Professional Documents
Culture Documents
SchedLog 120823
SchedLog 120823
EXE
=========================================================
Default Project..................................................PM-94
Use scheduling options from......................................PM-94
Projects:
PM-
94............................................................Updated Schedule- 18-
July-23-Monitoring Program
Scheduling/Leveling Settings:
-----------------------------
General
-------
Scheduling ......................................................Yes
Leveling ........................................................No
Ignore relationships to and from other projects .................No
Make open-ended activities critical .............................No
Use Expected Finish Dates .......................................Yes
Schedule automatically when a change affects dates ..............No
Level resources during scheduling ...............................No
Recalculate assignment costs after scheduling ...................No
When scheduling progressed activities use .......................Progress
Override
Calculate start-to-start lag from ...............................Early Start
Define critical activities as Total Float less than or equal to .0
Compute Total Float As ..........................................Finish Float
Calculate float based on finish date of .........................Each project
Calendar for scheduling Relationship Lag ........................Predecessor
Activity Calendar
Advanced
--------
Calculate multiple float paths...................................No
Statistics:
-----------
# Projects.......................................................1
# Activities.....................................................2291
# Not Started....................................................236
# In Progress....................................................350
# Completed......................................................1705
# Relationships..................................................3845
# Activities with Constraint.....................................1
Project: PM-94 Activity: CON-ECB-3044 Cable Terminaltion of DC
& AC ups system
Errors:
-------
Warnings:
---------
Activities without predecessors..................................16
Project: PM-94 Activity: COMM-SAT-SGB-1020 SAT for LV Switchgear
panels-need termination to finsh-started
Project: PM-94 Activity: CON-800-1010-TIE Approval of Work Permit
for Isolation of existing DN 800 Pipeline
Project: PM-94 Activity: CON-DSV-2061 Blinding Concreting
works
Project: PM-94 Activity: CON-ECB-2080 Installation of
Batteries
Project: PM-94 Activity: CON-EPH-1105 Form, Reinforcement &
Concrete Placement for Foundation for Steel Platform over Discharge Header
pipelines
Project: PM-94 Activity: CON-EPH-1160 Installation of Steel
Platform over Suction Header pipelines (External)
Project: PM-94 Activity: CON-EPH-1191 Blinding concreting
works for Grade Slab
Project: PM-94 Activity: CON-EPH-5040 Excavation works
Project: PM-94 Activity: CON-IVC1-0900 Excavation works
Project: PM-94 Activity: CON-REL-ELEC-1008 Site Preparation
Project: PM-94 Activity: CON-SSV-1090 Interlocking surve
vessel
Project: PM-94 Activity: CON-SSV-2000 Installation of Suction
Surge Vessel #1
Project: PM-94 Activity: NOC-ADCD-2010 Site Inspection and
Comments rectification
Project: PM-94 Activity: PED-1000 Letter of Award
Project: PM-94 Activity: TC-MCC-ELEC-1000 33 kV Medium Voltage
System-swut
Project: PM-94 Activity: TC-MCC-ELEC-1012 AC UPS System-ecb
Out-of-sequence activities.......................................237
Project: PM-94 Activity: COMM-ENR-ELEC-1000 Energizing and SAT
