Name of Work: Construction of Low Cost Stall ( Stall No.
01 to 20) in Kamakhyaguri Principal
Market Yard under Alipurduar Zilla RMC Following Current PWD Schedule Building & Road with Latest Corrigendum Abstract Sheet Item Description of Items Amount No. A. Stall No. 01 & 02 = 3,54,512.70
B. Stall No. 03 & 11 = 14,57,434.10
C. Stall No. 12 & 20 = 14,57,434.10
1 Total Estimated Cost = 32,69,380.90
2 Add: GST @ 18% on Sl. No. 1 = 5,88,488.56
3 Cost including GST & excluding cess = 38,57,869.46 4 Labour Welfare Cess @ 1% on Sl. No. 3 = 38,578.69 5 Total cost including GST & Cess = 38,96,448.15 6 Add 3% Contingency on Sl. No. 3 = 1,15,736.08 7 Total Cost = 40,12,184.23 Say: 40,12,184.00 Rupees Forty Lakh Twelve Thousand One Hundred Eighty Four Only