Professional Documents
Culture Documents
04340003E-01-SPC-0001 - Concrete Spec Rev D Final
04340003E-01-SPC-0001 - Concrete Spec Rev D Final
CONCRETE SPECIFICATION
For
Rev D
19 July 2022
04340004E-01-SPC-0001
C:\Users\melaniew\Documents\04340001\New Project\Copy in PW\Library Documents\Docusign\04340003E-01-SPC-0001 - Concrete Spec Rev D Final.docx
Page i of 28
DocuSign Envelope ID: A4BF1485-D514-49B2-9813-29457AAEF208
REVISION SCHEDULE
Approval
PROJECT TEAM
8/2/2022
R Du Plessis Civil / Structural Engineer RSV
8/2/2022
D van Biljon Lead Engineer RSV
8/2/2022
F Uys GES: Mechanical TRP
8/2/2022
K Janse van Rensburg Manager Assistant: Projects TRP
Page 2 of 28
DocuSign Envelope ID: A4BF1485-D514-49B2-9813-29457AAEF208
CONTENTS
1. SCOPE .................................................................................................................................... 6
1.1 Applicable Regulations ...................................................................................................... 6
Page 3 of 28
DocuSign Envelope ID: A4BF1485-D514-49B2-9813-29457AAEF208
8. CURING................................................................................................................................. 18
8.1 Exposed Surfaces ........................................................................................................... 18
8.2 Low Temperatures .......................................................................................................... 18
8.3 High Temperatures.......................................................................................................... 18
9. FORMS .................................................................................................................................. 18
9.1 Installation ....................................................................................................................... 18
9.2 Materials and fixing ......................................................................................................... 19
Page 4 of 28
DocuSign Envelope ID: A4BF1485-D514-49B2-9813-29457AAEF208
INDEX OF TABLES
Table 1: SA National Standards ...................................................................................................... 6
Page 5 of 28
DocuSign Envelope ID: A4BF1485-D514-49B2-9813-29457AAEF208
1. SCOPE
This General Specification establishes the quality of material and workmanship and defines how
quality is measured for designing, detailing, furnishing, delivering, forming, placing, finishing and
curing concrete, including reinforcing and embedded items, constructing joints and placing grout and
associated concrete operations for process plant facilities
1.1 Applicable Regulations
The Contractor shall conform with all relevant statutes, ordinances, regulations, by-laws or other
enactments that are applicable at all times during the execution of the Order including, without
limitation, the Mine Health and Safety Act (with specific reference to Chapter 2, including but not
limited to Sections 21 and 22), no 29 of 1996. The Contractor shall ensure that the machinery, plant,
equipment, apparatus, materials, or services to be supplied comply therewith, including all
amendments and re-enactments thereof and other provisions having the force of law, and with any
local and domestic regulations.
2. GENERAL REQUIREMENTS
▪ In order to complete the works, the Contractor undertakes to provide all adequate and
competent labour, supervision, tools, equipment, installed and consumable materials,
services, testing devices and services, warehousing, and each and every item of expense
necessary to complete the works;
▪ The Contractor shall carry out cube tests, provide quality plans and any other tests that the
Employer may require in terms of the drawings and this specification;
▪ The Contractor shall obtain all the necessary permits for the complete performance of the
works, and for the hauling, loading and off-loading of materials, scaffolding, and other
materials;
▪ The Employer will designate the boundary limits of access roads, parking areas, storage
areas, and construction areas. The Contractor shall not trespass in or on areas not so
designated;
▪ The Contractor shall satisfy the intent of each code, specification, drawing, and all other
documents issued as part of the Contract.
3. APPLICABLE STANDARDS
Unless otherwise specified or shown, the following codes and regulations shall apply to all concrete
work and materials employed for the operations above mentioned:
Table 1: SA National Standards
SANS 121: 2011 Hot-dipped galvanized coatings on fabricated iron and steel articles
SANS 135: 2011 ISO metric bolts, screws and nuts (hexagon and square)
Page 6 of 28
DocuSign Envelope ID: A4BF1485-D514-49B2-9813-29457AAEF208
SANS 282: 2011 Bending dimensions and scheduling of steel reinforcement for concrete
Cast iron surface boxes and manhole and inspection covers and
SANS 558: 2015
frames.