testing for Free Issued 33KV Switchgear
Project: PM-94 Activity: COMM-ENR-ELEC-1004 Energization of
Capacitor Bank-01
Project: PM-94 Activity: COMM-ENR-ELEC-1008 Energization of
Capacitor Bank-02
Project: PM-94 Activity: COMM-ENR-ELEC-1012 Energization of
11/0.415 kV Distribution Transformer 1
Project: PM-94 Activity: COMM-ENR-ELEC-1016 Energization of
11/0.415 kV Distribution Transformer 2
Project: PM-94 Activity: COMM-SAT-ECB-1002 SAT for 11/415 kV 2.5MVA
Trafo Protection panels started
Project: PM-94 Activity: COMM-SAT-ECB-1004 SAT for 33/11kV
Transformer 1
Project: PM-94 Activity: COMM-SAT-ECB-1006 SAT for 33/11kV
Transformer 2
Project: PM-94 Activity: COMM-SAT-ECB-1008 SAT for 11/0.415 kV
Distribution Transformer 1
Project: PM-94 Activity: COMM-SAT-ECB-1010 SAT for 11/0.415 kV
Distribution Transformer 2
Project: PM-94 Activity: COMM-SAT-ECB-1012 SAT for Phase Shift
Transformer PST-1
Project: PM-94 Activity: COMM-SAT-ECB-1014 SAT for Phase Shift
Transformer PST-2
Project: PM-94 Activity: COMM-SAT-ECB-1016 SAT for VSD panel 1-VFD
Project: PM-94 Activity: COMM-SAT-ECB-1018 SAT for VSD panel 2 VFD
Project: PM-94 Activity: COMM-SAT-ECB-1020 SAT for Local control
panel for sump pump
Project: PM-94 Activity: COMM-SAT-ECB-1026 SAT for DCS panels
Project: PM-94 Activity: COMM-SAT-ECB-1030 SAT for Distribution
board for MOV
Project: PM-94 Activity: COMM-SAT-ECB-1032 SAT for main
Distribution board for Fans
Project: PM-94 Activity: COMM-SAT-ECB-1038 SAT for 110V DC UPS
@11kV
Project: PM-94 Activity: COMM-SAT-SGB-1006 SAT for Capacitor Bank-
01
Project: PM-94 Activity: COMM-SAT-SGB-1010 SAT for SMDB 2-LINK LV
PANEL
Project: PM-94 Activity: COMM-SAT-SGB-1014 SAT for HVAC panel
Project: PM-94 Activity: COMM-SAT-SGB-1016 SAT for 110V DC UPS
@33kV
Project: PM-94 Activity: COMM-SAT-SGB-1018 SAT for dc ups system in
33kv room
Project: PM-94 Activity: CON-100CS-2010-TIE Submission of PTW
for Isolation of existing DN1200 CS pipeline at T-1400
Project: PM-94 Activity: CON-1200-1030 TIE Submission of Work
Permit for Isolation of existing DN 1200 Pipeline-no civil structure
Project: PM-94 Activity: CON-1200-1040 TIE Approval of Work Permit
for Isolation of existing DN 1200 Pipeline-cs pipe
Project: PM-94 Activity: CON-1200-1050 TIE Tie-in works at T17 A/B-
Weld Joint-PS Discharge Header-01 to Mirfa Tank Farm/MZPS (DN1200 G-5809 Pipeline-
cs pipe
Project: PM-94 Activity: CON-1200-1170-TIE Tie-in works at T19,
Flange Connection-
Project: PM-94 Activity: CON-1400CS-2190 TIE Application for
Permit
Project: PM-94 Activity: CON-1400CS-2250 Placing Precast
protection slab, along Road Crossing #3 add backfill & reinstatement
Project: PM-94 Activity: CON-1400CS-2270 Open-cut works for
existing Road Crossing #3
Project: PM-94 Activity: CON-1400CS-2280 Install DN 1400 CS
Pipeline (Line #1) at Road Crossing #3 incl., Excavation, Bedding, Laying, etc.,
Project: PM-94 Activity: CON-1400CS-2300 Install DN 1400 CS
Pipelines (Line #1 & #2) from RC #3 to Plant Header incl., Excavation, Bedding,
Laying, etc.,
Project: PM-94 Activity: CON-1400CS-2330 Backfilling & Compaction
works (From Tie-in point T5&6 to Main Plant Suction Header)
Project: PM-94 Activity: CON-1600CS-1000 Construction of Pipe
Support for Laying DN 1600 & DN 1200 CS Discharge Header pipelines (3 Lines)-cs
pump dischage
Project: PM-94 Activity: CON-1600CS-1020 Tie-in connection
between Plant Discharge Headers with DN 1200 pipelines of Pumps discharge
Project: PM-94 Activity: CON-1600CS-3000 TIE Submission of PTW
for Isolation of existing DN 1200 Bye-Pass pipeline-independent cs pipe
Project: PM-94 Activity: CON-1600CS-3010 TIE Approval of PTW
