Professional Documents
Culture Documents
RUNTU
00+000.00 - 05+000.00 RUTIN JALAN 5,000.00
05+000.00 - 12+200.00 HOLDING 7,200.00
12+200.00 - 12+900.00 RUTIN JALAN 700.00
12+900.00 - 14+140.00 RUTIN KONDISI 1,240.00
14+140.00 - 21+440.00 RUTIN JALAN 7,300.00
21,440.00
KUJAN - RUNTU
00+000.00 - 07+000.00 RUTIN KONDISI 7,000.00
07+000.00 - 07+100.00 RUTIN JALAN 100.00
07+100.00 - 08+104.00 REKONSTRUKSI 1,004.00
08+100.00 - 09+000.00 RUTIN JALAN 900.00
08+900.00 - 10+707.00 REKONSTRUKSI 1,807.00
10+700.00 - 16+200.00 RUTIN JALAN 5,500.00
16+200.00 - 16+725.00 REKONSTRUKSI 525.00
16+500.00 - 17+000.00 RUTIN JALAN 500.00
17+000.00 - 17+535.00 REKONSTRUKSI 535.00
17+500.00 - 18+350.00 RUTIN JALAN 850.00
18+350.00 - 33+950.00 HOLDING 15,600.00
33+950.00 - 42+477.00 RUTIN JALAN 8,527.00
42+420.00 42,848.00
38+900.00
13,000.00
DATA SURVEY
RUAS JALAN RUNTU - SP. RUNTU
Total 11,668.90
DATA SURVEY
RUAS JALAN KUJAN - RUNTU
Total 21,374.60
DATA SURVEY
RUAS JALAN RUNTU - SP. RUNTU
No. Mata
Uraian Satuan Harga Satuan Jumlah Harga Jumlah Harga
Pembayaran Kuantitas Kuantitas
(Rupiah) (Rupiah) (Rupiah)
DIVISI 1. UMUM
1.2 Mobilisasi LS 1.00 195,653,559.61 195,653,559.61 1.00 195,653,559.61
1.8.(1) Manajemen dan Keselamatan Lalu Lintas LS 1.00 96,847,636.36 96,847,636.36 1.00 96,847,636.36
1.17.(1a) Pengujian pH Buah 3.00 198,000.00 594,000.00 3.00 594,000.00
1.17.(1b) Pengujian Oksigen Terlarut (DO) Buah 3.00 225,000.00 675,000.00 3.00 675,000.00
1.17.(1c) Pengujian Zat Padat Terlarut (TDS) Buah 3.00 216,000.00 648,000.00 3.00 648,000.00
1.17.(1d) Pengujian Zat Tersuspensi (TSS) Buah 3.00 216,000.00 648,000.00 3.00 648,000.00
1.17.(1e) Pengujian Biological Oxygen Demand (BOD) Buah 3.00 225,000.00 675,000.00 3.00 675,000.00
1.17.(1f) Pengujian Chemical Oxygen Demand (COD) Buah 3.00 288,000.00 864,000.00 3.00 864,000.00
1.17.(1g) Pengujian Coliform Buah 3.00 378,000.00 1,134,000.00 3.00 1,134,000.00
1.17.(1h) Pengujian E. Coli Buah 3.00 306,000.00 918,000.00 3.00 918,000.00
1.17.(1i) Pengujian Destruksi Cu, Pb, Cd, Ni, Fe, Zn, Ag, Co, Mn Buah 3.00 441,000.00 1,323,000.00 3.00 1,323,000.00
1.17.(1j) Pengujian Temperatur (Suhu) Buah 3.00 198,000.00 594,000.00 3.00 594,000.00
1.17.(2a) Pengujian Vibrasi Lingkungan untuk Kenyamanan dan Kesehatan Buah 3.00 684,000.00 2,052,000.00 3.00 2,052,000.00
1.17.(2b) Pengujian Tingkat Getaran Kendaraan Bermotor Buah 3.00 855,000.00 2,565,000.00 3.00 2,565,000.00
1.17.(3a) Pengujian NoX Buah 3.00 387,000.00 1,161,000.00 3.00 1,161,000.00
1.17.(3b) Pengujian Sulfurdioksida (SO2) Buah 3.00 468,000.00 1,404,000.00 3.00 1,404,000.00
1.17.(3c) Pengujian Karbondioksida (CO2) Buah 3.00 504,000.00 1,512,000.00 3.00 1,512,000.00
1.17.(3d) Pengujian Hidro Carbon (HC)-CH4 Buah 3.00 486,000.00 1,458,000.00 3.00 1,458,000.00
1.17.(3f) Pengujian Total Partikulat (TSP) - Debu Buah 3.00 468,000.00 1,404,000.00 3.00 1,404,000.00
