Name of Work: Construction of Low Cost Stall ( Stall No.

01 to 20) in Kamakhyaguri Principal


Market Yard under Alipurduar Zilla RMC
Following Current PWD Schedule Building & Road with Latest Corrigendum
Abstract Sheet
Item
Description of Items Amount
No.
A. Stall No. 01 & 02 = 3,54,512.70

B. Stall No. 03 & 11 = 14,57,434.10

C. Stall No. 12 & 20 = 14,57,434.10

1 Total Estimated Cost = 32,69,380.90

2 Add: GST @ 18% on Sl. No. 1 = 5,88,488.56


3 Cost including GST & excluding cess = 38,57,869.46
4 Labour Welfare Cess @ 1% on Sl. No. 3 = 38,578.69
5 Total cost including GST & Cess = 38,96,448.15
6 Add 3% Contingency on Sl. No. 3 = 1,15,736.08
7 Total Cost = 40,12,184.23
Say: 40,12,184.00
Rupees Forty Lakh Twelve Thousand One Hundred Eighty Four Only