for Isolation of existing DN 1200 Bye-Pass pipeline-cs pipe
Project: PM-94 Activity: CON-1600CS-6000 TIE Submission of PTW
-modifiction of existing fan house, access ladder and platform inside pumping stn
Project: PM-94 Activity: CON-1600CS-6010 TIE Approval of PTW-cs
pipe
Project: PM-94 Activity: CON-1600CS-6020 TIE Tie-in works @ T-8
& T-11-Weld Joint / Flange-Pump - 7 Discharge-cs pipe
Project: PM-94 Activity: CON-1600CS-7000 TIE Submission of PTW-
modifiction of existing , access ladder and platform inside pumping stn
Project: PM-94 Activity: CON-1600CS-7020 TIE Tie-in works @ T-9
& T-10-Weld Joint / Flange
Project: PM-94 Activity: CON-1800CS-1000 Installation of DN 1800
CS pipeline - Extension of Plant Suction Header
Project: PM-94 Activity: CON-1800CS-1010 Installation of
Butterfly valve & fittings @ Future connection end
Project: PM-94 Activity: CON-1800CS-1060 Pressure testing works
for DN 1800 & DN 1400
Project: PM-94 Activity: CON-1800CS-2010 Construction of Pipe
supports for laying DN 1800 CS pipeline-cs-cast support concrete
Project: PM-94 Activity: CON-800-1000-TIE Submission of Work
Permit for Isolation of existing DN 800 Pipeline
Project: PM-94 Activity: CON-800-1020-TIE Tie-in works at T-18A &
T18B, Weld Joint / Flange
Project: PM-94 Activity: CON-800CS-2020 TIE Tie-in works at T-
18C & T18D, Weld Joint / Flange
Project: PM-94 Activity: CON-ACB-2020 Installation of
Ventillation system
Project: PM-94 Activity: CON-ACB-2050 Installation of Fire
Extinguishers
Project: PM-94 Activity: CON-ADDC-1000 Laying of 33KV Power
cable from ADDC Power Grid to New Switchgear Building
Project: PM-94 Activity: CON-ADDC-1012 Termination works at
ADDC Power Grid
Project: PM-94 Activity: CON-CCTV-1021 Installation of CCTV
System
Project: PM-94 Activity: CON-CPS-1000 Installation of
Permanent Cathodic Protection system
Project: PM-94 Activity: CON-CPS-1002 Testing & Commissioning
of Cathodic Protection system
Project: PM-94 Activity: CON-DSV-2005 DN1200x800 CS Piping
Installation reparation, fit-up & alignment,-discgahe
Project: PM-94 Activity: CON-DSV-2025 DN100 SS316 Compressed
Air Line Piping Installation
Project: PM-94 Activity: CON-DSV-2047 Pipe Support Fixing -
weld joint preparation, welding, painting
Project: PM-94 Activity: CON-DSV-2070 Installation of BFV,
Ball Valve & Instruments, Etc.
Project: PM-94 Activity: CON-DSV-2079 Grouting for pipe
support
Project: PM-94 Activity: CON-DSV-2081 Surface preparation and
Epoxy coating works
Project: PM-94 Activity: CON-ECB-1490 Installation of Steel
Gates
Project: PM-94 Activity: CON-ECB-1559 Basement Cable room /
Ground floor Epoxy Painting Works
Project: PM-94 Activity: CON-ECB-2100 Installation of VSD
cooling system panel
Project: PM-94 Activity: CON-ECB-2160 Installation of Fire
Water pipeline (Water spray system) with nozzles at Basement
Project: PM-94 Activity: CON-ECB-2210 Installation of Fire
rated ducting works at Electrical & Control rooms
Project: PM-94 Activity: CON-ECB-2291 Cladding Works of
Package Units Drain Piping System-1 & System-2
Project: PM-94 Activity: CON-ECB-2340 Installation of Exhaust
Fans
Project: PM-94 Activity: CON-ECB-2342 Installation of HVAC
control panel
Project: PM-94 Activity: CON-ECB-2345 Installation of Cooling
Water Pump Skid
Project: PM-94 Activity: CON-ECB-2347 SS316 Piping
Installation - preparation, fit-up & alignment, production welding, NDT
Project: PM-94 Activity: CON-ECB-2349 Pipe Support Fixing
Project: PM-94 Activity: CON-ECB-2351 Installation of BFV,
Ball Valve & Instruments, Etc.
Project: PM-94 Activity: CON-ECB-2390 Installation of
sprinkler system - sprinkler head and accessories, alarm check valve, gate valves,
etc.