1.17.(3g) Pengujian Timah Hitam (Pb) Buah 3.00 450,000.00 1,350,000.00 3.00 1,350,000.00
1.19 Keselamatan dan Kesehatan Kerja LS 1.00 122,170,000.00 122,170,000.00 1.00 122,170,000.00
1.21 Manajemen Mutu LS 1.00 92,000,000.00 92,000,000.00 1.00 92,000,000.00
DIVISI 2. DRAINASE
2.1.(1) Galian untuk Selokan Drainase dan Saluran Air M3 1,857.66 43,728.00 81,231,756.48 1,113.75 48,702,060.00
2.2.(1) Pasangan Batu dengan Mortar M3 488.68 1,099,338.00 537,224,493.84 137.06 150,675,266.28
DIVISI 7. STRUKTUR
7.1 (5a) Beton Struktur, fc’30 Mpa M3 3.56 2,510,434.00 8,937,145.04 1.30 3,258,740.33
7.1 (7a) Beton Strukur, fc’20 MPa M3 16.00 2,227,712.00 35,643,392.00 16.00 35,643,392.00
7.3 (3) Baja Tulangan Sirip BjTS 420A Kg 52.05 25,030.00 1,302,811.50 52.05 1,302,811.50
7.6 (1) Pondasi Cerucuk, Penyediaan dan Pemancangan M1 5,224.00 14,739.00 76,996,536.00 5,224.00 76,996,536.00
7.9.(1) Pasangan Batu M3 130.22 1,057,685.00 137,731,740.70 130.22 137,731,740.70
7.10.(3a) Bronjong dengan Kawat yang dilapisi Galvanis M3 325.02 956,164.00 310,772,423.28 325.02 310,772,423.28
7.14.(1) Papan Nama Jembatan Buah 8.00 756,208.00 6,049,664.00 8.00 6,049,664.00
A Jumlah Harga Pekerjaan ( termasuk Biaya Umum dan Keuntungan ) 32,595,454,545.45 32,595,454,545.45
B Pajak Pertambahan Nilai ( PPN ) = 10% x (A) 3,259,545,454.55 3,259,545,454.55
C Jumlah Total Harga Pekerjaan = (A) + (B) 35,855,000,000.00 35,855,000,000.00
D Jumlah Total Harga Pekerjaan (Dibulatkan) 35,855,000,000.00 35,855,000,000.00
PAKET PEKERJAAN : PRESERVASI JALAN KUJAN - RUNTU - SIMPANG RUNTU
NOMOR KONTRAK : HK 0201-Bb29.5.1/KTRK/03, TANGGAL 05 JANUARI 2022
NILAI KONTRAK : Rp. 35.855.000.000,00
DIVISI 1. UMUM
1.2 Mobilisasi LS 1.00 195,653,559.61 195,653,559.61 1.00 195,653,559.61
1.8.(1) Manajemen dan Keselamatan Lalu Lintas LS 1.00 96,847,636.36 96,847,636.36 1.00 96,847,636.36
1.17.(1a) Pengujian pH Buah 3.00 198,000.00 594,000.00 3.00 594,000.00
1.17.(1b) Pengujian Oksigen Terlarut (DO) Buah 3.00 225,000.00 675,000.00 3.00 675,000.00
1.17.(1c) Pengujian Zat Padat Terlarut (TDS) Buah 3.00 216,000.00 648,000.00 3.00 648,000.00
1.17.(1d) Pengujian Zat Tersuspensi (TSS) Buah 3.00 216,000.00 648,000.00 3.00 648,000.00
1.17.(1e) Pengujian Biological Oxygen Demand (BOD) Buah 3.00 225,000.00 675,000.00 3.00 675,000.00
1.17.(1f) Pengujian Chemical Oxygen Demand (COD) Buah 3.00 288,000.00 864,000.00 3.00 864,000.00
1.17.(1g) Pengujian Coliform Buah 3.00 378,000.00 1,134,000.00 3.00 1,134,000.00
1.17.(1h) Pengujian E. Coli Buah 3.00 306,000.00 918,000.00 3.00 918,000.00
1.17.(1i) Pengujian Destruksi Cu, Pb, Cd, Ni, Fe, Zn, Ag, Co, Mn Buah 3.00 441,000.00 1,323,000.00 3.00 1,323,000.00
1.17.(1j) Pengujian Temperatur (Suhu) Buah 3.00 198,000.00 594,000.00 3.00 594,000.00