SANS 675: 2011 Zinc coated fencing wire (plain and barbed).
SANS 727: 2003 Windows and doors made from rolled mild steel sections
SANS 748: 2002 Road tar binders prepared from coke oven crudes
SANS 749: 2003 Road tar binders prepared from Lurgi-gasification crudes
SANS 952: 2011 Parts 1 & 2 - Polyolefin film for damp – and waterproofing in buildings
Page 7 of 28
DocuSign Envelope ID: A4BF1485-D514-49B2-9813-29457AAEF208
SANS 1115: 2007 Cast iron gratings for gullies and storm water drains.
SANS 1143: 2008 Mushroom and countersunk – head bolts and nuts.
Page 8 of 28
DocuSign Envelope ID: A4BF1485-D514-49B2-9813-29457AAEF208
Page 9 of 28
DocuSign Envelope ID: A4BF1485-D514-49B2-9813-29457AAEF208
SANS 10100-2: 2014 Structural use of concrete – materials and execution of work.
SANS 10162: 2011 The structural use of steel – Part 1 Hot rolled, part 2 cold formed
SANS 10167: 2011 The quality evaluation of fusion welded joints in steel structures.
SANS 10400: 1990 The application of the National Building Regulations. Parts A to XA
SANS 62305: 2011 Safety earthing, bonding and lightning protection. Parts 1 - 4
Page 10 of 28
DocuSign Envelope ID: A4BF1485-D514-49B2-9813-29457AAEF208
BS 6187 Demolition
Page 11 of 28
DocuSign Envelope ID: A4BF1485-D514-49B2-9813-29457AAEF208
Title
ISO 2631-1978 Guide for the evaluation of human response to whole body vibration.
C&CI – Concrete Industrial floors on the ground – Louis R Marais & Bryan D Perrie
4. SITE SURVEY
The Contractor shall carry out the following survey work:
▪ Verify and accept site topography and original ground levels prior to commencement of any
excavations and/or installation and notify the Employer of any discrepancies;
▪ Create temporary construction bench marks from the primary site beacons advised by
Employer as the beacons accepted for the site;
▪ The accuracy of these temporary construction beacons shall be to enable holding down bolts
to be located to ±3 millimetres from their designated position on plan, and -3 to +5 mm from
their designed elevation.
The permitted tolerance of construction shall comply with the requirements of SANS 1200 G: 1982
with respect to the placing of concrete structures, holding down bolts and fixtures.
5. MATERIALS
5.1 Portland cement
The composition of cement products shall conform to SANS 50197-1
▪ Portland cement shall conform to the standard quoted above and shall be declared to the
Engineer in terms of the designation of products listed in the standard. Cement used for
concrete in exposed surfaces of a structure shall be the same brand. The Engineer shall be
furnished with one copy of a certified mill test report for each delivery of cement.
▪ Other products conforming to the standard may be used as an alternate to Portland cement with
the approval of the Engineer provided the designation of the cement is declared and adhered to
in terms of SANS 50197-1.
5.2 Concrete aggregates
Aggregate shall conform to SANS 1083. Aggregate shall be taken from approved sources and will
be tested prior to use by the Engineer. Limits for organic impurities, soundness, alkali-reactivity and
shrinkage will be established by the Engineer.
C:\Users\melaniew\Documents\04340001\New Project\Copy in PW\Library Documents\Docusign\04340003E-01-SPC-0001 - Concrete Spec Rev D
Final.docx
Page 12 of 28
DocuSign Envelope ID: A4BF1485-D514-49B2-9813-29457AAEF208
5.3 Water
Water used in mixing concrete, shall be clean and free from injurious amounts of oils, acids, alkalis,
organic matter of other deleterious substances.
5.4 Metal reinforcement
Reinforcing bars and mesh shall conform to the following:
▪ Deformed bars shall be high tensile steel conforming to SABS 920, and with deformations
conforming to SABS 82. Reinforcement bars lacking grade identification shall on delivery be
accompanied by Manufacturer's certificate of grade to identify variations;
▪ Cold drawn wire or welded wire fabric shall conform to SANS 1024.