Project: PM-94 Activity: CON-ECB-3028 Installation of DC / AC
UPS system
Project: PM-94 Activity: CON-ECB-3032 Installation of k05 of
11kv switchgear
Project: PM-94 Activity: CON-ECB-3064 Termination of LV cable
termination
Project: PM-94 Activity: CON-EPH-1095 Form, Reinforcement &
Concrete Placement for Foundation for Steel Platform over Suction Header pipelines-
mafi
Project: PM-94 Activity: CON-EPH-1115 Form, Reinforcement &
Concrete Placement for Access Ramp
Project: PM-94 Activity: CON-EPH-1140 Installation of
Structural Steel works including installation & Overlapping of Sandwitch panels-
(addtl Duration)
Project: PM-94 Activity: CON-EPH-1213 Pump House Floor
Painting works
Project: PM-94 Activity: CON-EPH-1220 Masonry Block works
Project: PM-94 Activity: CON-EPH-2030 Installation of Exhaust
Fans at Roof Top
Project: PM-94 Activity: CON-EPH-2043 Installation of Main
Pumps
Project: PM-94 Activity: CON-EPH-2053 Installation of Pump
Motor Cooling system piping work
Project: PM-94 Activity: CON-EPH-2054 LV cable Termination
works LV cable
Project: PM-94 Activity: CON-EPH-2058 Lighting & Small power
Project: PM-94 Activity: CON-EPH-2063 Installation of
Strainers
Project: PM-94 Activity: CON-EPH-2073 Installation of related
piping network (DN 1400) CS Pipe
Project: PM-94 Activity: CON-EPH-2075 Installation of Cooling
Water Pump Skid
Project: PM-94 Activity: CON-EPH-2077 SS316 Piping
Installation - preparation, fit-up & alignment, production welding, NDT
Project: PM-94 Activity: CON-EPH-2079 Pipe Support Fixing
Project: PM-94 Activity: CON-EPH-2081 Installation of BFV,
Ball Valve & Instruments, Etc.
Project: PM-94 Activity: CON-EPH-2150 HVAC Duct Installatiom
Works
Project: PM-94 Activity: CON-EPH-2160 Installation of Exhaust
Fan
Project: PM-94 Activity: CON-EPH-2170 Installation of Fresh
Air Fans
Project: PM-94 Activity: CON-EPH-2200 Installation of Pump &
Motor - Pump 9
Project: PM-94 Activity: CON-EPH-2205 Installation of Pump &
Motor - Pump 10
Project: PM-94 Activity: CON-EPH-5112 Surface preparation and
painting works
Project: PM-94 Activity: CON-ESL-1005 Installation of Street
Lighting works incl., Street Lighting Poles & DB
Project: PM-94 Activity: CON-ESL-1007 LV cable Cable Laying &
Termination works STREET POST
Project: PM-94 Activity: CON-ETR-1080 Trench Backfilling,
Route Markers
Project: PM-94 Activity: CON-ETR-1083 Laying FOC
Project: PM-94 Activity: CON-FHW-1000 Laying 150 dia under
ground Fire hydrant pipeline / Deludge system Riser at Electrical Building
Project: PM-94 Activity: CON-FMC1-1140 Construction of Precast
Top Cover Slab along with Air vent pipes & DI cover Frame
Project: PM-94 Activity: CON-FMC1-1170 External Painting works
Project: PM-94 Activity: CON-FMC1-2000 Installation of Flow
Meter & Fittings
Project: PM-94 Activity: CON-FMC1-2010 Provision of Power
Supply to Flow Meter
Project: PM-94 Activity: CON-FMC2-1018-TIE Submission of PTW for
Weld Joint-connect to t 1d
Project: PM-94 Activity: CON-FMC2-1028-TIE Approval of PTW for Weld
Joint-hydrotest line 1st
Project: PM-94 Activity: CON-FMC2-1038-TIE Tie in T1G/T1H Weld
Joint
Project: PM-94 Activity: CON-FMC2-2025 Electrical and control
cable laying LV cable
Project: PM-94 Activity: CON-FMC2-2030 Installation of Flow
meters and fittings
Project: PM-94 Activity: CON-FMC2-2040 Provision of Power
Supply to Flow meters