1.17.(2a) Pengujian Vibrasi Lingkungan untuk Kenyamanan Buah 3.00 684,000.00 2,052,000.00 3.00 2,052,000.00
dan Kesehatan
1.17.(2b) Pengujian Tingkat Getaran Kendaraan Bermotor Buah 3.00 855,000.00 2,565,000.00 3.00 2,565,000.00
1.17.(3a) Pengujian NoX Buah 3.00 387,000.00 1,161,000.00 3.00 1,161,000.00
1.17.(3b) Pengujian Sulfurdioksida (SO2) Buah 3.00 468,000.00 1,404,000.00 3.00 1,404,000.00
1.17.(3c) Pengujian Karbondioksida (CO2) Buah 3.00 504,000.00 1,512,000.00 3.00 1,512,000.00
1.17.(3d) Pengujian Hidro Carbon (HC)-CH4 Buah 3.00 486,000.00 1,458,000.00 3.00 1,458,000.00
1.17.(3f) Pengujian Total Partikulat (TSP) - Debu Buah 3.00 468,000.00 1,404,000.00 3.00 1,404,000.00
1.17.(3g) Pengujian Timah Hitam (Pb) Buah 3.00 450,000.00 1,350,000.00 3.00 1,350,000.00
1.19 Keselamatan dan Kesehatan Kerja LS 1.00 122,170,000.00 122,170,000.00 1.00 122,170,000.00
1.21 Manajemen Mutu LS 1.00 92,000,000.00 92,000,000.00 1.00 92,000,000.00
DIVISI 2. DRAINASE
2.1.(1) Galian untuk Selokan Drainase dan Saluran Air M3 1,100.00 x ( 1,25 + 1,00 ) / 2 x 0.90 1,857.66 43,728.00 81,231,756.48 1,113.75 48,702,060.00
2.2.(1) Pasangan Batu dengan Mortar M3 150.00 x (((1,75+1,60)/2x1,15))-(((1,25+1,00)/2x0,90)) 488.68 1,099,338.00 537,224,493.84 137.06 150,675,266.28
3.2.(1a) Timbunan Biasa dari Sumber Galian M3 50.00 x 2 x 0.33 330.40 185,940.00 61,434,576.00 33.07 6,149,232.00
3.2.(2a) Timbunan Pilihan dari Sumber Galian M3 3,513.00 x 2 x 0.21 x 2 2,702.70 215,300.00 581,891,310.00 2,950.92 635,333,076.00
DIVISI 5. PERKERASAN BERBUTIR
5.1.(1) Lapis Pondasi Agregat Kelas A M3 3,513.00 x 7 x 0.22 6,774.34 813,194.00 5,508,852,641.96 5,410.02 4,399,395,803.88
5.1.(3) Lapis Pondasi Agregat Kelas S M3 3,513.00 x 2 x 0.195 x 2 2,980.58 703,705.00 2,097,449,048.90 2,740.14 1,928,250,218.70
6.1 (2a) Lapis Perekat - Aspal Cair/Emulsi Liter 3,513.00 x 7 x 0.20 x 2 6,419.70 19,410.00 124,606,377.00 9,836.40 190,924,524.00
6.3(5a) Laston Lapis Aus (AC-WC) Ton 3,513.00 x 7 x 0.04 x 2.280 x 6.00% x 0.30% 2242.7 403.69 1,968.71 1,476,571.00 2,906,940,093.41 2,242.30 3,310,915,153.30
6.3(6a) Laston Lapis Antara (AC-BC) Ton 3,513.00 x 7 x 0.06 x 2.287 x 5.70% x 0.30% 3374.4 577.02 2,953.06 1,426,721.00 4,213,192,716.26 3,373.80 4,813,471,309.80
6.3(7a) Laston Lapis Pondasi (AC-Base) Ton 3,513.00 x 7 x 0.095 x 2.295 x 5.30% x 0.30% 5361.5 852.47 4,675.68 1,357,864.00 6,348,937,547.52 5,360.60 7,278,965,758.40
A Jumlah Harga Pekerjaan ( termasuk Biaya Umum dan Keuntungan ) 24,401,591,870.59 24,401,591,870.59
B Pajak Pertambahan Nilai ( PPN ) = 10% x (A) 2,440,159,187.06 2,440,159,187.06
C Jumlah Total Harga Pekerjaan = (A) + (B) 26,841,751,057.65 26,841,751,057.65
D Jumlah Total Harga Pekerjaan (Dibulatkan) 26,841,751,000.00 26,841,751,000.00
DATA SURVEY
REKONSTRUKSI JALAN KUJAN - RUNTU
Galian Biasa
Panjang Lebar Luas
No. STA. Posisi Ket.