5.5 Admixtures
Admixtures shall not be used in concrete unless approved in writing by the Engineer. Refer to
concrete repairs below in Section 20.
5.6 Storage
Materials shall be stored in such a manner as to prevent deterioration or intrusion of foreign matter.
Any material which has deteriorated, or which has been damaged shall not be used for concrete.
Cement shall be stored off the ground and adequately protected from the weather. No cement which
has hardened or contains lumps shall be used. Aggregate piles shall be separated sufficiently to
prevent mixing prior to use.
6. CONCRETE QUALITY AND ALLOWABLE STRESSES
6.1 Control
Concrete shall conform to the requirements of SANS 10100 parts 1 and 2, the design and use of
structural concrete.
6.1.1 Unless otherwise specified on drawings or project documentation concrete classes shall be as
follows:
Page 13 of 28
DocuSign Envelope ID: A4BF1485-D514-49B2-9813-29457AAEF208
Page 14 of 28
DocuSign Envelope ID: A4BF1485-D514-49B2-9813-29457AAEF208
▪ Graphs showing relationship between slump and water content per cubic metre of mix;
▪ Data relating to the source of supply, grading, physical properties and characteristics of the
aggregate.
6.4 Tests of the concrete and other materials
Tests will be made by the Engineer from time to time to determine whether the materials and
methods in use are such as to produce concrete of the quality specified. The tests shall be made
by an approved testing laboratory at the expense of the Owner. The Contractor shall co-operate
fully with the laboratory in providing samples for all the tests. Samples shall be taken in accordance
with SANS 5861-2: 2006 and placed for curing in accordance with SANS 5861-3: 2006. Slump tests
shall be recorded in accordance with SANS 5862-1: 2006 and hardness tests in accordance with
SANS 5863: 2006.
▪ Materials failing to meet the requirements specified shall not be used unless otherwise approved
by the Engineer;
▪ Concrete that has a slump greater than the limits specified shall not be used unless otherwise
approved by the Engineer;
▪ Compressive strength tests that fail to meet the requirements and leave reasonable doubt as to
the adequacy of the structure may require a load test or core drills in accordance with SANS
5865 of the structure to be taken, if so directed by the Engineer. Such tests or drilling shall be
made at the Contractor's expense and should these tests indicate that the concrete does not
conform to these specifications, the Contractor shall remove and replace this concrete or take
such corrective measures as directed by the Engineer.
If the tests indicate that the concrete meets the specification requirements, the Contractor shall be
reimbursed for the cost of the load or core drilling.
7. MIXING AND PLACING CONCRETE
The Engineer shall be given a minimum of 24 hours’ notice before placing any concrete.
7.1 Mixing of Concrete
All concrete shall be mixed until there is a uniform distribution of the materials and shall be
discharged completely before the mixer is recharged. All mixing shall be maintained in good
operating condition to prevent critical breakdowns during the progress of the work. Sufficient spare
parts and personnel shall be maintained at the mixing site to provide continuous mixing during critical
pours.
Mixers and agitators shall be operated within the limits of capacity and speed of rotation designated
by the equipment manufacturer.
7.2 Job Mixed Concrete
For job mixed concrete, mixing shall be done in a batch mixer of approved type. The mixer shall be
rotated at a speed and for periods recommended by the manufacturer. Mixing time shall be
measured from the time all cement and aggregate are in the drum. The batch shall be so discharged
into the mixer that some water shall be in the drum by the end of the first one-fourth of the specified
mixing time. Variations from the specified minimum mixing time may be used if approved by the
Engineer.
C:\Users\melaniew\Documents\04340001\New Project\Copy in PW\Library Documents\Docusign\04340003E-01-SPC-0001 - Concrete Spec Rev D
Final.docx
Page 15 of 28
DocuSign Envelope ID: A4BF1485-D514-49B2-9813-29457AAEF208
Page 16 of 28
DocuSign Envelope ID: A4BF1485-D514-49B2-9813-29457AAEF208
Page 17 of 28
DocuSign Envelope ID: A4BF1485-D514-49B2-9813-29457AAEF208
Page 18 of 28
DocuSign Envelope ID: A4BF1485-D514-49B2-9813-29457AAEF208
All surfaces exposed to concrete shall be oiled or prepared with other approved dressing materials.