Project: PM-94 Activity: CON-HSW-5044 Formation & Compaction
works
Project: PM-94 Activity: CON-HSW-5048 Sub-base and compaction
works
Project: PM-94 Activity: CON-HSW-5052 Installation of Kerb
stone
Project: PM-94 Activity: CON-HSW-5064 Laying of Sand Bedding
Project: PM-94 Activity: CON-IVC1-0904 Blinding Concreting
works
Project: PM-94 Activity: CON-IVC1-0906 Curing works for
Blinding concrete
Project: PM-94 Activity: CON-IVC1-0908 Water proofing
application - Prinmer + Membrane
Project: PM-94 Activity: CON-IVC1-0910 Protection Screed
Project: PM-94 Activity: CON-IVC1-0912 Curing works for
Protection Screed
Project: PM-94 Activity: CON-IVC1-0914 Constuction of Base Slab
Project: PM-94 Activity: CON-IVC1-0916 Construction of RCC Wall
Project: PM-94 Activity: CON-IVC1-1100 Insert WS Sleeve &
Grouting works incl., Curing
Project: PM-94 Activity: CON-IVC1-1110 Waterproofing works
Project: PM-94 Activity: CON-IVC1-1113 Construction of Precast
Top Cover Slab along with Air vent pipes & DI cover Frame
Project: PM-94 Activity: CON-IVC1-1120 Backfilling & Compaction
works
Project: PM-94 Activity: CON-IVC1-1174 Internal Painting works
Project: PM-94 Activity: CON-IVC1-2000 Installation of
Motorized Butterfly Valves & Fittings
Project: PM-94 Activity: CON-IVC1-2008 Electrical and control
cable laying LV cable
Project: PM-94 Activity: CON-IVC1-2010 Provision of Power
Supply to Motorized Butter fly Vales
Project: PM-94 Activity: CON-IVC1-MZ-1034 External Painting works
Project: PM-94 Activity: CON-IVC2-2000 TIE Submission of PTW for
Isolation of DN 1200 Byepass pipeline-cs
Project: PM-94 Activity: CON-IVC2-2002 TIE Approval of PTW for
Isolation of DN 1200 Byepass pipeline-relocation foc cable b4 tie in
Project: PM-94 Activity: CON-IVC2-2004 TIE Modification of DN 1200
pipeline to install Butterfly valve
Project: PM-94 Activity: CON-IVC2-2006 TIE Tie-in works @ T-24A &
T-24B-Weld Joint / Flange-
Project: PM-94 Activity: CON-IVC2-2020 Excavation works
Project: PM-94 Activity: CON-IVC2-2029 Excavation additional
Duration
Project: PM-94 Activity: CON-IVC2-2100 Construction of RCC Wall
Project: PM-94 Activity: CON-IVC2-2110 Concrete Benching works
to maintain slope
Project: PM-94 Activity: CON-IVC2-2120 Insert WS Sleeve &
Grouting works incl., Curing
Project: PM-94 Activity: CON-IVC2-2130 Waterproofing works
Project: PM-94 Activity: CON-IVC2-2160 Construction of Precast
Top Cover Slab along with Air vent pipes & DI cover Frame
Project: PM-94 Activity: CON-IVC2-2163 Backfilling & Compaction
works
Project: PM-94 Activity: CON-IVC2-2191 Internal Painting works
Project: PM-94 Activity: CON-MZ-5000 Installation of Butterfly
Valve, Dismantling Joint & Fittings(BF), VS, etc.,
Project: PM-94 Activity: CON-MZ-5010 Grouting works
Project: PM-94 Activity: CON-MZ-8030 Installation of Butterfly
Valve, Dismantling Joint & Fittings(BF), VS, etc.,
Project: PM-94 Activity: CON-MZ-9000 CS pipeline - Hydrotesting &
Disinfection works and Backfilling works
Project: PM-94 Activity: CON-MZ-9010 Installation of Cathodic
Protection System and tie-in with the existing system
Project: PM-94 Activity: CON-PAS-1005 Laying of necessary
cabling & Integration with the existing facilities cctv
Project: PM-94 Activity: CON-REL-CVL-1028 Demolotion of existing
ground slab , beams, wall of existing pump room