(M) (M) (M2)
Rel Pengaman
Panjang Luas
No. STA. Posisi Ket.
(M) (M1)
No. Mata
Uraian Satuan Perhitungan Harga Satuan Jumlah Harga Jumlah Harga
Pembayaran Kuantitas Kuantitas
(Rupiah) (Rupiah) (Rupiah)
10.1.(6) Perbaikan Lapis Pondasi Agregat Kelas S M3 1,557.00 x 1 x 0.12 326.10 806,496.00 262,998,345.60 186.84 150,685,712.64
10.1.(22) Pengendalian Tanaman M2 38,700.00 x 2 x 2 x 75% x 4 145,600.00 1,012.00 147,347,200.00 464,400.00 469,972,800.00
A Jumlah Harga Pekerjaan ( termasuk Biaya Umum dan Keuntungan ) 723,395,785.60 723,395,785.60
B Pajak Pertambahan Nilai ( PPN ) = 10% x (A) 72,339,578.56 72,339,578.56
C Jumlah Total Harga Pekerjaan = (A) + (B) 795,735,364.16 795,735,364.16
D Jumlah Total Harga Pekerjaan (Dibulatkan) 795,735,000.00 795,735,000.00
DATA SURVEY
PEMEL. RUTIN JALAN KUJAN - RUNTU
Pembersihan Drainase
Panjang Lebar Luas
No. STA. Posisi Ket.
(M) (M) (M1)
Pengendalian Tanaman
Panjang Lebar Luas
No. STA. Posisi Ket.
(M) (M) (M2)
No. Mata
Uraian Satuan Perhitugan Harga Satuan Jumlah Harga Jumlah Harga
Pembayaran Kuantitas Kuantitas
(Rupiah) (Rupiah) (Rupiah)
10.1.(4) Perbaikan Lapis Pondasi Agregat Kelas A M3 866.40 x 0.1248 927,140.00 108.10 100,223,834.00
10.1.(6) Perbaikan Lapis Pondasi Agregat Kelas S M3 317.00 x 1 x 0.12 299.74 806,496.00 241,739,111.04 38.04 30,679,107.84
10.1.(9) Perbaikan Campuran Aspal Panas M3 866.40 x 0.05 3,726,390.00 43.32 161,427,214.80
10.1.(22) Pengendalian Tanaman M2 21,400.00 x 2 x 2 x 75% x 4 145,600.00 1,012.00 147,347,200.00 256,800.00 259,881,600.00
A Jumlah Harga Pekerjaan ( termasuk Biaya Umum dan Keuntungan ) 572,830,911.04 572,830,911.04
B Pajak Pertambahan Nilai ( PPN ) = 10% x (A) 57,283,091.10 57,283,091.10
C Jumlah Total Harga Pekerjaan = (A) + (B) 630,114,002.14 630,114,002.14
D Jumlah Total Harga Pekerjaan (Dibulatkan) 630,114,000.00 630,114,000.00
DATA SURVEY
PEMEL. RUTIN JALAN RUNTU - SIMPANG RUNTU
Total 866.40
Total 866.40
Pembersihan Drainase
Panjang Lebar Luas
No. STA. Posisi Ket.
(M) (M) (M1)
Pengendalian Tanaman
Panjang Lebar Luas
No. STA. Posisi Ket.
