MOTSARO 

CONSTRUCTION THE CONSTRUCTION AND UPGRADE OF SECURITY INFRASTRUCTURES AT TOMPI SELEKA AGRICULTURAL COLLEGE EPHRAIM MOGALE MUNICIPALITY


ID Task Name Duration Start Finish February 2023 March 2023 April 2023 May 2023 June 2023 July 2023 August 2023 September 2023
2 5 8 11 14 17 20 23 26 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15
1 THE CONSTRUCTION AND UPGRADE OF SECURITY  156 days Wed 2/8/23 Wed 9/13/23
INFRASTRUCTURES AT TOMPI SELEKA AGRICULTURAL COLLEGE

2 PRELIMINARY & GENERAL 146 days Wed 2/8/23 Wed 8/30/23

3 Site Handover 1 day Wed 2/8/23 Wed 2/8/23

4 Contractual Obligations 145 days Thu 2/9/23 Wed 8/30/23 0%

5 Site Establishment 15 days Thu 2/9/23 Wed 3/1/23

7 EARTH WORKS 14 days Thu 3/2/23 Tue 3/21/23

8 Site Clearance 3 days Thu 3/2/23 Mon 3/6/23

9 Excations for foundations for structures and trenches 7 days Tue 3/7/23 Wed 3/15/23

10 Material Sourcing 10 days Tue 3/7/23 Mon 3/20/23 0%

11 De‐Watering 7 days Mon 3/13/23 Tue 3/21/23 0%

12

13 STEEL STRUCTURE 90 days Thu 3/16/23 Wed 7/19/23

14 Reinforcement for footings 10 days Thu 3/16/23 Wed 3/29/23

15 Concrete for foundations 28 days Thu 3/30/23 Mon 5/8/23

16 Steel Structure 30 days Tue 5/9/23 Mon 6/19/23 0%

17 Roof Coverings 15 days Tue 6/20/23 Mon 7/10/23 0%

18 Insulations 7 days Tue 7/11/23 Wed 7/19/23 0%

19

20 BUILDING WORKS (Entrance Gate & Security Centre House) 89 days Thu 3/16/23 Tue 7/18/23

21 Excavations for foundations 10 days Thu 3/16/23 Wed 3/29/23 0%

22 Soil Poisoning 5 days Thu 3/30/23 Wed 4/5/23 0%

23 Concrete for foundations 20 days Thu 4/6/23 Wed 5/3/23

Task Summary External Milestone Inactive Summary Manual Summary Rollup Finish‐only Critical Split


Project: THE CONSTRUCTION AND
Split Project Summary Inactive Task Manual Task Manual Summary Deadline Progress
Date: Thu 2/9/23
Milestone External Tasks Inactive Milestone Duration‐only Start‐only Critical

Page 1
MOTSARO CONSTRUCTION THE CONSTRUCTION AND UPGRADE OF SECURITY INFRASTRUCTURES AT TOMPI SELEKA AGRICULTURAL COLLEGE EPHRAIM MOGALE MUNICIPALITY
ID Task Name Duration Start Finish February 2023 March 2023 April 2023 May 2023 June 2023 July 2023 August 2023 September 2023
2 5 8 11 14 17 20 23 26 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15
24 Buildings 30 days Wed 4/26/23 Tue 6/6/23

25 Roof Coverings 20 days Wed 5/24/23 Tue 6/20/23 0%

26 Closures 10 days Wed 6/21/23 Tue 7/4/23 0%

27 Plumbing & Sewage Installations 15 days Wed 6/7/23 Tue 6/27/23 0%

28 Electrical Installations 15 days Wed 6/28/23 Tue 7/18/23 0%

29

30 ELECTRICAL, ACCESS CONTROL & SECURITY LIGHTS 30 days Wed 7/19/23 Tue 8/29/23

31 High Voltage Electrical power line (Eskom registered  20 days Wed 7/19/23 Tue 8/15/23 0%


contractor)

32 Electrical reticulation of the entrance gate buliding, control  20 days Wed 7/26/23 Tue 8/22/23 0%


room including security lights

33 Access Control Infrastructure 5 days Wed 8/23/23 Tue 8/29/23 0%

34

35 PAVING, GARDEN & ARTWORKS 70 days Wed 6/7/23 Tue 9/12/23

36 Road Pavements 30 days Wed 6/7/23 Tue 7/18/23

37 Artwork 30 days Wed 6/21/23 Tue 8/1/23

38 Gardening 30 days Wed 8/2/23 Tue 9/12/23

39

40 SECURTY WATCHTOWER 88 days Thu 3/16/23 Mon 7/17/23

41 Earth works 5 days Thu 3/16/23 Wed 3/22/23 0%

42 Concrete (Structural) 28 days Tue 5/9/23 Thu 6/15/23 0%

43 Structural Steel Works 15 days Tue 6/20/23 Mon 7/10/23 0%

44 Panel Toilet 5 days Tue 7/11/23 Mon 7/17/23 0%

45

46 Project Commissioning 1 day Wed 9/13/23 Wed 9/13/23

Task Summary External Milestone Inactive Summary Manual Summary Rollup Finish‐only Critical Split


Project: THE CONSTRUCTION AND
Split Project Summary Inactive Task Manual Task Manual Summary Deadline Progress
Date: Thu 2/9/23
Milestone External Tasks Inactive Milestone Duration‐only Start‐only Critical