Project: PM-94 Activity: CON-REL-ELEC-1000 Submission of PTW for
existing Fiber Optic Cable & 11KV Cable-FMC
Project: PM-94 Activity: CON-REL-ELEC-1002 Aproval of Work permit
for re-routing of existing FOC cable
Project: PM-94 Activity: CON-REL-ELEC-1006 RELOCATION OF EXIstING
LIGHT POLES AND SIGN POST
Project: PM-94 Activity: CON-REL-ELEC-1010 Re-routing of existing
Fiber Optic Cable & 11KV Cable FOC
Project: PM-94 Activity: CON-RELMEC-1000 Submit Permit-link tie
t8 cs-trqnfer sunp-civil dischage-1st relocqtion b4 tie
Project: PM-94 Activity: CON-RELMEC-1004 Submit Permit
Project: PM-94 Activity: CON-RELMEC-1008 Apprvoal
Project: PM-94 Activity: CON-RELMEC-1012 Relocation of Existing
Sump Pumps
Project: PM-94 Activity: CON-RELMEC-1016 Re-Routing of DN150 DI
Discharge Pipe using uPVC,
Project: PM-94 Activity: CON-RELMEC-1032 modification of exisitng
Fan house-dsicharge pipe link
Project: PM-94 Activity: CON-RELMEC-1036 Submit Permit
Project: PM-94 Activity: CON-RELMEC-1044 Dismantling and
Relocation of access staircase
Project: PM-94 Activity: CON-RELMEC-1048 Submit Permit-complete
Line 1
Project: PM-94 Activity: CON-RELMEC-1056 Approval
Project: PM-94 Activity: CON-RELMEC-1060 Re-instatement of
Existing DN400 DI Recirculation Pipeline
Project: PM-94 Activity: CON-RRT-1000 Submission of Work
permit for re-routing of existing Fire House Cabinet
Project: PM-94 Activity: CON-RRT-1008 Re-routing works of
existing Fire House Cabinet
Project: PM-94 Activity: CON-SGB-1300 Installation of Doors &
Windows
Project: PM-94 Activity: CON-SGB-1360 Installation of Steel
Gratings
Project: PM-94 Activity: CON-SGB-2059 Cable Tray & Cable
Pulling works LV cable
Project: PM-94 Activity: CON-SGB-2061 Earthing & Lightning
Protection system
Project: PM-94 Activity: CON-SGB-2063 33kv Cable Termination
works(lv, 33k, FOC,CONTROL
Project: PM-94 Activity: CON-SGB-2065 Installation of Public
Address system cctv
Project: PM-94 Activity: CON-SGB-2069 Installation of
Telephone cctv
Project: PM-94 Activity: CON-SGB-2070 Installation of Exhaust
Fans
Project: PM-94 Activity: CON-SGB-2071 Installation of Intercom
Facilities cctv
Project: PM-94 Activity: CON-SSV-2005 Piping works including
Hand Rails & Access Platform for SSV-01
Project: PM-94 Activity: CON-SSV-2015 Piping works including
Hand Rails & Access Platform for SSV-02
Project: PM-94 Activity: CON-SSV-2025 Piping works including
Hand Rails & Access Platform for SSV-03
Project: PM-94 Activity: CON-SSV-2060 Installation of BFV,
NRV, Ball Valve & Instruments, Etc.
Project: PM-94 Activity: CON-SSV-2100 Installation of Mobile
Air Compressor
Project: PM-94 Activity: CON-SSV-9088 Excavation works
Project: PM-94 Activity: CON-SSV-9158 Constuction of
Foundation
Project: PM-94 Activity: CON-SSV-9168 Constuction of Pedestals
Project: PM-94 Activity: CON-SSV-9178 Waterproofing works
Project: PM-94 Activity: CON-SSV-9188 Backfilling & Compaction
works
Project: PM-94 Activity: CON-SSV-9198 Grouting for pipe
support
Project: PM-94 Activity: CON-SSV-9208 Surface preparation and
Epoxy coating works
Project: PM-94 Activity: CON-SSV-9210 Pipe Support Fixing -
weld joint preparation, welding, painting
Project: PM-94 Activity: CON-SSV-9212 CS Piping Installation -
preparation, fit-up & alignment, prod. welding, NDT, internal-1200
Project: PM-94 Activity: CON-SSV-9214 Installation of BFV,
Ball Valve & Instruments, Etc.