(M) (M) (M2)
No. Mata
Uraian Satuan Perhitungan Harga Satuan Jumlah Harga Jumlah Harga
Pembayaran Kuantitas Kuantitas
(Rupiah) (Rupiah) (Rupiah)
10.1.(9) Perbaikan Campuran Aspal Panas M3 1,577.00 x 0.05 91.10 3,726,390.00 339,474,129.00 78.85 293,825,851.50
10.1.(11) Perbaikan Asbuton Campuran Panas Hampar Dingin M3 100.00 x 0.05 5.00 3,745,675.00 18,728,375.00 5.00 18,728,375.00
A Jumlah Harga Pekerjaan ( termasuk Biaya Umum dan Keuntungan ) 479,889,629.00 479,889,629.00
B Pajak Pertambahan Nilai ( PPN ) = 10% x (A) 47,988,962.90 47,988,962.90
C Jumlah Total Harga Pekerjaan = (A) + (B) 527,878,591.90 527,878,591.90
D Jumlah Total Harga Pekerjaan (Dibulatkan) 527,879,000.00 527,879,000.00
DATA SURVEY
PEMEL. RUTIN KONDISI KUJAN - RUNTU
Total 1,445.00
Total 1,577.00
Total 100.00
PAKET PEKERJAAN : PRESERVASI JALAN KUJAN - RUNTU - SIMPANG RUNTU
NOMOR KONTRAK : HK 0201-Bb29.5.1/KTRK/03, TANGGAL 05 JANUARI 2022
NILAI KONTRAK : Rp. 35.855.000.000,00
No. Mata
Uraian Satuan Perhitungan Harga Satuan Jumlah Harga Jumlah Harga
Pembayaran Kuantitas Kuantitas
(Rupiah) (Rupiah) (Rupiah)
10.1.(9) Perbaikan Campuran Aspal Panas M3 202.50 x 0.05 13.09 3,726,390.00 48,778,445.10 10.13 37,748,330.70
10.1.(11) Perbaikan Asbuton Campuran Panas Hampar Dingin M3 100.00 x 0.05 5.00 3,745,675.00 18,728,375.00 5.00 18,728,375.00
A Jumlah Harga Pekerjaan ( termasuk Biaya Umum dan Keuntungan ) 89,062,825.10 89,062,825.10
B Pajak Pertambahan Nilai ( PPN ) = 10% x (A) 8,906,282.51 8,906,282.51
C Jumlah Total Harga Pekerjaan = (A) + (B) 97,969,107.61 97,969,107.61
D Jumlah Total Harga Pekerjaan (Dibulatkan) 97,969,000.00 97,969,000.00
DATA SURVEY
PEMEL. RUTIN KONDISI RUNTU - SIMPANG RUNTU
Total 281.70
Total 202.50
Total 100.00
PAKET PEKERJAAN : PRESERVASI JALAN KUJAN - RUNTU - SIMPANG RUNTU
NOMOR KONTRAK : HK 0201-Bb29.5.1/KTRK/03, TANGGAL 05 JANUARI 2022
NILAI KONTRAK : Rp. 35.855.000.000,00
No. Mata
Uraian Satuan Perhitungan Harga Satuan Jumlah Harga Jumlah Harga
Pembayaran Kuantitas Kuantitas
(Rupiah) (Rupiah) (Rupiah)
10.1.(9) Perbaikan Campuran Aspal Panas M3 11,677.70 x 0.05 573.82 3,726,390.00 2,138,277,109.80 583.89 2,175,801,857.10
A Jumlah Harga Pekerjaan ( termasuk Biaya Umum dan Keuntungan ) 3,114,555,529.80 3,114,555,529.80
B Pajak Pertambahan Nilai ( PPN ) = 10% x (A) 311,455,552.98 311,455,552.98
C Jumlah Total Harga Pekerjaan = (A) + (B) 3,426,011,082.78 3,426,011,082.78
D Jumlah Total Harga Pekerjaan (Dibulatkan) 3,426,011,000.00 3,426,011,000.00
DATA SURVEY
PENUNJANG/HOLDING KUJAN - RUNTU
Total 8,101.70
Perbaikan Campuran Aspal Panas
No. Panjang Lebar Luas
STA. Posisi Ket.