All forms shall be properly cleaned before the application of "Form-oil".
9.2 Materials and fixing
Forms shall be of steel, plywood or finished lumber of sufficient strength to resist all loads including
wet concrete and construction loads and shall be sufficiently tight to prevent any leakage of mortar
and to provide the type of concrete finish shown on the drawings or as directed by the Engineer.
Forms for columns, walls and deep beams, shall be designed for the hydrostatic pressure of wet
concrete.
As far as possible, wedges and clamps shall be used in preference to nails. Where ties shall not be
used where discolouration of the finish would be objectionable, or where watertight concrete is
required. Ties shall be so arranged that when forms are removed, all metal shall be not less than 25
mm from any surface exposed to weather. Great care shall be taken to keep the form work in its
proper position, and it shall be checked by levels or other methods to ensure this. All beam forms
shall have a chamber of 1mm per 51cm of length. All angles of forms shall be chamfered with
19 mm strips to produce clean, straight and uniform edges.
Forms shall be removed in such a manner as to ensure the complete safety of the structure. Where
the structure as a whole is supported on shores, beam and girder sides, column and similar vertical
forms may be removed after 48 hours, provided the concrete is sufficiently hard as not to be injured
and adequate curing is provided. In no case shall the supporting forms or shoring be removed until
the members have acquired sufficient strength to support safely their weight and the load thereon.
The results of suitable tests may be used as evidence that the concrete has attained sufficient
strength. In the absence of such test results, the minimum period that shall elapse shall be as
approved by the engineer.
10. CONSTRUCTION JOINTS
10.1 Joints not indicated on the drawings
Such joints shall be so made as to least impair the strength of the structure and as approved by the
Engineer. The surfaces of all construction joints shall be cleaned of all debris, water and loose
particles and then scrubbed with a wire brush or by other approved methods and thoroughly washed
to remove all laitance. Immediately before the placing of new concrete, all joints shall be thoroughly
wetted and slushed with a thick paste of cement grout.
10.2 Interfaces between elements
After depositing concrete in the columns or walls, sufficient time shall be allowed for shrinkage before
depositing in beams, girders or slabs supported thereon. Beam girders, brackets and haunches
shall be considered as part of the floor system and shall be placed monolithically with the floor.
10.3 Positioning Joints
The position of joints and stops shall be decided in advance based on the capacity of the batch plant
in operation. In general, joints should be made along the line of maximum and minimum shear and
be properly keyed and doweled. Joints in columns shall be horizontal. Principal reinforcing shall
pass through all joints.
Page 19 of 28
DocuSign Envelope ID: A4BF1485-D514-49B2-9813-29457AAEF208
11. REINFORCEMENT
11.1 Metal reinforcement at the time concrete is placed, shall be free from loose rust, scale or other
coatings that will destroy or reduce the bond.
11.2 Reinforcements shall be bent in accordance with SANS282 "Bending dimensions and
scheduling of steel reinforcement for concrete. The number size, form and position of
reinforcement shall be as indicated on the drawings.
11.3 Metal reinforcement shall be accurately placed and adequately secured in position by concrete
spacers or stools or hangers. Rods crossing one another shall be securely bound with 1,25mm
diam. annealed wire. All stirrups shall be properly fastened to the rods so as to retain their
position during the placing of concrete. Joining the main reinforcing by welding shall not be
permitted, unless approved by the Engineer. Reinforcement shall not be cut or displaced in
position without the approval of the Engineer.
