 8Φ 15 3.83 57.45 L = 1.57 + 0.46 + 6.00 x 0.30 = 3.83
1 8Φ 15 2.63 39.45 L = 1.57 + 0.46 + 0.60 = 2.63
No's = 1.57 / 0.200 = 9.00
Long Span 1 8Φ 4 5.36 21.44 L = 4.00 + 0.46 + 3.00 x 0.30 = 5.36
1 8Φ 5 5.51 27.55 L = 4.00 + 0.46 + 3.50 x 0.30 = 5.51
No's = 4.00 / 0.28 = 32
Temp Bar SS 1 8Φ 32 1.40 44.77 L = 1.57 x 0.70 + 0.30 = 1.40
No's = 1.57 / 0.30 = 14
Temp Bar LS 1 8Φ 14 3.10 43.40 L = 4.00 x 0.70 + 0.30 = 3.10

Slab 9 RS1 1.57 x 3.50 m. span I/I 1 No's


Short span C/C 140 280 c/c
Long span C/C 140 280 c/c
No's = 3.50 / 0.140 = 26
Short span C/C 1 8Φ 13 3.83 49.79 L = 1.57 + 0.46 + 6.00 x 0.30 = 3.83
1 8Φ 13 2.63 34.19 L = 1.57 + 0.46 + 0.60 = 2.63
No's = 1.57 / 0.140 = 13.00
Long Span 1 8Φ 6 5.16 30.96 L = 3.50 + 0.46 + 4.00 x 0.30 = 5.16
1 8Φ 7 4.56 31.92 L = 3.50 + 0.46 + 0.60 = 4.56
No's = 3.50 / 0.28 = 28
Temp Bar SS 1 8Φ 28 1.40 39.17 L = 1.57 x 0.70 + 0.30 = 1.40
No's = 1.57 / 0.30 = 14
Temp Bar LS 1 8Φ 14 2.75 38.50 L = 3.50 x 0.70 + 0.30 = 2.75

Total Length 8 mm dia = 4475.63


wt per rm 0.395
8 mm dia steel wt. 1767.87
S.I. 10034
Rate 48.60
Amount 85918.57
B/f 1630316.29
G. Total 1716234.87
B/f 1716234.87

Item No. 23
Factory made pressed steel frames for doors with one or more rebates including necessory fixing lugs,
hinges, lock strike plate, etc. complete, as specified supplied and fixed of size 125 x 60 mm

5 1.00 + 2.14 x 2 = 26.40 Rm. PD10B


S.I. Rate Amount
26.40 10082 285.60 7539.84

Item No. 24

PCC 1:3:6 filling in Factory made pressed steel sheet 1.25 mm thick single rebate door frames.
1 26.40 0.105 0.06 cum. 0.17
S.I. Rate Amount
0.17 4025 2579.00 428.94

Item No. 25
Tie bars in door frames

5 1.00 Rm. 5.00 PD10B


S.I. Rate Amount
5.00 80.00 400.00

Item No. 26

Taring to door frames in contact of wall/ columns

5 1.00 Rm. 27.4 PD10B


S.I. Rate Amount
27.40 100.00 2740.00

Total C/o 1727343.65


Item No. 27
B/f 1727343.65

Plain framed, pannelled shutter (One Panal) with lock rail and panel of 9 mm B.W.P. commercial ply

or 12 mm veveered on both faces. The size of rail and stile as per IS 1003 (Part I), klin seasoned and

chemically pressure treated in second class hard word rail and style of 35 mm thick.

5 0.91 2.05 sqm. 9.33 PD10B


Qty. S.I. Rate Amount
9.33 8021 1436.10 13395.22

Item No. 28

200 mm long 10 mm dia tower bolt

Door No. Qty. Total Qty

PD10B 5 2 = 10 No's
Qty. S.I. Rate Amount
10 9004 52.80 528.00

Item No. 29

125 mm long D- type handle with 32 x 3 plate

Door No. Qty. Total Qty

PD10B 5 2 = 10 No's
Qty. S.I. Rate Amount
10 965 31.03 310.30

Item No. 30

Wooden door stopper with 50 mm butt hinge

PD10B 5 1 = 5 No's
Qty. S.I. Rate Amount
5 LS 75.00 375.00

Item No. 31
Factory Fixed Glazed Windows
8 1.50 1.20 = 14.40 BW15B
1 0.50 0.90 = 0.45 SLV5
Qty. S.I. Rate Amount
14.85 10070 1335.80 19836.63
Item No. 32

4 mm thick glass pan sheet for steel windows

1 14.85 0.90 13.37


Total 13.37 SI Rate Amount
16006 470.50 6288.23

Item No. 34

Supply and fixing factory made solid PVC moulded door shutter, 28 to 30 mm thick (stiles), with 2,4

or 6 raised panel design with 2 mm thick moulded PVC sheet on the front face & 2 mm plain colour

PVC sheet on back face face, suppling and fixing in frame at site as per specification and drawings.