Titik (M) (M) (M2)
Total 11,677.70
PAKET PEKERJAAN : PRESERVASI JALAN KUJAN - RUNTU - SIMPANG RUNTU
NOMOR KONTRAK : HK 0201-Bb29.5.1/KTRK/03, TANGGAL 05 JANUARI 2022
NILAI KONTRAK : Rp. 35.855.000.000,00
No. Mata
Uraian Satuan Perhitungan Harga Satuan Jumlah Harga Jumlah Harga
Pembayaran Kuantitas Kuantitas
(Rupiah) (Rupiah) (Rupiah)
10.1.(9) Perbaikan Campuran Aspal Panas M3 4,826.20 x 0.05 315.89 3,726,390.00 1,177,129,337.10 241.31 899,215,170.90
A Jumlah Harga Pekerjaan ( termasuk Biaya Umum dan Keuntungan ) 1,457,885,871.90 1,457,885,871.90
B Pajak Pertambahan Nilai ( PPN ) = 10% x (A) 145,788,587.19 145,788,587.19
C Jumlah Total Harga Pekerjaan = (A) + (B) 1,603,674,459.09 1,603,674,459.09
D Jumlah Total Harga Pekerjaan (Dibulatkan) 1,603,675,000.00 1,603,675,000.00
DATA SURVEY
PENUNJANG/HOLDING RUNTU - SIMPANG RUNTU
Total 4,826.20
Perbaikan Campuran Aspal Panas
No. Panjang Lebar Luas
STA. Posisi Ket.
Titik (M) (M) (M2)
Total 4,826.20
PAKET PEKERJAAN : PRESERVASI JALAN KUJAN - RUNTU - SIMPANG RUNTU
NOMOR KONTRAK : HK 0201-Bb29.5.1/KTRK/03, TANGGAL 05 JANUARI 2022
NILAI KONTRAK : Rp. 35.855.000.000,00
DIVISI 7. STRUKTUR
7.6 (1) Pondasi Cerucuk, Penyediaan dan Pemancangan M1 600.00 14,739.00 8,843,400.00 600.00 8,843,400.00
7.10.(3a) Bronjong dengan Kawat yang dilapisi Galvanis M3 88.02 956,164.00 84,161,555.28 88.02 84,161,555.28
A Jumlah Harga Pekerjaan ( termasuk Biaya Umum dan Keuntungan ) 218,773,747.28 218,773,747.28
B Pajak Pertambahan Nilai ( PPN ) = 10% x (A) 21,877,374.73 21,877,374.73
C Jumlah Total Harga Pekerjaan = (A) + (B) 240,651,122.01 240,651,122.01
D Jumlah Total Harga Pekerjaan (Dibulatkan) 240,651,000.00 240,651,000.00
PAKET PEKERJAAN : PRESERVASI JALAN KUJAN - RUNTU - SIMPANG RUNTU
NOMOR KONTRAK : HK 0201-Bb29.5.1/KTRK/03, TANGGAL 05 JANUARI 2022
NILAI KONTRAK : Rp. 35.855.000.000,00
No. Mata
Uraian Satuan Perhitungan Harga Satuan Jumlah Harga Jumlah Harga
Pembayaran Kuantitas Kuantitas
(Rupiah) (Rupiah) (Rupiah)
DIVISI 7. STRUKTUR
7.6 (1) Pondasi Cerucuk, Penyediaan dan Pemancangan M1 1,272.00 14,739.00 18,748,008.00 1,272.00 18,748,008.00
7.10.(3a) Bronjong dengan Kawat yang dilapisi Galvanis M3 108.00 956,164.00 103,265,712.00 108.00 103,265,712.00
7.14.(1) Papan Nama Jembatan Buah 2.00 756,208.00 1,512,416.00 2.00 1,512,416.00
A Jumlah Harga Pekerjaan ( termasuk Biaya Umum dan Keuntungan ) 197,038,664.00 197,038,664.00
B Pajak Pertambahan Nilai ( PPN ) = 10% x (A) 19,703,866.40 19,703,866.40
C Jumlah Total Harga Pekerjaan = (A) + (B) 216,742,530.40 216,742,530.40
D Jumlah Total Harga Pekerjaan (Dibulatkan) 216,743,000.00 216,743,000.00