11.4 The cover as specified on the drawings shall be measured from the face of the concrete to the
outside of the main reinforcement, excluding stirrups and column ties nearest the face of the
concrete. The minimum clear distance between bars and forms, unless noted, shall be the
diameter of round bars, or 25mm, whichever is greater. The clear distance between parallel
bars shall not be less than 25mm or less than 1-1/3 times the maximum size of the course
aggregate. Unless noted otherwise on the drawings. The concrete cover for reinforcement
shall be as follows unless otherwise specified on drawings and project documentation noting
that SANS 2001:CC1 applies in general:
Table 5: Cover to concrete
11.5 Splices of reinforcement shall provide sufficient lap to transfer the stress between bars by bond
and shear. The length of splices shall be as indicated on the drawings. In splices, the bars
shall be in contact and wired together, and the minimum clear distances as specified above
shall be maintained between bars or between wired splices shall be made only where indicated
on the drawings or as approved by the Engineer.
11.6 Offsets in reinforcements shall be made in a region in which lateral support is provided, where
offset, the slope of the inclined portion shall not be more than 1 in 6 from the vertical.
Page 20 of 28
DocuSign Envelope ID: A4BF1485-D514-49B2-9813-29457AAEF208
Page 21 of 28
DocuSign Envelope ID: A4BF1485-D514-49B2-9813-29457AAEF208
Page 22 of 28
DocuSign Envelope ID: A4BF1485-D514-49B2-9813-29457AAEF208
floating level. While the concrete is still green, but sufficiently hardened to bear a man's
weight without deep imprint, it shall be floated either by hand or mechanical means to a
true, even place with no coarse aggregate visible. Sufficient pressure shall be used on
the floats to bring moisture to the surface. After surface moisture has disappeared, the
surfaces shall be trowelled to a smooth even finish. If machine trowel is used, trowel
marks shall be removed be hand steel trowelling. When a hard burnished surface is
required, the surface shall be steel trowelled by hand after the machine trowelling. The
steel trowelling shall produce a ringing sound from the trowels.
▪ Surfaces indicated to have monolithic wood float finish shall be finished as specified for
monolithic steel trowel finish except that steel trowelling shall be omitted. After the
surface moisture has disappeared, the surfaces shall be finished with a wood float to a
level, even surface. The surface shall have a granular texture which will not be slick
when wet.
▪ Surfaces indicated to receive fill and-or mortar setting beds shall be finished by tamping
the concrete with special tools to force the coarse aggregate away from the surface, and
screeding with straight edges to bring the surface to the required level.
▪ Surfaces indicated to have monolithic broomed finish shall be finished as specified for
monolithic steel trowel except that the hand steel trowelling shall be omitted. After the
machine trowelling is completed, the surface shall be broomed with fibre-bristle brush or
broom in a direction perpendicular to the main line of traffic.
▪ Surfaces indicated to have abrasive monolithic finish shall be finished as specified for
monolithic finish except that before the steel trowelling is commenced, an abrasive
material shall be evenly applied to the surface at a rate of not less than 0,85 kilograms
of abrasive material to each square metre. The surfaces shall then be steel trowelled as
specified for monolithic finish. The abrasive material shall be aluminium oxide so graded
that 100% of the particles are retained on a No 30 sieve and 100% will pass a No 12
sieve, or other similar product.
17. CONSTRUCTION TOLERANCES
16.1 Work shall be carefully and accurately set out, true to position, levels, slopes and dimensions
as shown and specified.
16.2 In addition to tolerances specified in paragraph 16 herein, tolerances shall be those specified
in SABS 1200 G and as follows.
16.3 Tolerance for cover reinforcement shall ensure fixing compliant with Table 5 and:
a) Where the nominal cover is 25 mm or more 6 mm
b) Where the nominal cover is less than 25 mm + 6 mm – 3 mm
16.4 Tolerances for longitudinal location of bends and ends of bars shall be 50mm except at
discontinuous ends of members where the tolerance shall be 12 mm.
18. SUPERVISION AND INSPECTION
17.1 The Contractor shall employ, on the site, a competent supervisor to be responsible for all
concrete work.
Page 23 of 28
DocuSign Envelope ID: A4BF1485-D514-49B2-9813-29457AAEF208
17.2 No concrete shall be placed until the area, reinforcement and all sleeves and accessories are
approved in their final position by the Engineer.