1 0.70 2.10 1.47 PVC7


1 0.80 2.10 1.68 PVC8
Total 3.15 SI Rate Amount
8101 2421.30 7627.10

Item No. 35

Supply and fixing of solid PVC door frame of size 50 mm x 47 mm made ouit of 5 mm plain colour
PVC sheet reinforced with MS square tube, suppling and fixinx in opening as per specification and
drawing.

1 0.70 2.14 4.98


1 0.80 2.14 5.08
Total 10.06 SI Rate Amount
8095.00 335.30 3373.12

Total C/o 1779077.24


Item No. 37
B/f 1779077.24
10 mm thick rendering on fair faces of brick work or concrete surfaces in cement sand mortar 1:6 as in
internal surfaces of walls finished fair even and smooth without using extra cement.

No. Length Height Quantity Unit Description

1 14.54 2.94 42.75 M² Book Store


Lenth = (3.50 + 7.80) x 2 = 22.60
1 11.34 2.94 33.34 M² TRG Store
Length = (4.23 + 2.77) x 2 = 14.00
1 12.28 2.94 36.10 M² Staff Room
Length = (3.00 + 3.00) x 2 = 12.00
1 15.34 2.94 45.10 M² Passage
Length = (1.00 + 3.23) x 2 = 8.46
1 11.34 2.94 33.34 M² Class Room
Length = (9.30 + 6.00) x 2 = 30.60
1 26.52 2.94 77.97 M² Verandah
Length = (15.50 + 1.80) x 2 = 34.60
1 47.40 2.94 139.36 M² Toilet
Length = (1.50 + 3.90) x 2 = 10.80
1 7.74 0.94 7.28 M² Passage
Length = (1.50 + 2.10) x 2 = 7.20
Deductions
5 1.00 2.00 -10.00 M² PD10B
1 0.80 2.00 -1.60 M² PVCD8
1 0.70 2.00 -1.40 M² PVCD7
8 1.50 1.20 -14.40 M² BW15B
1 0.50 0.60 -0.30 M² SLV5
387.53 M²
Qty. S.I. Rate Amount
387.53 14001, 14005 89.80 34800.19

Item No. 38

15 mm thick rendering on rough faces of brick work or concrete surfaces I two layer of 10 mm thick in cement

sand mortar 1:6 and 5 mm thick in cement sand mortar 1:4 mixed with water proofing compound as in

external surfaces of walls finished fair even and smooth.

No. Length Height Quantity Unit Description

1 55.88 3.65 203.96 M² Length = (19.68 + 8.26) x 2 = 55.88


Total 203.96 M²
Qty. S.I. Rate Amount
203.96 14001, 14005, 127.40 25984.76
14004
Item No. 39

5 mm thick rendering on rough faces of brick work or concrete burfaces in cement sand mortar 1:4 as in RCC
surfaces of ceilling finished fair even and smooth.

No. Length Height Quantity Unit Description

1 3.50 7.80 27.30 M² Book Store


1 4.23 2.77 11.72 M² TRG Store
1 3.00 3.00 9.00 M² Staff Room
1 1.00 3.23 3.23 M² Passage
1 9.30 6.00 55.80 M² Class Room
1 15.50 1.80 27.90 M² Verandah
1 1.50 3.90 5.85 M² Toilet
1 1.50 2.10 3.15 M² Passage
Total 134.95 M²
Qty. S.I. Rate Amount
14001, 14004,
134.95 14005, 14003 99.70 13454.23
Total 1853316.42
1779077.24
mortar 1:6 as in

iption

Store
7.80) x 2 = 22.60
Store
2.77) x 2 = 14.00
Room
3.00) x 2 = 12.00
sage
+ 3.23) x 2 = 8.46
Room
6.00) x 2 = 30.60
ndah
+ 1.80) x 2 = 34.60
ilet
3.90) x 2 = 10.80
sage
+ 2.10) x 2 = 7.20
ctions
10B
CD8
CD7
15B
V5