PAKET PEKERJAAN : PRESERVASI JALAN KUJAN - RUNTU - SIMPANG RUNTU
NOMOR KONTRAK : HK 0201-Bb29.5.1/KTRK/03, TANGGAL 05 JANUARI 2022
NILAI KONTRAK : Rp. 35.855.000.000,00
No. Mata
Uraian Satuan Perhitungan Harga Satuan Jumlah Harga Jumlah Harga
Pembayaran Kuantitas Kuantitas
(Rupiah) (Rupiah) (Rupiah)
A Jumlah Harga Pekerjaan ( termasuk Biaya Umum dan Keuntungan ) 261,866,675.60 261,866,675.60
B Pajak Pertambahan Nilai ( PPN ) = 10% x (A) 26,186,667.56 26,186,667.56
C Jumlah Total Harga Pekerjaan = (A) + (B) 288,053,343.16 288,053,343.16
D Jumlah Total Harga Pekerjaan (Dibulatkan) 288,053,000.00 288,053,000.00
PAKET PEKERJAAN : PRESERVASI JALAN KUJAN - RUNTU - SIMPANG RUNTU
NOMOR KONTRAK : HK 0201-Bb29.5.1/KTRK/03, TANGGAL 05 JANUARI 2022
NILAI KONTRAK : Rp. 35.855.000.000,00
No. Mata
Uraian Satuan Perhitungan Harga Satuan Jumlah Harga Jumlah Harga
Pembayaran Kuantitas Kuantitas
(Rupiah) (Rupiah) (Rupiah)
DIVISI 7. STRUKTUR
7.1 (5a) Beton Struktur, fc’30 Mpa M3 1.02 2,510,434.00 2,560,642.68 1.02 2,560,642.68
7.3 (3) Baja Tulangan Sirip BjTS 420A Kg 52.05 25,030.00 1,302,811.50 52.05 1,302,811.50
7.6 (1) Pondasi Cerucuk, Penyediaan dan Pemancangan M1 920.00 14,739.00 13,559,880.00 920.00 13,559,880.00
7.10.(3a) Bronjong dengan Kawat yang dilapisi Galvanis M3 99.00 956,164.00 94,660,236.00 99.00 94,660,236.00
7.14.(1) Papan Nama Jembatan Buah 2.00 756,208.00 1,512,416.00 2.00 1,512,416.00
A Jumlah Harga Pekerjaan ( termasuk Biaya Umum dan Keuntungan ) 182,108,514.18 182,108,514.18
B Pajak Pertambahan Nilai ( PPN ) = 10% x (A) 18,210,851.42 18,210,851.42
C Jumlah Total Harga Pekerjaan = (A) + (B) 200,319,365.60 200,319,365.60
D Jumlah Total Harga Pekerjaan (Dibulatkan) 200,319,000.00 200,319,000.00
PAKET PEKERJAAN : PRESERVASI JALAN KUJAN - RUNTU - SIMPANG RUNTU
NOMOR KONTRAK : HK 0201-Bb29.5.1/KTRK/03, TANGGAL 05 JANUARI 2022
NILAI KONTRAK : Rp. 35.855.000.000,00
No. Mata
Uraian Satuan Perhitungan Harga Satuan Jumlah Harga Jumlah Harga
Pembayaran Kuantitas Kuantitas
(Rupiah) (Rupiah) (Rupiah)
DIVISI 7. STRUKTUR
7.1 (5a) Beton Struktur, fc’30 Mpa M3 0.90 x 0.40 x 0.33 0.12 2,510,434.00 301,252.08 0.12 301,252.08
7.6 (1) Pondasi Cerucuk, Penyediaan dan Pemancangan M1 2,432.00 14,739.00 35,845,248.00 2,432.00 35,845,248.00
7.9.(1) Pasangan Batu M3 130.22 1,057,685.00 137,731,740.70 130.22 137,731,740.70
7.14.(1) Papan Nama Jembatan Buah 2.00 756,208.00 1,512,416.00 2.00 1,512,416.00
- Beton Strukur, fc’20 Mpa M3 3.5 x 1.5 x 0.20 x 4 2,227,712.00 4.17 9,300,000.00
A Jumlah Harga Pekerjaan ( termasuk Biaya Umum dan Keuntungan ) 237,138,425.08 237,138,425.08