Project: PM-94 Activity: CON-SWS-1000 Laying of pipeline for
Circulated water system covering Electrical Building, Compressor Building and
Extended Pump House
Project: PM-94 Activity: CON-TERMI-1004 Cable Termination @ 33Kv
Switchgear
Project: PM-94 Activity: CON-WC1-1100 Construction of Precast
Top Cover Slab along with Air vent pipes & DI cover FrameB+10 % NXT WEEK
Project: PM-94 Activity: CON-WC1-1122 Internal Painting works
Project: PM-94 Activity: CON-WC1-1132 Construction of Precast
Top Cover Slab along with Air vent pipes & DI cover FrameB+10 % NXT WEEK
Project: PM-94 Activity: ENG-DD-1087 Approval of Cause and effect
diagram along with interlocks, protection and sequence logics--
Project: PM-94 Activity: ENG-MS-2015 Approval of Method Statement
for Installation of Cooling Pumps-NS
Project: PM-94 Activity: ENG-MS-2030 Submission of Method
Statement for Installation of Air Compressors
Project: PM-94 Activity: ENG-SD-2095 Approval of New Electrical &
Control room - Fire Fighting Layout & details-NS
Project: PM-94 Activity: ENG-SD-3140 Submission of Communication
Signal Exchange List
Project: PM-94 Activity: IMS-58 Completion of “Foreign
Material” delivery to site
Project: PM-94 Activity: NOC-ADCD-1010 Approval of Design
Drawings for Fire Alarm & Fire Fighting system for New Structures
Project: PM-94 Activity: NOC-ADCD-2000 Submission of Request
for Site Inspection
Project: PM-94 Activity: NOC-ADDC-5000 Submission of Request
for Tie-in connection @ ADDC Power Grid
Project: PM-94 Activity: PROC-3115 Delivery of Aluminum Doors &
Windows
Project: PM-94 Activity: PROM-1460 Material Verification and
Submission of RCDR for Mobile Air Compressor
Project: PM-94 Activity: PROM-1470 Approval of RCDR for Mobile
Air Compressor
Project: PM-94 Activity: PROM-1822 Finish Deliveries of
Ventilation system for Pump House
Project: PM-94 Activity: PROM-1840 Approval of RCDR for
Ventilation system for Pump House-hvac
Project: PM-94 Activity: PROM-2120 Material Verification and
Submission of RCDR for Ventilation system for Battery Room & Cable Basement at E&C
Building
Project: PM-94 Activity: TC-11KV-1000 Fault Sudy by
Contractor-k05
Project: PM-94 Activity: TC-33KV-1000 Fault Sudy by
Contractor-33
Project: PM-94 Activity: TC-LV-1000 Fault Sudy by Contractor-LV
Cable
Project: PM-94 Activity: TC-MCC-2138 New pipework at Madinat Zayed
system
Project: PM-94 Activity: TC-MCC-2142 Stationary Air Compressor
System
Project: PM-94 Activity: TC-MCC-CVL-2020 Civil 33kV Switchgear
Building
Project: PM-94 Activity: TC-MCC-ELEC-1004 11 kV Medium Voltage
System-ecb
Project: PM-94 Activity: TC-MCC-ELEC-1008 Low Voltage System-ecb
Project: PM-94 Activity: TC-MCC-ELEC-1016 DC UPS System-ecb
Project: PM-94 Activity: TC-MCC-FIRE-1000 Cranes & Lifting
Equipment (Modification & extension)
Project: PM-94 Activity: TC-MCC-FIRE-1004 Fire Fighting System-
Elctrical & control building
Project: PM-94 Activity: TC-MCC-FIRE-1008 Fire Fighting System- 33
kV Switch gear building
Project: PM-94 Activity: TC-MCC-FIRE-1016 Cathodic Protection
system at Madinat Zayed
Project: PM-94 Activity: TC-MCC-FIRE-1020 Cathodic Protection
system at Mirfa
Project: PM-94 Activity: TC-MCC-HVAC-1000 HVAC System- Electrical
Control Building
Project: PM-94 Activity: TC-MCC-MISC-1008 Earthing system
Project: PM-94 Activity: TC-MEC-MCC-1000 Suction surge vessel SV-
4600 system
Project: PM-94 Activity: TC-MEC-MCC-1024 DN 800 interconnection
pipeline to DN 1200
Project: PM-94 Activity: TC-MEC-MCC-1052 Discharge Surge Vessels
SV-5301 & SV-5302 System
Scheduling/Leveling Results:
----------------------------
# Projects Scheduled/Leveled.....................................1
# Activities Scheduled/Leveled...................................586
# Relationships with other projects..............................0
Data Date........................................................18-Jul-23
Earliest Early Start Date........................................18-Jul-23