10 mm thick in cement

oofing compound as in

iption

+ 8.26) x 2 = 55.88

Amount
25984.76
d mortar 1:4 as in RCC

Periphery

22.6
14
12
8.46
30.6
34.6
10.8
7.2
140.26
B/f 1853316.42

Item No. 40
Preperation of surfaces and applying three coats of White Wash to exposed RCC surfaces

Area of ceilling Plaster


Qty. S.I. Rate Amount
134.95 15002, 15007 12.70 1713.83

Item No. 42

Preperation of surfaces and applying two coats of Oil Bound Distemper to internal surfaces of walls
Area of internal plaster except area of White wash
15001, 15003,
387.53 15009 30.50 11819.67

Item No. 43

Preperation of surfaces and applying two coats of cement base paint to external surfaces of walls
Area of external Plaster
Qty. S.I. Rate Amount
203.96 15001, 31.70 6465.60
15010

Total C/o 1873315.51


B/f 1873315.51

Item No. 45

20 to 25 mm thick kota stone of size 550 x 500 as in flooring over 20 mm thick bedding layer in cement
sand mortar 1:3 over base as specified including cutting polishing etc complete.

1 15.50 1.80 27.90 M² Verandah


1 1.00 3.23 3.23 M² Passage
1 1.50 2.10 3.15 M² Passage
13013,
Total 34.28 14009, 673.10 23073.87
14010

Item No. 47

40 mm thick PCC 1:2:4 type B1 using 20 mm graded stone aggregate over sub base (100 mm thick PCC
1:4:8 type D2 using 40 mm graded stone aggregate) over rammed earth finished fair even and
smoothusing extra cement with groove of size 30 x 10 mm.

1 3.50 7.80 27.30 M² Book Store


1 4.23 2.77 11.72 M² TRG Store
13033, 130.30
Total 39.02 13040 5083.93

Item No. 49

Non skid ceramic tiles 7 to 8 mm thick (square/ reactangular), white in colour, area of each tile
exceeding 0.06 sqm. But not exceeding 0.11 sqm. In floors etc. set and jointed in neat cement slurry and
pointed in white or colured cement to match with joint free non skid tiles laid over 15 mm thick bedding
layerin cement sand mortar 1:4 over 25 mm thick PCC 1:2:4 type B0 using 12.5 mm thick graded stone
aggregate over sub base as specified. (Sub base 75 mm thick PCC 1:4:8 type D2).

1 3.00 3.00 9.00 M² Staff Room


1 9.30 6.00 55.80 M² Class Room
1 1.50 3.90 5.85 M² Toilet
13082,
Total 70.65 531.60 37557.54
13085

Item No. 50

75 mm thick PCC 1:4:8 using 40 mm graded stone aggregate as in sub base under floor over rammed
earth
143.95
143.95 S.I. Rate Amount
13035 176.40 25392.27
Item No. 51

6 to 8 mm thick glazed tiles dado in toilet and bath over 15 mm thick cement sand mortar bedding layer
in 1:6 jointed pointed in white cement.

1 5.30 2.10 11.13 M² Toilet - 1


1 5.30 2.10 11.13 M² Toilet - 2
1 7.17 2.10 15.06 M² Ladies Toilet
1 7.74 2.10 16.25 M² Gents Toilet

53.57 M² S.I. Rate Amount


13081 514.30 27551.57

Item No. 52

Material and labour for treating the top surface of filled earth at the rate of 5 liters of emulsion per
square meter of surface.

Area of sub base under floor


143.95
3049 80.60 11602.14

Item No. 53

Material and labour for anti termite treatment along the external wall below concrete or masonary
apron using chemical emulsion @ 2.25 liter per linear meter including drilling and plugging holes etc in
apron.

Area of sub base under floor


140.26
3053 53.20 7461.83

Total 2011038.65
B/F 2011038.65
Item No. 54

Supply and fixing of Vitreous china padestal pan and trap, white in colour, including connection to
drain (or outgoing pipe) and to flushing pipem antisyphonage pipe etc., complete, excluding fixing
bolts, flushing cistern and flush piep.