B Pajak Pertambahan Nilai ( PPN ) = 10% x (A) 23,713,842.51 23,713,842.51
C Jumlah Total Harga Pekerjaan = (A) + (B) 260,852,267.59 260,852,267.59
D Jumlah Total Harga Pekerjaan (Dibulatkan) 260,852,000.00 260,852,000.00
PAKET PEKERJAAN : PRESERVASI JALAN KUJAN - RUNTU - SIMPANG RUNTU
NOMOR KONTRAK : HK 0201-Bb29.5.1/KTRK/03, TANGGAL 05 JANUARI 2022
NILAI KONTRAK : Rp. 35.855.000.000,00
No. Mata
Uraian Satuan Perhitungan Harga Satuan Jumlah Harga Jumlah Harga
Pembayaran Kuantitas Kuantitas
(Rupiah) (Rupiah) (Rupiah)
DIVISI 7. STRUKTUR
7.1 (5a) Beton Struktur, fc’30 Mpa M3 1.00 x 0.45 x 0.35 2.42 2,510,434.00 6,075,250.28 0.16 396,845.57
7.14.(1) Papan Nama Jembatan Buah 2.00 756,208.00 1,512,416.00 2.00 1,512,416.00
A Jumlah Harga Pekerjaan ( termasuk Biaya Umum dan Keuntungan ) 89,487,784.28 89,487,784.28
B Pajak Pertambahan Nilai ( PPN ) = 10% x (A) 8,948,778.43 8,948,778.43
C Jumlah Total Harga Pekerjaan = (A) + (B) 98,436,562.71 98,436,562.71
D Jumlah Total Harga Pekerjaan (Dibulatkan) 98,437,000.00 98,437,000.00
PAKET PEKERJAAN : PRESERVASI JALAN KUJAN - RUNTU - SIMPANG RUNTU
NOMOR KONTRAK : HK 0201-Bb29.5.1/KTRK/03, TANGGAL 05 JANUARI 2022
NILAI KONTRAK : Rp. 35.855.000.000,00
No. Mata
Uraian Satuan Perhitungan Harga Satuan Jumlah Harga Jumlah Harga
Pembayaran Kuantitas Kuantitas
(Rupiah) (Rupiah) (Rupiah)
DIVISI 7. STRUKTUR
7.1 (7a) Beton Strukur, fc’20 MPa M3 11.429 x 7 x 0.20 16.00 2,227,712.00 35,643,392.00 16.00 35,643,392.00
7.10.(3a) Bronjong dengan Kawat yang dilapisi Galvanis M3 30.00 956,164.00 28,684,920.00 30.00 28,684,920.00
A Jumlah Harga Pekerjaan ( termasuk Biaya Umum dan Keuntungan ) 74,328,312.00 74,328,312.00
B Pajak Pertambahan Nilai ( PPN ) = 10% x (A) 7,432,831.20 7,432,831.20
C Jumlah Total Harga Pekerjaan = (A) + (B) 81,761,143.20 81,761,143.20
D Jumlah Total Harga Pekerjaan (Dibulatkan) 81,761,000.00 81,761,000.00
PAKET PEKERJAAN : PRESERVASI JALAN KUJAN - RUNTU - SIMPANG RUNTU
NOMOR KONTRAK : HK 0201-Bb29.5.1/KTRK/03, TANGGAL 05 JANUARI 2022
NILAI KONTRAK : Rp. 35.855.000.000,00
No. Mata
Uraian Satuan Perhitungan Harga Satuan Jumlah Harga Jumlah Harga
Pembayaran Kuantitas Kuantitas
(Rupiah) (Rupiah) (Rupiah)
A Jumlah Harga Pekerjaan ( termasuk Biaya Umum dan Keuntungan ) 495,500,000.00 495,500,000.00
B Pajak Pertambahan Nilai ( PPN ) = 10% x (A) 49,550,000.00 49,550,000.00
C Jumlah Total Harga Pekerjaan = (A) + (B) 545,050,000.00 545,050,000.00
D Jumlah Total Harga Pekerjaan (Dibulatkan) 545,050,000.00 545,050,000.00
DATA SURVEY
RUAS JALAN RUNTU - SP. RUNTU
RENCANA REALISASI
Panjang Lebar Luas Panjang Lebar Luas
No. STA. Posisi Lingkup Ket.
(M) (M) (M2) (M) (M) (M2)