19. LOW OR NO FINES CONCRETE
The design mix for the low fines concrete is as follows;
▪ 1350 kg of 19 mm stone or 15 wheelbarrows
▪ 200 kg coarse washed river sand or 1 x wheelbarrow
▪ 80 kg cement
▪ 100 L water – add only enough for a dry screed type of mix, once placed do not compact, to
level off, a Bomag drum roller without the vibration can be used.
20. CONCRETE REPAIRS:
These are repairs to the cracks and spalling
A general specification is to be adhered to as described below:
The cracks and spalled areas are to be to be identified in conjunction with the method statement and
a table of repairs prepared to be agreed to by the site management before cleaning. The areas local
to such cracks and spalling are to be spray cleaned at a pressure of 240 bar to the satisfaction of
the site inspector delegated to this contract (or representative appointed by site management).
On approval that surfaces have been properly prepared the cracks and spalled areas are to be
scabbled and routed to expose the rebar to a depth of 20 mm behind the rebar by breaking out the
concrete and incising the perimeters of the work areas.
On approval by the inspector that the exposure has been satisfactorily prepared a coating is to be
applied by brush to the exposed rebar and scabbled surfaces of an integral crystalline waterproofing
slurry to be applied to concrete as per manufacturer’s specifications such as Xypex or equivalent.
An integral crystalline waterproofing repair mortar is to be used in concrete repairs, construction
joints and tie-holes as per manufacturers’ specifications above mentioned to restore the original
finish to plinths and bases.
Should the product be used in a concrete mix design the admix is processed as follows: Add
Integral crystalline waterproofing additive with tracing agent, minimum dosage 0.8% by weight of
all cementitious content to concrete when batching. All to manufacturers specifications. Concrete
must be placed protected and cured according to SANS 10100-2. (20 year warranty)
When this product is applied as a slurry, even from the negative side, it penetrates up to a meter
deep into the concrete. It closes and seals all pores and capillaries up to 0.4mm. It is ideal for existing
structures and concrete rehabilitation.
It also offers the following benefits
▪ It reduces chloride penetration;
▪ It reduces carbonation of concrete;
▪ It increases the compressive strength of concrete;
▪ It prevents freeze thaw damage;
Page 24 of 28
DocuSign Envelope ID: A4BF1485-D514-49B2-9813-29457AAEF208
Page 25 of 28
DocuSign Envelope ID: A4BF1485-D514-49B2-9813-29457AAEF208
21.5 LIMITATIONS
▪ The flintkote bitumen base mastic should not be laid if rain is imminent. Should there be doubt
about the setting time then thinner layers must be applied, also adequately cover the areas
concerned in the event of precipitation;
▪ Un-set mastic must be protected against frost in cold climates;
▪ In petroleum tank installations the bituminous mastic should not come into contact with the
liquids contained therein and detail work should be so performed so as to alleviate this
possibility;
▪ Good housekeeping should be employed for optimum performance.
21.6 DATA SHEETS
Technical information may be found in the relevant ABE data sheets and it is recommended that
particular attention be paid to the following:
▪ Surface preparation;
▪ Mixing;
▪ Pot life;
▪ Over coating time;
▪ Curing time;
▪ Safety precautions.
21.7 YIELD DETERMINATION
The total on the absolute yield, under mix proportion guide, is the approximate volume you will obtain
when mixing in those proportions. Allow approximately 10 % for waste.
Example:
Tank base diameter = 2.0 metres
Tank base mastic = 13 mm thick
Volume of material required = π/4 x 22 x 0.013 x 1000 = 40.8 litres say 41 litres, add 10 % waste =
45 litres.
Therefore 45 litres divided by 71 litres, from the mix proportion guide under the absolute yield,
equates to + 63 % of the proportions in the table, parts by mass or parts by volume.
Page 26 of 28
DocuSign Envelope ID: A4BF1485-D514-49B2-9813-29457AAEF208
ASSUMPTIONS
Bulking factors may vary according to moisture content and handling of materials.
4,750 85 – 100
2,360 69 – 90
1,180 45 – 70
0,600 30 – 50
0,300 18 – 30
0,150 10 – 21
0,075 5 – 15
Page 27 of 28
DocuSign Envelope ID: A4BF1485-D514-49B2-9813-29457AAEF208
Page 28 of 28