Qty. S.I. Rate Amount


1 18251, 18302 1,018.40 1,018.40

Item No. 55

Pressed steel, enamelled white valveless syphonic action type, flushing cistern, low level, white
with inlet, ball valve, float and handle including brackets with capacity 10 liters.

Qty. S.I. Rate Amount


18315,
1 1,574.90 1,574.90
18264

Item No. 56

Vitreous china wash basin, while, flat back and size 580 x 450 iroun (for Hospital use) excluding
taps, waste, chain and plug and porcelain stopper but including brackets, including cutting for and
pinning in ends of brackets or erecting stand.
No.
1
Qty. S.I. Rate Amount
1 18330, 18269 957.30 957.30

Item No. 57

Looking mirror
No.
1
Qty. S.I. Rate Amount
1 300.00 300.00

Item No. 58
Soap nitch

1
Qty. S.I. Rate Amount
1 - 300.00 300.00

Item No. 59
Floor trap
No.
4
Qty. S.I. Rate Amount
4 18,212 481.70 1,926.80

Item No. 60

Gully Trap
No.
1
Qty. S.I. Rate Amount
1 18,231 318.50 318.50

Item No. 61

Soil/ Vent pipe 100 mm dia CI as per IS 3989 spun pipe

Qty. S.I. Rate Amount


6.50 18,156 691.20 4,492.80

Item No. 62

75 mm dia CI spun pipe as per IS 3989 as Waste pipe

Qty. S.I. Rate Amount


10.00 18,156 595.00 5,950.00

Item No. 63

75 mm dia bend/ TEE


3
Qty. S.I. Rate Amount
3 18,158 337.10 1,011.30

Item No. 64

100 mm dia bend/ TEE


3
Qty. S.I. Rate Amount
3 18,158 414.00 1,242.00

Item No. 65

Peg set of two


1
Qty. S.I. Rate Amount
1 100.00 100.00

Item No. 66

600 mm long Stainless Steel Towel Rail


1
Qty. S.I. Rate Amount
1 600.00 600.00

Total 2,030,830.65
B/f 2,030,830.65

Item No. 67

50 mm thick PCC 1:3:6 as in plinth protection over 75 mm thick brocken stone aggregate hard
core over rammed earth.

(A) PCC Plinth protection

1 43.24 0.75 sqm. 32.43 Length = (19.86 + 0.75 x 2 + 8.26) x 2 =


43.24 Rm.
Total 32.43 36 136.10 4448.75
1.08
137.18

(B) Hard core


32.43 0.08 2.43 3042 895.10 2177.11

Item No. 68

Material and labour for treating the soil under plinth protection at the rate of 5 liter of
emulsion per square meter of surface area.

1 32.43 3050 80.60 2613.86

Item No. 69

Material and labour for anti termite treatment along the external wall below concrete or
masonary apron using chemical emulsion @ 2.25 liter per linear meter including drilling and
plugging holes etc in apron.

1 43.24 3053 53.20 2300.37

Total Amount 2042370.73


B/f 2042370.73
Item No. 70

Aluminium paint @0.11 Kg/ sqm. Over a layer of 3 mm thick APP membrane sheet over a coat of bitumen

primer @ 0.40 Ltr/ Sqm. Over a coat of plaster in cement sand mortar 1:4, 10 mm thick over RCC slab.

1 19.68 8.26 162.56 sqm.


Total 162.56 sqm.

Qty. S.I. Rate Amount


PCC Padding 162.56 13037 135.97 22102.31
Al Paint 162.56 60.00 9753.41
Bitumen Primer 162.56 11051 47.00 7640.17
APP Membrane 162.56 11068.00 171.80 27927.26
Plaster 162.56 14001 91.10 14808.92
Total 82232.07

Item No. 71

Fan Hooks

Qty. S.I. Rate Amount


5.00 LS 75.00 375.00

Item No. 72

HDPE Water storage tank 500 ltrs capacity

Qty. S.I. Rate Amount


1 18082 2203.49 2203.49

Item No. 73

Base slab for HDPE Water storage tank

Qty. S.I. Rate Amount


2 LS 5000.00 10000.00

Item No. 74

Misc & unseen items like cub board shutters, shelves, window cill, ramps, Parapet etc.
Amount
22818.71

Total 2160000.00

You might also like