Seleka Agricultural College Cash Flow
Seleka Agricultural College Cash Flow
FLOW PROJECTION
February March April May June July
THE CONSTRUCTION AND UPGRADE OF SECURITY INFRASTRUCTURES AT TOMPI SELEKA AGRICULTURAL COLLEGE
PRELIMINARY & GENERAL R66,737.41 R102,330.70 R88,983.22 R102,330.70 R97,881.54
EARTH WORKS R290,514.84
STEEL STRUCTURE R135,692.33 R226,153.89 R260,076.97 R248,769.28
BUILDING WORKS (Entrance Gate & Security Centre House) R261,815.77 R436,359.62 R501,813.56 R479,995.58
ELECTRICAL, ACCESS CONTROL & SECURITY LIGHTS
PAVING, GARDEN & ARTWORKS R161,439.30
SECURTY WATCHTOWER R119,023.28 R198,372.13 R228,127.94 R218,209.34
Project Commissioning
Total R66,737.41 R909,376.92 R949,868.86 R1,092,349.17 R1,206,295.04
Page 1
CASH FLOW PROJECTION
July August September October Total
THE CONSTRUCTION AND UPGRADE OF SECURITY INFRASTRUCTURES AT TOMPI SELEKA AGRICULTURAL COLLEGE
PRELIMINARY & GENERAL R93,432.38 R97,881.54 R649,577.49
EARTH WORKS R290,514.84
STEEL STRUCTURE R147,000.03 R1,017,692.50
BUILDING WORKS (Entrance Gate & Security Centre House) R261,815.77 R1,941,800.30
ELECTRICAL, ACCESS CONTROL & SECURITY LIGHTS R289,179.00 R674,751.00 R963,930.00
PAVING, GARDEN & ARTWORKS R188,345.85 R206,283.55 R71,750.80 R627,819.50
SECURTY WATCHTOWER R109,104.67 R872,837.36
Project Commissioning
Total R1,088,877.70 R978,916.09 R71,750.80 R6,364,171.99