Latest Early Finish Date.........................................30-Sep-23
Exceptions:
-----------
Critical Activities..............................................37
Project: PM-94 Activity: CON-1200-1000 TIE Submission of Work
Permit for Isolation of existing DN 1200 Pipeline-suction line finish
Project: PM-94 Activity: CON-1200-1010 TIE Approval of Work Permit
for Isolation of existing DN 1200 Pipeline-line to complete
Project: PM-94 Activity: CON-1200-1020 TIE Tie-in-T2G/T2F - Flange
Connection
Project: PM-94 Activity: CON-1200-1244 TIE Submission of Work
Permit for Isolation of existing DN 1200 Pipeline-cs pipe
Project: PM-94 Activity: CON-1200-1248 TIE Approval of Work Permit
for Isolation of existing DN 1200 Pipeline-cs pipe
Project: PM-94 Activity: CON-1200-1252 TIE Tie-in works at T19,
Flange Connection-cs pipe
Project: PM-94 Activity: CON-1400-1020 TIE STARTING CHAINAGE AT
TIE-IN POINT T2H- Flange Connection
Project: PM-94 Activity: CON-1600CS-5000 TIE Submission of PTW-
Concrete Support FDTN Discharge Header 2 cs pipe
Project: PM-94 Activity: CON-1600CS-5010 TIE Approval of PTW-cs
pipe
Project: PM-94 Activity: CON-1600CS-5020 TIE Tie-in works @ T-
13, Flange Connection-cs pipe
Project: PM-94 Activity: CON-1800CS-2010 Construction of Pipe
supports for laying DN 1800 CS pipeline-cs-cast support concrete
Project: PM-94 Activity: CON-700CS-1000 TIE Submission of Work
Permit for Isolation of existing DN 700 Pipeline
Project: PM-94 Activity: CON-700CS-1004 TIE Approval of Work
Permit for Isolation of existing DN 700 Pipeline-complete l1 first
Project: PM-94 Activity: CON-700CS-1008 TIE Tie-in works at
T2D-Weld Joint
Project: PM-94 Activity: CON-TIE-COC1-1000 Submission of PTW for
Weld Joint-suction line
Project: PM-94 Activity: CON-TIE-COC1-1004 Approval of PTW for Weld
Joint
Project: PM-94 Activity: CON-TIE-COC1-1008 Tie in T1D-Weld Joint-
line 1st
Project: PM-94 Activity: DEMOB-1000 Demobilization and Site
Reinstatement works
Project: PM-94 Activity: DL&FAC-1000 Start of Defect Liability
Period & Obtain FAC (For Two Years starts from next of PAC date)
Project: PM-94 Activity: IMS-64 Completion of Testing,
Commissioning
Project: PM-94 Activity: IMS-90 Mirfa Tie in Completion
Project: PM-94 Activity: IMS-94 Initial Run/Initial
Acceptance Test
Project: PM-94 Activity: PCO-MPS-1087 PAC walkdown inspection
Project: PM-94 Activity: PCO-MPS-1088 Clearance
Project: PM-94 Activity: PCO-MPS-1090 Receipt of Provisional
Acceptance (PAC) certificate
Project: PM-94 Activity: RF-1000 Demonstration of Scenerio-1:
New pumps pumping to Madinat Zayed and Existing pumps (#7 & #8) pumping to Musaffah
Project: PM-94 Activity: RF-1010 Demonstration of Scenerio-2:
1 pump supplement new pumps to MZ and One pump supplement ex. 3000 Pumps to
Mussaffah
Project: PM-94 Activity: RF-1020 Demonstration of Scenerio-3:
New 1 pump pumping normally to MZ and New 1 pump supplement the ex. 3000 Pumps to
Mussaffah
Project: PM-94 Activity: RF-1030 Contractor to prepare
Emergency manuals, Emergency cards and Procedures for implementing the Emergency
Operation
Project: PM-94 Activity: RF-1040 Conduct Rehersal without
Actual Flow Reversal taking place on how to establish the Reserve mode on Manual
mode
Project: PM-94 Activity: RF-1050 Demonstration of Scenerio-4:
New pumps and existing pumps able to transfer water from Mirfa Tank Farm to
Musaffah
Project: PM-94 Activity: RF-1060 Demonstration of Scenerio-5:
All pumping operation from Mirfa to Musaffah stopped
Project: PM-94 Activity: TC-MPS-1000 Ready for Commissioning
certificate
Project: PM-94 Activity: TC-MPS-1998 Trial Operation Works
Project: PM-94 Activity: TC-MPS-2000 Initial Operation /
Commissioning works (HVAC, Main Pumps Operational test; Final Set points & Testing)
Project: PM-94 Activity: TC-MPS-3000 Performance Test/acceptance
Rest
Project: PM-94 Activity: TC-MPS-4000 Reliability Testing works
(Uninterrupted operation)